This solicitation is for exterior stair improvement work at a Veterans Affairs medical facility. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 1 is seeking bids to complete exterior stair repairs and improvements as detailed in the attached plans and specifications. Bids are due by the date listed in the IFB document and the contract is expected to be awarded shortly thereafter. The selected contractor will be responsible for furnishing all labor, materials, equipment and supervision to complete the exterior stairwork as outlined. Relevant experience with similar projects for government agencies is preferred.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SHEET 1 OF 15

EXTERIOR STAIR AND RAILING IMPROVEMENTS

VA CENTRAL WESTERN MASSACHUSETTS

HEALTHCARE SYSTEM—LEEDS, MA

PROJECT NUMBER: 631-22-002

DRAWING INDEX

SHEET NUM-

BER OF TOTAL

Site

No.

Bldg.

No. SHEET TITLE

1 of 15 Cover Sheet

2 of 15 General notes

3 of 15 Overall Site Plan

4 of 15 1 4 Building 4 Site Plan

5 of 15 1 4 Building 4 Stair Plan

6 of 15 3 20 Building 20 Stair and Walkway 1 of 2

7 of 15 3 20 Building 20 Stair and Walkway 2 of 2

8 of 15 2 4 Building 4 Lower Ramp Railing

8 of 15 5 20 Building 20 to Parking Lot P Stair and Walkway

9 of 15 4 20 Existing site plan

10 of 15 4 20 Existing Wall and New Fence Details

11 of 15 6 11 Building 11 South Stair Railing & Gate

11 of 15 7 11 Building 11 North Railing

12 of 15 8 11 Building 11 Demo Sidewalk & Stairs

12 of 15 9 60 Infill Wall and add railing

12 of 15 10 1 Biomed Stair repair

13 of 15 Erosion Control Details

14 of 15 Sidewalk Details

15 of 15 Stair Details

SHEET 2 OF 15

SHEET 3 OF 15

OVERALL SITE PLAN

SITE BUILDING DESCRIPTION

1 Building 4 Remove and Replace the metal stairs and sidewalks at the surrounding the entrances

2 Building 4 Southeast – Install metal railing along the exit ramp

3 Building 20 Construct a sidewalk with stairs from Building 1 to Building 20

4 Building 20 Install Fence on top of Retaining wall for fall protection

5 Building 20 Construct a new sidewalk from Parking lot P to Building 20

6 Building 11 Remove and replace the metal railings outside the stage entrance

7 Building 11 Remove and replace the metal railings on south side stairs

8 Building 11 Remove exterior stairs near the patio and the associated sidewalk

9 Building 60 Remove the exterior step and install a concrete wall at the opening

10 Building 1 Repair the stairs and stairwell walls

SHEET 4 OF 15

SITE 1—BUILDING 4 SITE PLAN

SHEET 5 OF 15

SPECIAL NOTES:

1.REVISE BALUSTERS TO 4” O.C. VERTICAL BALUSTERS SEE DETAILS 5 AND

6 ON SHEET 15

2.ALL DIMENSIONS ARE TO BE FIELD VERIFIED

3.SHOP DRAWINGS MUST BE APPROVED BY COR PRIOR TO FABRICATION

SITE 1—BUILDING 4 METAL STAIRS

SHEET 6 OF 15

SITE 3—BUILDING 1 TO BUILDING 20

STAIRS & WALKWAY 1 OF 2

SHEET 7 OF 15

SITE 3—BUILDING 1 TO BUILDING 20

STAIRS & WALKWAY 2 OF 2

SPECIAL NOTES:

1.SEE SHEET 15 DETAILS 1,2, & 3 FOR STAIR AND

RAILING DETAILS

2.SEE SHEET 14 FOR SIDEWALK DETAIS

3.FIELD VERIFY ALL DIMENSIONS

SHEET 8 OF 15

SHEET 9 OF 15

SITE 4—BUILDING 20 RETAINING

WALL EXISTING CONDITIONS

EXISTING WALL

LOCATION

SHEET 10 OF 15

SHEET 11 OF 15

SHEET 12 OF 15

SITE 9—BUILDING 60 INFILL WALL

AND ADD RAILING

SITE 10—BUILDING 20 RETAINING

WALL EXISTING CONDITIONS

SITE 8—BUILDING 11 DEMO STAIRS

AND WALKWAY

INSTALL RAILINGS TO CLOSE OPENING. MATCH

EXISTING RAILING

1. REMOVE CONCRETE FROM EXTERIOR, BACK-

FILL, LOAM & SEED

2. DOWEL #4 BARS INTO EXISTING CONCRETE, 4

EACH SIDE.

3. INFILL OPENING WITH 3/4”, 4000PSI CON-

CRETE.

4. RUB AND FINISH TO MATCH EXISTING.

1. REMOVE EXISTING NOSINGS

2. REPAIR DETERIORATED CONCRETE STEPS TO SOUND

CONCRETE

3. SEAL CRACKS IN CONCRETE TO REMAIN

4. REFASTEN RAILINGS TO NORTH WALL

SHEET 13 OF 15

SHEET 14 OF 15

SHEET 15 OF 15