S02 Statement of Work.pdf
PDF 832 KB Posted
- Solicitation number
- 36C10D25B0001
- Issued by
-
Department of Veterans Affairs
About this file
This document is a Statement of Work (SOW) for the replacement of approximately 178 Variable Air Volume (VAV) terminal units in Building 46 at the St. Petersburg, Florida Veterans Affairs Regional Office (VARO).
The SOW requires the contractor to provide all labor, materials, and supervision necessary to replace the existing VAV boxes and ensure they are fully compatible and functional with the existing Johnson Controls Metasys system. Key requirements include submittal of product data, project schedule, safety plan, and other documents; pre-construction training and meetings; removal and replacement of VAV boxes and thermostats; testing and balancing; and a final punch list. The contractor must comply with security, safety, environmental, and quality control requirements. The period of performance is 180 calendar days. The related federal contract opportunity is an Invitation for Bids (IFB) solicitation for this VAV box replacement project at the St. Petersburg VARO.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C10D25B0001 0002.docx | DOCX document | |
| S02 VAV Box Schedule.pdf | ||
| 36C10D25B0001 0001.docx | DOCX document | |
| S05 Final Request for Information Responses - Questions 1-73.pdf | ||
| S02 Amended Statement of Work.pdf | ||
| S02 As-Built Drawings.pdf | ||
| S02 Justification and Approval.pdf | ||
| S04 Site Visit Sign-In Sheet.pdf | ||
| S02 Project Drawings .pdf | ||
| S02 Requests for Information Form.docx | DOCX document | |
| 36C10D25B0001_2.docx | DOCX document | |
| S02 Limitations on Subcontracting Certificate of Compliance - Special Trade Construction.docx | DOCX document | |
| S02 Construction Wage Rate Determination (Pinellas County - FL).pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ent of Work
Variable Air Volume (VAV)
Terminal Unit Replacements
Table of Contents
1. Background
2. Scope
2.1 - Submittals
2.2 - Products
2.2.1 - Labeling
2.2.2 - Calibration
2.2.3 - Compatibility of Related Equipment
2.2.4 - Equipment and Materials Identification
2.2.5 - Air Terminal Units (VAV Boxes)
2.3 - Non-Personal Services
2.4 - Subcontract Management
2.5 - Schedule and Hours of Work
2.6 - Period of Performance……………………………………….……………………………….7
3. Performance Requirements
3.1 - Pre-Construction Conference…………………….………………………………………….8
3.2 - Pre-Construction Mandatory Training
3.3 - Mandatory Document Submissions
3.4 - Terminal Units / VAV Boxes …….…………………………………………………………..9
3.5 - Project Meetings…………………………….………………………………………...………9
3.6 - Punch List Activities
4. Safety
4.1 - Security
4.1.1 - Badging and Identification
4.2 - Safety
4.2.1 - Mishaps
5. Government Furnished Materials
6. Environmental Requirements
6.1 - Non-Hazardous Waste Disposal……………………………....…………………………..12
6.2 - Hazardous Waste Disposal…………………………………….…………………..………12
7. Quality
7.1 - Quality Control ...............................................................................................……….13
8. Related Documents.………………………..……...……………………………………..…….13
Attachment A - Location of VAVs.……………………………………………………………… 15
Attachment B - VA Forms ………………………………………………….…………………….16
Statement of Work
Variable Air Volume (VAV) Terminal Unit Replacements
1. Background
The St. Petersburg, Florida, Veterans Affairs Regional Office (VARO) consistently has difficulties of maintaining the temperature inside Building 46. The major contributing factor for the air temperature stability or lack thereof is the replacement of numerous VAV boxes. As of September 5, 2024, the St. Petersburg VARO must replace approximately one hundred seventy-eight (178) terminal units to manage the air temperatures within Building 46.
