S02 - ATTACHMENT N - Construction Schedule.pdf

PDF 299 KB Posted

Attached to
Q702--Stockton CBOC Activation Contract
Solicitation number
36C77623Q0249
Issued by

About this file

This document is an RFQ for the Stockton CBOC Activation Contract. The solicitation is seeking proposals for the activation of a new Community Based Outpatient Clinic in Stockton, California for the Department of Veterans Affairs Technology Acquisition Center Austin. Key requirements include construction and buildout services to prepare the new CBOC facility for operations. An attached schedule details the construction timeline and milestones spanning from May 2022 through July 2023, including site development, utilities installation, building enclosure, interior construction and finishes, elevators, central utility plant buildout, closeout activities, and warranty periods. Proposals are due by February 14, 2023, with contract award anticipated by March 29, 2023. The solicitation is designated for small business set-aside and targets SDVOSB/VOSB concerns.

View the file

Other files

File Type Posted
S05 - Stockton IOTA RFQ_Questions and Answers - REVISED 4-26.pdf PDF
36C77623Q0249 0002.docx DOCX document
S02 - ATTACHMENT G - Stockton Updated FF_E List 26 April 2023.xlsx XLSX spreadsheet
36C77623Q0249 0001.docx DOCX document
S02 - ATTACHMENT G - UPDATED Stockton FFE List.xlsx XLSX spreadsheet
S05 - Stockton IOTA RFQ_Questions and Answers - FINAL.pdf PDF
SCHEDULE.docx DOCX document
S02 - ATTACHMENT A - IOTA PWS - STOCKTON - Revised.pdf PDF
S02 - 36C77623Q0249.pdf PDF
S02 - ATTACHMENT F - WBS template.pdf PDF
S02 - ATTACHMENT L - Pricing Worksheet - Stockton CBOC.xlsx XLSX spreadsheet
S02 - ATTACHMENT H - QASP - STOCKTON.pdf PDF
S02 - ATTACHMENT D - Risk Management Plan and Register Template.xlsx XLSX spreadsheet
S02 - ATTACHMENT A - Stockton - IOTA PWS.pdf PDF
S02 - ATTACHMENT M - Meeting Minutes template.pdf PDF
S02 - ATTACHMENT B - Travel Authorization Request.pdf PDF
S02 - ATTACHMENT G - FFE List.xlsx XLSX spreadsheet
S02 - ATTACHMENT J - VSC Security Request Forms - 2023.pdf PDF
S02 - ATTACHMENT I - PDAT Summary.pdf PDF
S02 - ATTACHMENT E - Change Management Plan and Log Template.xlsx XLSX spreadsheet
S02 - ATTACHMENT C - Contract Staff Roster.pdf PDF
S02 - ATTACHMENT K - Wage Rate Determination (Stockton - San Joaquin County).pdf PDF
36C77623Q0249.docx DOCX document
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Activity ID Activity Name Original Duration Remaining Duration

Total Float Start Finish

VA Livermore CBOC & CUP - January 2023VA Livermore CBOC & CUP - January 2023 680 107 -43 13-May-20 A 03-Jul-23

Contract ModificationsContract Modifications 675 101 -37 13-May-20 A 23-Jun-23

CM0010-6 RFI 522 Site Security - BCD 37 / CPE 57 10 2 -21 13-May-20 A 02-Feb-23

CM0015-2 RFI 241 Added Waste Lines - BCD 39 / CPE 10 10 2 22 01-Jun-20 A 02-Feb-23

CM0016-1 RFP 22 Canopy Light Fixtures BCD 26 / CPE 51 10 3 16 01-Jun-20 A 03-Feb-23

CM0016-2 RFP 32 Fire Piping & Dr Hdwre 1A10P and 3A134A - BCD 50 / CPE 87 10 2 18 01-Jun-20 A 02-Feb-23

CM0025-1 RFP 26 Upgrade hardware/software of Video Surveillance - BCD 33 / CPE 60 Avigilon20 2 -21 17-Aug-22 A 03-Mar-23

CMP005-1 RFP 47 Manthey Rd Improvements - BCD 79 / CPE 140 80 10 -1 25-Aug-22 A 14-Feb-23

CM0020-2 RFP 38 EPPS Upgrade - BCD 61 / CPE 111 10 1 -10 12-Sep-22 A 02-Mar-23

CM0030-4 BCD 105 - CPE 144 Add REX to Doors 8 1 -37 07-Nov-22 A 01-Feb-23

CMP008 RFP 51 Pharmacy Redesign - Balance 1 101 -37 10-Nov-22 A 23-Jun-23

CM0029-6 BCD 104 Sub 28 16 00-2.1 Intrusion Detect. changes 10 1 -47 21-Nov-22 A 01-Feb-23

CM0028-1 RFP 52 upgrade door operators 1 1 5 01-Dec-22 A 01-Feb-23

CM0031-6 CPE 156 RFI 1062 RWL conflict at Spandrel Glass 10 2 -33 27-Dec-22 A 02-Feb-23

CM0031-9 CPE 195 RFP 65 rough-in for PGE antenna metering 15 10 -23 27-Dec-22 A 14-Feb-23

CMP003-1 RFP 28 City Water Tie-ins - BCD 38 / CPE 77 15 7 -5 23-Jan-23 A 09-Feb-23

