OIG - Follow-up Questions 07082008.doc
DOC document 26 KB Posted
- Attached to
- FY09 Annual Financial Audit Statement
- Solicitation number
- SAQMMA08R0247
About this file
This attachment is the responses to follow-on questions received 8 July 2008
View the file
Other files
| File | Type | Posted |
|---|---|---|
| OIG - SAQMPD08R0247 - 2nd Revision.pdf | ||
| OIG - RFP SAQMMA08R0247 - 07-03-2008.pdf | ||
| OIG - Responses to Questions of 06-18-2008.doc | DOC document | |
| OIG - DD254.pdf | ||
| OIG - ACH.pdf | ||
| SAQMMA08R0247- REVISED.pdf | ||
| SAQMMA08R0247 Attachment 1 2.pdf | ||
| SAQMMA08R0247.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Responses to Question Received on 08 July 2008
1. We understand that the contractor is to provide certain pricing information in B-4, to include rate per hour and total extended amounts. It appears that your intent is for B.4 to be completed using the exact specified hours per labor category and the contractors’ desired labor rates per hour to calculate the “extended pricing”. We would like to confirm that this is the Department's intent (i.e., all offerors complete Section B.4 using the specified hours per labor category provided in the revised RFP Section B.4).
Include proposed, i.e., labor hour rate by labor category and then include total amount. For example, Partner/Principal 2,700 hours, rate desired - proposed $2.00 per hour, Amount $5,400.
2. In addition, for non-audit specialists, it is unclear whether the contractor is to calculate an extended amount for the specialists using the specified specialist hours and the contractor’s rate per hour for non-audit specialists or whether contractors are to use the specified extended amounts that are already included in Section B.4 of the revised RFP (i.e., $25,000 in base year and $50,000 in option years).
So that all proposals can be evaluated consistently, for the completion of Section B.4, should the contractor insert our requested specialist rate per hour and extend the total amount by the specified specialist hours (i.e., 2,000 hours in the base year and 1,500 hours in the option years), therefore ignoring the stated extended amounts (i.e.,, $25,000 and $50,000) currently provided in the RFP?
Follow the approach as discussed above under audit specialists. The proposed contract will be a labor hour contract. Thus, the proposed labor hour rate is the critical amount when the Department compares the costs of individual proposals.
Laobr hours performed under the contract will likely vary from the hours stated in the request for proposals.
3.
Within the questions and answers posted on July 3 for the above referenced solicitation, July 11 was indicated as the due date. However, the FedBizOpps Modification/Amendment states that the RFP is extended to 2:00 p.m. on Tuesday, 15 July 2008.
Please confirm that the new due date is Tuesday, July 15 at 2:00 p.m.
Due date has been extended until 2:00 pm on 15 July 2008 EST.