This is a Notice to Contractors for the Sacramento County Airports Department, specifically for the Sacramento Mather Airport Runway 4R/22L Rehabilitation project. The project involves comprehensive rehabilitation of the primary runway, including removing existing Portland Cement Concrete (PCC) and Asphalt Concrete (AC) pavements, installing crushed aggregate base course, constructing asphalt emulsified recycled base course, installing bituminous asphalt and Portland cement concrete pavements, adding pavement markings, and installing centerline and touchdown zone light cans and electrical conduits. The project is released on September 14, 2023, with pre-bid questions due by October 6, 2023, and bid submissions required electronically by October 26, 2023, at 2:00 pm.

The estimated construction cost is $31,600,000, and a Class A California contractor's license is required. The project is divided into three phases of civil and electrical improvements, with some portions funded by AIP (Airport Improvement Program) and others non-AIP funded. The bid will be awarded based on the base bid only, with detailed line-item pricing for various tasks such as pavement removal, excavation, base course installation, asphalt and concrete surface courses, electrical work, and temporary markings. Bidders must comply with federal provisions including Davis-Bacon wage requirements, Buy America provisions, equal employment opportunity goals, and various certification requirements related to Iran contracting, trade restrictions, and labor standards.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NOTICE TO CONTRACTORS

SACRAMENTO MATHER AIRPORT REHABILITATE ASPHALT/

CONCRETE SECTION FOR RUNWAY 4R/22L

County of Sacramento

9660 Ecology Lane

Sacramento, CA 95827

RELEASE DATE: September 14, 2023

DEADLINE FOR QUESTIONS: October 6, 2023

RESPONSE DEADLINE: October 26, 2023, 2:00 pm

RESPONSES MUST BE SUBMITTED ELECTRONICALLY TO:

https://secure.procurenow.com/portal/saccounty https://secure.procurenow.com/portal/%7bproject.government.code%7d

NOTICE TO CONTRACTORS

SACRAMENTO MATHER AIRPORT REHABILITATE ASPHALT/ CONCRETE

SECTION FOR RUNWAY 4R/22L

1. Introduction

2. Notice to Contractors

3. Pricing Proposal

4. Vendor Submissions

Attachments:

A - MHR_4R-22L_IFB Plans - Full Size_(OG)

B - MHR_4R-22L_IFB Special Provisions_(OG)

Notice to Contractors #4512 Title: SACRAMENTO MATHER AIRPORT REHABILITATE ASPHALT/ CONCRETE SECTION FOR RUNWAY 4R/22L

1. Introduction

1.1. Summary

The scope of this project consists of rehabilitating PCC and AC pavements of Runway 4R-22L at Mather

Airport. The work includes:

• Remove existing PCC pavement

• Remove existing AC pavement

• Install crushed aggregate base course

• Construct asphalt emulsified recycled base course

• Install bituminous asphalt pavement

• Install Portland cement concrete pavement

• Install pavement markings

• Install centerline and touchdown zonez light cans and electrical conduits.

1.2. Background

Sacramento Mather Airport (Mather) is approximately 12 miles east of downtown Sacramento and includes two Runways 4R/22L (primary) and 4L/22R (secondary). The primary Runway 4R/22L has a length of 11,301 feet and consists of two types of pavements, Asphalt Concrete (AC), and Portland Cement Concrete (PCC).

The secondary Runway 4L/22R has a length of 6,081 feet sand is entirely an AC runway. Department staff conducts regular inspections of Mather’s runways to determine maintenance, repairs, and improvements necessary to meet applicable safety and operational requirements established by the FAA. Those inspections are documented into the Mather 2016 Pavement Maintenance/Management Plan (PMMP). Pavement inspections note both the AC and PCC pavement on Runway 4R/22L are showing deep-seated distress in several areas and require rehabilitation to correct identified deficiencies. The Project will consist of removal and replacement of the existent PCC and AC pavement, base course work, and restoration of striping.