2. Scope
Contractor will provide all labor, personnel, transportation, materials, apparatus, tools, equipment, services, and supervision necessary to perform the installation of one hundred seventy-eight (178) terminal units. Furthermore, upon replacing the terminal units, the Contractor will also ensure that the units are connected to and compatible with the existing Johnson Controls Metasys, which shall include graphic display, location on floor drawings, and functionality. The replacement terminal units will appear and function on metasys as do the existing terminal units being displayed on the Johnson Controls Metasys. The Contractor shall also replace the existing thermostat. Upon completion of replacing the terminal units, the Contractor will ensure that the ceiling grid and ceiling tiles are returned to preexisting condition.
The Contractor will conduct a joint final punch list with the Contracting Officer’s Representative (COR) that ensures all units are functioning appropriately.
2.1 Submittals
Material submittals shall be distributed to the COR and the Contracting Officer for review before installation and application. The Contractor shall create, update, distribute, file, maintain, reproduce, and allow VA access to documents necessary or appropriate in the performance of work under this Statement of Work. The Contractor is responsible for all submittals meeting the VA specifications and requirements. All submittals will be presumed to meet the VA specifications unless the Contractor has requested a variance in writing and approved by COR prior to providing the submittal. The Contractor, at no expense to VA, must correct and resubmit improperly prepared records rejected by the COR.
The Contractor shall provide all applicable material submittals for this project to be reviewed by the COR and the Contracting Officer. The COR shall review and issue appropriate action (approve, disapprove, revise/resubmit) on each material submittal within five (5) business days of receipt. Material submittals shall also include a Project Superintendent Letter, OSHA Certifications, and Schedule of Values/Project Schedule. Material submittals shall also include Shop Drawings, Product Data, and Samples.
Contractor shall make all necessary field measurements and investigations to assure that the equipment and assemblies will meet requirements. Contractor shall also verify all equipment that requires regular maintenance, calibration, etc. are accessible from the floor or permanent work platform.
Contractor will provide complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide that at a minimum shall incorporate the following information:
1. Complete list indicating all components of the systems;
2. Complete diagrams of the internal wiring for each item of equipment;
3. Diagrams with terminals identified to facilitate installation, operation and maintenance;
and
4. List of recommended replacement parts to keep in stock supply, including sources of supply, for equipment.
2.2 Products
Contractor shall provide maximum standardization of components to reduce spare part requirements. Performance and warranty of all components that comprise an assembled unit shall be the responsibility of the manufacturer of the completed assembly. For product assembly and product variance, the following guidelines must be used:
1. All components of an assembled unit need not be products of the same manufacturer.
2. Constituent parts that are alike shall be products of a single manufacturer.
3. Components shall be compatible with each other and with the total assembly for intended service.
Contractor shall guarantee performance of component assemblies and shall also replace elements of the assemblies, as required, to deliver specified performance of the complete assembly.
Equipment and components of equipment shall bear manufacturer's name, trademark, model number, serial number and performance data on a nameplate securely affixed in a conspicuous place or otherwise permanently marked upon the components of the equipment.
Major items of equipment, which serve the same function, must be the same make and model.
Exceptions must be approved by the VA, but may be permitted if performance requirements cannot be met.
2.2.1 Labeling
Control box shall be clearly marked with an identification label that lists such information as nominal cubic feet per minute (CFM), maximum factory-set airflow limits, minimum factory-set airflow limits, coil type, and coil connection orientation, where applicable.
2.2.2 Calibration
Factory calibrates air terminal units to air flow rate indicated. All settings including maximum and minimum air flow shall be field adjustable.
2.2.3 Compatibility of Related Equipment
Equipment and materials installed shall be compatible in all respects with other items being furnished as well as with existing items for a result that will be a complete and fully operational plant conforming to contract requirements.
2.2.4 Equipment and Materials Identification
Control Items: Label all instrumentation, temperature and humidity sensors, controllers, and control dampers. Identify and label each item as said item appears on the control diagrams.
