This document is a Performance Bond template that outlines the legal agreement between a Contractor, Surety, and Owner. The bond serves as a guarantee that the Contractor will faithfully perform the contracted work according to specified terms and conditions. While the specific project details are left blank to be filled in, the template indicates that the bond covers a contract involving drawings and specifications prepared by an Engineer/Architect, with the Surety providing financial protection to the Owner in case of Contractor default.

The Performance Bond establishes key provisions including the Surety's obligations if the Contractor fails to complete the project, such as completing the contract, obtaining new bids, or arranging a new contract with another bidder. The bond includes a two-year statute of limitations for legal action, restricts right of action to only the named Owner, and allows the Surety to waive notice of contract alterations or time extensions. The bond's monetary value and specific project details would be inserted into the blank spaces in the actual executed document, making this a standard legal form for protecting the Owner's interests in a construction or service contract.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE BOND

KNOW ALL MEN BY THESE PRESENTS, that (here insert full name and address or legal title of Contractor) as Principal herinafter called contractor and (here insert full name and address or legal title of Surety

As Surety, hereinafter called Surety, are held and firmly bound unto (here insert full name and address or legal title of Owner)

As Obligee, hereinafter called Owner, in the amount of

Dollars $___________________________ for the payment whereof Contractor and Surety bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.

WHEREAS,

Contractor has by written agreement dated 20 , entered into a contract with Owner for (here insert full name, address and description of project)

In accordance with Drawings and Specifications prepared by (here insert full name and address or legal title of Engineer/Architect)

Which contract is by reference made a part hereof, and is hereinafter referred to as the Contract.

PERFORMANCE BOND

NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that, if Contractor, shall promptly and faithfully perform said Contract, then this obligation shall be null and void; otherwise it shall remain in full force and effect.

The Surety hereby waives, notice of any alteration or defaults, under the contract or contracts of completion extension of time made by the Owner. arranged under this paragraph sufficient funds to pay the cost of completion less the balance of the contract price;

Whenever Contractor shall be, and declared by Owner but not exceeding, including other costs and damages to be in default under the Contract, the Owner having for which the Surety may be liable hereunder, the amount performed Owner’s obligations thereunder, the surety set forth in the first paragraph hereof. The term “balance may promptly remedy the default, or shall promptly of the contract price,” as used in this paragraph, shall mean the total amount payable by Owner to Contractor

1) Complete the Contract in accordance with its terms under the Contract and any amendments thereto, less and conditions, or the amount properly paid by Owner to Contractor.

2) Obtain a bid or bids for completing the Contract in Any suit under this bond must be instituted before accordance with its terms and conditions, and upon de- the expiration of two (2) years from the date on which termination by Surety of the lowest responsible bidder, final payment under the Contract falls due.

or, if the Owner elects, upon determination by the Owner and the Surety jointly of the lowest responsible No right of action shall accrue on this bond to or for bidder, arrange for a contract between such bidder and the use of any person or corporation other than the Owner, and make available as Work progresses (even Owner named herein or the heirs, executors, adminis-though there should be a default of a succession of trators or successors of the Owner.

Signed and sealed this day of 20