1.3. Contact Information

Kathy Sutton

P&D ASO III

Email: suttonk@saccounty.gov

Phone: (916) 874-0771

Department:

Airports

Department Head:

Cindy Nichol

Director

1.4. Timeline

Release Project Date September 14, 2023

Question Submission Deadline October 6, 2023, 12:00pm mailto:suttonk@saccounty.gov tel:(916)874-0771

Question Response Deadline October 13, 2023, 11:55pm

Bid Submission Deadline October 26, 2023, 2:00pm

2. Notice to Contractors

2.1. ADVERTISEMENT SUMMARY

Notice is hereby given that the Board of Supervisors of the County of Sacramento will receive sealed bids for the following project:

BID DATE: Thursday, October 26, 2023

SUBMIT BIDS TO: COUNTY OF SACRAMENTO. SUBMIT ELECTRONIC RESPONSES VIA THE SACRAMENTO

COUNTY ELECTRONIC BIDDING PORTAL (SACCOUNTYEBIDS). BIDDERS MUST ELECTRONICALLY SUBMIT

THEIR BID ONLINE NO LATER THAN 2:00 PM ON THE DAY OF THE BID. BID OPENING(S) WILL BE ONLINE

AT 2:00 PM AT THE FOLLOWING LINK: SACCOUNTYEBIDS.

Responses delivered by hand, fax, telephone, e-mail, or any postal carrier will not be accepted. If bidder uploads a file to SacCountyEbids, it is the bidder's responsibility to ensure the file is not corrupt or damaged. If County is unable to open an attachment because it is damaged, corrupt, infected, etc., it may disqualify bidder’s submission. See this training guide for assistance in entering your online response.

FOR: SACRAMENTO MATHER AIRPORT REHABILITATE ASPHALT/ CONCRETE SECTION FOR RUNWAY

4R/22L

CONTRACT NUMBER: 4512

ESTIMATED CONSTRUCTION COST: $31,600,000

CONTRACTOR LICENSE REQUIRED: Class A

PRE-BID QUESTIONS DUE VIA Q&A: Date: Friday, October 6, 2023 No later than: 12:00 pm

PROJECT DESCRIPTION: The work to be performed under this contract includes the furnishing of all labor, materials, equipment, and and other incidental work for: The scope of this project consists of rehabilitating PCC and AC pavements of Runway 4R-22L at Mather Airport. The work includes: Remove existing PCC pavement. Remove existing AC pavement, Install crushed aggregate base course, Construct asphalt emulsified recycled base course, Install bituminous asphalt pavement, Install Portland cement concrete pavement, Install pavement markings, Install centerline and touchdown zonez light cans and electrical conduits.

BASIS FOR AWARD: The basis for award shall be base bid only, with no additive or deductive items, or no consideration of additive or deductive items.

CONTRACT INFORMATION: Contract Documents are contained herein and include: Notice to

Contractors, the Sacramento County Standard Construction Specifications, the Special Provisions, the

Bid Proposal form and any attachments, exhibits, drawings, addenda, and/or documents provided by the Project Manager that pertain to this project.

• Contract Documents are available at: SacCountyEbids https://secure.procurenow.com/portal/saccounty https://secure.procurenow.com/portal/saccounty https://secure.procurenow.com/portal/saccounty http://help.procurenow.com/en/articles/5815468-opengov-procurement-vendor-training https://secure.procurenow.com/portal/saccounty

• The Standard Construction Specifications, which are incorporated by reference in the Contract

Documents, may be downloaded at: https://saccountyspecs.saccounty.gov/Pages/default.aspx.

2.2. PRE-BID MEETING

There is no pre-bid meeting for this project.

2.3. BID GUARANTEES

Each bid must be submitted on the bid forms provided in the Contract Documents; however, if none are provided, the surety may issue on its own paper. Each bid must also be accompanied by security in the form of a bid bond issued by a corporate surety, a certified check or cashier's check payable to the

Treasurer of Sacramento County, or cash for an amount not less than ten percent (10%) of the aggregate sum of the bid.

2.4. BONDS

The successful bidder shall be required to execute a material and labor Payment Bond and Performance

Bond, issued by a corporate surety, acceptable to the County of Sacramento, each for not less than one hundred percent (100%) of the contract price.

Pursuant to Public Contract Code, section 22300, the Contractor may, at its own expense, substitute securities for any money being withheld by the County to ensure performance under this contract. The

Contractor must notify the County of its intent to pursue this option prior to the issuance/execution of a contract.

2.5. LICENSE REQUIREMENTS

Award of this contract requires a valid California contractor's license with the classification identified above.

Public Contract Code, section 4104(a)(1), requires that any person making a bid must submit the name, location of the place of business, and the subcontractor’s license number on the bid form.

No contractor or subcontractor may be listed on a bid proposal for a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code, section 1725.5 [with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)].

No contractor or subcontractor may be awarded a contract for public work on a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code, section 1725.5.

