This document is an Addendum No. 2 to the contract documents for the SAC 30634 Temporary Ground Boarding Walkways project issued by the Savannah Airport Commission. The project consists of constructing temporary ground boarding enclosures for the Savannah Hilton Head International Airport. The addendum provides clarification on the waterproofing requirements for the plywood walkway structure and confirms that there are no flooring requirements. All bidders must acknowledge receipt of this Addendum No. 2 in their bid proposal.
The project is located in Chatham County and the City of Savannah, Georgia. There are no specific details provided on pricing terms, set asides, incumbent contractors, funding requirements or sources, or contract term and renewal options.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SAC 30634 Addendum No_ 1.pdf | ||
| SAC 30634 Addendum No_ 3.pdf | ||
| SAC 30634 Temp Ground Boarding Notice To Bidd.pdf | ||
| SAC 30634 Addendum No_ 4 .pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TO: All Plan Holders
Dodge Data & Analytics
Construction Market Data Group
ISQFT
Savannah Entrepreneurial Center
Construction Journal
FROM: Jim Aiello
Assistant Director of Engineering
DATE: March 26, 2024
SUBJ: SAC 30634
Temporary Ground Boarding Walkways
Savannah Airport Commission
Attached please find Addendum No. 2 to the contract documents. All bidders shall acknowledge the receipt of Addendum No. 2 in the place provided in the bid proposal.
CM
ENCL: SAC 30634 – Addendum No. 2
CC: Engineering Files
SAC 30634 ADDENDUM NO. 2 A.2-1
SAVANNAH AIRPORT COMMISSION
SAC 30634
Temporary Ground Boarding Walkways
Addendum No. 2
The following amendments, additions, deletions shall be made to the contract documents. In so far as these documents are at variance with this Addendum No. 2 dated March 26th, 2024, the addendum shall govern:
Questions & Answers
Questions 1 & 2 are from Michael Herren of Berenyi:
1. It was mentioned that the walkway should be weather-resistant and not weather-proof.
What is the expectation for waterproofing the walkway structure? We would like to wrap the plywood but want to make sure everyone else is pricing it that way also.
Response: The plywood is to be protected as we do not want rainwater dripping through the temporary walkway roof area after a rain event. See SCAFFOLD
ENCLOSURE NOTES on plan Sheet No. C4.01.
2. Are there any flooring requirements in the walkways?
Response: No, there are no flooring requirements.