This document provides download links to LIDAR files and photos of buildings at the San Diego VA Health Care System as well as details for an upcoming solicitation to replace primary substations, transformers, and switches at the facility. The solicitation will be issued by the Department of Veterans Affairs Office of Construction and Facilities Management as a total service-disabled veteran-owned small business set-aside for a firm fixed price contract. The scope of work involves replacing nine substations in Buildings 1 and 2 that have reached or are nearing the end of their useful life. The project magnitude is estimated between $10-20 million. The solicitation is expected to be released on July 22, 2022, and a pre-proposal conference/site visit will be scheduled. Qualified contractors are encouraged to attend.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DZ--Replace Primary Substation, Transformer & Dual Primary Selective Switches Solicitation, newest first.
File Type Posted
36C10F22B0004 0001.docx DOCX document
P07. Wage Deternimation San Diego CA20220001 - 04292022.docx DOCX document
C27. Replace Primary Substation-Final Stamped Drawings_0000003559.pdf PDF
S02. IFB 36C10F22B0004 Replace Primary Substation Transformer Dual Selective Switches Project 664-19-303 VAMC San Diego_Rev2.docx DOCX document
C28. Replace Primary Substation-Final Specifications 20220712.docx DOCX document
S11.1 JV Sample.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

664-19-304 San Diego VA LIDAR Download Links:

• Free LIDAR Viewing Software – Jetstream Viewer (Download and Install First) o https://a360.co/3P4D8MI

LIDAR

• Building 1 – Level 1 Interstitial o Center and South https://a360.co/3OMzasz o East https://a360.co/3usWMu7 o Northeast https://a360.co/3AzP1pV o Northwest https://a360.co/3P5zzpA o North https://a360.co/3bXtCwN o Southeast https://a360.co/3yVuH1f o Southwest https://a360.co/3AtTVVq

• Building 1 – Level 2 Interstitial o East https://a360.co/3Aw54oW o North https://a360.co/3akcMaR o South https://a360.co/3uvEFDP o West https://a360.co/3Rf3spu

• Building 1 – Level 3 Interstitial o East https://a360.co/3o1zc45 o West https://a360.co/3yoLXu0 https://a360.co/3yihi1D o North https://a360.co/3uuqejk o South https://a360.co/3yIEEij

• Building 1 – Level 4 Interstitial o East https://a360.co/3O1NAnv o North https://a360.co/3P6UWqr o South https://a360.co/3ynYzSk o West https://a360.co/3usdF7W

• Building 1 – Level 5 Interstitial o East https://a360.co/3bUVFgi o North https://a360.co/3AzUa1d o South https://a360.co/3NNcAhW o West https://a360.co/3AzNlN8

• Building 1 – Level 6 Interstitial o East https://a360.co/3bRdTiE o North https://a360.co/3usPcPY o South https://a360.co/3nJMIZQ o West https://a360.co/3utQCtA

• Building 1 – Level 7 o Penthouse https://a360.co/3P6jtMh

• Building 2 o Electrical Sub-Station https://a360.co/3yMd3wE o Mezzanine https://a360.co/3AzUwoz o Roof https://a360.co/3AxRdhS o Site North of B2 https://a360.co/3ykP4TY o Electrical Room https://a360.co/3As8PeL o Boiler Room https://a360.co/3ysomZI https://a360.co/3NNF4Ik o B2 Exterior https://a360.co/3Ih80Yi

• Building 11 – Level 0 o Level 0 Interstitial https://a360.co/3P7iyLD https://a360.co/3Avs3QF o Northwest Mechanical Room https://a360.co/3IhvM6m o Southwest Mechanical Room https://a360.co/3AxAw62 o East Mechanical Room https://a360.co/3NR1KYe

• Building 11 – Level 1 o Interstitial https://a360.co/3NHDiZm o East Mechanical Room https://a360.co/3uubPn3 o Northwest Mechanical Room https://a360.co/3upARnq

• Building 11 – Level 2 o East Mechanical Room https://a360.co/3aizCzJ o Northwest Mechanical Room https://a360.co/3OUYi0k

Field Survey Photos:

• Building 1 and Building 11 o https://a360.co/3OQOjZQ

• Building 2 o https://a360.co/3PdfsG9

File details come from the government source that posted it. Updated .