2.6. LABOR COMPLIANCE PROGRAM (FEDERAL FUNDING)

All labor on the project shall be paid no less than the minimum wage rates as established by the U.S.

Secretary of Labor or as determined by the Director of the California Department of Industrial Relations.

The higher of the two rates will be paid in accordance with the following statutes:

A. The Davis Bacon Act and related federal acts; or

B. California Labor Code section 1770 et seq.

https://saccountyspecs.saccounty.gov/Pages/default.aspx

Copies of the minimum wage rates established by the Secretary of the U.S. Department of Labor

(www.wdol.gov) and the prevailing rate of per diem wages as determined by the Director of the

California Department of Industrial Relations (http://www.dir.ca.gov/OPRL/PWD/index.htm) are on file at the office of the Labor Compliance Program, 9700 Goethe Road, Suite D, Sacramento, California

95827, and are available upon request.

The County of Sacramento will not accept lower State wage rates not specifically included in the Federal

Minimum Wage Decision. This includes “helper” (or other classifications based on hours of experience) or any other classification not appearing in the Federal Wage Decision. Where the Federal Wage

Decision does not contain the State wage rate determination otherwise available for use by the

Contractor and subcontractors, the Contractor and subcontractors shall pay not less than the Federal minimum wage rate which most closely approximates the duties of the employees in question.

The County of Sacramento received final approval from the Director of the California Department of

Industrial Relations to enforce a Labor Compliance Program effective March 15, 1994. All questions regarding this Labor Compliance Program and prevailing wage requirements should be directed to the office of Labor Compliance Program at 916-875-2711.

This is a Construction project in accordance with Labor Code section 1771.5.

2.7. NON-DISCRIMINATION

This contract is subject to State contract non-discrimination and compliance requirements pursuant to

Government Code section 12990.

The County of Sacramento hereby notifies all Bidders that it will affirmatively insure that in any contract entered into pursuant to this advertisement, disadvantaged & minority business enterprises will be afforded full opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, or national origin in consideration for an award.

2.8. ADDITIONAL FEDERAL PROVISIONS (IF ANY)

N/A

2.9. BUY AMERICA

This project is subject to the “Buy America” provisions of the Surface Transportation Assistance Act of

1982, as amended by the Intermodal Surface Transportation Efficiency Act of 1991 (23 USC 313).

2.10. FAA / AIP LANGUAGE

Contractor will, at all times during the term of this Agreement, comply with the provisions of the FAA

Airport Sponsor Assurances (Assurances) and any subsequent revisions, updates, or amendments thereto. The provisions of the Assurances may change during the Term of this Agreement, and those changes will be incorporated into this Agreement without the necessity of a formal amendment. County is not responsible for notifying Contractor of any changes to the Assurances. Contractor is required to contact the FAA for any updates or revisions. The Assurances document is available on the FAA’s website, and is incorporated into this Agreement by this reference.

https://www.faa.gov/airports/aip/grant_assurances https://www.faa.gov/airports/aip/grant_assurances

FAA GENERAL CONTRACT PROVISIONS FOR SOLICITATIONS

NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT

OPPORTUNITY

1. The Offeror’s or Bidder’s attention is called to the “Equal Opportunity Clause” and the “Standard

Federal Equal Employment Opportunity Construction Contract Specifications” set forth herein.

2. The goals and timetables for minority and female participation, expressed in percentage terms for the

Contractor’s aggregate workforce in each trade on all construction work in the covered area, are as follows:

Timetables

Goals for minority participation for each trade: 16.1%

Goals for female participation in each trade: 6.9%

These goals are applicable to all of the Contractor’s construction work (whether or not it is Federal or federally assisted) performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, it shall apply the goals established for such geographical area where the work is actually performed. With regard to this second area, the

Contractor also is subject to the goals for both its federally involved and non-federally involved construction.

The Contractor’s compliance with the Executive Order and the regulations in 41 CFR Part 60-4 shall be based on its implementation of the Equal Opportunity Clause, specific affirmative action obligations required by the specifications set forth in 41 CFR 60-4.3(a) and its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade, and the Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor or from project to project for the sole purpose of meeting the

Contractor’s goals shall be a violation of the contract, the Executive Order and the regulations in 41 CFR

Part 60-4. Compliance with the goals will be measured against the total work hours performed.

