SATPC0040857 Tab 04 SOW Rev.pdf

PDF 240 KB Posted

Attached to
REDSoX Front and rear spider rough machining. Federal contract opportunity
Solicitation number
80NSSC26930468Q
Issued by
National Aeronautics and Space Administration Shared Services Center

About this file

This is a Statement of Work for machining services for the MSFC ST12 project. The contractor is required to machine two part types: 2 units of RDSX-102-001 FRONT APERTURE and 2 units of RDSX-154 REAR APERTURE from customer-supplied 17-4 PH stainless steel alloy in H1150 heat treat condition. Work must be completed within 35 business days from the date of award to maintain the project schedule ahead of launch.

The contractor must perform finish machining with windows left at 0.125" stock (with EDM work reserved for the customer), meet all geometric dimensional and tolerance specifications per drawings, apply stress relief heat treatment per SAE AMS2759/11, and achieve a minimum surface roughness of 125 microinches/3.2 micrometers Ra. Additional requirements include bag and tag preparation, formal inspection with dimensional reporting, and provision of ITAR/EAR registration, finishing certification, and certificates of conformance. Specific print exceptions apply: the part must be machined to 0.125" before stress relief, no passivation is required, and lapping per note 11 will be performed by the customer. The contractor must meet all geometric dimensional and tolerance specifications called out in the engineering drawings.

View the file

Other files for this federal contract opportunity

Other files attached to REDSoX Front and rear spider rough machining., newest first.
File Type Posted
SATPC0040857 Tab 10 RFQ Open Market (FO).pdf PDF
SATPC0040857 Tab 04 5 SOW Rev 2.pdf PDF
SATPC0040857 Tab 10 RFQ Open Market.pdf PDF
SATPC0040857 Tab 10 RFQ Open Market.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MSFC ST12 requires machining of the following parts:

2 ea. RDSX-102-001 FRONT APERTURE.STEP 2 ea. RDSX-154 REAR APERTURE.STEP

Requirements:

Work shall be completed within 35 business days or less from date of award to maintain project schedule ahead of launch.

Contractor shall meet geometric dimensional and tolerance called out in drawings Customer supplied 17- Stress relief heat treat per SAE AMS2759/11 Smallest Roughness: 125uin/3.2um Ra Bag and Tag

Contractor shall provide

Certification, Certificate of .

EDM windows at .125" stock Print relief P

File details come from the government source that posted it. Updated .