S02 Project Specifications .pdf
PDF 168 KB Posted
- Solicitation number
- 36C24124R0034
About this file
This document provides project specifications for a roof replacement project at a VA medical center. The project involves a full tear-off of existing roof systems on two buildings and installation of a new fluid-applied membrane roofing system incorporating insulation, a base ply sheet, and polyurethane roof coating. The specifications define requirements for roof tear-off, deck preparation, insulation, flashing, and application of the new membrane. The related federal contract opportunity is a request for SF330 qualifications from architecture and engineering firms for design services on the roof replacement and solar upgrade project. The solicitation is a full and open competition being conducted by the VA Veterans Health Administration VISN 1 to design and engineer the roof replacement and addition of solar panels.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24124R0034.docx | DOCX document | |
| S02 Drawings - Existing .pdf | ||
| S02 Past Performance Questionnaire.pdf | ||
| S02 Drawings - Replacement and Restoration .pdf | ||
| S02 Statement of Work .pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VA West Haven Date of Issue (01/06/2022) Building 1 & 2 Building 1&2
061053 - Page 1 of 6
MISCELLANEOUS ROUGH CARPENTRY
SECTION 061053 - MISCELLANEOUS ROUGH CARPENTRY
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Rooftop equipment bases and support curbs.
2. Wood blocking, cants, and nailers.
1.2 DEFINITIONS
A. Boards or Strips: Lumber of less than 2 inches nominal (38 mm actual) size in least dimension.
B. Dimension Lumber: Lumber of 2 inches nominal (38 mm actual) or greater size but less than 5 inches nominal 5 inches nominal (114 mm actual) size in least dimension.
C. Board Foot: Unit of measure for volume of lumber, equal to 144 cubic inches.
1.3 ACTION SUBMITTALS
A. Product Data: For each type of process and factory-fabricated product. Indicate component materials and dimensions and include construction and application details.
1. Include data for wood-preservative treatment from chemical treatment manufacturer and certification by treating plant that treated materials comply with requirements. Indicate type of preservative used and net amount of preservative retained.
2. Include data for fire-retardant treatment from chemical treatment manufacturer and certification by treating plant that treated materials comply with requirements. Include physical properties of treated materials based on testing by a qualified independent testing agency.
3. For fire-retardant treatments, include physical properties of treated lumber both before and after exposure to elevated temperatures, based on testing by a qualified independent testing agency according to ASTM D5664.
4. For products receiving a waterborne treatment, include statement that moisture content of treated materials was reduced to levels specified before shipment to Project site.
5. Include copies of warranties from chemical treatment manufacturers for each type of treatment.
1.4 QUALITY ASSURANCE
A. Testing Agency Qualifications: For testing agency providing classification marking for fire-retardant treated material, an inspection agency acceptable to authorities having jurisdiction that
Building 1&2
061053 - Page 2 of 6 periodically performs inspections to verify that the material bearing the classification marking is representative of the material tested.
1.5 DELIVERY, STORAGE, AND HANDLING
A. Stack lumber flat with spacers beneath and between each bundle to provide air circulation.
Protect lumber from weather by covering with waterproof sheeting, securely anchored. Provide for air circulation around stacks and under coverings.
PART 2 - PRODUCTS
2.1 WOOD PRODUCTS, GENERAL
A. Lumber: American Softwood Lumber Standard PS 20 and applicable rules of grading agencies indicated. If no grading agency is indicated, provide lumber that complies with the applicable rules of any rules-writing agency certified by the ALSC Board of Review. Provide lumber graded by an agency certified by the ALSC Board of Review to inspect and grade lumber under the rules indicated.
1. Factory mark each piece of lumber with grade stamp of grading agency.
2. Where nominal sizes are indicated, provide actual sizes required by American Softwood Lumber Standard PS 20 for moisture content specified. Where actual sizes are indicated, they are minimum dressed sizes for dry lumber.
3. Provide dressed lumber, S4S, unless otherwise indicated.
B. Maximum Moisture Content of Lumber: 19 percent unless otherwise indicated.
2.2 WOOD-PRESERVATIVE-TREATED MATERIALS
A. Preservative Treatment by Pressure Process: AWPA U1; Use Category UC2 for interior construction not in contact with the ground, Use Category UC3b for exterior construction not in contact with the ground, and Use Category UC4a for items in contact with the ground.
1. Preservative Chemicals: Acceptable to authorities having jurisdiction and containing no arsenic or chromium.
B. Kiln-dry lumber after treatment to a maximum moisture content of 19 percent. Do not use material that is warped or does not comply with requirements for untreated material.
C. Mark lumber with treatment quality mark of an inspection agency approved by the ALSC Board of Review.
D. Application: Treat all miscellaneous carpentry, not requiring fire-retardant treatment, unless otherwise indicated.
Building 1&2
061053 - Page 3 of 6
2.3 FIRE-RETARDANT-TREATED MATERIALS
A. General: Where fire-retardant-treated materials are indicated or required by applicable code, use materials complying with requirements in this article, that are acceptable to authorities having jurisdiction, and with fire-test-response characteristics specified as determined by testing identical products per test method indicated by a qualified testing agency.
B. Fire-Retardant-Treated Lumber and Plywood by Pressure Process: Products with a flame spread index of 25 or less when tested according to ASTM E84, and with no evidence of significant progressive combustion when the test is extended an additional 20 minutes, and with the flame front not extending more than 10.5 feet (3.2 m) beyond the centerline of the burners at any time during the test.
1. Use treatment that does not promote corrosion of metal fasteners.
2. Exterior Type: Treated materials shall comply with requirements specified above for fire-retardant-treated lumber and plywood by pressure process after being subjected to accelerated weathering according to ASTM D2898. Use for exterior locations and where indicated.
C. Kiln-dry lumber after treatment to a maximum moisture content of 19 percent. Kiln-dry plywood after treatment to a maximum moisture content of 15 percent.
