Sample_Agreement.pdf
PDF 660 KB Posted
- Attached to
- Alberta Road Reconstruction Phase III
- Solicitation number
- RFP 2027-10
- Issued by
- Hidalgo County, Texas
About this file
This Agreement Between Owner and Contractor is a construction contract executed by the City of Edinburg for the Alberta Road Reconstruction Phase III project (RFP 2027-10). The project consists of constructing a raised concrete median along Closner Boulevard, concrete riprap, sidewalk improvements, and paving work along Alberta Road between Closner Boulevard and I-69C, including roadway reconstruction and mill-and-overlay resurfacing. The contractor must furnish all labor, materials, equipment, supervision, traffic control, and permits necessary for completion. The work is divided into four milestones: (1) concrete median along Closner Boulevard within 60 days of Notice to Proceed; (2) roadwork along Alberta Road between Closner Boulevard and I-69C within 60 days of section start date; (3) concrete riprap, sidewalk, and handrails at the drainage canal on the south side of Alberta Road within 30 days of section start date; and (4) punch list completion within 30 days of Substantial Completion. Substantial Completion is required within 150 days of Notice to Proceed, with final completion within 30 days thereafter. The contract is effective December 2026 and is designed by South Texas Infrastructure Group, LLC, which serves as the Engineer and Owner's representative.
The contract pricing is based on unit price work and lump sum amounts to be specified in the contractor's bid. Progress payments are made monthly on or about the 25th day at 95 percent of completed work value, with 5 percent retainage held until Substantial Completion. Upon Substantial Completion, the Owner pays an amount to reach 100 percent of work completed, less 200 percent of the punch list value. Liquidated damages for delays range from $100 to $800 per day depending on contract amount, with additional special damages recoverable for Owner's costs in engineering, observation, inspection, and administration services. The contractor must obtain a performance bond and payment bond prior to execution. The contract requires the contractor to have examined all contract documents, visited the site, and become familiar with local conditions and applicable laws and regulations. A 0 percent interest rate applies to unpaid amounts past due. Contract documents include General Conditions (EJCDC C-700, 2018), Supplementary Conditions, Specifications, and drawings consisting of multiple sheets titled "Alberta Rd Reconstruction Phase III & Intersection w/ Closner Blvd," along with Addenda 1-6.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF EDINBURG AGREEMENT
00500 - 1
Document 00500
AGREEMENT BETWEEN OWNER AND CONTRACTOR
FOR CONSTRUCTION CONTRACT
This Agreement is by and between CITY OF EDINBURG (“Owner”) and (Contractor Name) (“Contractor”).
Terms used in this Agreement have the meanings stated in the General Conditions and the Supplementary Conditions.
Owner and Contractor hereby agree as follows:
WORK
1.01 Contractor shall complete all Work as specified or indicated in the Contract Documents.
The Work is generally described as follows: The Contractor shall furnish all labor, materials, equipment, supervision, traffic control, permits, and incidentals necessary to construct and install the complete and operational roadway and drainage improvements for the Project, including concrete medians, concrete rip rap, sidewalk, pavement reconstruction, pavement resurfacing (mill and overlay), pavement striping, and SWPPP measures.
1.02 Contractor is responsible for requesting a permit from the City of Edinburg – Permits Department in a timely manner as soon as a Notice to Proceed is issued.
THE PROJECT
2.01 The Project, of which the Work under the Contract Documents is a part, is generally described as follows: RFP 2027-10 – Alberta Road Reconstruction Phase III
ENGINEER
3.01 The Owner has retained South Texas Infrastructure Group, LLC. (“Engineer”) to act as Owner’s representative, assume all duties and responsibilities of Engineer, and have the rights and authority assigned to Engineer in the Contract.
3.02 The part of the Project that pertains to the Work has been designed by South Texas Infrastructure Group, LLC.
CONTRACT TIMES
4.01 Time is of the Essence
A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract.
00500 - 2
4.02 Contract Times: Dates
A. The Work will be substantially complete on or before (Date) (150 days from Notice to Proceed), and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before (Date) (30 days from Substantial Completion).
