Y1DA--FY26 NRM (PROJ: 573A4-26-110) DB - Climatize Building 78
Solicitation number
36C24826R0021-01
Issued by

About this file

This document is a Standard Form 30 (Amendment of Solicitation/Modification of Contract) for the Department of Veterans Affairs Network Contracting Office 8 in Tampa, FL. The amendment extends the phase 1 solicitation number 36C24826R0021 for the "DB - Climatize Building 78" project (Project Number: 573A4-26-110) to a new closing date of 12/05/2025.

The amendment includes responses to two Request for Information (RFI) questions: (1) confirming that the Superintendent, Quality Control (QC), and Site Safety and Health Officer (SSHO) roles can be covered by the same person, and (2) clarifying which proposal outline (Section 2.06 or 2.09) should be used for the current phase one proposal process. The government specifies that bidders should use Section 2.06 for the current phase one proposal submission, with Section 2.09 applicable to the future phase two process.

View the file

Other files

File Type Posted
S02 - Attachment 05 - Specialized.docx DOCX document
PHASE RESPONSE TO RFI.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

0001 11-20-2025

573A4-26-110

36C248

Department of Veterans Affairs Network Contracting Office 8 (NCO 8)

8875 Hidden River Pkwy Suite 525 Tampa FL 33637

36C248

Department of Veterans Affairs Network Contracting Office 8 (NCO 8)

8875 Hidden River Pkwy Tampa FL 33637

To all Offerors/Bidders

36C24826R0021

X

X X

Project Title: DB - Climatize Building 78 Project: 573A4-26-110

The purpose of this amendment is to extend the phase 1 solicitation number 36C24826R0021 closing date to 12/05/2025, provide Government responses to RFI and attachment 5 of the solicitation specialized experience

All Offerors are required to acknowledge receipt of this amendment 0001.

CALIXTE SAINTIL

Contracting Officer

Response to PHASE ONE RFI 36C24826R0021| (PROJ: 573A4-26-110) DB - Climatize Building 78

1. Can Superintendent, QC, and SSHO Be covered by the same person?

• It can be the same a.

2. 2.06 Technical Proposal preparation instructions has 2nd package Factor 1-4 content in a different order than 2.09 Evaluation Factors. Please confirm which proposal outline for presentation is to be used.

• Please use 2.06 this is for phase one and 2.09 is for phase two (we are currently in phase one of the proposal process.

Response to PHASE ONE RFI

36C24826R0021| (PROJ: 573A4-26-110) DB - Climatize Building 78

Phase one proposals are due on or before 12/05/2025

File details come from the government source that posted it. Updated .