Ceiling Grid Labels: 50 millimeters (2 inches) long by 15 millimeters (1/2 inch) wide by 0.025 millimeters (1 mil) thick ultraviolet (UV) resistant metalized polyester label with red border color and black custom lettering on white background interior. Peel and stick adhesive backing. Label and adhesive manufactured specifically for use in equipment inventory tagging.
Custom print labels with above ceiling heating, ventilation, and air conditioning (HVAC) equipment numbers.
2.2.5 Air Terminal Units (VAV Boxes)
General: Factory built, pressure independent units, factory set field adjustable air flow rate, suitable for single duct applications. Use of dual-duct air terminal units is not permitted.
Capacity and Performance: The maximum capacity of a single terminal unit shall not exceed 566 liters per second (1,700 CFM).
Casing: Unit casing shall be constructed of galvanized steel no lighter than 0.85 millimeters (22 gauge). Provide hanger brackets for attachment of supports.
Lining Material: Suitable to provide required acoustic performance, thermal insulation, and prevent sweating. Meet the requirements of National Fire Protection Association (NFPA) 90A and comply with Underwriters Laboratories (UL) 181 for erosion as well as American Society for Testing and Materials (ASTM) C 665 antimicrobial requirements. Insulation shall consist of 13 millimeter (1/2 inch) thick, non-porous foil faced rigid fiberglass insulation of 4 pounds per cubic foot, secured by full length galvanized steel z-strips, which enclose and seal all edges. Tape and adhesives shall not be used. Materials shall be non-friable and with surfaces, including all edges, fully encapsulated and faced with perforated metal or coated to such an extent that the air stream will not detach material.
Access Panels or Doors: Provide panels large enough for inspection, adjustment, and maintenance without disconnecting ducts. Provide panels also for cleaning heating coils attached to each unit even if there are no moving parts. Panels shall be insulated to the same standards as the rest of the casing as well as secured and gasketed airtight. Panel accessibility shall require no tool other than a screwdriver to remove.
Total Leakage from Casing: Shall not exceed 2 percent of the nominal capacity of the unit when subjected to a static pressure of 750 pascal (Pa) - 3 inch water gauge (wg) with all outlets sealed shut and inlets fully open.
Octopus Connector: Factory installed, lined air distribution terminal. Provide butterfly-balancing damper with locking means in connectors that contain more than one outlet.
Dampers: Construct dampers and other internal devices of corrosion resisting materials, which do not require lubrication or other periodic maintenance. Damper Leakage shall not be greater than 2 percent of maximum rated capacity, when closed against inlet static pressure of 1 Kilopascal (kPa) - 1 inch WG.
2.3 Non-Personal Services
The Government shall neither supervise employees of the Contractor or subcontractor forces nor control the method by which the Contractor performs the required tasks. Under no circumstances shall the Government assign tasks to, or prepare work schedules for, employees of the Contractor or subcontractor forces. The Contractor shall be responsible for managing all employees of the Contractor and subcontractor forces as well as to guard against any actions that are of the nature of personal services or give the perception of personal services. If the Contractor believes that any actions constitute, or are perceived to constitute personal services, then the Contractor shall notify the Contracting Officer immediately.
2.4 Subcontract Management
The Contractor shall be responsible for any subcontract management necessary to integrate work performed on this requirement. The Contractor shall also be responsible and accountable for subcontractor performance on this requirement. At all times during performance of this Contract as well as until the work is completed and accepted, the Contractor shall directly superintend the work. The Contractor shall have a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the Contractor on the worksite at all times.
The Contractor will manage work distribution to ensure there are no Organizational Conflict of Interest considerations. Contractors may add subcontractors to the team after notification to the Contracting Officer and COR with proper documentation [Standard Form 1413].
2.5 Schedule and Hours of Work
All work will be performed Monday through Friday, except Federal holidays, between the hours of 6:00 am and 6:00 pm Eastern Standard Time (EST). Work may be performed on Saturdays or Sundays through prior coordination with and approval by the COR. The Contractor must provide the Contracting Officer and COR with a Project Schedule as well as a Schedule of Values prior to the commencement of any work at the project site.
