Sample Task Order Performance Work Statement.pdf

PDF 2 MB Posted

Attached to
Operations, Maintenance, Repair, Replacement, Rehabilitation (OMRRR) and Operational Testing (OT) Services
Solicitation number
W912EP26RA004
Issued by

About this file

This is a Performance Work Statement (PWS) for a non-personal services contract to video inspect, clean, and re-inspect the C-44 Reservoir's Toe Trench Drainage (TTD) System located in Martin County, Florida near Indiantown. The TTD system encompasses over 48,600 feet of 12-inch dual-wall HDPE perforated pipe with 56 manholes spaced 800 to 1,100 feet apart, designed to collect and transport through-foundation seepage and groundwater to perimeter canals. The system has been accumulating iron-based sediment (ochre) since commencing operations in January 2022. The contract period is 180 calendar days from task order execution, with operations conducted Monday through Sunday, 0700 to 1900 hours, excluding federal holidays. The contractor must provide all personnel, equipment, supplies, transportation, tools, materials, and supervision necessary to perform the work.

The contractor is required to complete three primary tasks: (1) pre-inspect and video document current TTD system conditions; (2) clean and remove sediments, silts, vegetation, and debris from pipes, manholes, outfalls, and headwalls using hydro jetting equipment not exceeding 12,000 psi; and (3) post-inspect and video document conditions after cleaning. All CCTV inspections must utilize equipment capable of pan/tilt viewing with 275-degree pan and 360-degree rotation, achieving minimum 480-line resolution video with accurate footage counters, operable in fully submerged conditions, and captured in MP4 or WMV format at 852 x 480 pixels and 30 frames per second minimum. Pre-procedure submittals including cleaning procedures, CCTV inspection plans, and safety plans per EM 385 are due at least ten business days before work initiation. A government-selected test section must be completed and approved before full-scale work commences. The contractor must provide pre- and post-cleaning photographs of each manhole and headwall structure, maintain turbidity control measures, and submit all submittals to the government within two business days of task completion. De-watering and obstruction of TTD system flows are prohibited unless government-approved, and the contractor is responsible for restoring any damage resulting from cleaning operations.

View the file

Other files

File Type Posted
Sample Task Order Price Sheet.xlsx XLSX spreadsheet
Labor Rates Price Sheet.xlsx XLSX spreadsheet
Solicitation - W912EP26RA004.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT

C-44 Cont. 2 Reservoir: Toe Trench System Pre-Inspection, Cleaning and Post Inspection

1. GENERAL INFORMATION

1.1 Description of Services: This is a non-personal services contract to video inspect, clean out and video inspect the C-44 Reservoir’s Toe Trench Drainage (TTD) System. The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items to perform all services as defined in this Performance Work Statement.

1.2 Background: The TTD system is located at the downstream toe of the embankment and generally runs parallel to the embankment and reservoir perimeter canals. The TTD system is comprised of 4 main materials; drain sand, drain gravel, dual wall HDPE perforated pipe and geotextile. The reservoir is currently authorized to operate between a 3 ft and 10 ft pool. In the last 6-8 months, the reservoir pool has been between 3 ft and 5.5 ft. Along its more than 48,600 feet of HDPE perforated drainpipe, manholes are situated every 800 to 1100 feet of pipe, with a total of 56 manholes (Attachment A for locations).

Each manhole contains three pipes. Pipes within the TTD system, which run parallel to the embankment and canal, are perforated, and have an invert of El. 19 Ft. NAVD88. These pipes, which are submerged, transport any collected groundwater into the manholes. The third pipe in each manhole rests at a higher elevation (invert El. 20 ft. NAVD88). This pipe runs perpendicular to the embankment, is partially submerged, and is not perforated. The purpose of this pipe is to divert groundwater collected by the perforated pipes and drain from the manholes to the perimeter canal. The 12 – inch solid wall outfall pipe slopes downward from the manhole to an invert elevation of 19 ft. NAVD88 at the discharge point

(perimeter canal end wall).

The TTD system is designed to collect, filter, and transport through-foundation seepage/groundwater to the perimeter canals and has been operating since January 2022Dissolved solids in the groundwater, mainly iron, are present, and are accumulating in the TTD system (commonly referred to as ochre). The iron content of the groundwater is also apparent by the rusty reddish-brown color of the water in the perimeter canals.