3. The Contractor shall provide written notification to the Director of the Office of Federal Contract

Compliance Programs (OFCCP) within 10 working days of award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the name, address, and telephone number of the subcontractor;

employer identification number of the subcontractor; estimated dollar amount of the subcontract;

estimated starting and completion dates of the subcontract; and the geographical area in which the subcontract is to be performed.

4. As used in this notice and in the contract resulting from this solicitation, the “covered area” is

Sacramento County.

BUY AMERICAN PREFERENCE

The Contractor agrees to comply with 49 USC § 50101, which provides that Federal funds may not be obligated unless all steel and manufactured goods used in AIP funded projects are produced in the

United States, unless the Federal Aviation Administration has issued a waiver for the product; the product is listed as an Excepted Article, Material Or Supply in Federal Acquisition Regulation subpart

25.108; or is included in the FAA Nationwide Buy American Waivers Issued list.

The bidder must complete and submit the Buy America certification included herein with their bid or offer. The County will reject as nonresponsive any bid or offer that does not include a completed

Certificate of Buy American Compliance.

TITLE VI SOLICITATION NOTICE

The County, in accordance with the provisions of Title VI of the Civil Rights Act of 1964 (78 Stat. 252, 42

USC §§ 2000d to 2000d-4) and the Regulations, hereby notifies all bidders or offerors that it will affirmatively ensure that any contract entered into pursuant to this advertisement, [select disadvantaged business enterprises or airport concession disadvantaged business enterprises] will be afforded full and fair opportunity to submit bids in response to this invitation and no businesses will be discriminated against on the grounds of race, color, national origin (including limited English proficiency), creed, sex (including sexual orientation and gender identity), age, or disability in consideration for an award.

DAVIS-BACON REQUIREMENTS

The Davis-Bacon Act ensures that laborers and mechanics employed under the contract receive pay no less than the locally prevailing wages and fringe benefits as determined by the Department of Labor. 2

CFR § 200, Appendix II(D); 29 CFR Part 5.

CERTIFICATION OF OFFEROR/BIDDER REGARDING DEBARMENT

By submitting a bid/proposal under this solicitation, the bidder or offeror certifies that neither it nor its principals are presently debarred or suspended by any Federal department or agency from participation in this transaction.

DISADVANTAGED BUSINESS ENTERPRISE

The requirements of 49 CFR part 26 apply to this contract. It is the policy of the County to practice nondiscrimination based on race, color, sex, or national origin in the award or performance of this contract. The Owner encourages participation by all firms qualifying under this solicitation regardless of business size or ownership.

FEDERAL FAIR LABOR STANDARDS ACT (FEDERAL MINIMUM WAGE)

All contracts and subcontracts that result from this solicitation incorporate by reference the provisions of 29 CFR part 201, et seq, the Federal Fair Labor Standards Act (FLSA), with the same force and effect as if given in full text. The FLSA sets minimum wage, overtime pay, recordkeeping, and child labor standards for full and part-time workers.

The Contractor has full responsibility to monitor compliance to the referenced statute or regulation. The Contractor must address any claims or disputes that arise from this requirement directly with the U.S. Department of Labor – Wage and Hour Division.

TRADE RESTRICTION CERTIFICATION

By submission of an offer, the Offeror certifies that with respect to this solicitation and any resultant contract, the Offeror –

1) is not owned or controlled by one or more citizens of a foreign country included in the list of countries that discriminate against U.S. firms as published by the Office of the United States Trade

Representative (USTR);

2) has not knowingly entered into any contract or subcontract for this project with a person that is a citizen or national of a foreign country included on the list of countries that discriminate against U.S.

firms as published by the USTR; and

3) has not entered into any subcontract for any product to be used on the Federal project that is produced in a foreign country included on the list of countries that discriminate against U.S. firms published by the USTR.

This certification concerns a matter within the jurisdiction of an agency of the United States of America and the making of a false, fictitious, or fraudulent certification may render the maker subject to prosecution under Title 18 USC Section 1001.

The Offeror/Contractor must provide immediate written notice to the Owner if the Offeror/Contractor learns that its certification or that of a subcontractor was erroneous when submitted or has become erroneous by reason of changed circumstances. The Contractor must require subcontractors provide immediate written notice to the Contractor if at any time it learns that its certification was erroneous by reason of changed circumstances.