2.6 Period of Performance
The period of performance for this project will be one hundred eighty (180) calendar days from the issuance of the Notice to Proceed (NTP) that includes the performance and completion of all services incorporated in this Statement of Work.
3. Performance Requirements
The following section specifies the performance objectives and performance elements for this Contract.
3.1 Pre-Construction Conference
After the initial requisite post-award documentation is submitted by the Contractor, then the Contractor shall attend the Preconstruction Conference face-to-face at the St. Petersburg VARO. At a minimum, the Project Foreman and Site Superintendent will attend.
Initial Post-Award Documentation Deliverables
1) Performance Bond
2) Payment Bond
3) Liability Insurance Certificate
3.2 Pre-Construction Mandatory Training
Contractor will ensure all employees who will be working on this project attend the VA Information Assurance and Security Training prior to beginning any work on this project. Refer to Section 4 within this Statement of Work for further instructions.
Deliverables
1) VA Information Security Training
2) Rules of Behavior Training
3.3 Mandatory Document Submissions
Contractor will submit the following documentation:
• Site Superintendent Letter on company letterhead within ten (10) business days from the issuance of the Notice to Proceed (NTP).
• Project Schedule to the Contracting Officer and COR within ten (10) business days from the issuance of the NTP.
• Schedule of Values to the Contracting Officer and COR within ten (10) business days from the issuance of the NTP.
• Current Occupational Safety and Health Administration (OSHA) 30 hour Safety Training Certificate for the Project Foreman and Site Superintendent. OSHA 10 hour Safety Training Certificate for all other employees should be maintained by the Contractor and provided to the Contracting Officer and COR upon request.
• Health/Safety Plan within ten (10) business days or prior to any work performed inside the building.
• Risk Assessment / Activity Hazards Analysis (AHA) within ten (10) business days or prior to any work performed inside the building.
• Standard Form (SF) 1413 for each subcontract engaged during the project or on the work site within ten (10) business days or prior to any work performed inside the building.
• Material Submittals for any materials utilized during the performance of the project including the terminal units. All VAV boxes must meet the same salient characteristics of the existing VAV boxes.
• Daily Logs supplied to the Contracting Officer and COR for regular compliance checks of project status and monitor performance progress.
Refer to Section 4 within this Statement of Work for specific training and document submission requirements.
Deliverables
1) Executed NTP
2) Site Superintendent Letter
3) Project Schedule
4) Schedule of Values
5) OSHA 30 hour Certificate
6) Health / Safety Plan
7) Risk Assessment / AHA
8) Any and all SF 1413s
9) Any and all Material Submittals
10) Daily Logs
3.4 Terminal Units / VAV Boxes
Contractor will remove ceiling grid and ceiling panels, as required, in order to replace the one hundred eighty-seven (178) terminal units located throughout Building 46 at the St. Petersburg VARO. Contractor will ensure upon replacement of the existing terminal units that the new terminal units are connected and fully functional on the Metasys system. Contractor shall also ensure that the graphics for the terminal units are installed and functioning on the Metasys system.
Graphics install would include ensuring the terminal unit graphic is identifiable, displayed, and functional as the existing terminal unit graphics on the Metasys system. A Test-Adjust-Balance (TAB) must be performed for each terminal unit ensuring it performs to existing design specifications.
Deliverables Operator’s Manual for terminal units
3.5 Project Meetings
The Contractor shall attend each project meeting that will be conducted. Said project meetings will be scheduled on a biweekly basis. Meeting minutes shall be drafted, completed, and submitted by the Contractor to the Contracting Officer and COR within three (3) business days after each designated meeting.