The TTD system is comprised of the following components.

• Perforated dual wall 12-inch diameter HDPE pipe with drilled 5/16-inch perforations spaced evenly along its circumference.

• A two-stage filter composed of a drain sand and a No.57 gravel.

• A Type 1 non-woven geotextile fabric wrapped around the No. 57 gravel.

• 4 ft. inside diameter manholes

• Dual wall 12-inch diameter pipe HDPE pipe, non-perforated (manholes to perimeter canal)

• Concrete end walls along the perimeter canal.

SAMPLE

Figure 1 provides a typical plan and section view of the TTD system.

Figure 2 provides a typical cross-section of the TTD two-stage filter.

Figure 3 provides a cross-sectional view of a typical manhole structure.

Figure 4 provides a Cross-Sectional View of Concrete End-Wall Structure.

Figure 5 the location of the C-44 reservoir.

Figure 6 site location.

Figure 7 C-44 Reservoir Manhole Locations.

Figure 1: Toe Trench Drain System Typical Plan and Section View

Figure 2: Cross-Sectional View of TTD Two-Stage Filter.

Figure 3: Cross-Sectional View of Manhole.

Figure 4: Cross-Sectional View of Concrete End-Wall Structure.

1.3 Objective: The TTD system is composed of 56 – 48” manholes that provide access to 12-inch dual wall High-Density Polyethylene (HDPE) encircling the outer perimeter of the C-44 reservoir embankment. The objective of this PWS is to video document the current conditions, clean (remove foreign elements) from all pipe walls and perforations, manholes, outfalls, and gravel that immediately surrounds the perforated pipe without damaging or compromising the TTD system and video inspect completed conditions after cleaning. It is understood that all coordination and fieldwork associated with this work will be performed by Army Corps staff and Government contractors. Some adjustments to the

Contractor’s proposed procedures discussed herein should be anticipated based on the actual field conditions.

1.4 Restrictions:

1. Personal Services: The Government shall neither supervise contractor employees nor control the method by which the contractor performs the required tasks. Under no circumstances shall the

Government assign tasks to, or prepare work schedules for, individual contractor employees. It shall be the responsibility of the contractor to manage its employees and to guard against any actions that are of the nature of personal services, or give the perception of personal services. If the contractor believes that any actions constitute, or are perceived to constitute personal services, it shall be the contractor's responsibility to notify the Procuring Contracting Officer (PCO) immediately.

2. Inherently Governmental: Avoidance of Performance Closely Associated with Inherently

Governmental Functions. Task orders issued under this IDIQ Contract will receive special consideration to avoid inclusion of services which are considered closely associated with inherently governmental functions. Under no circumstances will this IDIQ Contract be utilized in a manner which would require the Contractor to manage another contractor, nor in manner such as where the Contractor might influence official evaluations of other contractors; neither directly nor indirectly.

3. Brooks-Act Prohibition: Under this contract, the Contractor is prohibited from performing architect-engineer type services which require a registration by state law. The Contractor is prohibited from performing architect-engineer type services, associated with the design or construction of real property (land and structures). The Contractor is prohibited from performing ancillary architect-engineer type services, which require supervision by a registered professional. The Contractor is prohibited from performing survey or mapping services associated with architect-engineer type planning, development construction, design, or alteration of real property.

1.5 Scope: The contractor shall furnish all materials, equipment, supplies, personnel, and all other services required to remove debris, clean out specified pipes, video inspect and document the condition of specified pipes. Services will include video inspect and document current conditions of pipe interior, removal of all materials from within and adjacent to specified pipes; disposal of other debris described below; video inspection and documentation of pipe conditions after cleaning and associated tasks. The contractor shall accomplish the complete clean out and documentation of pipe conditions to verify the pipe has been cleaned in accordance with this PWS and it’s condition post cleaning.

1.6 Period of Performance: Shall begin on the date of the task order execution and end 180 calendar days later.

1.7 Place of Performance: The project site is within the north-central area of Martin County near

Indiantown, north of the C-44 Canal at the intersection of Florida Routes 76 and 710– see Figure 4.

Figure 5: C-44 Reservoir Location

1.8 Site Access.

The field office is located on SW Minute Maid Route (27°04'31.4 "N 80°26'15.1 "W). For site access, please enter from the south using the site access road (north-south road) off SW Citrus Blvd (Figure 6:

Site Location). GPS mapping may take you to the western entrance; however, this is a gated private road.