4.03 Milestones
A. Parts of the Work must be substantially completed on or before the following Milestone(s):
1. Milestone 1: Concrete median along Closner Boulevard to be completed within 60 days from the Notice to Proceed.
2. Milestone 2: Roadwork along Alberta Road between Closner Boulevard and I- 69C to be completed within 60 days from the section start date. The section start date shall be the earlier of the first day on which the work for the section begins or the date provided to Contractor by Owner in a Notice to Proceed.
3. Milestone 3 / Substantial Completion: Concrete rip rap, sidewalk, and handrails at the drainage canal located on the south side of Alberta Rd, located approximately 1,250 linear feet west of the intersection of Sugar Rd and Alberta Rd, to be completed within 30 days from the section start date. The section start date shall be the earlier of the first day on which the work for the section begins or the date provided to Contractor by Owner in a Notice to Proceed.
4. Milestone 4 / Final Completion: Punch list to be completed within 30 days from the Substantial Completion.
4.04 Liquidated Damages
A. Contractor and Owner recognize that time is of the essence as stated in Paragraph 4.01 above and that Owner will suffer financial and other losses if the Work is not completed and Milestones not achieved within the Contract Times, as duly modified. The parties also recognize the delays, expense, and difficulties involved in proving, in a legal proceeding, the actual loss suffered by Owner if the Work is not completed on time. Accordingly, instead of requiring any such proof, Owner and Contractor agree that as liquidated damages for delay (but not as a penalty):
1. Substantial Completion: Contractor shall pay Owner based on fees below for each day that expires after the time (as duly adjusted pursuant to the Contract) specified above for Substantial Completion, until the Work is substantially complete.
For Contract of Amount Cost Per Day
$5,000.00 To $25,000.00 $100.00
$25,000.01 To $100,000.00 $200.00
$100,000.01 To $500,000.00 $250.00
00500 - 3
$500,000.01 To $1,000,000.00 $300.00
$1,000,000.01 To $2,000,000.00 $400.00
$2,000,000.01 To $3,000,000.00 $500.00
$3,000,000.01 To $4,000,000.00 $600.00
$4,000,000.01 To $5,000,000.00 $700.00
$5,000,000.01 And Over $800.00
2. Completion of Remaining Work: After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times (as duly adjusted pursuant to the Contract) for completion and readiness for final payment, Contractor shall pay Owner $XX for each day that expires after such time until the Work is completed and ready for final payment.
3. Liquidated damages for failing to timely attain Milestones, Substantial Completion, and final completion are not additive, and will not be imposed concurrently.
B. If Owner recovers liquidated damages for a delay in completion by Contractor, Owner is not precluded from recovering other damages, whether actual, direct, excess, or consequential, for such delay, including for special damages (if any) specified in this Agreement.
4.06 Special Damages
A. Contractor shall reimburse Owner (1) for any fines or penalties imposed on Owner as a direct result of the Contractor’s failure to attain Substantial Completion according to the Contract Times, and (2) for the actual costs reasonably incurred by Owner for engineering, construction observation, inspection, and administrative services needed after the time specified in Paragraph 4.02 for Substantial Completion (as duly adjusted pursuant to the Contract), until the Work is substantially complete.
B. After Contractor achieves Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times, Contractor shall reimburse Owner for the actual costs reasonably incurred by Owner for engineering, construction observation, inspection, and administrative services needed after the time specified in Paragraph 4.02 for Work to be completed and ready for final payment (as duly adjusted pursuant to the Contract), until the Work is completed and ready for final payment.
C. The special damages imposed in this paragraph are supplemental to any liquidated damages for delayed completion established in this Agreement.
00500 - 4
CONTRACT PRICE
5.01 Owner shall pay Contractor for completion of the Work in accordance with the Contract Documents, the amounts that follow, subject to adjustment under the Contract:
A. For all Work other than Unit Price Work, a lump sum of N/A.
All specific cash allowances are included in the above price in accordance with Paragraph 13.02 of the General Conditions.
B. For all Unit Price Work, an amount equal to the sum of the extended prices (established for each separately identified item of Unit Price Work by multiplying the unit price times the actual quantity of that item).