Deliverables Meeting Minutes
3.6 Punch List Activities
The Contractor will conduct a walkthrough with the COR to prepare a 'joint' punch list. From any faults, omissions, or improvements identified in the ‘joint’ punch list, the Contractor will proceed to correct accordingly. Upon the Contractor correcting all faults identified on the ‘joint’ punch list, the COR and the Contractor will then conduct another walkthrough. After acceptance by the COR that all faults have been adequately corrected and the work accepted, the Contractor will then submit an executed 'Release of Claim' letter to the Contracting Officer and the COR. Final payment will not be processed or approved until an executed Release of Claims has been properly submitted by the Contractor.
Deliverables
1) Punch List
2) Executed Release of Claims
4. Security and Safety
This section describes the special requirements for this effort. The following subsections provide details of various considerations on this effort.
4.1 Security
During normal business hours designated as 6:00 am to 6:00 pm EST, the Contractor is required to enter and exit the St Petersburg VARO through the front entrance. Entering or exiting the building through any other door will require VARO approval and an escort will be required. Upon entering the building, the Contractor, employees of the Contractor, any subcontractors, or other personnel associated with the Contractor will be required to show proof of identity, by means of valid photo identification, as well as pass through a security screening.
Based upon the sensitivity and personal information processed at the VARO, applicable individuals with the Contractor, employees of the Contractor, any subcontractors, or other personnel associated with the Contractor for this project will be required to complete VA Privacy and Information Security and Rules of Behavior Training. This training will be provided by the COR to the applicable individuals with the Contractor, employees of the Contractor, any subcontractors, or other personnel associated with the Contractor for this project. The Contractor will coordinate and schedule the training with the COR. The VA Privacy and Information Security and Rules of Behavior Training must be completed within ten (10) business days from the contract award date. Additionally, VA Form 20-0334 and VA Form 0711 must be completed by the applicable individuals with the Contractor, employees of the Contractor, any subcontractors, or other personnel associated with the Contractor for this project. Original copies of the VA Form 20-0344 and VA Form 0711 must be submitted to the COR before construction-related services commence.
VA Form 20-0344 and VA Form 0711 are enclosed as Attachment B within this Statement of Work.
4.1.1 Badging and Identification
Homeland Security Presidential Directive (HSPD) 12 directs all federal agencies and departments to issue identity credentials. Pursuant to HSPD 12, federal agencies shall issue government workers, contractors, and affiliates with a credential that provides the attributes of security, authentication, trust, and privacy, which can be used in verifying identities upon entering federal buildings and/or gaining access to federal computer networks.
All applicable individuals with the Contractor, employees of the Contractor, any subcontractors, or other personnel associated with the Contractor for this project that will enter the VARO space are required to have an individual non-personal identification verification (PIV) badge before any construction-related services work commences. Therefore, the Contractor shall complete Section I of the VA Form 0711 for all employees, employees of subcontractors, or other personnel associated with the Contractor who will be working inside the VARO space on any aspect of this project. The Contractor must provide all of the completed VA Forms 0711 to the COR within five (5) business days from the contract award date. Once the COR receives a properly completed VA Form 0711, a non-PIV badge will take approximately two (2) business days to be prepared.
The Contractor will be notified by the COR when each employee, employee of subcontractors, or other personnel must report to Room 238 (PIV Office) for photographs and issuance of a non-PIV badge. The employee, employee of subcontractors, or other personnel must bring two
(2) forms of identification when reporting to Room 238. The Contractor is responsible for the cost of fingerprinting and background investigations, if required. The Contractor should also include the time necessary to process non-PIV badges in the construction project schedule.
4.2 Safety
Equipment: The Contractor shall provide all safety equipment, devices, material data safety sheets (MSDS), and personal protective equipment (PPE), as required, for employees and subcontractor forces. Copies of all MSDS shall be provided to the COR.
OSHA: Prior to commencing work, the Contractor shall provide proof that an OSHA designated "competent person” will maintain a presence at the work site during all times. The Project Foreman and Site Superintendent for the Contractor will have completed no less than thirty (30) hours of OSHA approved safety training. The Site Superintendent may be the same individual as the Site Safety and Health Officer (SSHO). All other employees of the Contractor will have no less than ten (10) hours of OSHA approved safety training.