D. Identify fire-retardant-treated wood with appropriate classification marking of testing and inspecting agency acceptable to authorities having jurisdiction.
E. Application: Treat items required to be fire-retardant treated in accordance with applicable code, including the following:
1. Concealed blocking.
2.4 MISCELLANEOUS LUMBER
A. General: Provide miscellaneous lumber indicated and lumber for support or attachment of other construction, including the following:
1. Blocking.
2. Nailers.
3. Rooftop equipment bases and support curbs.
4. Cants.
B. For items of dimension lumber size, provide Construction or No. 2 grade lumber of any species.
C. For blocking not used for attachment of other construction, Utility, Stud, or No. 3 grade lumber of any species may be used provided that it is cut and selected to eliminate defects that will interfere with its attachment and purpose.
Building 1&2
061053 - Page 4 of 6
D. For blocking and nailers used for attachment of other construction, select and cut lumber to eliminate knots and other defects that will interfere with attachment of other work.
2.5 FASTENERS
A. General: Provide fasteners of size and type indicated that comply with requirements specified in this article for material and manufacture.
1. Where carpentry is exposed to weather, in ground contact, pressure-preservative treated, or in areas of high relative humidity, provide fasteners of Type 304 Stainless Steel.
B. Nails, Brads, and Staples: ASTM F1667.
C. Power-Driven Fasteners: NES NER-272.
D. Wood Screws: ASME B18.6.1.
E. Screws for Fastening to Metal Framing: ASTM C954, length as recommended by screw manufacturer for material being fastened.
F. Lag Bolts: ASME B18.2.1 (ASME B18.2.3.8M).
G. Bolts: Steel bolts complying with ASTM A307, Grade A (ASTM F568M, Property Class 4.6);
with ASTM A563 (ASTM A563M) hex nuts and, where indicated, flat washers.
H. Expansion Anchors: Anchor bolt and sleeve assembly of material indicated below with capability to sustain, without failure, a load equal to 6 times the load imposed when installed in unit masonry assemblies and equal to 4 times the load imposed when installed in concrete as determined by testing per ASTM E 488/E488M conducted by a qualified independent testing and inspecting agency.
1. Material: Stainless steel with bolts and nuts complying with ASTM F593 and ASTM F594, Alloy Group 1 or 2 (ASTM F738M and ASTM F836M, Grade A1 or A4).
PART 3 - EXECUTION
3.1 INSTALLATION, GENERAL
A. Set carpentry to required levels and lines, with members plumb, true to line, cut, and fitted. Fit carpentry to other construction; scribe and cope as needed for accurate fit. Locate nailers, blocking, and similar supports to comply with requirements for attaching other construction.
B. Where wood-preservative-treated lumber is installed adjacent to metal decking, install continuous flexible flashing separator between wood and metal decking.
C. Framing Standard: Comply with AF&PA's WCD 1, "Details for Conventional Wood Frame Construction," unless otherwise indicated.
Building 1&2
061053 - Page 5 of 6
D. Install plywood backing panels by fastening to studs; coordinate locations with utilities requiring backing panels. Install fire-retardant treated plywood backing panels with classification marking of testing agency exposed to view.
E. Do not splice structural members between supports unless otherwise indicated.
F. Provide blocking and framing as indicated and as required to support facing materials, fixtures, specialty items, and trim.
G. Provide fire blocking in furred spaces, stud spaces, and other concealed cavities as indicated and as follows:
1. Fire block concealed spaces behind combustible cornices and exterior trim at not more than 20 feet (6 m) o.c.
H. Sort and select lumber so that natural characteristics will not interfere with installation or with fastening other materials to lumber. Do not use materials with defects that interfere with function of member or pieces that are too small to use with minimum number of joints or optimum joint arrangement.
I. Comply with AWPA M4 for applying field treatment to cut surfaces of preservative-treated lumber.
1. Use inorganic boron for items that are continuously protected from liquid water.
2. Use copper naphthenate for items not continuously protected from liquid water.
J. Securely attach carpentry work to substrate by anchoring and fastening as indicated, complying with the following:
1. Table 2304.9.1, "Fastening Schedule," in ICC's International Building Code.
K. Use steel common nails unless otherwise indicated. Select fasteners of size that will not fully penetrate members where opposite side will be exposed to view or will receive finish materials.
Make tight connections between members. Install fasteners without splitting wood. Drive nails snug but do not countersink nail heads unless otherwise indicated.
3.2 WOOD BLOCKING, AND NAILER INSTALLATION
A. Install where indicated and where required for attaching other work. Form to shapes indicated and cut as required for true line and level of attached work. Coordinate locations with other work involved.
B. Attach items to substrates to support applied loading. Recess bolts and nuts flush with surfaces unless otherwise indicated.
Building 1&2
061053 - Page 6 of 6
3.3 PROTECTION
A. Protect miscellaneous rough carpentry from weather. If, despite protection, miscellaneous rough carpentry becomes wet, apply EPA-registered borate treatment. Apply borate solution by spraying to comply with EPA-registered label.
END OF SECTION 061053
Building 1&2
070150.19 - Page 1 of 12
PREPARATION FOR RE-ROOFING
SECTION 070150.19 - PREPARATION FOR RE-ROOFING
1.1 SUMMARY
A. Section Includes:
1. Roof replacement preparation consisting of full roof tear-off of entire roof system.
2. Roof rehabilitation preparation of roof system at designated roof areas.
3. Removal of flashings and counterflashings.
4. Temporary roofing.
5. Temporary roof drainage.
6. Removal and reinstallation of indicated components, accessories, and equipment.
7. Recycling of non-hazardous demolition and construction waste.
1.2 DESCRIPTION OF WORK
A. Re-roofing preparation Work consists of the following:
1. Preparation for Roof Area:
a. Preparation for: Roof replacement.
b. Existing Roof Type: Granular surfaced modified bituminous.
c. Existing Deck Type: Metal deck& Concrete deck.
d. Roof tear-off.
e. Removal and reinstallation of indicated components, accessories, and equipment.
f. Salvaging of non-hazardous demolition and construction waste.
g. Recycling of non-hazardous demolition and construction waste.
h. Uplift securement.
i. Removal of base flashings.
j. Temporary roof membrane.