Contact COR for access details. Please coordinate the time of arrival with POC/TPOC.

Figure 6: Site Location (NTS)

1.9 Recognized Holidays:

New Year’s Day Labor Day

Martin Luther King Jr.’s Birthday Columbus Day

President’s Day Veteran’s Day

Memorial Day Thanksgiving Day

Independence Day Christmas Day

Juneteenth SAMPLE

2. CONTRACTOR ADMINISTRATION AND MANAGEMENT

2.1 Business Relations: The contractor shall successfully integrate and coordinate all activity needed to execute the requirement. The contractor shall manage the timeliness, completeness, and quality of problem identification. The contractor shall provide corrective action plans, proposal submittals, timely identification of issues, and effective management of subcontractors. The contractor shall seek to ensure customer satisfaction and professional and ethical behavior of all contractor personnel.

2.2 Contractor Personnel, Disciplines, and Specialties: Reserved

2.3 Key Personnel: Reserved

2.4 Identification of Contractor Employees: Reserved

2.5 Subcontract Management: The contractor shall be responsible for any subcontract management necessary to integrate work performed on this requirement and shall be responsible and accountable for subcontractor performance on this requirement. The prime contractor will manage work distribution to ensure there are no Organizational Conflict of Interest (OCI) considerations. Contractors may add subcontractors to their team after notification to the KO or Contracting Officer Representative (COR).

2.6 Contractor Travel: Reserved.

3. SECURITY

3.1 Security Requirements: Reserved.

3.2 Antiterrorism/Operation Security (AT/OPSEC) Requirements: Reserved

3.3 Physical Security: Reserved

3.4 Key Control: Reserved

4. QUALITY

4.1 Quality Control:

The contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s quality control program is the means by which he assures himself that his work complies with the requirement of the contract. After acceptance of the quality control plan the contractor shall receive the contracting officer’s acceptance in writing of any proposed change to his QC system.

4.2 Quality Assurance:

The government shall evaluate the contractor’s performance under this contract in accordance with the

Performance Requirement Summary (PRS). Additionally, the Government will use a Quality Assurance

Surveillance Plan (QASP), in the inspection of the services. This plan is primarily focused on what the

Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).

4.3 Quality Assurance Surveillance Plan (QASP): The Government shall monitor the Contractors performance under this Task/Delivery Order in accordance with the Governments QASP.

4.4 Performance Requirements Summary: The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success. Note: Each task order will require a PRS as necessary for the Quality Assurance as outlined in Exhibit A.

5. GOVERNMENT CONTRACT ADMINISTRATION

5.1 Post Award Conference/Periodic Progress Meetings: Reserved

5.2 Contracting Officer Representative (COR): The (COR) will be identified by separate letter. The

COR monitors all technical aspects of the contract and assists in contract administration The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract: perform inspections necessary in connection with contract performance:

maintain written and oral communications with the Contractor concerning technical aspects of the contract: issue written interpretations of technical requirements, including Government drawings, designs, specifications: monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies; coordinate availability of government furnished property, and provide site entry of

Contractor personnel. A letter of designation issued to the COR, a copy of which is sent to the

Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.

5.3 Contractor Performance Assessment Reporting System (CPARS): This task order requires reporting in the Contractor Performance Assessment Reporting System (CPARS). Any task order awarded that is valued at greater than $1,000,000.00 is subject to reporting in CPARS. The contractor is responsible for providing and maintaining a representative in CPARS who has the authority to review and accept performance reports on behalf of the contractor.

6. OTHER REQUIREMENTS AND INFORMATION

6.1 Hours of Operation: The contractor is responsible for conducting business, anytime between the hours of 0700 to 1900 Monday thru Sunday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. For other than firm fixed price contracts, the contractor will not be reimbursed when the government facility is closed for the above reasons. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the

Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.

6.2 Other Direct Costs: Reserved.

6.3 Data Rights: Reserved.

6.4 Organizational Conflict of Interest: Contractor and subcontractor personnel performing work under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent

Organizational Conflict of Interests (OCI) as defined in FAR Subpart 9.5. The Contractor shall notify the

Contracting Officer immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the Contracting Officer to avoid or mitigate any such OCI. The Contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the Contracting Officer and in the event the Contracting Officer unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the Contracting Officer may effect other remedies as he or she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.

