This document is a contract modification for Project #626-24-509 to repair the ACRE North Stairwell. The modification provides answers to questions received during a site visit. Key details include:
The project requires replacing VCT flooring tiles, painting the replaced stairwell doors on both sides, allowing daytime work hours, requiring negative air machines and ventilation, repairing/replacing only damaged lighting, confirming a bid bond is required, and providing rubber cove base. The stairwell treads will remain, but the underside of the stairs will be painted. The walls are to be painted in a main color of Accessible Beige with an accent of Moody Blue at the landings. Access panels and an electrical outlet also need to be replaced. The first floor must remain open for emergency egress during construction. The solicitation number is 36C24924B0010, and the contract is being issued by the Department of Veterans Affairs Network Contracting Office 9.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24924B0010 0001.docx | DOCX document | |
| RFI Form_626-24-509 - Repair ACRE North Stairwell.docx | DOCX document | |
| 36C24924B0010_1.docx | DOCX document | |
| P07-Wage Determination_TN20240178 03-22-2024.pdf | ||
| Contractor EMR_626-24-509 - Repair ACRE North Stairwell.docx | DOCX document | |
| C28_Drawings_626-24-509 REPAIR NORTH ACRE STAIRWELL .pdf | ||
| UEI _ TAX ID.docx | DOCX document | |
| C27_626-24-509 Specs.pdf | ||
| S02-CALCULATION OF SELF PERFORMED WORK_626-24-509 - Repair ACRE North Stairwell.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
626-24-509 - Repair ACRE North Stairwell
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 626-24-3-4209-0147 626-24-509 Department of Veterans Affairs Network Contracting Office 9 (90C)
NCO 9
1639 Medical Center Parkway, Suite 204 Murfreesboro
TN
37129 90C Network Contracting Office 9 Department of Veterans Affairs Network Contracting Office (90C) 1639 Medical Center Parkway Suite 204 Murfreesboro
TN
37129 To all Offerors/Bidders
36C24924B0010 07-05-2024
X X X
Bids Due 07/15/2024 at 13:00 CT
626-3640162-4209-854200-3223 23NRNR000
X The purpose of this amendment is to answers to RFI questions received from the site visit for project 626-24-509 - Repair ACRE North Stairwell.
See Page 2 for answers to site visit questions.
Michael R. Brown Contracting Officer 36C24924B0010, Questions and Answers
1. What type of flooring are you looking to replace the flooring with? The same type of VCT tile? Are we to replace all tile?
Answer:
· VCT: Tarkett VCT II Mushroom 593
· Yes, replace all tile floors.
2. Are all interior sides of the stairwell doors on every floor to be painted? Are exteriors of the doors to be painted? (The side outside of the stairwell).
Answer: The replaced door will require paint on both sides to match previous paint color.
3. Work hours? Is during the day during normal workdays acceptable?
Answer: Yes, this is acceptable. Loud work may need to take place afterhours or on weekends.
4. Are negative air machines and negative ventilation required?
Answer: Yes. Air scrubbers will be required. If any work in a corridor is required, then containment is required. Fire retardant barriers for all floors will be required.
5. Are all lights to be replaced or just the non functional light on the 12th landing to be replaced? Only one appears to be damaged/non functional. This can be repaired with a ballast and bulbs most likely is this acceptable?
Answer: Only damaged/nonfunctional lights are to be repaired. Replace light and housing w/ LED.
6. The cover page on the sf1442 states "no" in the bond required blank, just verifying no bid or performance bond is required for this project with satisfactory and relevant prior past performance as there is some boiler plate verbiage about bonds in the solicitation documents.
Answer: A bid bond is required for this project.
PERFORMANCE AND PAYMENT BONDS: In accordance with Contract Clause 52.228-15, and FAR 28.102, Contractors are reminded that any amount awarded over $35,000.00 shall require a Payment Bond (SF 25A), and awards exceeding $150,000.00 shall require both Payment and Performance Bonds (SF 25).
7. What are you wanting to cover the stairs with? A rubber fire safety stair tread?
Answer: The treads are to remain.
8. Do we replace all rubber cove base?
Answer: Yes, Tarkett/Johnsonite Duracove Base 4”H Burnt Umber.
9. Will we be allowed use of elevators for materials?
Answer: Research areas and floors are off limits due to gowning and other infection control measures. Only second and sixth (can’t traverse through research animal area) are available for materials. Ensure there is no damage to elevators and coordinate with COR prior to loading.
10. Are we to paint all steel handrails and steel framework for the steps?
Answer: No paint for handrails or steel framework. This is to remain as-is. Unless damaged during construction, document precondition. If damaged, match existing color. Underside of stairwells that are repaired are to be painted.
11. Are the floor heating units to remain? Yes, they will remain in place.
13. First floor needs to remain open for an emergency egress when it is not under construction.
14. Ensure thorough cleaning of treads, risers, and stair system to COR satisfaction after construction.
15. Plan to replace two access panels.
16. Replace specified outlet from drawings and the cover.
17. What color should the walls be painted?
Wall color (main): SW7036 Accessible Beige Wall color (accent at landings): SW 6221 Moody Blue