Building 1&2
070150.19 - Page 2 of 12
1.3 MATERIALS OWNERSHIP
A. Except for items or materials indicated to be reused, reinstalled, or otherwise indicated to remain Owner's property, demolished materials shall become Contractor's property and shall be removed from Project site.
1.4 DEFINITIONS
A. Roofing Terminology: Refer to ASTM D1079 "Standard Terminology Relating to Roofing and Waterproofing" and glossary in applicable edition of NRCA's "The NRCA Roofing Manual:
Membrane Roof Systems" for definition of terms related to roofing work in this Section.
B. Full Roof Tear-Off: Removal of existing membrane roofing system from deck.
C. Remove: Detach items from existing construction and legally dispose of them off-site unless indicated to be removed and reinstalled.
D. Construction Waste: Building and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations. Construction waste includes packaging.
E. Demolition Waste: Building and site improvement materials resulting from demolition or selective demolition operations.
F. Disposal: Removal off-site of demolition and construction waste and subsequent sale, recycling, reuse, or deposit in landfill or incinerator acceptable to authorities having jurisdiction.
G. Recycle: Recovery of demolition or construction waste for subsequent processing in preparation for reuse.
H. Salvage: Recovery of demolition or construction waste and subsequent sale or reuse in another facility.
1.5 PREINSTALLATION MEETINGS
A. Preliminary Roofing Conference: Before starting removal Work, conduct conference at Project site.
1. Coordinate with roofing preinstallation meetings specified in Division 07 roofing section(s).
2. Review methods and procedures related to roofing tear-off, including, but not limited to, the following:
a. Reroofing preparation, including roofing system manufacturer's written instructions.
b. Temporary protection requirements for existing roofing system components that are to remain.
Building 1&2
070150.19 - Page 3 of 12
c. Existing roof drains and roof drainage during each stage of reroofing, and roof-drain plugging and plug removal.
d. Construction schedule and availability of materials, Installer's personnel, equipment, and facilities needed to avoid delays.
e. Existing roof deck conditions requiring Owner's Consultant notification.
f. Condition and acceptance of existing roof deck and base flashing substrate for reuse.
g. Structural loading limitations of roof deck during reroofing.
h. Base flashings, special roofing details, drainage, penetrations, equipment curbs, and condition of other construction that affect reroofing.
i. HVAC shutdown and sealing of air intakes.
j. Shutdown of fire-suppression, -protection, and -alarm and -detection systems.
k. Asbestos removal and discovery of asbestos-containing materials.
l. Governing regulations and requirements for insurance and certificates if applicable.
m. Existing conditions that may require Owner's Consultant notification before proceeding.
1.6 ACTION SUBMITTALS
A. Product Data: For each type of product indicated.
B. B. Temporary Roofing: Include Product Data and description of temporary roofing system. If temporary roof will remain in place, submit surface preparation requirements needed to receive permanent roof, and submit a letter from roofing membrane manufacturer stating acceptance of the temporary membrane and that its inclusion will not adversely affect the roofing system's resistance to fire and wind.
1.7 INFORMATIONAL SUBMITTALS
A. Qualification Data: For Installer including certificate that Installer is licensed to perform asbestos abatement and for refrigerant recovery technician.
B. Digital Images or Videos: Show existing conditions of adjoining construction and site improvements, including exterior and interior finish surfaces, which might be misconstrued as having been damaged by reroofing operations. Submit before Work begins.
C. Proposed Protection Measures: Submit report, including Drawings, that indicates the measures proposed for protecting individuals and property for environmental protection, for dust control and for noise control. Indicate proposed locations and construction of barriers.
Building 1&2
070150.19 - Page 4 of 12
D. Schedule of Re-Roofing Preparation Activities: Indicate the following:
1. Detailed sequence of re-roofing preparation work, with starting and ending dates for each activity. Ensure occupants' on-site operations are uninterrupted.
2. Interruption of utility services. Indicate how long utility services will be interrupted.
3. Coordination for shutoff, capping, and continuation of utility services.
4. Use of elevator and stairs.
5. Coordination of Owner's continuing occupancy of portions of existing building.
E. Statement of Refrigerant Recovery: Signed by refrigerant recovery technician responsible for recovering refrigerant, stating that all refrigerant that was present was recovered and that recovery was performed according to EPA regulations. Include name and address of technician and date refrigerant was recovered.
F. Landfill Records: Indicate receipt and acceptance of hazardous wastes, such as asbestos-containing material, by a landfill facility licensed to accept hazardous wastes.
1.8 CLOSEOUT SUBMITTALS
A. Certified statement from manufacturer of existing warranted roof system stating that existing roof warranty has not been affected by Work performed under this Section.
1.9 QUALITY ASSURANCE
A. Installer Qualifications: Installer of new membrane roofing system.
1. Approved by warrantor of existing roof system to work on existing roofing.
2. Licensed to perform asbestos abatement in the jurisdiction where Project is located.
B. Refrigerant Recovery Technician Qualifications: Certified by an EPA-approved certification program.
C. Regulatory Requirements:
1. Comply with governing EPA notification regulations before beginning membrane roofing removal.
2. Comply with hauling and disposal regulations of authorities having jurisdiction.
1.10 PROJECT / FIELD CONDITIONS
A. Owner will occupy portions of building immediately below reroofing area.
1. Conduct reroofing so Owner's operations will not be disrupted.
Building 1&2
070150.19 - Page 5 of 12
2. Provide Owner with not less than 48 hours' written notice of activities that may affect Owner's operations.
3. Coordinate work activities daily with Owner so Owner can place protective dust or water leakage covers over sensitive equipment or furnishings, shut down HVAC and fire-alarm or -detection equipment if needed, and evacuate occupants from below the work area.