Unless the restrictions of this clause are waived by the Secretary of Transportation in accordance with

49 CFR 30.17, no contract shall be awarded to an Offeror or subcontractor:

1) who is owned or controlled by one or more citizens or nationals of a foreign country included on the list of countries that discriminate against U.S. firms published by the USTR; or

2) whose subcontractors are owned or controlled by one or more citizens or nationals of a foreign country on such USTR list; or

3) who incorporates in the public works project any product of a foreign country on such USTR list.

Nothing contained in the foregoing shall be construed to require establishment of a system of records in order to render, in good faith, the certification required by this provision. The knowledge and information of a contractor is not required to exceed that which is normally possessed by a prudent person in the ordinary course of business dealings.

The Offeror agrees that, if awarded a contract resulting from this solicitation, it will incorporate this provision for certification without modification in all lower tier subcontracts. The Contractor may rely on the certification of a prospective subcontractor that it is not a firm from a foreign country included on the list of countries that discriminate against U.S. firms as published by USTR, unless the Offeror has knowledge that the certification is erroneous.

This certification is a material representation of fact upon which reliance was placed when making an award. If it is later determined that the Contractor or subcontractor knowingly rendered an erroneous certification, the Federal Aviation Administration (FAA) may direct through the Owner cancellation of the contract or subcontract for default at no cost to the Owner or the FAA.

CERTIFICATION REGARDING LOBBYING

The Bidder or Offeror certifies by signing and submitting this bid or proposal, to the best of his or her knowledge and belief, that:

(1) No Federal appropriated funds have been paid or will be paid, by or on behalf of the Bidder or

Offeror, to any person for influencing or attempting to influence an officer or employee of an agency, a

Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with the awarding of any Federal contract, the making of any Federal grant, the making of any Federal loan, the entering into of any cooperative agreement, and the extension, continuation, renewal, amendment, or modification of any Federal contract, grant, loan, or cooperative agreement.

(2) If any funds other than Federal appropriated funds have been paid or will be paid to any person for influencing or attempting to influence an officer or employee of any agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with this

Federal contract, grant, loan, or cooperative agreement, the undersigned shall complete and submit

Standard Form-LLL, “Disclosure Form to Report Lobbying,” in accordance with its instructions.

(3) The undersigned shall require that the language of this certification be included in the award documents for all sub-awards at all tiers (including subcontracts, subgrants, and contracts under grants, loans, and cooperative agreements) and that all sub-recipients shall certify and disclose accordingly.

This certification is a material representation of fact upon which reliance was placed when this transaction was made or entered into. Submission of this certification is a prerequisite for making or entering into this transaction imposed by section 1352, title 31, U.S. Code. Any person who fails to file the required certification shall be subject to a civil penalty of not less than $10,000 and not more than

$100,000 for each such failure.

PROCUREMENT OF RECOVERED MATERIALS

Contractor and subcontractor agree to comply with Section 6002 of the Solid Waste Disposal Act, as amended by the Resource Conservation and Recovery Act, and the regulatory provisions of 40 CFR Part

247. In the performance of this contract and to the extent practicable, the Contractor and subcontractors are to use products containing the highest percentage of recovered materials for items designated by the Environmental Protection Agency (EPA) under 40 CFR Part 247 whenever:

1) The contract requires procurement of $10,000 or more of a designated item during the fiscal year;

or

2) The contractor has procured $10,000 or more of a designated item using Federal funding during the previous fiscal year.

The list of EPA-designated items is available at www.epa.gov/smm/comprehensive-procurement-guidelines-construction-products.

Section 6002(c) establishes exceptions to the preference for recovery of EPA-designated products if the contractor can demonstrate the item is:

a) Not reasonably available within a timeframe providing for compliance with the contract performance schedule;

b) Fails to meet reasonable contract performance requirements; or

c) Is only available at an unreasonable price.

https://www.epa.gov/smm/comprehensive-procurement-guidelines-construction-products https://www.epa.gov/smm/comprehensive-procurement-guidelines-construction-products

2.11. QUESTIONS

Direct pre-bid questions to the Project Manager, Kathy Sutton, via the Q&A tab in the portal. ALL PRE-

BID QUESTIONS MUST BE SUBMITTED IN WRITING NO LATER THAN Friday, October 6, 2023 BY 12:00

pm. Questions received after that time will not be answered. Responses will be by addenda to the bid documents.

The Board reserves the right to reject any or all bids, to waive any informality in any bid, and to determine which bid, in their judgment, is the lowest responsive bid of a responsible Bidder.

By order of the Board of Supervisors of the County of Sacramento, Sacramento County, California, dated: September 12, 2023.

