This statement of work outlines technical support services required for research cooling tower maintenance at a NASA facility in 2024. Key tasks include monitoring ozone systems and water chemistry, calibrating sensors, performing biofilm testing, recording chemical usage, managing blow-down processes, and developing a WaterTrac database. The contractor will also communicate any observed issues and recommended resolutions. Services will be coordinated in advance with NASA personnel.
The related federal contract opportunity is a special notice for research cooling tower maintenance contract renewal in 2024, issued under solicitation number 80NSSC24857720Q by the National Aeronautics and Space Administration Shared Services Center. The period of performance is January 1, 2024 to December 31, 2024.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SATPC0033850 Tab 07 Capability Statement SAM.gov.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work for Research Cooling Tower Maintenance CY2024 Contract Renewal
Date: 12-05-2023
Period of Performance: 01/01/2024 to 12/31/2024
Technical Support Services include the following tasks as applicable:
• Monitor operational effectiveness of ozone systems.
• Calibrate and clean control sensors
• Furnish, replace, weigh, and monitor corrosion coupons
• Perform bioslide testing to monitor biofilm development and control on Cooling Tower
#2 monthly and Cooling Tower #3 as required.
• Sample, test, and adjust water system chemistry as required.
• Record the chemical and total water usage for Cooling Tower #2.
• Maintain chemical feed pump settings and adjust chemical treat rates as required.
• Manage water system blow-down process and cooling tower cycles of concentration.
Adjust settings as necessary.
• Develop, record, and deliver WaterTrac™ Database and Software reflecting each cooling tower and service visit.
• Communicate observed issues and recommended workarounds or work orders to correct observed deficiencies.
• Note: Specific technical support visitation dates shall be coordinated with the NASA GRC technical Point of Contact and the Security Office prior to actual date of Service.
File details come from the government source that posted it. Updated .