This is a Statement of Work (SOW) for the STRIVE Main Electronics Box (MEB) Investigation, effective May 4, 2026, issued by NASA's Goddard Space Flight Center for the Stratosphere Troposphere Response using Infrared Vertically-resolved Light Explorer mission. The contractor must conduct an 8-month investigation to develop the MEB concept and define electrical, thermal, mechanical, and flight software interfaces for the STRIVE mission payload. The MEB must utilize the Sensors Unlimited 1280JSX Enclosed Camera form factor or equivalent, operate within -10°C to +50°C, accept +28 VDC to +34 VDC input, and support multiple complex interfaces including RS-422 communications, LVDS SpaceWire for science data transmission at 66.9 Mbps peak rate, power distribution to subsystems, 10 heater service outputs, 35 temperature sensor inputs, and 4 pulse commands for actuators. Three items remain to be determined: maximum and average power requirements (TBD-1), heater service output specifications (TBD-2), and temperature sensor specifications (TBD-3).
The contractor must deliver an MEB development schedule with Integration and Test approach and early Engineering Model delivery possibilities; MEB qualification testing plan; Electrical Ground Support Equipment list; comprehensive MEB specifications covering general information, electrical interfaces, mechanical envelope, thermal characteristics, and environmental limits; and an MEB Users Guide addressing flight software interfaces, system initialization, watchdog servicing, and memory scrubbing. Deliverables are due in initial draft form at month two, interim draft at month four, and final draft at month seven. Post-completion engineering support of 4 hours per week is required. The contractor must support weekly video meetings, monthly status reports, a kickoff technical interchange meeting at the contractor's facility, two technical interchange meetings at Goddard, and a specification review meeting, along with discussion of alternative parts for radiation mitigation.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Effective Date: May 4, 2026
Check https://idptdms.gsfc.nasa.gov to verify that this is the correct version prior to use.
400-FORM-0002 (4/16/2014)
National Aeronautics and Space Administration
Goddard Space Flight Center Greenbelt, Maryland
Reference Document
STRIVE-MGMT-SOW-0002, Revision - Stratosphere Troposphere Response using Infrared
Vertically-resolved Light Explorer, Code 404
STRIVE Main Electronics Box Investigation Statement of Work (SOW) https://idptdms.gsfc.nasa.gov/
STRIVE MEB Investigation SOW STRIVE-MGMT-SOW-0002, Revision -
Reference Document ii Check https://idptdms.gsfc.nasa.gov to verify that this is the correct version prior to use.
400-FORM-0002 (4/16/2014)
Table of TBDs
Action Item No.
Location Summary Individual/ Organization
Actionee TBD-1 Section 2 Max and Average Power Electrical TBD-2 Section 2 Heater Service Outputs Thermal TBD-3 Section 2 Temperature Sensors Thermal
Reference Document iii Check https://idptdms.gsfc.nasa.gov to verify that this is the correct version prior to use.
400-FORM-0002 (4/16/2014)
Table of Contents
1 PURPOSE
2 MEB SPECIFICATIONS
3 DURATION OF THE STUDY
4 DELIVERABLES
5 TECHNICAL EXANGE MEETINGS, REPORTS, AND REVIEWS
Appendix A Abbreviations and Acronyms
Reference Document
Check https://idptdms.gsfc.nasa.gov to verify that this is the correct version prior to use.
1 PURPOSE
The Contractor shall conduct an investigation to develop the Main Electronics Box (MEB) concept and define electrical, thermal, mechanical, flight software interfaces that will meet the requirements for Stratosphere Troposphere Response using Infrared Vertically-resolved light Explorer (STRIVE) mission payload.
2 MEB SPECIFICATIONS
• Mechanical Form Factor: Utilize the Sensors Unlimited standard 1280JSX Enclosed
Camera form factor or equivalent.
• Thermal Requirements: Temperature of the mechanical interface is expected to be held within the range of -10 °C to +50 °C operational and -20°C to +50°C survival.
• Voltage input range is +28 VDC to +34 VDC.