4. Before working over structurally impaired areas of deck, notify Owner to evacuate occupants from below the affected area.
a. Verify that occupants below the work area have been evacuated before proceeding with work over the impaired deck area.
B. Protect building to be reroofed, adjacent buildings, walkways, site improvements, exterior plantings, and landscaping from damage or soiling from reroofing operations.
C. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities.
D. Limit construction loads on roof to rooftop equipment wheel loads and uniformly distributed loads not exceeding recommendations of Contractor's professional engineer based upon site inspection and analysis.
E. Weather Limitations: Proceed with reroofing preparation only when existing and forecasted weather conditions permit Work to proceed without water entering existing roofing system or building.
1. Remove only as much roofing in one day as can be made watertight in the same day.
F. Daily Protection: Coordinate installation of roofing so insulation and other components of roofing system not permanently exposed are not subjected to precipitation or left uncovered at the end of the workday or when rain is forecast.
G. Hazardous Materials: It is not expected that hazardous materials such as asbestos-containing materials will be encountered in the Work.
1. If materials suspected of containing hazardous materials are encountered, do not disturb;
immediately notify Owner's Consultant and Owner.
a. Obtain direction from Owner's Consultant before proceeding with work in the affected area.
PART 2 - PRODUCTS
2.1 TEMPORARY PROTECTION MATERIALS
A. EPS Insulation: Molded (expanded) polystyrene, ASTM C578.
B. Plywood: NIST DOC PS 1, Grade CD, Exposure 1.
C. Oriented Strand Board (OSB): NIST DOC PS 2, Exposure 1.
Building 1&2
070150.19 - Page 6 of 12
2.2 DECK REPAIR/REPLACEMENT MATERIALS
A. Metal Deck Repair Materials:
1. Roof Deck: Fabricate panels, without top-flange stiffening grooves, to comply with "SDI Specifications and Commentary for Steel Roof Deck," in SDI Publication No. 31, and with the following:
a. Gage, rib depth, rib configuration to match existing; three span; lapped and stitched joints.
b. Sheet Steel: ASTM A653/A653M, Grade A structural quality; with G90 coating (galvanized).
2. Fasteners:
a. Mechanical Fasteners: Corrosion-resistant, low-velocity, power-actuated or pneumatically driven carbon-steel fasteners; or self-drilling, self-threading screws.
b. Side-Lap Fasteners: Corrosion-resistant, hexagonal washer head; self-drilling, carbon-steel screws, No. 10 (4.8 mm) minimum diameter.
3. Accessories: Provide manufacturer's standard accessory materials for deck that comply with requirements indicated.
B. Concrete Deck Repair Materials:
1. Bonding Agent: Epoxy-modified, cementitious bonding and anticorrosion agent consisting of water-insensitive epoxy adhesive, portland cement, and water-based solution of corrosion-inhibiting chemicals that forms a protective film on steel reinforcement.
2. Patching Mortar: Trowelable cementitious repair mortar for vertical and overhead, repairs up to 2 inches (50 mm) per lift, one component, fiber reinforced, polymer modified repair mortar containing corrosion inhibitor.
a. Compressive Strength: Not less than 6000 psi (41400 kPa) at 28 days when tested according to ASTM C 109/C 109M, modified 2-inch (50-mm) cubes.
2.3 TEMPORARY ROOFING MATERIALS
A. Design and selection of materials for temporary roofing are responsibilities of Contractor.
2.4 TEMPORARY ROOF DRAINAGE
A. Design and selection of materials for temporary roof drainage are responsibilities of the Contractor.
Building 1&2
070150.19 - Page 7 of 12
PART 3 - EXECUTION
3.1 PREPARATION, GENERAL
A. Protection of In-Place Conditions: Protect existing roofing system that is indicated not to be reroofed.
1. Loosely lay 1-inch- (25-mm-) minimum thick, molded expanded polystyrene (EPS) insulation over the roofing membrane in areas indicated.
a. Loosely lay 15/32-inch (12-mm) plywood or OSB panels over EPS. Extend EPS past edges of plywood or OSB panels a minimum of 1 inch (25 mm).
2. Limit traffic and material storage to areas of existing roofing membrane that have been protected.
3. Maintain temporary protection and leave in place until replacement roofing has been completed. Remove temporary protection on completion of reroofing.
4. Comply with requirements of existing roof system manufacturer's warranty requirements.
B. Seal or isolate windows that may be exposed to airborne substances created in removal of existing materials.
C. Shut off rooftop utilities and service piping before beginning the Work.
D. Test existing roof drains to verify that they are not blocked or restricted.
1. Immediately notify Owner's Consultant of any blockages or restrictions.
E. Coordinate with Owner to shut down air-intake equipment in the vicinity of the Work.
1. Cover air-intake louvers before proceeding with reroofing work that could affect indoor air quality or activate smoke detectors in the ductwork.
F. Pollution Control: Comply with environmental regulations of authorities having jurisdiction.
Limit spread of dust and debris.
1. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
2. Remove debris from building roof by chute, hoist, or other device that will convey debris to grade level.
G. Refrigerant: Before starting re-roofing preparation, remove refrigerant from mechanical equipment to be removed and reinstalled, according to 40 CFR 82 and regulations of authorities having jurisdiction.
Building 1&2
070150.19 - Page 8 of 12
H. Temporary Weather Protection: During removal operations, have sufficient and suitable materials on-site to facilitate rapid installation of temporary protection in the event of unexpected rain.
I. Roof Drain Protection: Maintain roof drains in functioning condition to ensure roof drainage at end of each workday.
1. If roof drains are temporarily blocked or unserviceable due to roofing system removal or partial installation of new membrane roofing system, provide alternative drainage method to remove water and eliminate ponding. Do not permit water to enter into or under existing membrane roofing system components that are to remain.
2. Prevent debris from entering or blocking roof drains and conductors.
a. Use roof-drain plugs specifically designed for this purpose.
b. Remove roof-drain plugs at end of each workday, when no work is taking place, or when rain is forecast.