6.5 Phase In/Phase Out: Reserved.

7. DEFINITIONS AND ACRONYMS

7.1 Definitions:

CONTRACTOR. A supplier or vendor having a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.

CONTRACTING OFFICER. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.

CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the U.S. Government appointed by the contracting officer to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.

DELIVERABLE. All goods, out-puts, end products, services, work, work product, items, materials and property to be created, developed, produced, delivered, performed or provided by or on behalf of, or made available through, Contractor (or any agent, contractor or subcontractor of the contractor) in connection with this contract. Most deliverables take the form of a tangible product (hardware, software, data, written report, completed installation, etc.), but some can also be less tangible (meeting facilitator or custodial services).

KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.

QUALITY ASSURANCE. The government procedures to verify that services being performed by the

Contractor are performed according to acceptable standards.

QUALITY ASSURANCE Surveillance plan (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

SUBCONTRACTOR. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.

WORK WEEK. Is defined as Monday through Friday, unless specified otherwise.

7.2 Acronyms:

ACOR Alternate Contracting Officer's Representative

AFARS Army Federal Acquisition Regulation Supplement

AR Army Regulation

CCE Contracting Center of Excellence

CFR Code of Federal Regulations

CONUS Continental United States (excludes Alaska and Hawaii)

COR Contracting Officer Representative

COTR Contracting Officer's Technical Representative

COTS Commercial Off the Shelf

DA Department of the Army

DD250 Department of Defense Form 250 (Receiving Report)

DD254 Department of Defense Contract Security Requirement List

DFARS Defense Federal Acquisition Regulation Supplement

DMDC Defense Manpower Data Center

DOD Department of Defense

FAR Federal Acquisition Regulation

HIPAA Health Insurance Portability and Accountability Act of 1996

KO Contracting Officer

OCI Organizational Conflict of Interest

OCONUS Outside Continental United States (includes Alaska and Hawaii)

ODC Other Direct Costs

PIPO Phase In/Phase Out

POC Point of Contact

PRS Performance Requirements Summary

PWS Performance Work Statement

QA Quality Assurance

QAP Quality Assurance Program

QASP Quality Assurance Surveillance Plan

QC Quality Control

QCP Quality Control Program

8. GOVERNMENT FURNISHED PROPERY, EQUIPMENT, SERVICES AND MATERIALS

8.1 Property. Reserved

8.2 Equipment. Reserved

8.3 Services. Reserved

8.4 Materials. Reserved

9. CONTRACTOR REQUIREMENTS

9.1 Contractor Furnished Items.

9.1.1 Materials temporarily needed to perform the work. (i.e. portable toilets, sediment control, turbidity screens, traffic control devices, others)

9.1.2 Equipment including: jet/vac equipment, dewatering pumps, fuel tank, tool trailers, water trucks and other as needed.

9.2 Submittals.

9.2.1 Safety Plans per EM 385 to include but not limited to: accident prevention plan, activity hazard analysis for vehicle, confined space entry, equipment & power tool operations, excavation, fuel, crane lift & placement, PPE, traffic control, rigging, other.

9.2.2 Pipe cleaning work plan, work schedule, quality control plan, video inspection plan, others. See Section 10.2.7 for more details on submittals.

10. PERFORMANCE REQUIREMENTS

10.1 Basic Services: The contractor shall provide services to: pre-inspect and document current conditions, remove of all materials from within and adjacent to specified pipes; removal & appropriate disposal of other debris; video inspection and documentation of pipe conditions and associated tasks.

10.2 Specific Services:

Figure 6 shows the location map of the manholes. Attachment A contains the as-builts drawing for the

TTD system including the northing, and easting, invert of TTD pipe, manhole bottom, and perimeter canal outfalls information. Table 1 displays the approximated distances between adjacent manholes.

Please note that the distances reflected within Table 1 is by project centerline stationing and does not represent the actual distance between manholes with curves or bends. De-watering of the perforated 12 in diameter HDPE pipe is prohibited during any phase of the cleaning and/or CCTV operation. Obstructing, using end caps, inflatable packers, or similar methods that block TTD system flows during any phase of the cleaning and/or CCTV inspection process is prohibited unless otherwise deemed necessary and approved by the Government. During cleaning and preparations, the Contractor is required to undertake the proper precautions to protect the TTD system and surrounding areas from damage. The Contractor is responsible for restoring any damage, which resulted from cleaning or preparation operations to pre-existing conditions.