Unit Price Work (Base Bid) Item No. Description Unit Estimated
Quantity Unit Price
Extended Price
1 24” H.P. DRAIN PIPE (EXAMPLE) LF 700 $46.50 $32,550.00
Total of all Extended Prices for Unit Price Work (subject to final adjustment based on actual quantities) $XX
The extended prices for Unit Price Work set forth as of the Effective Date of the Contract are based on estimated quantities. As provided in Paragraph 13.03 of the General Conditions, estimated quantities are not guaranteed, and determinations of actual quantities and classifications are to be made by Engineer.
C. Total of Lump Sum Amount and Unit Price Work (subject to final Unit Price adjustment) $XX.
D. For all Work, at the prices stated in Contractor’s Bid, attached hereto as an exhibit.
PAYMENT PROCEDURES
6.01 Submittal and Processing of Payments
A. Contractor shall submit Applications for Payment in accordance with Article 15 of the General Conditions. Applications for Payment will be processed by Engineer as provided in the General Conditions.
6.02 Progress Payments; Retainage
A. Owner shall make progress payments on the basis of Contractor’s Applications for Payment on or about the 25th day of each month during performance of the Work as provided in Paragraph 6.02.A.1 below, provided that such Applications for Payment have been submitted in a timely manner and otherwise meet the requirements of the Contract. All such payments will be measured by the Schedule of Values
00500 - 5 established as provided in the General Conditions (and in the case of Unit Price Work based on the number of units completed) or, in the event there is no Schedule of Values, as provided elsewhere in the Contract.
1. Prior to Substantial Completion, progress payments will be made in an amount equal to the percentage indicated below but, in each case, less the aggregate of payments previously made and less such amounts as Owner may withhold, including but not limited to liquidated damages, in accordance with the Contract.
a. 95 percent of the value of the Work completed (with the balance being retainage); and
b. 95 percent of cost of materials and equipment not incorporated in the Work (with the balance being retainage).
B. Upon Substantial Completion, Owner shall pay an amount sufficient to increase total payments to Contractor to 100 percent of the Work completed, less such amounts set off by Owner pursuant to Paragraph 15.01.E of the General Conditions, and less 200 percent of Engineer’s estimate of the value of Work to be completed or corrected as shown on the punch list of items to be completed or corrected prior to final payment.
6.03 Final Payment
A. Upon final completion and acceptance of the Work, Owner shall pay the remainder of the Contract Price in accordance with Paragraph 15.06 of the General Conditions.
6.04 Consent of Surety
A. Owner will not make final payment, or return or release retainage at Substantial Completion or any other time, unless Contractor submits written consent of the surety to such payment, return, or release.
6.05 Interest
A. All amounts not paid when due will bear interest at the rate of 0 percent per annum.
CONTRACT DOCUMENTS
7.01 Contents
A. The Contract Documents consist of all of the following:
1. This Agreement.
2. Bonds:
a. Performance bond (together with power of attorney).
b. Payment bond (together with power of attorney).
3. General Conditions.
4. Supplementary Conditions.
00500 - 6
5. Specifications as listed in the table of contents of the project manual (copy of list attached).
6. Drawings (not attached but incorporated by reference) consisting of xx sheets with each sheet bearing the following general title: Alberta Rd Reconstruction Phase III & Intersection w/ Closner Blvd.
7. Addenda (numbers 1 to 6, inclusive).
8. The following which may be delivered or issued on or after the Effective Date of the Contract and are not attached hereto:
a. Notice to Proceed.
b. Work Change Directives.
c. Change Orders.
d. Field Orders.
e. Warranty Bond, if any.
B. The Contract Documents listed in Paragraph 7.01.A are attached to this Agreement (except as expressly noted otherwise above).
C. There are no Contract Documents other than those listed above in this Article 7.
D. The Contract Documents may only be amended, modified, or supplemented as provided in the Contract.
REPRESENTATIONS, CERTIFICATIONS, AND STIPULATIONS
8.01 Contractor’s Representations
A. In order to induce Owner to enter into this Contract, Contractor makes the following representations:
1. Contractor has examined and carefully studied the Contract Documents, including Addenda.
2. Contractor has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.
3. Contractor is familiar with all Laws and Regulations that may affect cost, progress, and performance of the Work.
4. Contractor has carefully studied the reports of explorations and tests of subsurface conditions at or adjacent to the Site and the drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the Supplementary Conditions, with respect to the Technical Data in such reports and drawings.
