S02-CALCULATION OF SELF PERFORMED WORK_626-24-509 - Repair ACRE North Stairwell.docx
DOCX document 19 KB Posted
- Solicitation number
- 36C24924B0010
About this file
This document is a Calculation of Self-Performed/Subcontracted Work for a federal construction contract opportunity. The contract is to Repair the ACRE North Stairwell (Project #626-24-509) and is solicited by the Department of Veterans Affairs, Veterans Health Administration, Veterans Integrated Service Network 9.
The document outlines the requirements for the Service-Disabled Veteran-Owned Small Business (SDVOSB) awardee to self-perform at least 15% of the contract value, with a breakdown of personnel and material/equipment costs by specification division. It provides a suggested format for the offeror to identify the SDVOSB vendor status, personnel costs, and material/equipment costs. The offeror must also calculate the percentage of self-performed work. The solicitation number is 36C24924B0010.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24924B0010 0002.docx | DOCX document | |
| 36C24924B0010 0001.docx | DOCX document | |
| RFI Form_626-24-509 - Repair ACRE North Stairwell.docx | DOCX document | |
| 36C24924B0010_1.docx | DOCX document | |
| P07-Wage Determination_TN20240178 03-22-2024.pdf | ||
| Contractor EMR_626-24-509 - Repair ACRE North Stairwell.docx | DOCX document | |
| C28_Drawings_626-24-509 REPAIR NORTH ACRE STAIRWELL .pdf | ||
| UEI _ TAX ID.docx | DOCX document | |
| C27_626-24-509 Specs.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CALCULATION OF SELF-PERFORMED/SUBCONTRACTED WORK (xxx-xx-xxx)
Offerors for General Construction (NAICS code 238160- Roofing Contractors) must provide at least 15 percent (25% for specialty trade NAICS codes with 237 and 238 prefix) of the cost of the contract performance incurred for personnel must be performed by the Service Disabled Veteran Owned Small Business (SDVOSB) awardee or those of a verified SDVOSB subcontractor. Provide a breakdown of material and personnel costs, by specification division listed for the project. Home Office overhead, profit/fee and bond costs shall be added after a subtotal of personnel and material/Equipment costs has been calculated. Clearly identify the personnel costs you will be performing, and the personnel costs of other eligible service disabled veteran-owned small business concerns. Below is a suggested format.
| Specification Division |
| SDVOB Vendor (Y or N) |
| Personnel Cost |
| Material/Equipment Costs |
Division 01
| $ |
| $ |
Division 02
| $ |
| $ |
Division 03
| $ |
| $ |
(Add additional lines as necessary for each Division applicable to this project)
| $ |
| $ |
| $ |
| $ |
Sub Total (Personnel Costs, Material/Equipment Costs)
| Profit |
| $ |
| Home Office Overhead |
| $ |
| Bond |
| $ |
| Grand Total |
| $ |
Calculation of self-performed personnel costs:
1. Total personnel costs * both prime and all subcontractors: $
2. Subtract all subcontractor personnel costs* that are not SDVOSB companies that will perform work on this contract: $
3. Remainder is ‘Total amount of work to be self-performed under the
| Contract’: | $ | |
| 4. Self-performed work = Line 3/Line 1 x 100 = | % |
*personnel costs include labors, mechanics, other tradesmen, and office personnel directly charged to the project (includes project manager, job superintendent, administrative, estimators, etc.)