Clerk of the Board

3. Pricing Proposal

BID TABULATION

Line Item Pay Item Description Quantity Unit of

Measure Unit Cost Total

RUNWAY 4R-22L REHABILITATION

1 C-100 Contractor Quality

Control Program (CQCP)

1 LS

2 C-102-5.1a SWPPP 1 LS

3 C-102-5.1b Installation & Removal of

Temp Erosion Control

1 AL $20,000.00

4 C-105 Mobilization 1 LS

5 SCP-148-4.1 Airfield Construction Area

Control

1 LS

6 SCP-148-4.2 Safety Plan Compliance

Document

1 LS

7 SCP-34 73

19-1 Temporary Jet Blast

Deflector

222 LF

RUNWAY 4R-22L REHABILITATION: PHASE 1 CIVIL IMPROVEMENTS

8 P-101-5.1 Concrete Pavement

Removal

14,200 SY

9 P-101-5.2 Joint and Crack Repair 700 LF

10 P-101-5.3a Removal of Foreign

Substances/Contaminates

150,710 SF

11 P-101-5.3b Removal of Foreign

Substances/Contaminates

6,050 SF

12 P-101-5.5 Concrete Spall Repair 330 SF

13 P-101-5.7 4" Asphalt Cold Mill 5,450 SY

14 P-152-4.1 Unclassified Excavation 5,390 CY

Line Item Pay Item Description Quantity Unit of

Measure Unit Cost Total

15 P-401-8.1 Asphalt Surface Course 1,280 TON

16 P-501-8.1 Concrete Pavement 14,200 SY

17 P-603-5.1 Emulsified Asphalt Tack

Coat

820 GAL

18 P-620-5.4d Temporary Runway and

Taxiway Marking

117,650 SF

RUNWAY 4R-22L REHABILITATION: PHASE 2 CIVIL IMPROVEMENTS

19 P-101-5.1 Concrete Pavement

Removal

29,360 SY

20 P-101-5.2 Joint and Crack Repair 315 LF

21 P-101-5.3a Removal of Foreign

Substances/Contaminates

97,330 SF

22 P-101-5.3b Removal of Foreign

Substances/Contaminates

525 SF

23 P-101-5.5 Concrete Spall Repair 525 SF

24 P-101-5.6 Asphalt Pavement

Removal

3,930 SY

25 P-101-5.7 4" Asphalt Cold Mill 7,550 SY

26 P-152-4.1 Unclassified Excavation 1,150 CY

27 P-207-5.1 In-place Full Depth

Recycled (FDR) Asphalt

Aggregate Base Course

3,930 SY

28 P-207-5.2 Emulsified Asphalt 56 TON

29 P-209-5.1 Crushed Aggregate Base

Course

2,850 CY

30 P-401-8.1 Asphalt Surface Course 5,920 TON

Unit Cost Total

31 P-501-8.1 Concrete Pavement 29,360 SY

32 P-603-5.1 Emulsified Asphalt Tack

Coat

3,660 GAL

33 P-610-6.2 Cable Arresting System

Foundations 1 Ls

34 P-620-5.4d Temporary Runway and

Taxiway Marking

56,250 SF

RUNWAY 4R-22L REHABILITATION: PHASE 3 CIVIL IMPROVEMENTS

35 P-101-5.1 Concrete Pavement

Removal

1,790 SY

36 P-101-5.5 Concrete Spall Repair 180 SF

37 P-101-5.6 Asphalt Pavement

Removal

28,290 SY

38 P-101-5.7 4" Asphalt Cold Mill 46,530 SY

39 P-152-4.1 Unclassified Excavation 5,890 CY

40 P-207-5.1 In-place Full Depth

Recycled (FDR) Asphalt

Aggregate Base Course

28,290 SY

41 P-207-5.2 Emulsified Asphalt 410 TON

42 P-209-5.1 Crushed Aggregate Base

Course

420 CY

43 P-401-8.1 Asphalt Surface Course 27,260 TON

44 P-603-5.1 Emulsified Asphalt Tack

Coat

16,000 GAL

45 P-620-5.2b Marking 161,000 SF

RUNWAY 4R-22L REHABILITATION: PHASE 1 CIVIL IMPROVEMENTS (NON-AIP FUNDED)

