About this file
Performance Bond Summary
This is a Performance Bond template document applicable to the City of Meriden's Edison Middle School Roof Replacement project. The bond serves as a financial guarantee that the selected contractor will promptly and faithfully perform all obligations under the roofing contract. The bond is required in an amount equal to one hundred percent of the contract price, estimated at approximately $5,946,600 based on architectural cost estimates. The contractor must submit the performance bond concurrent with execution of the contract, with the bond remaining in effect throughout the project duration until final completion and payment. The bond includes a two-year statute of limitations for claims from the final payment date, and the surety waives notice of any contract alterations, defaults, or extensions of time made by the Owner. The bonding company agrees to either remedy contractor defaults or arrange for completion of the work by another qualified contractor, with costs deducted from the remaining contract balance.
The performance bond obligates the contractor and surety jointly and severally to ensure completion of the roof replacement work in accordance with all contract specifications, drawings, and conditions, including the installation of TPO or PVC membrane roofing covering approximately 111,920 square feet, removal and replacement of deteriorated decking, installation of roof insulation, flashings, and accessories. The bond protects the City of Meriden's interests by providing financial recourse should the contractor fail to complete the project or meet contractual obligations, including adherence to the substantial completion deadline of 15 days after Notice to Proceed with final completion 15 days thereafter, prevailing wage requirements, minority and small business enterprise set-asides, and all quality assurance and control requirements specified in the contract documents.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE BOND
KNOW ALL MEN BY THESE PRESENTS, that (here insert full name and address or legal title of Contractor) as Principal herinafter called contractor and (here insert full name and address or legal title of Surety
As Surety, hereinafter called Surety, are held and firmly bound unto (here insert full name and address or legal title of Owner)
As Obligee, hereinafter called Owner, in the amount of
Dollars $___________________________ for the payment whereof Contractor and Surety bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
WHEREAS,
Contractor has by written agreement dated 20 , entered into a contract with Owner for (here insert full name, address and description of project)
In accordance with Drawings and Specifications prepared by (here insert full name and address or legal title of Engineer/Architect)
Which contract is by reference made a part hereof, and is hereinafter referred to as the Contract.
PERFORMANCE BOND
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that, if Contractor, shall promptly and faithfully perform said Contract, then this obligation shall be null and void; otherwise it shall remain in full force and effect.
The Surety hereby waives, notice of any alteration or defaults, under the contract or contracts of completion extension of time made by the Owner. arranged under this paragraph sufficient funds to pay the cost of completion less the balance of the contract price;
Whenever Contractor shall be, and declared by Owner but not exceeding, including other costs and damages to be in default under the Contract, the Owner having for which the Surety may be liable hereunder, the amount performed Owner’s obligations thereunder, the surety set forth in the first paragraph hereof. The term “balance may promptly remedy the default, or shall promptly of the contract price,” as used in this paragraph, shall mean the total amount payable by Owner to Contractor
1) Complete the Contract in accordance with its terms under the Contract and any amendments thereto, less and conditions, or the amount properly paid by Owner to Contractor.
2) Obtain a bid or bids for completing the Contract in Any suit under this bond must be instituted before accordance with its terms and conditions, and upon de- the expiration of two (2) years from the date on which termination by Surety of the lowest responsible bidder, final payment under the Contract falls due.
or, if the Owner elects, upon determination by the Owner and the Surety jointly of the lowest responsible No right of action shall accrue on this bond to or for bidder, arrange for a contract between such bidder and the use of any person or corporation other than the Owner, and make available as Work progresses (even Owner named herein or the heirs, executors, adminis-though there should be a default of a succession of trators or successors of the Owner.