Safety Plan and AHA: Contractor will provide a site-specific safety plan as well as an AHA. An example of a VA approved AHA can be found at http://www.usace.army.mil/Portals/2/docs/AHA2.pdf.
Compliance: The Contractor shall comply with all applicable Federal, State, and local requirements regarding workers’ health and safety. Said requirements include, but are not limited to, those found in Federal OSHA as well as State OSHA statutes and regulations, such as applicable provisions of Title 29 in the Code of Federal Regulations (CFR), Parts 1910 and 1926. Contractor is solely responsible in determining the legal requirements applicable to any construction-related activities that shall ensure safe and healthy working conditions for all employees of the Contractor and subcontractor forces.
4.2.1 Mishaps
Mishap Notification: The Contractor shall promptly report pertinent facts regarding mishaps involving Government property damage or injury to Government personnel caused by the employees of the Contractor or subcontractor forces. The Contractor shall notify the Contracting Officer and the COR, in writing, within four (4) hours of any mishap or incident. The aforementioned Government personnel will consequently then notify the Safety Officer.
Notifications from the Contractor of any mishap that are made after duty hours shall be reported to the appropriate Government personnel on duty at the time of the mishap. The Contractor shall immediately secure the affected area of the project site and/or the damaged property if requested by the Contracting Officer, the COR, or the Safety Officer. The Contractor must impound pertinent maintenance and training records until released by the investigating Safety Officer.
Mishap Investigation: The Contractor, employees of the Contractor, and subcontractor forces shall cooperate in any resulting safety investigation from mishaps involving Government property damage or injury to Government personnel. If the Government determines to investigate the mishap, then the Contractor and subcontractor forces shall cooperate fully and assist the Government personnel until the investigation is completed.
5. Government Furnished Materials
The Government shall provide the following items:
• Parking space availability and access to the VARO loading docks, as necessary.
• Space to place a container, if needed, for either material storage and/or dumpsters that must be coordinated with and approved by the COR.
• Staging area for VAV boxes, tools, and equipment in a location to be approved by the
COR.
6. Environmental Requirements
This section describes the potential environment-related components for this requirement. The following subsections provide details of various considerations on this effort.
6.1 Non-Hazardous Waste Disposal
Demolition: The Contractor shall provide all demolition, removal, and legal disposal of materials.
The Contractor shall ensure that facilities used for recycling, reuse, and disposal shall be permitted as the intended use to the extent required by local, state, and federal regulations.
Disposal: The Whole Building Design Guide website provides a Construction Waste Management Database that contains information on companies that haul, collect, and process recyclable debris from construction projects. To access this database, visit http://www.cwm.wbdg.org.
6.2 Hazardous Waste Disposal
Abatement: In order to provide for abatement and control of all environmentally hazardous materials arising from demolition and/or construction activities, the Contractor shall comply with http://www.cwm.wbdg.org/ all applicable environmentally hazardous material control and abatement as well as all applicable provisions of the Corps of Engineers Manual Number 385-1-1. Effective as of March 15, 2024, said Manual can be found as follows:
https://www.publications.usace.army.mil/Portals/76/EM%20385-1- 1%20_EFFECTIVE%2015March2024.pdf
Manifesto: The Contractor shall provide a waste manifesto for all hazardous waste disposals.
For any hazardous materials or hazardous waste removal, the Contractor shall also comply with all OSHA regulations, most notably the safety and health regulations for construction in 29 Code of Federal Regulations (CFR) Part 1926 as well as 29 CFR Subpart C, Section 1926.20.
7. Quality
This section describes the quality Control components for this effort. The following subsections provide details of various considerations on this effort.
7.1 Quality Control
The Contractor shall develop a Quality Control Plan (QCP) and maintain an effective quality control program to ensure services are performed in accordance with this Statement of Work.
The Contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The Contractor’s QCP is how to assure that the work complies with the requirements of the Contract.