5. Contractor has carefully studied the reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, with respect to Technical Data in such reports and drawings.
00500 - 7
6. Contractor has considered the information known to Contractor itself;
information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Contract Documents; and the Technical Data identified in the Supplementary Conditions or by definition, with respect to the effect of such information, observations, and Technical Data on (a) the cost, progress, and performance of the Work; (b) the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor; and (c) Contractor’s safety precautions and programs.
7. Based on the information and observations referred to in the preceding paragraph, Contractor agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract.
8. Contractor is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Contract Documents.
9. Contractor has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Contractor has discovered in the Contract Documents, and of discrepancies between Site conditions and the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.
10. The Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.
11. Contractor’s entry into this Contract constitutes an incontrovertible representation by Contractor that without exception all prices in the Agreement are premised upon performing and furnishing the Work required by the Contract Documents.
8.02 Contractor’s Certifications
A. Contractor certifies that it has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for or in executing the Contract. For the purposes of this Paragraph 8.02:
1. “corrupt practice” means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process or in the Contract execution;
2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process or the execution of the Contract to the detriment of Owner, (b) to establish Bid or Contract prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition;
3. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish Bid prices at artificial, non-competitive levels; and
00500 - 8
4. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.
8.03 Standard General Conditions
A. Owner stipulates that if the General Conditions that are made a part of this Contract are EJCDC® C-700, Standard General Conditions for the Construction Contract (2018), published by the Engineers Joint Contract Documents Committee, and if Owner is the party that has furnished said General Conditions, then Owner has plainly shown all modifications to the standard wording of such published document to the Contractor, through a process such as highlighting or “track changes” (redline/strikeout), or in the Supplementary Conditions. The Supplementary Conditions may also the terms, conditions and provisions of the General Conditions.
00500 - 9
IN WITNESS WHEREOF, Owner and Contractor have signed this Agreement.
This Agreement will be effective on December ____, 2026 (which is the Effective Date of the Contract).
Owner: Contractor:
City of Edinburg (typed or printed name of organization) (typed or printed name of organization)
By: By:
(individual’s signature) (individual’s signature) Date: Date:
(date signed) (date signed) Name: Name:
(typed or printed) (typed or printed)
Title: Title:
(typed or printed) (typed or printed)
(If (Contractor Name) is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.)
Attest: Attest:
(individual’s signature) (individual’s signature) Title: Title:
(typed or printed) (typed or printed) Address for giving notices: Address for giving notices:
City of Edinburg
415 W. University Drive
Edinburg, TX 78539 Designated Representative: Designated Representative:
Name: Name:
(typed or printed) (typed or printed)
Title: Title:
(typed or printed) (typed or printed) Address: Address:
Phone: Phone:
Email: Email:
(If City of Edinburg is a public body, attach evidence of authority to sign and resolution or other documents authorizing execution of this Agreement.)
