SAC 30620 Addendum No_ 2 .pdf

PDF 276 KB Posted

Attached to
SAC 30620 Extend Taxiway G
Solicitation number
PE-33699-NONST-2024-000000025
Issued by
Chatham County, Georgia

About this file

This document is an Addendum No. 2 to the contract documents for the SAC 30620 Extend Taxiway G project issued by the Savannah Airport Commission. The project involves constructing an extension of Taxiway G and a bridge across Gulfstream Road at the Savannah Hilton Head International Airport. Bidders must acknowledge receipt of Addendum No. 2 and use the proposal forms provided in the Bid Documents without modification. The addendum clarifies that any proprietary or sole source hardware, software, interface, controls, or components for the airfield lighting control system will be procured by the Savannah Airport Commission outside of this AIP Funded Project, and the bid line item shall be for the purchase and installation of the regulator and the installation of the airport-purchased proprietary equipment.

The state and local contract opportunity is located within the jurisdictions of Chatham County and the City of Savannah in the state of Georgia. All questions must be submitted in writing via email, and no other details regarding pricing, set asides, incumbents, funding requirements, or sources are provided in the document.

View the file

Other files

File Type Posted
SAC 30620 Addendum No_ 1 .pdf PDF
SAC 30620 Taxiway G _ Notice To Bidders.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TO: All Plan Holders

Dodge Data & Analytics

Construction Market Data Group

ISQFT

Savannah Entrepreneurial Center

Construction Journal

FROM:

James Aiello

Assistant Director of Engineering

DATE: June 4, 2024

SUBJ: SAC 30620

Extend Taxiway G

Savannah Airport Commission

Attached please find Addendum No. 2 to the contract documents. All bidders shall acknowledge the receipt of Addendum No. 2 in the place provided in the bid proposal.

CM

ENCL: SAC 30620 Addendum No. 2

CC: Engineering Files

SAC 30620 ADDENDUM NO. 2 A.2-1

SAVANNAH AIRPORT COMMISSION

SAC 30620

Extend Taxiway G

Addendum No. 2

The following amendments, additions, deletions shall be made to the contract documents. In so far as these documents are at variance with this Addendum No. 2 dated June 4, 2024, the addendum shall govern:

General Note

Question & Answer

Bidding Contractors must use the proposal forms provided in the Bid Documents. The Proposal

Forms including Bid Schedules shall not be modified. Please note Addendum No. 1 includes a

Revised Bid Schedule.

Question 1 is Steve Shaw of Airport Lighting Company:

1. In regard to this project, L-109-7.1 Install New Regulator indicates to provide proprietary equipment for ALCMS integration as part of the install. All hardware/software/interface

& controls/components that are proprietary/sole source to the control system will need to be procured outside of this AIP Funded Project per AIP Guidelines, AIP Handbook 5100-

38D Change 1, 3-36 Limited Noncompetitive Proposal Situations (ALCMS

Modifications…).

Response: All hardware/software/interface & controls/components that are proprietary/sole source to the airfield lighting control system will be procured by the

Savannah Airport Commission outside of this AIP Funded Project.

The Bid Line Item shall be for the purchase and installation of the regulator and the installation of the airport purchased propriety equipment.