CBRN Rapid Response Trailer Specifications - Jan 2011.docx

DOCX document 405 KB Posted

Attached to
Rapid Response Trailer Requirement
Solicitation number
SAQMMA11SS0009
Issued by

About this file

Rapid Response Trailor Draft Specifications

View the file

Other files

File Type Posted
CBRN RRT Equipment List.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Department of State, Diplomatic Security Service Anti-Terrorism Assistance Program

Chemical, Biological, Radiological, and Nuclear (CBRN) Rapid Response Trailer (RRT) Specifications

1. Purpose - This trailer will be used as an equipment grant to Partner Nations. It will be delivered in accordance with the CBRN Operations and CBRN Operations Refresher Courses. Therefore, we cannot have vendor stickers and advertisements on the RRT.

2. General - In the below specifications, you will find a list of very specific items and some that are not very specific. The specific items cannot be substituted for similar products. The non-specific items can be found at most local stores and include things 5 gallon buckets and garden hoses. Any brand will work for our purposes as long as it is durable to endure the rough conditions that are often encountered in foreign countries. All gear must be new. Again, no substitutions will be accepted for brand or model specific gear.

3. Trailer - The RRT must meet the following specs:

14’ ENCLOSED COMMERCIAL TRAILER

· 214" long x 100" wide x 92" tall

· Dexter, Independent Torsion Suspension, 7000 GVWR, EZ Lube Axles

· Trailer Rated Radial Tires, ST 205/75R15 LRD

· Modular-Styled Wheels

· 4 Wheel Brakes with Breakaway Switch and Battery

· Safety Chains

· 16” on Center Wall Post, Floor on 24” Cross Members

· 6” I Beam Frame

· 24” Stone Guard on the front of the trailer

· Platform Height 21”

· Hitch Ball 2 5/16”

· Aluminum Fenders

· .030 Exterior Aluminum Metal – Color is TBD

· .080 Hard Aluminum Top Wrap

· One Piece Aluminum Roof

· Aluminum Tread Plate on Nose - 24" tall

· Double Weather Stripping on Doors

· Double Rear Swing Doors

· Door holdbacks on all doors

· 32” Side Door With a Flush Lock and Bar Lock - bar lock handle covers the flush lock

· Steel step at entrance door with non-skid surface

· Aluminum tread plate trim around wheel boxes

· ¾” Wolmanized Plywood Floor, 3/8” Plywood Interior Walls

· Armaguard Spray-on Protective coating on A frame for enhanced weather protection

· Z-tech undercoating on floor cross members and frame for enhanced weather protection

· Warranty 3 Years

· Must include towing kit – interchangeable and height adjustable 2 5/16" coupler and pintle hook, 2 5/16" hitch ball (minimum capacity of 6000 lbs), ball mount (minimum capacity of 6000 lbs), hitch pin

· Pre-shipping trailer maintenance (including brake adjustment, coupler adjustment, tire inspection, light inspection and repairs, as needed, when authorized by ATA)

· Forklift lift points must be attached to the bottom of the trailers as this is often sent via ocean freighter

Rear of RRT

Vendor must also:

· Label and pack bins as directed by ATA for each order

· Warehouse components until trailer is assembled

· Provide trailer operations and maintenance manual including manufacturer warranties and checklist of all components within

· Provide quality assurance program to ensure that all components ordered are packed in the trailer

· Provide 2 sets of keys for the trailer door lock and padlock and additional spare key hidden on the trailer to facilitate shipper inspections

· Provide secure trailer storage at vendor's location for up to one year after RRT is complete

· Assist in coordinating shipping logistics, including providing trailer specifications, contents and value as required by receiving country, as required

· Ship trailer to designated point of departure on time as specified by ATA's designated shipping agent

· Modify trailer as required to meet the shipper and/or receiving country transportation requirements

· Empty all SCBA bottles prior to shipping

· Answer questions as directed by ATA in relation to the RRT

· Provide regular status updates on trailer status once an order is received

4. Equipment List

SEE EQUIPMENT LIST PROVIDED SEPERATELY

5. Equipment Racking System – The two racking systems must be custom designed steel racks, sized to hold 3 rows of 4 bins each securely without the use of additional restraints during transit. These racks are made from 3/16" structural angle and 14 gauge tubular steel. Once welded, the racks are degreased and spray painted to maximize coverage and minimize rust. The racks are installed in the trailer by securing them to steel strapping panels that are built into the trailer wall (behind the plywood). The strapping panels are welded to the trailer wall posts to distribute the load of the steel racks to enhance the structural integrity and lifespan of the trailer. One will be mounted on each inner wall of the trailer towards the rear leaving 18” from the end of the rack to the rear door. They must also have enough space below the bottom shelf for storage of various equipment.

Left Rack, Rear View

Right Rack, Rear View

6. Spare Cylinder Racking System – The racking system must be approximately 35” x 24” x 33”. The unit will hold 8 Spare SCBA Cylinders. The rack will also have storage under the bottom shelf for various equipment. The rack must fit 8 cylinders, 4 wide and 2 high. The unit will be bolted to the floor and sides of the trailer.

Spare Rack with Cylinders

7. SCBA WalkAway Bracket Mounting – The brackets will be mounted on the front wall of the trailer. They will be mounted 4 across and 2 high. They will be evenly spaced from each other. Similar strapping panels for the racking systems will be installed in the nose of the trailer where the SCBA unit brackets are attached. While these straps also enhance the structural integrity and lifespan of the trailer, more importantly, they ensure the brackets will stay firmly attached to the wall as the SCBA units are being removed and replaced for training or during an incident