Renovation of Office Space Information Technology Office

View the file

Other files

File Type Posted
FedBizopps_Frequently_Asked_Question1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. EMBASSY LUANDA, ANGOLA

Scope of Work for the Purpose of a Contract

Renovation of Office Space: Information Technology Office 9/7/2016

Contents

1. LABOR-MATERIAL REQUIREMENTS TO PERFORM SERVICES

A. Summary

B. GENERAL

2. WORK TO BE DONE

C. Description

D. Site Limitations:

E. Performance period:

F. Warranty of work:

G. Site Conditions:

H. Materials:

3. LABOR

4. Evaluation of Offers

Appendix 1

1 | P a g e

1. LABOR-MATERIAL REQUIREMENTS TO PERFORM

SERVICES

A. Summary The Embassy of the United States of America, in Luanda, Angola is soliciting services of labor; materials and fully comprehensive work to renovate the information technology existing office space for more efficient use. This includes the demolition of two interior walls and the addition of two interior walls. The finishes include, drywall, paint, wall base, removal and replacement of ceiling tiles and grids, and new carpet.

B. GENERAL

A. The contractor shall provide all materials necessary for the fully comprehensive work, unless otherwise specified.

B. The provision of skilled labor means Certified/trained laborers with at least three years experience in their particular field, equipped with all hand/electrical tools, etc. necessary to carry out their work.

C. The contractor shall be able to operate simultaneously with two teams of laborers and schedule the work with a two-day advance notice

D. The contractor shall furnish the following documentation at time of bid.

i. Price breakdown of work according to SOW

ii. Timeline for work

iii. Certifications of skill sets for all foremen/supervisors

iv. Contact information for on-site supervisor

v. Copy of insurance policy for civil liability

vi. 3 references of previous work (Pictures and contact info)

The above documentation is mandatory at time of bid. Otherwise contractor will be deemed “Unacceptable”.

2. WORK TO BE DONE

C. Description

i. Demolish two existing walls.

ii. Build two additional walls

i. Each wall will have two layers of staggered 5/8” gypsum board for a 1 hour fire protection

ii. Walls will be painted white

iii. Move one door frame and door from demolished wall to new wall.

iv. Complete finish work of 5/8” thick double gypsum board for a 1 hour fire rating.

v. 6” rubber base will be added to the base of the wall for the entire suite as dimensioned in the reference plan

vi. Reconfiguration of the ceiling grid to match the existing ceiling grid

i. The ceiling tiles will be acoustic 2’ x 2’ ceiling tiles

vii. Removal of all existing carpet in the space

viii. Addition of 2’ x 2’ carpet tile will fill the entire space

2 | P a g e

D. Site Limitations:

1. Working hours are from 8:30AM to 5:00PM Monday thru Thursday and

8:30AM to 12:00PM on Friday unless otherwise specified. The contractor will be escorted by the resident or an embassy employees and all time.

2. The contractor will be fined $100.00USD per day if they fail to meet the start date of the provided schedule.

3. Employees caught sleeping on the job will be kicked off site and the contractor will be fined $100.00USD per violation.

E. Performance period:

1. Work will be completed by end of performance period or Contractor agrees to pay a 1% of the total contract value for each day as a fine or liquidated damages for going over the date. If there are any concerns regarding the

Performance period please raise the concern during the site visit.

F. Warranty of work:

1. The contractor agrees that

i. Materials and equipment used by the contractor and any subcontractor will be new and of good quality unless otherwise required

ii. The work will be free from defects for a period of 1 year and other than those inherent in the work as specified

iii. Work will conform to the requirements of the contract documents.

G. Site Conditions:

1. The site will be free of any debris related to the construction services at the end of the project. Cutting or welding on the ground shall not leave any markings of any kind. To prevent marking the ground it is recommended that the cutting or welding be done offsite or have a protective layer for the pavers/ concrete. Paint will be cleaned up using an outdoor faucet or away from the residence. There shall not be any paint residue left at the faucet area.

H. Materials:

1. All materials and finishes will be verified by the facility manager prior to the start of the project.

2. All materials and finishes shall be on site prior to the start of the project.

3. Contractors are prohibited from using any materials containing asbestos.

3. LABOR

1. All the work to be carried out at the site, not described in the list of the fully comprehensive work shall be calculated on a time and material basis approved by the contracting officer’s representative (COR).

2. Schedule a walkthrough with the COR at least one week prior to the completion of work for a SUBSTANTIAL COMPLETION walkthrough. This is dependent on the total length of the project. At which point the COR and the contractor will agree upon a punch list or items remaining to be completed prior to FINAL COMPLETION. Both parties will agree upon a time frame for the work to be done. At the Final Completion a walkthrough will be done

3 | P a g e and a certificate will be signed. The one year of warranty will be based upon that date.

4. Evaluation of Offers

1. Evaluation for awarding the contract shall be based upon economic offer and proven performance verified by references or already quality or work.

2. Vendor Information and Signature of Understanding

Vendor Name:

Date:

Name:

Signature:

4 | P a g e

Appendix 1

5 | P a g e

Substantial Completion Inspection

Inspecting work done so far as per the Scope of Work.

List any deficiencies needed to be completed to obtain Final Completion Certificate.

Work to be completed by Date: _____________________________

6 | P a g e

Embassy of the United States of America

Luanda, Angola

Final Completion Certificate

I, (COR) __________________ here by award (Contractor) ____________________ with a Final Completion Certificate for their work at __________________________.

The work has been deemed complete and satisfactory according to the Scope of

Work. Any and all remaining payments are authorized to be released to the contractor.

Signature _________________________ Date_______________________