The file is a Salient Characteristics document for a Portable 100-ton Chiller with Pump Package, detailing technical specifications for an air-cooled chiller unit with integrated pump system. The solicitation (W50S7X-25-Q-0008) is a small business set-aside, unfunded procurement issued by the Department of the Army National Guard, seeking a comprehensive chiller unit with extensive technical requirements including air-cooled scroll compressors, copper tube/aluminum fin condenser coils, UL safety certifications, and multiple operational features like high/low ambient temperature kits and standalone DDC temperature controls.
Key procurement details include a quote submission deadline of 23 April 2025 at 1:00 PM CST, with quotes to be emailed to specified points of contact. The chiller must be rated at 300 GPM with 100 foot/head pump capacity, mounted on a hot-dipped galvanized structural frame, and include comprehensive electrical, piping, and control system specifications. The solicitation requires a detailed technical proposal with specification sheets, photos, and warranties, with the award contingent on available appropriated funds and focusing on a complete working portable chiller unit that meets all specified salient characteristics.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Portable 100-ton Chiller with Pump Package Salient Characteristics
Provide one (1) air cooled chiller unit with the following features:
o Air-Cooled Scroll Packaged Chiller o Copper Tube / Aluminum Fin condenser coils o Evaporator-Shell and tube heat exchanger o Startup Included by manufacturer o 60 hertz; 460 volt 3 phases o High efficiency/performance o Full factory refrigerant charge o Provided freeze protection (External T-STAT control) o Refrigerant isolation valves (discharge valve) o UL listed to US and Canadian safety standard o ASHRAE 90.1 all versions compliant o AHRI certified Standard cooling (42 to 65F) o Grooved pipe connection o Factory insulation - all cold parts o High ambient kit (up to 125F) o Low ambient kit (down to 0F) o Chiller shall be provided with low leaving fluid temperature option of +10F o Single point power connection o Terminal block conn for incoming lines o Enclosure type UL 1995 rated for outdoor applications o Water strainer factory installed o Dual circuit machine for staging and efficiency o Scroll compressors for dynamic staging control and energy conservation.
o Control transformer power o Integrated non-fused disconnect - “thru the panel operator” o TEAO fan motors o Insulated evaporator o Condenser coil guards o Phase monitor and phase fail indicator light (red) o Main power on indicator (green) o Master on switch o Common trouble alarm terminal o Installed flow switch safety o Temperature and pressure gauges provided o Chiller will be provided with standalone DDC temperature controls.
o Chilled water barrel heaters for freeze protection o Chiller provided with hydronic isolation and drain valves.
o Main power wiring will include single (1) Cam Lok electrical connections and associated wiring o Chiller shall be furnished with a 2” x 4” label with white backing and black lettering stating “NOTE: 480-volt power should be applied a minimum of 1 hour before starting chiller. Compressor oil heaters utilize 480 volt power.”
� Provide and install pump rated @ 300 GPM @ 100 foot/head. Pump will be mounted to the chiller skid. The close coupled pump will be integrated into the interconnecting piping and hydronic components. Installation to include a pump starter, overload, control switch and breaker.
� Internal chiller piping package to include:
o Integrated bypass to provide operation of local or remote pumps o Chiller to be provided with isolation/balancing valves, bypass valve for remote pump operation, in-line strainer with blow down valve, and low level drain valve.
o Entering and leaving fluid temperature ports and thermometers o Entering and leaving pressure ports and gauges o Drain valves at chiller barrel, pump housing and at the piping manifold lowest point.
o Chiller will be provided with an additional differential pressure safety switch. This pressure switch is independent of the factory installed safety switch.
o Provide two (2) additional ¼” access ports for field pressure/temperature testing.
o Perform hydrostatic pressure testing to 125 PSIG of the entire pump, piping and component assembly to verify no leaks are present.
o 60’ of quick connect hoses and 60’ of return hoses.
� Provide structural mounting frame for the pump on the chiller skid. Hot dipped galvanized structural members.
� Provide and install all required electrical power wiring and control devices.
� Provide all required starters, overloads and disconnects.
� The skid shall be fabricated to mount the chiller unit to a trailer unit � The lifting frame material needs to have to ability to be loaded or moved with forklift � The chiller shall be attached to the structure along all sides.
� The entire skid and lifting frame shall be provided with a hot dipped galvanized coating for increased corrosion protection.
� The unit shall be manufactured in accordance with NEC codes, ETL requirements and labeled with the appropriate 3rd party NRTL as requested.
� Chiller / pump assembly shall be provided with a certified skid / lifting frame structural calculations and certificates issued by a 3rd party engineering firm.
� The exterior of the unit shall be properly prepared and coated white.
� Unit to be test run before acceptance.