The Contractor is required to adhere to the following requirements for all cleaning operations.

• The Contractor must provide pre and post cleaning photographs of each manhole and headwall structure to the Government.

• The Contractor cannot commence work until a successful test section has been completed and approved by the Government.

• The Contractor must provide a procedure for preventing contaminations from active cleaning operations of the manhole, headwall, outfall, and TTD systems from infiltrating into previously cleaned manhole, headwall, outfall, and TTD systems.

• The Contractor can clean only the concrete components of the headwall structure.

Figure 7: C-44 Reservoir Manhole Locations

The following will be clean for each manhole area.

a. TTD HDPE Pipes.

b. Outfall Pipe.

c. Manhole.

d. Outfall Pipe Headwall.

Table 1: Manhole to Manhole Distances

Canal Outfall Station MH to MH Distance (ft.) *

WRPC MH-1 0+64 MH-1 to MHPS-1 730

WRPC MHPS-1 7+94 MHPS-1 to MHPS-2 719

ERPC MHPS-2 15+13 MHPS-2 to MH-2 753

ERPC MH-2 22+66 MH-2 to MHMBR-1 875

ERPC MHMBR-1

31+40

MHMBR-1 to

MHMBR-2 709

ERPC MHMBR-2 38+49 MHMBR-2 to MH-3 1,006

ERPC MH-3 48+55 MH-3 to MH-4 890

ERPC MH-4 57+45 MH-4 to MH-5 880

ERPC MH-5 66+25 MH-5 to MH-6 880

ERPC MH-6 75+05 MH-6 to MH-7 880

ERPC MH-7 83+85 MH-7 to MH-8 880

ERPC MH-8 92+65 MH-8 to MH-9 880

ERPC MH-9 101+45 MH-9 to MH-10 880

ERPC MH-10 110+25 MH-10 to MH-11 880

ERPC MH-11 119+05 MH-11 to MH-12 880

ERPC MH-12 127+85 MH-12 to MHDS-1 936

ERPC MHDS-1 137+21 MHDS-1 to MHDS-2 679

WRPC MHDS-2 143+99 MHDS-2 to MH-13 925

WRPC MH-13 153+24 MH-13 to MH-14 981

WRPC MH-14 163+05 MH-14 to MH-15 880

WRPC MH-15 171+86 MH-15 to MH-16 880

WRPC MH-16 180+65 MH-16 to MH-17 880

WRPC MH-17 189+46 MH-17 to MH-18 880

WRPC MH-18 198+25 MH-18 to MH-19 880

WRPC MH-19 207+05 MH-19 to MH-20 880

WRPC MH-20 215+85 MH-20 to MH-21 880

WRPC MH-21 224+65 MH-21 to MH-22 880

WRPC MH-22 233+45 MH-22 to MHR-1 880

WRPC MHR-1 242+25 MHR-1 to MH-23 880

WRPC MH-23 251+05 MH-23 to MH-24 881

WRPC MH-24 259+86 MH-24 to MH-25 879

WRPC MH-25 268+65 MH-25 to MH-26 881

WRPC MH-26 277+45 MH-26 to MH-27 880

WRPC MH-27 286+25 MH-27 to MH-28 880

WRPC MH-28 295+05 MH-28 to MH-29 880

WRPC MH-29 303+85 MH-29 to MH-30 880

WRPC MH-30 312+66 MH-30 to MH-31 880

WRPC MH-31 321+45 MH-31 to MHR-2 880

WRPC MHR-2 330+25 MHR-2 to MH-32 880

WRPC MH-32 339+05 MH-32 to MH-33 880

WRPC MH-33 347+85 MH-33 to MH-34 880

WRPC MH-34 356+65 MH-34 to MH-35 880

WRPC MH-35 365+45 MH-35 to MH-36 880

WRPC MH-36 374+25 MH-36 to MH-37 880

WRPC MH-37 383+05 MH-37 to MH-38 880

WRPC MH-38 391+85 MH-38 to MH-39 880

Canal Outfall Station MH to MH Distance (ft.) *

WRPC MH-39 400+65 MH-39 to MH-40 880

WRPC MH-40 409+45 MH-40 to MH-41 880

WRPC MH-41 418+25 MH-41 to MHR-3 880

WRPC MHR-3 427+05 MHR-3 to MH-42 880

WRPC MH-42 435+85 MH-42 to MH-43 880

WRPC MH-43 444+65 MH-43 to MH-44 880

WRPC MH-44 453+45 MH-44 to MH-45 880

WRPC MH-45 462+25 MH-45 to MH-46 880

WRPC MH-46 471+05 MH-46 to MH-47 880

WRPC MH-47 479+85 MH-47 to MH-1 729

* Distances featured within Table 1 are by project centerline stationing and do not represent the actual distance between manholes around curves or bends.

2. Closed Circuit Television Video (CCTV):

The Contractor is required to produce a high-quality well lit, sharply focused, and color balanced video with the following requirements for all CCTV inspections. The Government reserves the right to designate which TTD system segments will be inspected.

a. Utilize a video camera system specifically engineered and manufactured for CCTV inspections.

b. The video camera system produces a video, which uses pan and tilt radial viewing.

