Solictation_Questions.pdf

PDF 81 KB Posted

Attached to
Refurbishing Telecommunications Facilities SE, Honduras
Solicitation number
SAQMMA17R0016
Issued by

About this file

Question and Answers for the Solicitation

View the file

Other files

File Type Posted
B-M_(A001).pdf PDF
SF_30_(A001)_(Signed).pdf PDF
SAQMMA17R0016.pdf PDF
J.3_AutoCAD_Drawing.zip ZIP file
J.2_Drawings.zip ZIP file
J.1_Adminstrative_Documents.zip ZIP file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers

Q&A # Drawing/Spec.

Reference Subject Description Responses

1 The fire suppression system specifications show 474 liters are required. This seems small for a building this size. Are the units supposed to be gallons? Please confirm unit of measure.

See floor plan ARQ‐15 for specifications, section C2.9.2 in which the contractor has to provide the design according and with compliance with local regulations.

2 In the symbols for Doors/Windows P/2 and P/3, it shows them made of wood. In the plans and diagrams, they are described as aluminum and glass. Please clarify the materials required.

See floor plan ARQ‐06 for specifications, doors are wooden doors with specification provided on section C‐210 and C‐5.8.1.

3 Who is going to supply The Patch Panel Rack The selected vendor will provide/supply the patch panel rack/cabinet

4 There is specify 24 outputs to computers in the patch panel 1 and 10 outputs to computers in patch panel 2, but the locations of these outputs are not detailed.

Who will carry out the installations of these points?

The 24 output / ports and 10 output/ports will be to provided enough scalability for future growth/demand of electronic peripherals if needed in the near future. Switches to be installed will be PoE switches to facilitate the installation of the 12 wireless access points specified on the floor plans.

5 There are 12 Poe Wireless access point, are those output to router Wi‐Fi? The 12 PoE wireless access points will be directly connected to the PoE switches, see ARQ‐11.

6 Can we to change the wood mopboard to a vinyl mopboard? No, maintain the specifications provided on published contract, which is wood mopboard

7 Where is going to be located the water cistern? The water cistern will be located close by where the power generator will be installed

8 What kind of wood the doors have to be made of? See contract information for specifications provided for this contract refer to section C‐210 and C‐5.8.1 and according to drawing ARQ‐06

9 I am inquiring about opportunity SAQMMA17R0016. Will a site visit be possible to determine the extent of the refurbishment?

A site visit was held on December 16, 2016