This is Addendum #1 for Request for Proposals (RFP) #S63500-00014852 issued by the Oregon Department of Fish and Wildlife (ODFW) for Coos Aerial Wildlife Surveys. The addendum, dated October 3, 2025, addresses a clarification regarding the project's performance period and work completion timeline. The project involves aerial wildlife surveys with a performance period initially spanning from January 1, 2026, to March 31, 2026, with a potential extension for a second performance period from January 1, 2027, to March 31, 2027.
The addendum specifically responds to a question about conflicting information in the original RFP document regarding the completion of flights. ODFW clarifies that the work will be completed during the specified performance period, with potential for an extended period in the following year. The document emphasizes that the answers and clarifications are for informational purposes only and do not constitute changes to the original RFP's terms, conditions, technical specifications, or requirements. The addendum was prepared by Marcus Jones from ODFW, who can be contacted at Marcus.Jones@odfw.oregon.gov for further inquiries.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM #1 – RFP #S63500-00014852 1
ADDENDUM #1
RFP #S63500-00014852
Coos Aerial Wildlife Surveys
October 3, 2025
This addendum modifies the Request for Proposals (RFP) document(s) for work only to the extent indicated herein. All other areas not specifically mentioned or affected by this addendum shall remain in full force. This addendum shall be added as a part of the original RFP document(s) and shall become part of the work required.
ADDENDUM
QUESTIONS AND ANSWERS:
Following are questions asked during the received by Proposers and ODFW’s answers. The answers and clarifications provided below by ODFW are for informational purposes ONLY and DO NOT constitute a change to the terms, conditions, technical specifications or requirements of the ITB/RFP.
Question 1: Could you please clarify when the work will be completed?
Section 1.1 (Top paragraph)- States the flights will be completed in December of 2025.
Section 1.1 (Performance Period)- States January 1, 2025-March 31, 2026.
Answer 1: Work will be completed during the Performance Period (January 1, 2026 – March 31, 2026). If extended, the second Performance Period will be January 1, 2027-March 31, 2027.ext
Addendum prepared by:
Marcus Jones Marcus.Jones@odfw.oregon.gov
END OF ADDENDUM No. 1 mailto:Marcus.Jones@odfw.oregon.gov