License No.:
(where applicable)
State:
00500 - 10
Page Intentionally Blank
| WORK |
| 1.01 Contractor shall complete all Work as specified or indicated in the Contract Documents. The Work is generally described as follows: The Contractor shall furnish all labor, materials, equipment, supervision, traffic control, permits, and incidenta... |
| 1.02 Contractor is responsible for requesting a permit from the City of Edinburg – Permits Department in a timely manner as soon as a Notice to Proceed is issued. |
| THE PROJECT |
| 2.01 The Project, of which the Work under the Contract Documents is a part, is generally described as follows: RFP 2027-10 – Alberta Road Reconstruction Phase III |
| ENGINEER |
| 3.01 The Owner has retained South Texas Infrastructure Group, LLC. (“Engineer”) to act as Owner’s representative, assume all duties and responsibilities of Engineer, and have the rights and authority assigned to Engineer in the Contract. |
| 3.02 The part of the Project that pertains to the Work has been designed by South Texas Infrastructure Group, LLC. |
| CONTRACT TIMES |
| 4.01 Time is of the Essence |
| A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract. |
| 4.02 Contract Times: Dates |
| A. The Work will be substantially complete on or before (Date) (150 days from Notice to Proceed), and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before (Date) (30 days from Substantial Comp... |
| 4.03 Milestones |
| A. Parts of the Work must be substantially completed on or before the following Milestone(s): |
| 1. Milestone 1: Concrete median along Closner Boulevard to be completed within 60 days from the Notice to Proceed. |
| 2. Milestone 2: Roadwork along Alberta Road between Closner Boulevard and I-69C to be completed within 60 days from the section start date. The section start date shall be the earlier of the first day on which the work for the section begins or the da... |
| 3. Milestone 3 / Substantial Completion: Concrete rip rap, sidewalk, and handrails at the drainage canal located on the south side of Alberta Rd, located approximately 1,250 linear feet west of the intersection of Sugar Rd and Alberta Rd, to be comple... |
| 4. Milestone 4 / Final Completion: Punch list to be completed within 30 days from the Substantial Completion. |
| 4.04 Liquidated Damages |
| A. Contractor and Owner recognize that time is of the essence as stated in Paragraph 4.01 above and that Owner will suffer financial and other losses if the Work is not completed and Milestones not achieved within the Contract Times, as duly modified.... |
| 1. Substantial Completion: Contractor shall pay Owner based on fees below for each day that expires after the time (as duly adjusted pursuant to the Contract) specified above for Substantial Completion, until the Work is substantially complete. |
| 2. Completion of Remaining Work: After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times (as duly adjusted pursuant to the Contract) for completion and readiness for final pay... |
| 3. Liquidated damages for failing to timely attain Milestones, Substantial Completion, and final completion are not additive, and will not be imposed concurrently. |
B. If Owner recovers liquidated damages for a delay in completion by Contractor, Owner is not precluded from recovering other damages, whether actual, direct, excess, or consequential, for such delay, including for special damages (if any) specified i...
| 4.06 Special Damages |
| A. Contractor shall reimburse Owner (1) for any fines or penalties imposed on Owner as a direct result of the Contractor’s failure to attain Substantial Completion according to the Contract Times, and (2) for the actual costs reasonably incurred by Ow... |
| B. After Contractor achieves Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times, Contractor shall reimburse Owner for the actual costs reasonably incurred by Owner for engineer... |
| C. The special damages imposed in this paragraph are supplemental to any liquidated damages for delayed completion established in this Agreement. |
| CONTRACT PRICE |
| 5.01 Owner shall pay Contractor for completion of the Work in accordance with the Contract Documents, the amounts that follow, subject to adjustment under the Contract: |
| A. For all Work other than Unit Price Work, a lump sum of N/A. |
| B. For all Unit Price Work, an amount equal to the sum of the extended prices (established for each separately identified item of Unit Price Work by multiplying the unit price times the actual quantity of that item). |
| The extended prices for Unit Price Work set forth as of the Effective Date of the Contract are based on estimated quantities. As provided in Paragraph 13.03 of the General Conditions, estimated quantities are not guaranteed, and determinations of actu... |
| C. Total of Lump Sum Amount and Unit Price Work (subject to final Unit Price adjustment) $XX. |
| D. For all Work, at the prices stated in Contractor’s Bid, attached hereto as an exhibit. |
| PAYMENT PROCEDURES |
| 6.01 Submittal and Processing of Payments |
| A. Contractor shall submit Applications for Payment in accordance with Article 15 of the General Conditions. Applications for Payment will be processed by Engineer as provided in the General Conditions. |
| 6.02 Progress Payments; Retainage |
| A. Owner shall make progress payments on the basis of Contractor’s Applications for Payment on or about the 25th day of each month during performance of the Work as provided in Paragraph 6.02.A.1 below, provided that such Applications for Payment have... |
| 1. Prior to Substantial Completion, progress payments will be made in an amount equal to the percentage indicated below but, in each case, less the aggregate of payments previously made and less such amounts as Owner may withhold, including but not li... |
| a. 95 percent of the value of the Work completed (with the balance being retainage); and |
| b. 95 percent of cost of materials and equipment not incorporated in the Work (with the balance being retainage). |
B. Upon Substantial Completion, Owner shall pay an amount sufficient to increase total payments to Contractor to 100 percent of the Work completed, less such amounts set off by Owner pursuant to Paragraph 15.01.E of the General Conditions, and less 20...