c. Provide a video camera system with the capacity to pan a minimum of 275 degrees and rotate 360 degrees.

d. Provide a camera that is operable in fully submerged conditions.

e. Provide a camera with an accurate footage counter which displays on the monitor and video recording the exact distance the camera has traveled to the nearest 1/10 of a foot.

f. Provide a video recording with a minimum 480 lines of resolution.

g. Provide a camera with a height adjustment so that the camera lens is typically centered within the pipe.

h. Provide adequate lighting for the camera that is required to create a clear color accurate picture of the entire periphery of the pipe.

i. Provide an accompanying computer and recording device capable of projecting and recording the project name, project location, date of inspection, time of inspection, operator name, direction of survey (upstream or downstream), manhole ID numbers (i.e. from MH-1 to MH-2), and ongoing footage and velocity (feet per minute) indicator onto the video screen.

j. The video recording continuously display manhole to manhole line segment, date of inspection, time of inspection, ongoing footage and velocity (feet per minute) counters onto the video screen for the duration of the inspection.

k. The video camera will be set to 0.00 feet at the entry point or beginning of each manhole-to-manhole line segment and/or TTD outfall.

l. Camera movement speeds through the line segment will be moderate and not to exceed a maximum velocity of 30 feet per minute.

m. Provide a full 360-degree view of the pipe, joints, and service connections.

n. The contractor employs manual winches, power winches, cable, powered rewinds, or other devices that do not obstruct the camera view or interfere with camera operations or CCTV inspection of the pipe conditions as the camera is moved through the TTD system.

o. If any minor defect of the TTD system is detected or identified by the Contractor temporarily halt the camera at each location and provide clear and color accurate video documentation of the defect or obstruction to the Government.

p. If any major defect of the TTD system is detected or identified which obstructs the continuation of the CCTV or cleaning operation immediately notify the Government and halt all work activities.

q. Capture an inspection video in either MP4 or Windows Media Video (WMV) format with a minimum resolution of 852 x 480 Pixels and an interlaced frame rate at a minimum of 30 frames per second.

3. Equipment.

The equipment, listed below, serves as a recommendation and additional equipment may be required.

The contractor is responsible for sourcing the equipment required to perform the job.

a. Hydro Jetting Equipment: All high-velocity pipe cleaning equipment will be constructed for ease and safety. The equipment will not damage the pipe or any of the surroundings.

Either a stationary nozzle or rotating nozzle can be used. The equipment hose and nozzle will be able to fit thru turns that are 25-45 degrees. A nozzle's maximum time to remain stationary in a pipeline should not exceed 60 seconds. All hydro jetting equipment is not exceeding a maximum of 12,000 psi within the perforated and solid wall HDPE pipes.

Equipment also includes a high-velocity gun for washing and scouring manhole walls, floors, and headwalls. The gun has to be capable of producing flows from a fine to solid spray without causing damage to the manhole walls, floors, and headwalls.

b. Sump Pump

c. CCTV Inspection Equipment

d. Other equipment

4. Water Quality.

The contractor is permitted to source water from the perimeter canal. Cleaning products or chemicals, which are in accordance with Federal and State regulations, are permitted upon approval by the

Government.

