SATPC0042582 Tab 04 5 SOW Rev 1.pdf

PDF 218 KB Posted

Attached to
Vacuum-jacketed hard lines for helium refrigeration system.
Solicitation number
80NSSC26942430Q
Issued by

About this file

This is a Statement of Work (SOW) for the procurement of vacuum-jacketed helium piping lines for NASA's Testbed for High Energy cRyogenic Materials And Superconductors (THERMAS) facility at Glenn Research Center in Cleveland, Ohio, dated August 7, 2026.

The contractor shall fabricate and deliver two vacuum-jacketed piping assemblies (Supply Line and Return Line) consisting of four total pipe spools and four male bayonet plugs, plus one vacuum operator assembly compatible with all pump-out ports. All piping must be designed, fabricated, tested, and inspected in accordance with ASME B31.3 Normal Fluid service for design conditions of 150 psig at temperatures ranging from -450°F to +80°F (-452°F to 300 K), with gaseous helium as the fluid medium. Process pipe (inner line) shall be Type 304L stainless steel per ASTM A403, while the outer vacuum jacket and all other components shall be 300 Series stainless steel. The contractor must perform piping flexibility analysis in CAESAR II, conduct 100% visual weld examination plus minimum 5% random radiography of circumferential butt welds, perform impact testing at -450°F, and conduct pressure testing at 165 psig (pneumatic) or 225 psig (hydrostatic) followed by liquid nitrogen cold-shock prior to shipment. All components must be precision cleaned to level VC per KSC-C-123 and meet stringent traceability requirements through unique identifiers and serial numbers. The contractor is responsible for submitting prefabrication approval drawings within 30 days of contract award and an Acceptance Data Package (ADP) electronically 10 days prior to hardware delivery, which must include as-built drawings, engineering analyses, material certifications, test results, and a signed Certificate of Conformance to ASME B31.3. Aerospace Quality clauses derived from AS9100 requirements apply, including special process certifications for tube flaring, tube bending, and welding, as well as comprehensive nondestructive inspection/test certifications and objective evidence of dimensional inspection for all delivered articles.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

August 7, 2026 Rev. 1

STATEMENT OF WORK

FOR

TESTBED FOR HIGH ENERGY CRYOGENIC

MATERIALS AND SUPERCONDUCTORS VACUUM-

JACKETED HELIUM LINE PROCURMENT

AUGUST 7, 2026

Table of Contents Table of Contents

1. Purpose

2. Scope

2.1 Deliverables

3. Applicable Documents

3.1 Engineering Drawings

3.2 Specifications, References and Documents

4. Government-Furnished Equipment

5. Submittals and Communication

5.1 Submission Method

5.2 Requests for Information

5.3 Deviations and Waivers

5.4 Meetings and Updates

5.5 Schedules

6. Design

7. Fabrication

7.1 Welding Requirements

7.2 Design Conditions

7.3 Materials

7.4 Testing

7.5 Marking

7.6 Components

8. Cleaning

9. Quality Assurance

9.1 Inspection and Acceptance

9.2 Contamination Control

9.3 Component Traceability

9.4 Additional Aerospace Quality Clauses

8.4.1 AQC04 Flow Down Requirements

8.4.2 AQC06 Certificate of Compliance – Raw Materials

8.4.3 AQC08 Special Process Certification

8.4.4 AQC16 Nondestructive Inspection/Nondestructive Test Certification

8.4.5 AQC17 100% Attribute Clause

8.5.6 Q39 Objective Evidence of Dimensional Inspection

10. Appendix A. Engineering Drawings B. Contract Data Requirements List

1. PURPOSE

The Cryogenic High-power Integrated Low Loss Motor Demonstration (CHILL) project at NASA Glenn Research Center (GRC) in Cleveland, OH is currently building the Testbed for High Energy cRyogenic Materials And Superconductors (THERMAS) at Building 191 to test materials and components for future high-power, superconducting aircraft powertrains. This facility will accommodate a large cryogenic helium refrigeration system that is housed inside a 40-foot shipping container. This container will be located outside Building 191, with vacuum-jacketed supply and return lines rounded into the test cell and connecting the refrigerator to the test hardware. This Statement of Work (SOW) defines the requirements for procurement of these lines.