3. If roof drains are temporarily blocked or unserviceable due to roofing system removal or partial installation of new membrane roofing system, provide alternative drainage method to remove water and eliminate ponding.
a. Do not permit water to enter into or under existing membrane roofing system components that are to remain.
3.2 ROOF TEAR-OFF
A. Notify Owner each day of extent of roof tear-off proposed for that day and obtain authorization to proceed.
B. Lower removed roofing materials to ground and onto lower roof levels, using dust-tight chutes or other acceptable means of removing materials from roof areas.
C. Roof Drainage: Remove roof drainage items indicated for removal.
D. Roof Tear-Off: Remove existing roofing membrane and other membrane roofing system components down to the deck.
1. Remove roof insulation and base sheets.
2. Remove excess asphalt from steel deck. A maximum of 15 lb/100 sq. ft. (0.72 kg/sq. m) of asphalt is permitted to remain on steel decks.
3. Remove fasteners from deck.
E. Roof Edge Specialties: Replace existing perimeter metal systems with new perimeter metal systems.
F. Inspect wood blocking, curbs, and nailers for deterioration and damage.
Building 1&2
070150.19 - Page 9 of 12
1. Replace existing wood components that exhibit signs of deterioration or other conditions detrimental to securement of roofing system components, including roof edge flashings.
3.3 DECK PREPARATION
A. Inspect deck after tear-off of membrane roofing system.
B. Verify that deck is sound and dry.
C. If broken or loose fasteners that secure deck panels to one another or to structure are observed or if deck appears or feels inadequately attached, immediately notify Owner. Do not proceed with installation until directed by Owner.
D. Unsuitable Deck: If deck surface is not suitable for receiving new roofing or if structural integrity of deck is suspect, immediately notify Owner. Do not proceed with installation until directed by Owner.
3.4 DECK REPAIR/REPLACEMENT
A. Repair existing deck to provide smooth working surface for installation of roof system.
1. Replace deck that cannot be repaired to sound condition.
B. Metal Deck Reattachment:
1. Mechanically reattach loose sections of deck to steel support members 12 inches (300
mm) on center (at every other rib) and 6 inches (150 mm) on center (at every rib) in roof corner and roof perimeter areas.
2. Side Laps: Mechanically fasten 18 inches (450 mm) on center.
3. Mechanically fasten steel deck to supporting member at each deck side lap, regardless of spacing.
4. Overlap steel deck end laps minimum 2 inches (50 mm); mechanically attach at the above listed factors.
C. Metal Deck Replacement:
1. Remove defective metal decking and examine supports; if supports are unsound, notify Architect and obtain direction before proceeding with deck replacement.
2. Install new metal decking in accordance with SDI, Design Manual for Composite Decks, Form Decks, Roof Decks
D. Concrete Deck Repair:
1. Remove spalled or deteriorated deck areas until sound base is reached.
Building 1&2
070150.19 - Page 10 of 12
2. Apply bonding agent and install patching mortar in accordance with manufacturer's instructions.
3. Allow patching mortar to fully set.
3.5 EQUIPMENT REMOVAL AND REINSTALLATION
A. General: Remove, store, protect and reinstall rooftop equipment as required to accommodate roof tear-off and subsequent roofing work.
1. Raise roof curbs, equipment mountings and other roof penetration flashings as required to accommodate additional insulation thickness and maintain base flashing height of not less than 8 inches (200 mm), unless otherwise indicated.
a. Provide wood assemblies and additional support with miscellaneous galvanized steel angles, as required to rebuild or raise existing roof curbs.
b. Extend vent and soil stacks and other roof penetrations, using matching materials, as required to accommodate additional insulation thickness.
2. Extend existing ductwork inside existing roof curbs to accommodate extension of curb.
a. Use materials matching existing ductwork; minimum of 20 ga. (0.9 mm) galvanized duct with Pittsburgh folded seam slip joints-typical.
B. Rooftop Equipment, Electrical: Engage a qualified electrician to perform electrical disconnection and reconnection.
1. Disconnect, reroute, extend and reconnect existing power feeders and control circuits (conduit and wiring) feeding the existing roof mounted equipment which is indicated to be raised and/or relocated to a new elevation/location and as required by the Contract.
2. Provide weatherproof exterior junction boxes, when required.
3. Make connections to mechanical equipment by using a maximum 18-inch (450-mm) length of liquid-tight flexible steel conduit.
a. Rigid connections to mechanical equipment are not permitted.
4. Relocate and reconnect existing disconnect switches presently installed on existing roof mounted equipment indicated to be raised and/or relocated.
C. Prevent discharge of refrigerant. Verify that refrigerant has been properly recovered from equipment to be removed.
D. Reinstall designated equipment.
1. Make electrical reconnections in accordance with applicable code and authorities having jurisdiction.
Building 1&2
070150.19 - Page 11 of 12
2. Recharge HVAC equipment with refrigerant required by equipment manufacturer.
3. Coordinate with Owner to test equipment and verify proper operation.
4. Notify Owner to have lightning protection system inspected and recertified after reinstallation.
E. Remove and dispose of designated abandoned equipment. Infill openings in deck with matching materials. Infill roofing system with materials of same type as existing, adjacent roofing system.
3.6 TEMPORARY ROOFING MEMBRANE
A. Install approved temporary roofing membrane over area to be reroofed.
B. Remove temporary roofing membrane before installing new roofing membrane.
3.7 FASTENER PULL-OUT TESTING
A. Fastener Testing: Retain independent testing and inspecting agency to conduct fastener pullout tests according to SPRI FX-1, and submit test report prior to installing new roofing system.
B. Uplift Securement: Provide additional uplift securement for existing roofing system with new screws and plates applied to each roof zone at densities required to resist wind uplift pressures.