Unit Cost Total

46 P-101-5.1 Concrete Pavement

Removal

5,910 SY

47 P-152-4.1 Unclassified Excavation 40 CY

48 P-209-5.1 Crushed Aggregate Base

Course

410 CY

49 P-501-8.1 Concrete Pavement 5,910 SY

RUNWAY 4R-22L REHABILITATION: PHASE 1 ELECTRICAL IMPROVEMENTS (NON-AIP FUNDED)

50 L-108-1 1-1/C No. 8 AWG, 5kV, L-

824C Cable

1,125 LF

51 L-108-2 1-1/C No. 6 AWG, 600V

Ground Wire

665 LF

52 L-110-1 Underground Electrical

Duct, 1-way, 2 inch in

New Concrete Panels

3,000 LF

53 L-125-1 L-868B Base Can in New

Concrete Panels

71 EA

54 L-125-2 L-868B Base Can in New

Asphalt

1 EA

55 L-125-3 L-868B Extension 72 EA

56 L-125-4 L-868B Spacer Package w/ Cover Plate

66 EA

57 L-125-6 Remove and Reinstall

Taxiway Edge Light

3 EA

58 L-125-7 Remove and Reinstall

Runway Edge Light

3 EA

59 L-125-8 L-868B TO L-867B

Adaptor Ring

3 EA

60 L-128-1A Electrical Demo for Phase

1 LS

Unit Cost Total

61 L-128-2A Miscellaneous Electrical

Work for Phase 1

1 LS

62 L-128-3A Temporary PAPI for

Phase 1

1 LS

63 L-128-4A Temporary Electrical

Work Associated with

Phase 1

1 LS

RUNWAY 4R-22L REHABILITATION: PHASE 2 ELECTRICAL IMPROVEMENTS (NON-AIP FUNDED)

64 L-108-1 1-1/C No. 8 AWG, 5kV, L-

824C Cable

500 LF

65 L-108-2 1-1/C No. 6 AWG, 600V

Ground Wire

300 LF

66 L-110-1 Underground Electrical

Duct, 1-way, 2 inch in

New Concrete Panels

7,906 LF

67 L-110-2 Underground Electrical

Duct, 1-way, 2 inch in

New Asphalt

1,781 LF

68 L-110-3 Underground Electrical

Duct, 1-way, 2 inch in

Existing Asphalt

300 LF

69 L-115-1 Aircraft Rated Electrical

Handhole, 4’x4’x4’, Installed Complete in

Place

1 EA

70 L-125-1 L-868B Base Can in New

Concrete Panels

207 EA

71 L-125-2 L-868B Base Can in New

Asphalt

39 EA

72 L-125-3 L-868B Extension 246 EA

Unit Cost Total

73 L-125-4 L-868B Spacer Package w/ Cover Plate

246 EA

74 L-125-5 L-867D Base Can with

Cover Plate

1 EA

75 L-128-1B Electrical Demo for Phase

1 LS

76 L-128-2B Miscellaneous Electrical

Work for Phase 2

1 LS

77 L-128-3B Temporary PAPI for

Phase 2

1 LS

78 L-128-4B Temporary Electrical

Work Associated with

Phase 2

1 LS

RUNWAY 4R-22L REHABILITATION: PHASE 3 ELECTRICAL IMPROVEMENTS (NON-AIP FUNDED)

79 L-110-2 Underground Electrical

Duct, 1-way, 2 inch in

New Asphalt

4,700 LF

80 L-125-2 L-868B Base Can in New

Asphalt

93 EA

81 L-125-3 L-868B Extension 93 EA

82 L-125-4 L-868B Spacer Package w/ Cover Plate

93 EA

83 L-128-1C Electrical Demo for Phase

1 LS

84 L-128-2C Miscellaneous Electrical

Work for Phase 3

1 LS

TOTAL

4. Vendor Submissions

4.1. What form of Bid Guaranty will Contractor be submitting?* ☐ Scanned Copy of Fully Executed Bid Bond

☐ E- bid bond( Use of Surety 2000)

☐ Cashier's or Certified Check

☐ Cash

*Response required

4.2. Bid Guarantee

Upload a scanned copy of your fully executed bid bond here if Contractor is submitting a scanned bid bond.

3. E-Bid Bond

Please enter your Bid Bond information from Surety2000 below If Contractor is submitting an E-Bid

Bond

4.3. Non-collusion Declaration*

The undersigned declares:

I am an authorized representative with binding authority for my company, the party making the foregoing bid.

The bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation. The bid is genuine and not collusive or sham. The bidder has not directly or indirectly induced or solicited any other bidder to put in a false or sham bid. The bidder has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or to refrain from bidding. The bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder. All statements contained in the bid are true. The bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, to any corporation, partnership, company, association, organization, bid depository, or to any member or agent thereof, to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such purpose.

Any person executing this declaration on behalf of a bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and does execute, this declaration on behalf of the bidder. I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct and that this declaration is executed on the date this bid is submitted.

☐ Please confirm

*Response required

4.4. Designation of Subcontractors - Unit Price Contracts*

Please download the below documents, complete, and upload.

• DESIGNATION_OF_SUBCONTRACTO...

*Response required

4.5. Iran Contracting Act Disclosure Form *

(California Public Contract Code, sections 2202-2208)

When responding to a bid or proposal or executing a contract or renewal for a County of Sacramento contract for goods or services of $1,000,000 or more, a vendor must either:

A. certify it is not on the current list of persons engaged in investment activities in Iran created by the California Department of General Services (“DGS”) pursuant to Public Contract Code section

2203(b) and is not a financial institution extending twenty million dollars ($20,000,000) or more in credit to another person, for 45 days or more, if that other person will use the credit to provide goods or services in the energy sector in Iran and is identified on the current list of persons engaged in investment activities in Iran created by DGS; or

B. demonstrate it has been exempted from the certification requirement for that solicitation or contract pursuant to Public Contract Code section 2203(c) or (d).

To comply with this requirement, please select one of the options below. Please note: California law establishes penalties for providing false certifications, including civil penalties equal to the greater of

$250,000 or twice the amount of the contract for which the false certification was made; contract termination; and three-year ineligibility to bid on contracts. (Public Contract Code section 2205.)

OPTION #1 - CERTIFICATION

I certify I am duly authorized to execute this certification on behalf of the vendor/financial institution, and the vendor/financial institution is not on the current list of persons engaged in investment activities in Iran created by DGS and is not a financial institution extending twenty million dollars ($20,000,000) or more in credit to another person/vendor, for 45 days or more, if that other person/vendor will use the credit to provide goods or services in the energy sector in Iran and is identified on the current list of persons engaged in investment activities in Iran created by DGS.

OPTION #2 – EXEMPTION

Pursuant to Public Contract Code sections 2203(c) and (d), a public entity may permit a vendor/financial institution engaged in investment activities in Iran, on a case-by-case basis, to be eligible for, or to bid on, submit a proposal for, or enters into or renews, a contract for goods and services. If you have obtained an exemption from the certification requirement under the Iran Contracting Act, please select

"EXEMPTION" below, and attach documentation demonstrating the exemption approval with your electronic submission.

☐ Certification

☐ Exemption https://government-project.s3.us-west-2.amazonaws.com/14260/4c72069d-701a-4f52-9d88-093a99683f23_DESIGNATION_OF_SUBCONTRACTORS.docx?AWSAccessKeyId=AKIARC2J5PZDGOGWDMYG&Expires=1697912855&Signature=cYP6siXJXt6YRtScMRGCiWXE3f8%3D&response-content-disposition=attachment%3B%20filename%3D%22DESIGNATION_OF_SUBCONTRACTORS.docx%22

4.6. Type of Business*

☐ C Corporation

☐ S Corporation

☐ Limited Liability C Corporation

☐ Partnership

☐ Limited Liability Partnership

☐ Sole Proprietor/Individual

☐ Other

*Response required

4.7. Type your Legal Company Name Here*

State your Company's Name Here. This will be verified against the California Secretary of State's

Website.

*Response required

4.8. Contractors State License Board (CSLB) Number*

Please enter your License Number here. This will be verified against the state database

*Response required

4.9. Contractors State License Board (CSLB) License Expiration Date * Enter your CSLB license expiration date:

4.10. Contractors State License Board (CSLB) License Classifications* Enter your current CSLB license classifications:

*Response required

4.11. California Department of Industrial Relations Registration* Please enter your Public Works Contractor Registration Number. This will be verified against the state database.

*Response required

4.12. Provide the full contact name, title, and e-mail of the signatory for your firm. Please provide contact information for the Contract Manager for your firm in order to distribute Contract Documents, including other recipients requiring a copy, if awarded.**

Signatory: name, title, email

Contract manager/admin: name, phone, email

4.13. I hereby certify under penalty of perjury that the above statements are true.*

☐ Please confirm

File details come from the government source that posted it. Updated .