2. SCOPE

The Contractor shall furnish all labor, engineering, equipment, materials, and services to schedule, coordinate, supervise, and provide quality control for fabrication, non-destructive evaluation (NDE) testing, cleaning, and safe shipping of piping assemblies and components for the THERMAS vacuum-jacketed lines as defined in this SOW, associated engineering drawings, and referenced standards and specifications.

2.1 Deliverables

1. The Contractor shall fabricate and deliver two (2) vacuum-jacketed piping assemblies, “Supply Line” and “Return Line”, consisting of two (2) piping spools (four total pipe spools) and two (2) male bayonet plugs per assembly.

2. The Contractor shall deliver one (1) vacuum operator assembly that is compatible with all pump-out ports supplied on each piping spool.

3. The Contractor shall provide an Acceptance Data Package (ADP) that contains all correspondence between the Contractor and NASA; quality control documents; as-built engineering drawings of the piping assemblies; engineering analyses; a signed Certificate of Conformance to ASME B31.3 for all assemblies/components; cleanliness, vacuum retention, and helium mass spec compliance; material certifications, final acceptance inspection records; and any other documentation required to administer the successful completion of the contract. An electronic copy of the ADP shall be delivered to the Government for review 10 days prior to hardware delivery. Hardware deliveries will not be accepted by the Government without an accompanying ADP.

3. APPLICABLE DOCUMENTS

The latest revision of the documents listed below form a part of this specification to the extent specified herein. In the event of conflict between the referenced documents and the contents of this specification, the contents of this specification shall govern.

3.1 Engineering Drawings

All required engineering drawings are listed in Appendix A.

3.2 Specifications, References and Documents

The drawings, specifications, and documents identified, and/or referenced in, the items above, are incorporated herein. The Contractor shall be responsible for reviewing all of the drawings, specifications, and references; and for notifying the Contracting Officer of any concerns.

Document Number Title

THERMAS_VJ_Lines_Spec_Rev0 Testbed for High Energy cRyogenic Materials And Superconductors (THERMAS) Helium Vacuum-Jacketed Line Specification

ANSI/NCSL

Z540.1-1994

Calibration Laboratories and Measuring and Test Equipment - General Requirements

ASME B31.3 Process Piping

ASME Section IX Boiler and Pressure Vessel Code, Welding and Brazing Procedures

4. GOVERNMENT-FURNISHED EQUIPMENT

No Government Furnished Equipment (GFE) will be supplied as part of this contract.

5. SUBMITTALS AND COMMUNICATION

The Contractor shall provide all of the data listed in Contract Data Requirements List (CDRL), found in Appendix B. All CDRL items shall be submitted to the NASA Contracting Officer and shall be subject to the unilateral approval of the NASA Contracting Officer. In the event of disapproval, the Contractor shall initiate immediate corrective action and shall resubmit to the NASA Contracting Officer for approval within five working days.

5.1 Submission Method

The Contractor shall submit all data deliverables electronically. All documents shall be submitted in an electronic format that is searchable (e.g., PDF). For documents that were scanned, the Contractor shall run "paper capture" or optical character recognition to convert the file to a searchable format before submittal.

5.2 Requests for Information

After contract award, the successful Contractor shall, when contract information or clarification is required by the Contractor, prepare and submit GRC Form GRC 9C, “Request for Information (RFI)” The form shall be submitted to the Contracting Officer and will be processed by the Government. The RFI will be returned to the contractor with the appropriate information/response.

The Contractor shall indicate on the RFI if the concern or question has an effect on schedule or cost. The form will be provided to the Contractor at the post award pre-work meeting.

5.3 Deviations and Waivers

Deviation requests are to be submitted when the Contractor wishes to deviate from a requirement in this Statement of Work, drawings, specifications, or standards. Waiver requests are to be submitted when the Contractor is unable to meet a requirement in this Statement of Work, drawings, specifications, or standards, and is requesting relief from that requirement. The Government shall hold final decision rights for the approval of deviation and waiver requests.

5.4 Meetings and Updates

The Contractor shall schedule and conduct post-award pre-work and other technical interchange meetings as requested by the Government throughout the period of performance. The Contractor shall allow periodic visits to the Contractor’s facilities for the purpose of in-process inspections and to convey additional information as required.