3.8 BASE FLASHING REMOVAL
A. Remove existing base flashings around parapets, curbs, walls, and penetrations.
1. Clean substrates of contaminants, such as asphalt, sheet materials, dirt, and debris.
B. Do not damage metal counterflashings that are to remain.
1. Replace metal counterflashings damaged during removal with counterflashings of same metal, weight or thickness, and finish.
3.9 PARAPET SHEATHING AND CLADDING
A. Parapet Sheathing: Inspect parapet sheathing for deterioration and damage. If parapet sheathing has deteriorated, immediately notify Owner's Architect.
B. Parapet Sheathing: Remove existing parapet sheathing and replace with new preservative-treated plywood sheathing, 19/32 inch (15 mm) thick. If parapet framing has deteriorated, immediately notify Owner.
C. Parapet Cladding: Remove, store, and reinstall parapet cladding and associated weather resistant barrier.
Building 1&2
070150.19 - Page 12 of 12
3.10 RECYCLING OF DEMOLITION AND CONSTRUCTION WASTE
A. Recycling of Roof Membrane and Insulation: Cut membrane and other components into manageable size, and package for pickup and handling in accordance with recycling vendor's requirements.
B. Prevent other materials or debris from intermixing with recycled material.
C. Submit final summary of progress reports, including percentage of recycled waste to quantity of total waste, by weight.
3.11 DISPOSAL
A. Collect demolished materials and place in containers. Promptly dispose of demolished materials. Do not allow demolished materials to accumulate on-site.
1. Storage or sale of demolished items or materials on-site is not permitted.
B. Transport and legally dispose of demolished materials off Owner's property.
3.12 CLEANING
A. Clean adjacent structures and improvements of dust, dirt, and debris caused by preparation for re-roofing operations. Return adjacent areas to condition existing before operations began.
END OF SECTION 070150.19
Building 1&2
075600.13 - Page 1 of 16
FLUID-APPLIED MEMBRANE ROOFING, INSULATED
SECTION 075600.13 - FLUID-APPLIED MEMBRANE ROOFING, INSULATED
1.1 SUMMARY
A. This Section includes fluid-applied roof membrane system on insulated metal deck& concrete deck, consisting of the following:
1. Roof insulation and cover board.
2. Base-ply sheet.
3. Application of fluid-applied, reinforced polyurethane roof membrane and membrane flashings.
B. Related Information:
1. Division 07 Section "Preparation for Re-Roofing" for existing roofing tearoff and substrate preparation for installation of new roofing membrane.
1.2 ROOFING CONFERENCES
A. Roofing Preinstallation Conference: Conduct conference at Project site. Review methods and procedures related to roofing system.
1. Meet with Owner; Architect; roofing materials manufacturer's representative; roofing Installer including project manager and foreman; and installers whose work interfaces with or affects roofing including installers of roof accessories and roof-mounted equipment requiring removal and replacement as part of the Work.
2. Review methods and procedures related to preparation, including membrane roofing system manufacturer's written instructions.
3. Review drawings and specifications.
4. Review temporary protection requirements for existing roofing system that is to remain, during and after installation.
5. Review roof drainage during each stage of roofing and review roof drain plugging and plug removal procedures.
6. Review and finalize construction schedule, and verify availability of materials, Installer's personnel, equipment, and facilities needed to make progress and avoid delays.
7. Review base flashings, special roofing details, drainage, penetrations, equipment curbs, and condition of other construction that will affect re-coating.
Building 1&2
075600.13 - Page 2 of 16
8. Review HVAC shutdown and sealing of air intakes.
9. Review shutdown of fire-suppression, -protection, and -alarm and -detection systems.
10. Review procedures for asbestos removal or unexpected discovery of asbestos-containing materials.
11. Review governing regulations and requirements for insurance and certificates if applicable.
12. Review existing conditions that may require notification of Owner before proceeding.
1.3 DEFINITIONS
A. Roofing Terminology: Refer to ASTM D 1079 "Standard Terminology Relating to Roofing and Waterproofing" and glossary in applicable edition of NRCA's "The NRCA Roofing Manual:
Membrane Roof Systems" for definition of terms related to roofing work in this Section.
1.4 ACTION SUBMITTALS
A. Product Data: For each type of product specified.
1.5 INFORMATIONAL SUBMITTALS
A. Photographs or Videotape: Show existing conditions of adjoining construction and site improvements, including exterior and interior finish surfaces, which might be misconstrued as having been damaged by re-coating operations. Submit before Work begins.
B. Inspection Reports: Reports of Roofing Inspector. Include weather conditions, description of work performed, tests performed, defective work observed, and corrective actions required and carried out.
1. Submit report within 48 hours after inspection.
1.6 CLOSEOUT SUBMITTALS
A. Maintenance Data: To include in maintenance manuals.
B. Warranties: Executed copies of approved warranty forms.
1.7 QUALITY ASSURANCE
A. Installer Qualifications: An employer of workers trained and certified by manufacturer, including a full-time on-site supervisor with a minimum of ten years' experience installing products comparable to those specified, able to communicate verbally with Contractor, Architect, and employees, and the following:
1. Qualified by the manufacturer to install manufacturer's product and furnish warranty of type specified.
Building 1&2
075600.13 - Page 3 of 16
B. Roofing Inspector Qualifications: A technical representative of manufacturer not engaged in the sale of products and experienced in the installation and maintenance of the specified roofing system, qualified to perform roofing observation and inspection specified in Field Quality Control Article, to determine Installer's compliance with the requirements of this Project, and approved by the manufacturer to issue warranty certification. The Roofing Inspector shall be one of the following:
1. An authorized full-time technical employee of the manufacturer.
1.8 DELIVERY, STORAGE, AND HANDLING
A. Deliver roofing materials to Project site in original containers with seals unbroken and labeled with manufacturer's name, product brand name and type, date of manufacture, approval or listing agency markings, and directions for storing and mixing with other components.
B. Handle and store roofing materials, and place equipment in a manner to avoid significant or permanent damage to deck or structural supporting members.
C. Protect materials from physical damage and from deterioration by sunlight, moisture, soiling, and other sources. Store in a dry location. Comply with manufacturer's written instructions for handling, storing, and protecting.