The QCP will be reviewed by the Government within ten (10) business days from the date of submission, then either accepted or disapproved for required revisions. The Contracting Officer or the COR may notify the Contractor of required modifications to the QCP during the period of performance. The Contractor shall then coordinate suggested modifications and obtain acceptance of an updated QCP by the Contracting Officer and the COR. Any program/plan modifications during the period of performance shall be submitted to the Contracting Officer and the COR for review no later than ten (10) business days before the proposed effective date of the change. Any version of a QCP shall be subject to the Government’s review and approval.
The Government may find the QCP "unacceptable" whenever the Contractor’s procedures do not accomplish quality control objective(s). The Contractor shall revise and resubmit the QCP within ten (10) business days from receipt of notice that the QCP was found unacceptable.
8. Related Documents
The following documents are related to this project:
a) VA Specification 23 36 00 titled Air Terminal Units.
b) VHA Directive 2011-036, Safety and Health During Construction, that can be found at http://www.va.gov/vhapublications/ViewPublication.asp?pub_ID=2448.
c) VA Handbook 6500.6, Appendix D, Contractor Rules of Behavior, that can be found at http://www.va.gov/vapubs/viewPublication.asp?Pub_ID=471&FType=2.
https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf http://www.va.gov/vhapublications/ViewPublication.asp?pub_ID=2448
d) ASCE 7-02 Minimum Design Loads for Buildings and Other Structures, Second Edition, that can be found at https://law.resource.org/pub/us/cfr/ibr/003/asce.7.2002.pdf.
e) 29 CFR Subpart C, Section 1926.20 - Application of the Multi-Employer Policy to Particular Construction Standards, that can be found at https://www.osha.gov/pls/oshaweb/owasrch.search_form?p_doc_type=INTERPRETATIONS&p _toc_level=3&p_keyvalue=1926.20&p_status=CURRENT.
f) ASTM 665-06 titled Standard Specification for Mineral-Fiber Blanket Thermal Insulation for Light Frame Construction and Manufactured Housing.
g) Air Movement and Control Association (AMCA) 410-1996 titled Recommended Safety Practices for Users and Installers of Industrial and Commercial Fans.
h) American Society of Mechanical Engineers (ASME) B31.9-2014 titled Building Services Piping.
i) ASME B31.1-2014 titled Power Piping.
j) NFPA 70, 2014 titled the National Electrical Code.
k) NFPA 101, 2015 titled Life Safety Code.
l) NFPA 90A titled Standard for the Installation of Air Conditioning and Ventilating Systems.
m) Air Conditioning, Heating, and Refrigeration Institute (AHRI) Standard 880-2017 (R2023) (I- P) titled Performance Ratings of Air Terminals.
n) AHRI Standard 885 titled Procedure for Estimating Occupied Space Sound Levels in the Application of Air Terminals and Air Outlets.
o) Johnson Controls Model TSS Single Duct VAV Terminal located at http://www.johnsoncontrols.com/en_au/-/media/jci/be/australia/air-systems/variable-air-volume-terminals/files/be_productcatalog_tss.pdf?la=en.
p) Florida Building Codes that can be found at http://floridabuilding.org/bc/bc_default.aspx.
http://www.johnsoncontrols.com/en_au/-/media/jci/be/australia/air-systems/variable-air-volume-terminals/files/be_productcatalog_tss.pdf?la=en http://www.johnsoncontrols.com/en_au/-/media/jci/be/australia/air-systems/variable-air-volume-terminals/files/be_productcatalog_tss.pdf?la=en
Attachment A – Location of VAVs
For the most-recent drawings of the VAV Box locations in Building 46, refer to the separate attachment titled ‘Project Drawings’. Nearly all of the VAV Boxes have not been replaced or moved since the inception of the initial building construction. Each of the three (3) floors of Building 46 have been broken down into four (4) quadrants, for a total of twelve (12) drawings, that properly depict the area and location of the VAV Boxes.
Attachment B - VA Forms