The Contractor shall be available for meetings as required by the Government. The Contractor shall provide meeting minutes to attendees two days after the meetings. The Contractor shall provide the Government with a written status update on a monthly basis, detailing progress made, problems encountered, and planned work.

5.5 Schedules

The Contractor shall provide a progress schedule to be updated monthly. The schedule shall include planned completion dates of important tasks and milestones.

6. DESIGN

The piping system shall be designed, fabricated, tested and inspected in accordance with ASME B31.3 Normal Fluid service for design conditions of 150 psig at -450 to 120°F. Any bellows type expansion joint in the piping system shall comply with ASME B31.3 Appendix X. Base metal and weld metal deposits shall be impact tested in accordance with ASME B31.3 Paragraph 323.3 at - 450 F and the certified reports of impact tests shall be submitted to NASA.

The piping system shall have piping flexibility analysis performed in CAESAR II in accordance with ASME B31.3 to comply with ASME B31.3 sustained and displacement allowable stresses.

The contractor shall ensure the flexible line can handle the displacement and torsional loads at the termination of the vacuum jacketed piping. Forces and moments due to relief valve discharge shall be considered in the analysis. The piping system shall be analyzed for contraction, relief valve reactions, and effects due to weight, wind, snow and seismic in accordance with ASME B31.3. Support locations and types shall be documented on the engineering drawings.

7. FABRICATION

The Contractor shall provide all management, material, labor, facilities, tools, equipment, and transportation necessary to procure, fabricate, assemble, inspect, test, mark, package and deliver the line items specified in the purchase contract. All pipe, flanges, bends, and fittings shall be designed, fabricated, inspected and tested in accordance with ASME B31.3.

7.1 Welding Requirements

Certified welders with the appropriate certification for the material being worked shall be used. All welding of pipe and pipe components shall be in accordance with ASME Boiler & Pressure Vessel Code, Section IX, Welding and Brazing Qualifications. Welds shall meet the requirements of ASME B31.3 for full-penetration welds unless otherwise noted on drawings. Liquid penetrants shall not be used on welds. Weld Procedures Specifications (WPS), Procedure Qualification Records (WPQ) and Welder Performance Qualification (WPQ) shall be qualified to -452 F for liquid helium piping and welds.

Upon completion of fabrication, the piping shall be examined in accordance with ASME B31.3 for Normal Fluid Service. Per Section 341.4.1 (b) (1), “Not less than 5% of circumferential butt and miter groove welds shall be examined fully by random radiography. The welds to be examined in each designation lot shall include the work product of each welder or welding operator whose welds are part of the lot.”. 100% of all completed welds shall be visually examined. Welds shall be accepted in accordance with ASME B31.3 and acceptance documentation shall be submitted to NASA. Non-Destructive Examination (NDE) technicians shall be qualified in accordance with

ASNT SNT-TC-1A.

7.2 Design Conditions

The line assembles shall have a design pressure of 150 psig, and an operating temperature range of 4 to 300 K (-452 to +80 °F). The fluid media is gaseous helium (GHe).

7.3 Materials

Process pipe (inner line) material shall be type 304L stainless steel per ASTM A403, outer pipe (vacuum jacket) and all other components shall be 300 Series stainless steel.

7.4 Testing

All fabricated pipe segments shall be pressure tested in accordance with ASME B31.3, and cold-shocked with liquid nitrogen (LN2) prior to shipment. Test pressure shall be 165 psig for pneumatic testing or 225 psig for hydrostatic testing.

7.5 Marking

All fabricated pipe segments shall be permanently and legibly marked with the following:

Fabrication date

Hydrostatic or pneumostatic test date and test pressure

Pressure and temperature rating

Fluid commodity

7.6 Components

A Certification of Compliance (COC) shall be provided for all fluid components purchased by the contractor to verify that traceability meets the required component specification requirements.

8. CLEANING

The Contractor shall be responsible for precision cleaning of all components to level VC per KSC- C-123 prior to installation. The Contractor is responsible for maintaining and preserving the cleanliness of all cleaned components until acceptance by NASA. After the Government performs integrated testing, if any rework is required, the Contractor shall be responsible for field cleaning the final installed assembly to level VC per KSC-C-123.