D. Store liquid materials in their original undamaged containers in a clean, dry, protected
E. location and within the temperature range required by roofing manufacturer. Protect
F. stored liquid material from direct sunlight.
G. Handle and store roofing materials and place equipment in a manner to avoid
H. permanent deflection of deck.
1.9 PROJECT / FIELD CONDITIONS
A. Protect building, adjacent buildings, walkways, site improvements, exterior plantings, and landscaping from damage or soiling from roofing operations.
B. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities.
C. Weather Limitations: Proceed with roofing work only when existing and forecasted weather conditions permit Work to proceed without water entering into existing roofing system or building.
1. Store all materials prior to application at temperatures between 60 and 90 deg. F.
2. Apply coatings within range of ambient and substrate temperatures recommended by manufacturer. Do not apply materials when air temperature is below 50 or above 110 deg.
F.
3. Do not apply roofing in snow, rain, fog, or mist.
Building 1&2
075600.13 - Page 4 of 16
D. Daily Protection: Coordinate installation of roofing so insulation and other components of roofing system not permanently exposed are not subjected to precipitation or left uncovered at the end of the workday or when rain is forecast.
E. Owner will occupy portions of building immediately below roofing area. Conduct roofing so Owner's operations will not be disrupted. Provide Owner with not less than 72 hours' notice of activities that may affect Owner's operations.
1.10 WARRANTY
A. Installer Warranty: Installer's warranty signed by Installer, as follows.
1. Upon project completion and final acceptance by the Owner and Architect, the Contractor shall obtain and deliver the Roofing System Manufacturer’s
2. 20 year full-system roofing Warranty and Inspection Program as specified, on
3. Manufacturer's customized form, without monetary limitation, in which manufacturer agrees to repair or replace components of the roofing system that fail in materials or workmanship within specified warranty period.
4. Special full-system roofing warranty includes membrane roofing, base/metal
5. flashings, roof insulation, fasteners, cover boards, roofing accessories, and all
6. other components of the specified roofing system.
7. Form of Warranty: Form acceptable to Roofing Manufacturer and Owner.
8. Scope of Warranty: Work of this Section.
9. Warranty Period: 2 years from date of completion.
B. Manufacturer's Warranty: Roof System Manufacturer's standard form in which Manufacturer agrees to repair or replace components of roofing system that fail in materials or workmanship within warranty period, as follows.
1. Form of Warranty: Manufacturer's standard warranty form.
2. Scope of Warranty: Work of this Section and including sheet metal details and termination details installed by the roof system Installer and approved by the Roof System Manufacturer.
3. Manufacturer’s warranties shall not start until the date of
4. Substantial Completion, or until all of the commissioning of respective systems are
5. complete and accepted by the Commissioning Authority and the Owner, whichever is later.
Building 1&2
075600.13 - Page 5 of 16
6. Roofing Signage: At entry points to roof, provide signage listing type of roofing system, manufacturer, date installed, and holder of the warranty.
7. Upon project completion and final acceptance by the Owner, the Inspection/Service program shall obligate the Roof System Manufacturer to provide follow-up inspections to the roof system, throughout the 20 year term of the warranty.
8. To ensure continuity-of-service and to limit responsibility to a single entity, the
9. Roof System Manufacturer shall utilize only employees/staff who are directly
10. employed by the Roof System Manufacturer to execute all aspects of the
11. warranty inspection/service agreement. This work shall not be sub-contracted
12. to outside Contractors or other third parties.
13. The Warranty/Inspection/Service agreement is intended to cover: General housekeeping, removal/disposal of accumulated organic rooftop debris, trash and similar material/items.
General preventive maintenance to roof drain flashings, base flashings, metal flashings, pitch-pockets, penetration flashings, wall flashings and similar related detailing.
14. Warranty Period: 20 years from date of completion.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Qualified: Subject to compliance with requirements, provide products by a manufacturer meeting the following:.
1. Qualification requirements are specified in: Part 1 Quality Assurance Article.
2.2 PERFORMANCE REQUIREMENTS
A. General: Provide roofing membrane and base flashings that remain watertight; do not permit the passage of water; and resist specified uplift pressures, thermally induced movement, and exposure to weather without failure.
1. Accelerated Weathering: Roofing system shall withstand 2000 hours of exposure when tested according to ASTM G 152, ASTM G 154, or ASTM G 155.
2. Impact Resistance: Roof membrane shall resist impact damage when tested according to ASTM D3746/D3746M, ASTM D4272/D4272M, or the "Resistance to Foot Traffic Test" in FM Approvals 4470.
B. Material Compatibility: Provide roofing materials that are compatible with one another under conditions of service and application required, as demonstrated by roofing manufacturer based on testing and field experience.
Building 1&2
075600.13 - Page 6 of 16
C. Roofing System Design: Provide roofing system that is identical to systems that have been successfully tested by a qualified testing and inspecting agency in accordance with ANSI/FM 4474, UL 580, or UL 1897, and to resist uplift pressures.
D. Flashings: Comply with requirements of Division 07 Sections "Sheet Metal Flashing and Trim" and "Manufactured Roof Specialties." Provide base flashings, perimeter flashings, detail flashings and component materials that comply with requirements and recommendations of the following:
1. NRCA Roofing Manual (Sixth Edition) for construction details and recommendations.
2. SMACNA Architectural Sheet Metal Manual (Seventh Edition) for construction details.
E. Exterior Fire-Test Exposure: ASTM E 108, Class A; for application and roof slopes indicated, as determined by testing identical membrane roofing materials by a qualified testing agency.
Materials shall be identified with appropriate markings of applicable testing agency.
2.3 MATERIALS
A. General: Roofing materials recommended by roofing system manufacturer for intended use and compatible with components of existing membrane roofing system.
B. Temporary Roofing Materials: Selection of materials and design of temporary roofing is responsibility of Contractor.
C. General: Provide adhesive and sealant materials recommended by roofing manufacturer for intended use and compatible with built-up roofing.