• Max and Average Power TBD-1
• Support the following interface:
o RS-422 1 PPS from spacecraft o RS-422 UART for command and telemetry to and from the spacecraft o LVDS SpaceWire to transmit science data to the spacecraft (66.9 Mbps peak rate) o Power (28V -34 V) 6 Amp Max o RS-422 1 PPS out to the Mechanism Control Electronics (MCE) o LVDS UART to the MCE for command and telemetry o Power output to the MCE (unregulated from the spacecraft) o RS-422 1 PPS out to the Focal Plane Interface Electronics (FPIE) o Power (12 Volts) to the FPIE o LVDS UART to the FPIE for command and telemetry o LVDS Spacewire input from the FPIE for science data o 4 28-volt pulse commands for actuators o 10 Heater service outputs (which ones are switched and the sizes are TBD-2) o Temperature sensors: 35 PRT inputs reading -243/60 and TBD-3 reading +60/-60 o LVDS UART to the ARGOS Camera for command and telemetry o Power (12 Volts) to the ARGOS Camera o RS-422 UART for command and telemetry to and from the cryo-cooler electronics
3 DURATION OF THE STUDY
The investigation will last for 8 months from award.
After all deliverables are complete, 4 hours per week of engineering support shall be provided.
4 DELIVERABLES
The Contractor shall deliver the following:
• MEB development schedule including the following o Including I&T approach o Including the EM MEB deliveries o Possibility of early EM deliveries for early interface testing
Reference Document
Check https://idptdms.gsfc.nasa.gov to verify that this is the correct version prior to use.
o Identification of all procurements and lead times
• MEB Qualification (what tests are going to be performed)
• List Electrical Ground Support Equipment (EGSE) that will be delivered/supported
• MEB Specifications:
o General Information: Features, Background, Block Diagram, Key Components o Electrical interfaces: Processor (description and usage), FPGA (description (block diagram, interfaces, clock and reset, programming process) and usage), memory, digital, analog, electrical power, inrush, timing, interface connector and connector pinouts.
o Mechanical interfaces: envelope, mass, and mechanical interface drawing o Thermal interfaces: locations for conducting away power dissipation, operating, qualification and survival limits.
o Environmental Specifications
• MEB Users Guide o FSW interfaces: command interface, downlink protocol, internal buffering.
o Initialization (system, processor, interfaces, memory, etc.)
o Watchdog servicing o Memory Scrubbing
Each deliverable shall be delivered as an initial draft two months after the beginning of the investigation, as an interim draft four months after the beginning of the investigation, and as a final draft seven months after the beginning of the investigation.
5 TECHNICAL EXANGE MEETINGS, REPORTS, AND REVIEWS
The Contractor shall support the following meetings, reports, and reviews:
• Discussion about alternative parts to mitigate radiation risk with parts list
• Weekly teams/zoom meeting for information exchanges, concerns, questions
• Monthly status report summarizing accomplishments, schedule forward, needs from
STRIVE team, status on any open items.
• A kickoff technical interchange meeting o The Contractor shall host and organize this meeting at the Contractor's facility
• Two technical interchange meetings at Goddard Space Flight Center
• A Specification and Users Guide document review with the customer team providing comments o The Contractor shall host this meeting at the Contractor's facility
Reference Document
Check https://idptdms.gsfc.nasa.gov to verify that this is the correct version prior to use.
Appendix A Abbreviations and Acronyms
ARGOS Aerosol Radiometer for Global Observation of the Stratosphere EGSE Electrical Ground Support Equipment EM Engineering Model FPGA Field Programmable Gate Array FPIE Focal Plane Interface Electronics FSW Flight Software I&T Integration and Test MCE Mechanism Control Electronics MEB Main Electronics Box STRIVE Stratosphere Troposphere Response using Infrared Vertically-resolved light
Explorer TBD To be determined
| 1 Purpose |
| 2 MEB Specifications |
| 3 duration of the study |
| 4 Deliverables |
| 5 technical exange meetings, reports, and reviews |
| Appendix A Abbreviations and Acronyms |
File details come from the government source that posted it. Updated .