9. QUALITY ASSURANCE

All equipment delivered under this specification shall conform to the highest commercial standards for fit, finish, and workmanship. The Contractor shall submit fabrication drawings to NASA for review and approval prior to beginning fabrication.

9.1 Inspection and Acceptance

The Contractor shall reference the following Inspection and Acceptance clauses:

FAR 52.246-2 Inspection of Supplies – Fixed Price (Aug 1996)

FAR 52.246-16 Responsibility for Supplies (Apr 1984)

FAR 52.246-15 Certificate of Conformance (Apr 1984)

9.2 Contamination Control

The Contractor’s cleaning procedures shall include Quality Assurance provisions for in-process controls to prevent contamination, including provisions for maintaining cleanliness of on-site, pre-packaged components, and sub-assemblies.

9.3 Component Traceability

Cleanliness certifications, hydrostatic and leak test results, and material certifications must be traceable to each item or component with a unique identifier (commonly referred to as A-Numbers or Find Numbers) and/or serial number. Copies of test results, certifications, and component data sheets shall be included in the final Acceptance Data Package for each unique component.

9.4 Additional Aerospace Quality Clauses

The Aerospace Quality clauses have been derived from AS9100 requirements. The Contractor should already be in compliance with AS9100 upon contract award and shall comply with the following clauses of this SOW.

8.4.1 AQC04 Flow Down Requirements

This clause mandates that all applicable requirements that are invoked or applied to the customer’s purchasing document, including this clause, shall be flowed down to the Contractor’s sub-tier suppliers.

8.4.2 AQC06 Certificate of Compliance – Raw Materials

The following clause applies when the Contractor will purchase (not including Government Furnished Equipment) raw materials to defined specification(s).

The Contractor will include with each shipment the raw material manufacturer's test report (e.g., mill test report) that states that the lot of material furnished has been tested, inspected, and found to be in compliance with the applicable material specifications. The test report will list the specifications, including revision numbers or letters, to which the material has been tested and/or inspected and the identification of the material lot to which it applies.

When the material specification requires quantitative limits for chemical, mechanical, or physical properties, the test report will contain the actual test and/or inspection values obtained. For aluminum mill products (except castings), certifications for chemistry may indicate compliance within the allowed range. Certifications for physical properties will show actual values.

When contractor supplies converted material produced by a raw material manufacturer, the contractor shall submit all pre and post conversion chemical/physical tests reports.

8.4.3 AQC08 Special Process Certification

Special processes shall be performed only by sources that have been surveyed and qualified/approved, by the supplier and/or the Customer, to perform those processes. The contractor shall provide to the Customer upon request all documentation showing evidence of special processor qualification and/or certification to perform special manufacturing, assembling, and test processing as required by the contract. The Contractor may elect to use only Customer approved sources.

A special process certification shall be provided with each shipment of item(s) delivered on this contract. Special Process Certifications may be in supplier format and shall include the following:

Customer’s Order number Part number(s) Serial and/or lot numbers, of the hardware processed (if applicable) Material process specification & revision

Objective evidence demonstrating compliance with the applicable process, (e.g., temperature charts and hardness test results for heat treatment, destructive test results, etc.)

A certification stating the special process was performed per the applicable drawing/specification requirements.

Organization’s name and address

When special processor is other than the Organization, provide a certification of compliance from the special processor stating the special process was performed per the applicable drawing/specification requirements. Certifications must include the processor’s name, address and be signed and dated by a company official.

Each certification must be signed and dated by a company official of the Organization and/or Processor attesting to the acceptance of the processes performed to the required specification(s).

The supplier shall retain all records associated with the selection and approval of supplier approved special process providers. Per contract or regulatory agency requirements, these records shall be made available to the Customer and/or regulatory agencies upon request. The supplier shall notify the Customer prior to destruction of records relative to this contract.

The Contractor shall insert the substance of this clause, including this sentence, in all lower-tier subcontracts for work performed under this contract.

The special processes involved with this Delivery Order are tube flaring, tube bending, and welding (where applicable to specification).