1. Liquid-type auxiliary materials shall comply with VOC limits of authorities having jurisdiction.
2.4 SHEET MATERIALS
A. Base-Ply Sheet:
1. SBS-modified asphalt coated composite polyester / fiberglass/fiberglass mat reinforced high tensile strength base sheet, ASTM D4601 Type II.
a. Tensile Strength at 77 deg. F (25 deg. C), minimum, ASTM D5147: Machine direction, 165 lbf/in (725 N); Cross machine direction, 150 lbf/in (660 N).
b. Tear Strength at 77 deg. F (25 deg. C), minimum, ASTM D5147: Machine direction, 260 lbf (1150 N); Cross machine direction, 230 lbf ( 1120 N).
c. Thickness, minimum, ASTM D5147: 0.060 inch (1.5 mm).
B. Flashing Base-Ply Sheet: Same product as base-ply sheet.
Building 1&2
075600.13 - Page 7 of 16
2.5 FLUID-APPLIED ROOFING MEMBRANE
A. Polyurethane Elastomeric Fluid-Applied System: Two-coat reinforced fluid-applied roofing membrane formulated for application over prepared existing roofing substrate.
1. Base Coat:
a. Polyurethane roof coating system base coat, bio-based, low-odor low-VOC two-part, for use with a compatible top coat.
1) Combustion Characteristics, UL 790: Maintains combustion characteristics of existing roof system.
2) Volatile Organic Compounds (VOC), maximum, ASTM D3960: 1 g/L.
3) Accelerated Weathering, 5000 hours, ASTM G154: Pass.
4) Hardness, Shore A, minimum, ASTM D2240: 80.
5) Solids, by volume, ASTM D2697: 100 percent.
6) Bio-Based Content, Minimum: 70 percent.
7) Minimum Thickness, Base Coat reinforced over Smooth BUR, MB, Concrete, Single-Ply: 48 mils (1.22 mm) wet.
2. Top Coat:
a. Polyurethane roof coating system top coat, bio-based low-odor low-VOC two-part, for application over compatible base coat.
1) Combustion Characteristics, UL790: Maintains combustion characteristics of existing roof system.
2) Volatile Organic Compounds (VOC), maximum, ASTM D3960: 6 g/L.
3) Solar Reflectance Index (SRI), ASTM E1980: For white, not less than 103.
4) Accelerated Weathering, 5000 hours, ASTM G 154: Pass.
5) Hardness, Shore A, minimum, ASTM D2240: 81.
6) Solids, by volume, ASTM D2697: 100 percent.
7) Bio-Based Content, Minimum: 60 percent.
8) Minimum Thickness, reinforced system: 32 mils (0.81 mm) wet.
9) Color: White.
Building 1&2
075600.13 - Page 8 of 16
3. Reinforcing Fabric:
a. Polyester Reinforcing and Protection Fabric: 100 percent stitch-bonded mildew-resistant polyester fabric intended for reinforcement of compatible fluid-applied membranes and flashings and as a protection layer under pavers or stone aggregates.
1) Tensile Strength, Minimum, ASTM D1682: 50 lbf (23 kg) avg..
2) Elongation, Minimum, ASTM D1682: 60 percent.
3) Tear Strength, Minimum, ASTM D1117: 16 lbf (7.3 kg) avg..
4) Weight: 3 oz./sq. yd (102 g/sq. m).
4. Primers:
a. Primer for Asphaltic and Single-Ply Membranes: Water-based, polymer-modified quick-dry low odor primer.
1) Volatile Organic Compounds (VOC), maximum, ASTM D3960: 1 g/L.
2) Solids, by weight: 70 percent.
b. Primer for Masonry Surfaces: Two-part high-solids epoxy-penetrating low-odor primer for masonry and concrete surfaces.
1) Volatile Organic Compounds (VOC), maximum, ASTM D3960: 0 g/L.
2) Solids, by weight: 100 percent.
c. Primer for Non-Porous Surfaces: Single-part, water based primer to promote adhesion of urethanes to metals, PVC and other non-porous surfaces.
1) Volatile Organic Compounds (VOC), maximum, ASTM D3960: 22 g/L.
2) Nonvolatile Content, minimum, ASTM D2369: 5 percent.
3) Density at 77 deg F (25 deg C): 8.3 lb/gal (1kg/L).
d. Primer for Intercoat and Substrate Adhesion: Single-part, quick-drying primer to promote adhesion of urethane products to previous urethane coats and to other approved surfaces.
1) Volatile Organic Compounds (VOC), maximum, ASTM D3960: 5 g/L.
2) Coverage Rate, 400 sq. ft/ gal.: 4 mils (0.10 mm) wet.
Building 1&2
075600.13 - Page 9 of 16
2.6 ADHESIVE MATERIALS
A. Base-Ply Sheet Adhesive:
1. Cold-applied bio-based low odor urethane roofing adhesive, two-part, USDA BioPreferred, formulated for compatibility and use with specified roofing membranes and flashings.
a. Volatile Organic Compounds (VOC), maximum, ASTM D3690: 0 g/L.
b. Low Temperature Flexibility, ASTM D2240: Pass at -30 deg F (-34 deg C).
c. Solids, by Volume, ASTM D2697: 100 percent.
d. Biobase Content, Minimum, ASTM D6866: 70 percent.
B. Flashing Base-Ply Sheet Adhesive: Same product as base-ply sheet adhesive.
2.7 AUXILIARY ROOFING MEMBRANE MATERIALS
A. General: Auxiliary materials recommended by roofing system manufacturer for intended use and compatible with existing roofing system and fluid-applied roofing system.
B. Joint Sealant: Elastomeric joint sealant compatible with applied coating, with movement capability appropriate for application.
1. Joint Sealant, Polyurethane: ASTM C920, Type S, Grade NS, Class 50 single-component moisture curing sealant, formulated for compatibility and use…