S02 BID SHEET Updated.docx

DOCX document 14 KB Posted

Attached to
Y1DA--630A4-20-424 NUCLEAR MEDICINE SPECT-CT SITE PREP
Solicitation number
36C24221B0034
Issued by

About this file

This document contains a bid sheet and federal contract opportunity notice for a nuclear medicine SPECT-CT site renovation project at a Department of Veterans Affairs medical center. The bid sheet outlines two items: a base bid for renovating approximately 1200 square feet of existing nuclear medicine space, including demolition, HVAC, electrical, and other work, with an estimated completion time of 155 days; and an alternate bid to perform the same work while operating double shifts to fast-track completion within 90 days. The related federal contract opportunity provides the project statement of work, which involves replacing condenser water piping from a chiller plant to cooling towers, and lists general contractor requirements such as obtaining badges, submitting schedules and safety plans, coordinating utility interruptions, and using containment equipment for above-ceiling work.

View the file

Other files

File Type Posted
S02 ALL POSTERS.pdf PDF
S02 ADDITIONAL INSERTS.pdf PDF
S02 SPECS.pdf PDF
S02 Participation Goals for Minorities and Females.pdf PDF
36C24221B0034.docx DOCX document
S02 DRAWINGS.pdf PDF
S02 VA ID PACKAGE UPDATED 01-16-2019.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Title: DESIGN NUCLEAR MEDICINE SPECT-CT SITE PREP Project No: 630A4-20-424

STATEMENT OF BID ITEM(S)

A. BASE BID ITEM I: Work includes renovating approximately 1200 sq. ft. of the existing Nuclear Medicine space on the 2nd Floor of Building 1 at the VA New York Harbor Healthcare System at 800 Poly Place, Brooklyn, NY. Work will include, but is not limited to, a complete gut renovation of the existing Nuclear Medicine SPECT CT Space, fire suppression work, electrical, plumbing, architectural, rigging services, construction administration, demolition, asbestos abatement, fireproofing, metal framing, gypsum board, acoustical ceilings, flooring, painting, HVAC, med gas, direct-digital controls, wiring devices, communications, telephone/data, fire alarm, etc.

Construction Estimate: $__________ Completion Time: 155 calendar days

B. Add ALT # 1 BID ITEM II: Everything in BASE BID ITEM I and double work shifts—contractor to work double shifts to fast-track project completion.

Construction Estimate: $__________ Completion Time: 90 calendar days