8.4.4 AQC16 Nondestructive Inspection/Nondestructive Test Certification

The Contractor will include with each shipment a certificate for the nondestructive inspection (NDI)/nondestructive test (NDT) performed. As a minimum, the certification shall contain the following information:

Customer’s Purchase Order / Contract number Name and address of the Company performing NDI/NDT;

Date of Inspection;

Quantity of parts tested by part number;

Specification or other requirement defining the NDI/NDT acceptance / rejection criteria;

Inspector/name/stamp and NDI/NDT certification level;

NDI/NDT specification including revision;

Material or item identification (part number, heat lot number, Foundry Record (FR) number;

Material or item traceability (serial number, lot number, batch number, lot/date code);

Inspection results (accept/reject);

Reference to previous NDI/NDT reports for repair/rework if applicable;

Reference to attached recordings i.e., films or photographs if applicable.

These records shall include all information required in the previous paragraph as well as acceptance / rejection criteria, and related test instrument data used in the NDI/NDT process.

8.4.5 AQC17 100% Attribute Clause

The Contractor is responsible for the performance, on a one hundred percent (100%) basis of all inspections and tests and record requirements specified in the contract. Unless otherwise specified in the contract, the Contractor may utilize independent inspection and testing laboratories or services that are acceptable to the Government.

8.5.6 Q39 Objective Evidence of Dimensional Inspection

The Contractor shall provide objective evidence with each shipment that all the articles were dimensionally inspected for conformance with drawing and Delivery Order requirements.

Objective evidence shall consist of records of actual dimensional readings taken during inspections, of each part, with the dimension and its tolerance noted. All out of tolerance measurements shall be clearly identified on the records, and the disposition of that part noted by the Organizations quality assurance organization. This information is to be submitted to NASA for acceptance/rejection of the out-of-tolerance condition, prior to submittal of the hardware.

Organization shall identify each inspection data sheet to the related Contract/Purchase Order, part number, revision and when applicable, serial number. The management representative responsible for the Contractor’s inspection activity, will certify that with signer’s title and date of signature indicated that all of the shipped parts were indeed inspected to the criteria specified and those actual measurements are the ones provided. If serial numbers are not assigned, then the supplier shall devise a method of linking the record of dimensional measurements with the specific part measured (e.g., taped, bagged together). Inspection equipment (e.g., tools, gages) used during dimensional measurement shall have its identification numbering recorded and have the ability to recall the parts inspected with that particular inspection device in the event it is subsequently found to be significantly out of tolerance.

10. APPENDIX

A. Engineering Drawings

Document Number Revision Title

N/A 0 THERMAS_VJ_lines_Rev0

B. Contract Data Requirements List

Description Delivery Frequency Date Required

C1 Prefabrication approval drawings Electronic Once Within 30 days after effective date of order

C2 As Built Drawings Electronic Once With ADP

C3 Vendor Data Electronic Once With ADP

C4 Commercial Warranties Electronic Once With ADP

C5 Acceptance Data Package Electronic Twice

Electronic copy 10 days prior to delivery of hardware, updated electronic and hard copy with delivery of hardware

C6 Sub-tier Contract Requirements Electronic Initial & each change With proposal and ADP

C7 Certificate of Conformance to ASME B31.3 Electronic Once With ADP

C8 Material Certifications Electronic Once With ADP

C9 Deviation & Waiver Request Electronic As Required

As needed; Approved Deviation/Waivers with

ADP

C10 Request for Information (RFI) Electronic As Required As needed and full set with

ADP

C11 Welder Performance Qualifications (WPQ) Electronic Twice Prior to welding /ADP

C12 Welding Procedure Specification (WPS) Electronic Twice Prior to welding /ADP

C13 Procedure Qualification Record (PQR) Electronic Twice Prior to welding /ADP

C14 Certification of Weld Inspector Electronic Twice Prior to welding /ADP

C15 Weld Inspection Record Electronic Twice Completion of welding inspection & ADP

C16 Cleaning Procedure Electronic Twice 30 days prior to cleaning, w/ADP

C17 Minutes of Meetings Electronic Each Meeting 2 days after each meeting and w/ADP

C18 Punch List with Disposition Electronic Once With ADP

C19 NDE Test Results Electronic Once With ADP

C20 Impact Test Results Electronic Once With ADP

C21 Hydrostatic or Pneumatic Test Reports Electronic Once With ADP

C22 Design Calculations and Specifications (per ASME B31.3)

Electronic Once With ADP