5. Turbidity

The Contractor has to conduct his operations in a manner to minimize turbidity. If monitoring reveals levels greater than the State water quality standard for turbidity, the contractor should find a way to reduce the turbidity prior to continuation of cleaning operations. The contractor provides turbidity barriers of sufficient buoyancy to prevent the top of the barrier from submerging under any water and wind conditions. If the top of the barrier becomes submerged for any reason, the Contractor has to suspend cleaning operations until the condition is corrected.

6. Cleaning Up.

The contractor has to clean up daily and leave the site equipment, tools, and material in a safe and secure area outside of the reservoir footprint.

7. Reporting.

The Contractor is required to submit the following information to the Government for review.

a. Pre-Procedure Submittals:

i. Submittals which are required prior to start of any work, includes schedules, tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work. Pre-procedure submittals are submitted at least 10 business days before initiation day.

These submittals should be provided and approved by the Government prior to initiation.

1. Cleaning Procedure Plan for the TTD System, Manholes, Headwalls, and

Outfalls.

2. Procedure Plan for CCTV inspection of TTD System.

b. Submittals:

i. The following submittals will be provided to the Government for review.

1. Test Section Results:

a. Photographs/descriptions-Pre and post cleaning of Government selected manhole and headwall cleanings. The government reserves the right to request additional cleanings of previously cleaned manhole and headwall segments.

b. CCTV-Pre and post cleaning CCTV inspection videos of

Government selected TTD system sections. The contractor is responsible for submitting high-quality visible video recordings, which adhere to all the video requirements as detailed within the

Closed-Circuit Television (CCTV) section

2. Cleaning:

a. Photographs/description of observation—Pre and post of manhole and headwall cleaning. The government reserves the right to request additional cleanings of previously cleaned manhole and headwall segments. Unless otherwise approved, provide the submittal to the government within 2 business days of completing cleaning.

3. CCTV Inspection:

The contractor is responsible for submitting high-quality visible video recordings, which adhere to all the video requirements as detailed within the Closed-Circuit Television (CCTV) section. The Contractor will provide descriptions and snapshots of any abnormalities observed during the inspection of TTD system, manholes, headwalls, and outfalls. Unless otherwise approved, provide Pre or Post CCTV inspection submittals and videos to the government within 2 business days of completing an inspection. The

Government reserves the right to request additional cleanings of previously cleaned TTD segments after reviewing post CCTV inspection recordings. The Government reserves the right to request additional

CCTV inspections of TTD segments which required more than one cleaning.

10.3 Task Heading and Standards:

8. Task 0 / Test Section. The contractor shall perform Tasks 1 to 3 on a manhole selected by the government to demonstrate all aspects of the work defined in this PWS. Unless otherwise approved, CCTV and cleaning shall be performed from the nearest manholes adjacent to the one selected and to the outfall of the selected manhole.

9. Task 1 / Inspect Current Conditions of TTD at C-44. The Contractor shall video inspect and document the current condition of the entire Toe Trench Drain System. . Video inspect all pipes extending from a manhole in their entirety and submit the pre-cleaning inspection submittal to the

Government prior to performing any cleaning.

10. Task 2/ Clean TTD at C-44. The Contractor shall clean and remove sediments, silts, vegetation

& other debris from the Toe Trench Drain System. Although not anticipated, if existing damage to the pipe is found during the pre-inspection, no cleaning shall be performed prior to receiving direction from the government.

11. Task 3 / Re-Inspect TTD at C-44. The Contractor shall video inspect and document the post cleaning condition of the entire Toe Trench Drain System and submit the post-cleaning inspection submittal.

11. REGULATIONS AND PUBLICATIONS

The Contractor must abide by all applicable regulations, publications, manuals, and local policies and procedures.

Technical Publications: All work performed under this contract shall be in accordance with the following publications, and contractor's personnel shall be familiar with and comply with same.

• Corps of Engineers Manual EM 385-1-1 - Safety and Health Requirements Manual.

• Corps of Engineers, Labor Relations Manual ER 1180-1-8.

• Quality Assurance Representatives Guide EP 415-1-261, Volumes 1 through 4.

• Department of the Army, Engineering Regulation ER 1180-1-6, 30 September 1995.

• Construction Quality Management.

• SAD QA Manual

12. CONTRACTOR MANPOWER AND REPORTING: Reserved.