PHASE RESPONSE TO RFI.pdf
PDF 66 KB Posted
- Solicitation number
- 36C24826R0021-01
About this file
This document is a Response to Phase One Request for Information (RFI) for project 36C24826R0021 (PROJ: 573A4-26-110), involving the climatization of Building 78. The RFI addresses two key clarification points: (1) confirming that the Superintendent, Quality Control (QC), and Site Safety and Health Officer (SSHO) roles can be covered by the same person, and (2) providing guidance on the correct technical proposal preparation instructions for the current phase of the proposal process. Specifically, the response indicates that for Phase One, participants should follow the proposal outline in section 2.06, while section 2.09 will be used for Phase Two of the proposal process.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| S02 - Attachment 05 - Specialized.docx | DOCX document | |
| S02 -PHASE 1 SOL AMEND 36C24826R0021 0001.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Response to PHASE ONE RFI 36C24826R0021| (PROJ: 573A4-26-110) DB - Climatize Building 78
1. Can Superintendent, QC, and SSHO Be covered by the same person?
• It can be the same a.
2. 2.06 Technical Proposal preparation instructions has 2nd package Factor 1-4 content in a different order than 2.09 Evaluation Factors. Please confirm which proposal outline for presentation is to be used.
• Please use 2.06 this is for phase one and 2.09 is for phase two (we are currently in phase one of the proposal process.