SAC 30634 Addendum No_ 2 .pdf

PDF 273 KB Posted

Attached to
SAC 30634 Temporary Ground Boarding Walways
Solicitation number
PE-33699-NONST-2024-000000013
Issued by
Chatham County, Georgia

About this file

This document is an Addendum No. 2 to the contract documents for the SAC 30634 Temporary Ground Boarding Walkways project issued by the Savannah Airport Commission. The project consists of constructing temporary ground boarding enclosures for the Savannah Hilton Head International Airport. The addendum provides clarification on the waterproofing requirements for the plywood walkway structure and confirms that there are no flooring requirements. All bidders must acknowledge receipt of this Addendum No. 2 in their bid proposal.

The project is located in Chatham County and the City of Savannah, Georgia. There are no specific details provided on pricing terms, set asides, incumbent contractors, funding requirements or sources, or contract term and renewal options.

View the file

Other files

File Type Posted
SAC 30634 Addendum No_ 1.pdf PDF
SAC 30634 Addendum No_ 3.pdf PDF
SAC 30634 Temp Ground Boarding Notice To Bidd.pdf PDF
SAC 30634 Addendum No_ 4 .pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TO: All Plan Holders

Dodge Data & Analytics

Construction Market Data Group

ISQFT

Savannah Entrepreneurial Center

Construction Journal

FROM: Jim Aiello

Assistant Director of Engineering

DATE: March 26, 2024

SUBJ: SAC 30634

Temporary Ground Boarding Walkways

Savannah Airport Commission

Attached please find Addendum No. 2 to the contract documents. All bidders shall acknowledge the receipt of Addendum No. 2 in the place provided in the bid proposal.

CM

ENCL: SAC 30634 – Addendum No. 2

CC: Engineering Files

SAC 30634 ADDENDUM NO. 2 A.2-1

SAVANNAH AIRPORT COMMISSION

SAC 30634

Temporary Ground Boarding Walkways

Addendum No. 2

The following amendments, additions, deletions shall be made to the contract documents. In so far as these documents are at variance with this Addendum No. 2 dated March 26th, 2024, the addendum shall govern:

Questions & Answers

Questions 1 & 2 are from Michael Herren of Berenyi:

1. It was mentioned that the walkway should be weather-resistant and not weather-proof.

What is the expectation for waterproofing the walkway structure? We would like to wrap the plywood but want to make sure everyone else is pricing it that way also.

Response: The plywood is to be protected as we do not want rainwater dripping through the temporary walkway roof area after a rain event. See SCAFFOLD

ENCLOSURE NOTES on plan Sheet No. C4.01.

2. Are there any flooring requirements in the walkways?

Response: No, there are no flooring requirements.