| 6.03 Final Payment |
| A. Upon final completion and acceptance of the Work, Owner shall pay the remainder of the Contract Price in accordance with Paragraph 15.06 of the General Conditions. |
| 6.04 Consent of Surety |
| A. Owner will not make final payment, or return or release retainage at Substantial Completion or any other time, unless Contractor submits written consent of the surety to such payment, return, or release. |
| 6.05 Interest |
| A. All amounts not paid when due will bear interest at the rate of 0 percent per annum. |
| CONTRACT DOCUMENTS |
| 7.01 Contents |
| A. The Contract Documents consist of all of the following: |
| 1. This Agreement. |
| 2. Bonds: |
| a. Performance bond (together with power of attorney). |
| b. Payment bond (together with power of attorney). |
| 3. General Conditions. |
| 4. Supplementary Conditions. |
| 5. Specifications as listed in the table of contents of the project manual (copy of list attached). |
| 6. Drawings (not attached but incorporated by reference) consisting of xx sheets with each sheet bearing the following general title: Alberta Rd Reconstruction Phase III & Intersection w/ Closner Blvd. |
| 7. Addenda (numbers 1 to 6, inclusive). |
| 8. The following which may be delivered or issued on or after the Effective Date of the Contract and are not attached hereto: |
| a. Notice to Proceed. |
| b. Work Change Directives. |
| c. Change Orders. |
| d. Field Orders. |
| e. Warranty Bond, if any. |
| B. The Contract Documents listed in Paragraph 7.01.A are attached to this Agreement (except as expressly noted otherwise above). |
| C. There are no Contract Documents other than those listed above in this Article 7. |
| D. The Contract Documents may only be amended, modified, or supplemented as provided in the Contract. |
| REPRESENTATIONS, CERTIFICATIONS, AND STIPULATIONS |
| 8.01 Contractor’s Representations |
| A. In order to induce Owner to enter into this Contract, Contractor makes the following representations: |
| 1. Contractor has examined and carefully studied the Contract Documents, including Addenda. |
| 2. Contractor has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work. |
| 3. Contractor is familiar with all Laws and Regulations that may affect cost, progress, and performance of the Work. |
| 4. Contractor has carefully studied the reports of explorations and tests of subsurface conditions at or adjacent to the Site and the drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been iden... |
| 5. Contractor has carefully studied the reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, with respect to Technical Data in such reports a... |
| 6. Contractor has considered the information known to Contractor itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Contract Documents; and t... |
| 7. Based on the information and observations referred to in the preceding paragraph, Contractor agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Pr... |
| 8. Contractor is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Contract Documents. |
| 9. Contractor has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Contractor has discovered in the Contract Documents, and of discrepancies between Site conditions and the Contract Documents, and the written ... |
| 10. The Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work. |
| 11. Contractor’s entry into this Contract constitutes an incontrovertible representation by Contractor that without exception all prices in the Agreement are premised upon performing and furnishing the Work required by the Contract Documents. |
| 8.02 Contractor’s Certifications |
| A. Contractor certifies that it has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for or in executing the Contract. For the purposes of this Paragraph 8.02: |
| 1. “corrupt practice” means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process or in the Contract execution; |
| 2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process or the execution of the Contract to the detriment of Owner, (b) to establish Bid or Contract prices at artificial non-competitive levels... |
| 3. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish Bid prices at artificial, non-competitive levels; and |
| 4. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract. |
| 8.03 Standard General Conditions |
| A. Owner stipulates that if the General Conditions that are made a part of this Contract are EJCDC® C-700, Standard General Conditions for the Construction Contract (2018), published by the Engineers Joint Contract Documents Committee, and if Owner is... |