Site DevelopmentSite Development 125 21 4 08-Jul-22 A 01-Mar-23

Utilities - Post Import SoilUtilities - Post Import Soil 8 4 -3 19-Dec-22 A 01-Mar-23

SD1720 JT. DW, FW & LPFW STA 66 to POC 8 4 -3 19-Dec-22 A 01-Mar-23

HardscapeHardscape 113 10 15 08-Jul-22 A 14-Feb-23

SD2310 Place Bollards 15 2 -19 08-Jul-22 A 02-Feb-23

SD3200 Chain Link Fence West Ret. Basin 10 3 -38 05-Dec-22 A 03-Feb-23

SD3190 Chain Link Fence East Ret. Basin 10 3 15 05-Dec-22 A 14-Feb-23

Area 102Area 102 10 1 -23 02-Sep-22 A 01-Feb-23

SD2950 Place Walks 102 10 1 -23 02-Sep-22 A 01-Feb-23

Area 103Area 103 10 1 -23 12-Sep-22 A 02-Feb-23

SD2960 Place Walks 103 10 1 -23 12-Sep-22 A 02-Feb-23

Area 106Area 106 54 9 -4 18-Jul-22 A 13-Feb-23

SD3060 Rebar / Place Light Base 106 10 2 -25 18-Jul-22 A 02-Feb-23

SD2920 Form / Rebar Walks 106 10 1 -20 25-Jul-22 A 01-Feb-23

SD3110 Install Light Pole Base 106 15 7 -4 12-Sep-22 A 13-Feb-23

Area 107Area 107 26 5 -20 01-Aug-22 A 07-Feb-23

SD2880 Rock Base Walks 107 10 2 -19 01-Aug-22 A 02-Feb-23

SD2930 Form / Rebar Walks 107 10 2 -20 02-Aug-22 A 03-Feb-23

SD2980 Place Walks 107 4 2 -20 05-Aug-22 A 07-Feb-23

LandscapeLandscape 89 12 -12 15-Aug-22 A 20-Feb-23

SD3540 Irrig. at Parking Lots 20 3 -23 15-Aug-22 A 07-Feb-23

SD3550 Irrig. at CBOC Bldg. 10 8 -12 10-Jan-23 A 20-Feb-23

Community Based Outpatient ClinicCommunity Based Outpatient Clinic 454 30 10 12-Apr-21 A 15-Mar-23

EnclosureEnclosure 194 11 18 12-Apr-21 A 15-Feb-23

East ElevationEast Elevation 3 1 18 10-Aug-22 A 01-Feb-23

Gridlines 6 to 8 - Area AGridlines 6 to 8 - Area A 3 1 18 10-Aug-22 A 01-Feb-23

CBOC-2890 Sealants East 6-8 3 1 18 10-Aug-22 A 01-Feb-23

North ElevationNorth Elevation 113 5 25 27-Jun-22 A 07-Feb-23

Gridlines K to N - Area AGridlines K to N - Area A 51 1 27 09-Sep-22 A 01-Feb-23

CBOC-2200 PRP System North K-N 5 1 -1 09-Sep-22 A 01-Feb-23

CBOC-3470 Parapet Cap North K-N 5 1 27 31-Oct-22 A 01-Feb-23

Gridlines G to K - Area AGridlines G to K - Area A 108 2 26 27-Jun-22 A 03-Feb-23

CBOC-2130 Metal Panels North G-K 12 1 -1 27-Jun-22 A 02-Feb-23

CBOC-2190 PRP System North G-K 5 1 -1 06-Sep-22 A 03-Feb-23

CBOC-3460 Parapet Cap North G-K 5 1 26 31-Oct-22 A 03-Feb-23

Gridlines D to G - Area AGridlines D to G - Area A 50 2 25 12-Sep-22 A 07-Feb-23

CBOC-2180 PRP System North D-G 5 1 25 12-Sep-22 A 06-Feb-23

CBOC-3450 Parapet Cap North D-G 5 1 25 31-Oct-22 A 07-Feb-23

RoofRoof 194 11 18 12-Apr-21 A 15-Feb-23

CBOC-3850 Roof Pavers 5 3 26 01-Sep-22 A 03-Feb-23

Jan Feb Mar Apr May Jun Jul Aug

03-Jul-23, VA Livermore CBOC & CUP - January 2023

23-Jun-23, Contract Modifications

RFI 522 Site Security - BCD 37 / CPE 57

RFI 241 Added Waste Lines - BCD 39 / CPE 10

RFP 22 Canopy Light Fixtures BCD 26 / CPE 51

RFP 32 Fire Piping & Dr Hdwre 1A10P and 3A134A - BCD 50 / CPE 87

RFP 26 Upgrade hardware/software of Video Surveillance - BCD 33 / CPE 60 Avigilon

RFP 47 Manthey Rd Improvements - BCD 79 / CPE 140

RFP 38 EPPS Upgrade - BCD 61 / CPE 111

BCD 105 - CPE 144 Add REX to Doors

RFP 51 Pharmacy Redesign - Balance

BCD 104 Sub 28 16 00-2.1 Intrusion Detect. changes

RFP 52 upgrade door operators

CPE 156 RFI 1062 RWL conflict at Spandrel Glass

CPE 195 RFP 65 rough-in for PGE antenna metering

RFP 28 City Water Tie-ins - BCD 38 / CPE 77

01-Mar-23, Site Development

01-Mar-23, Utilities - Post Import Soil

JT. DW, FW & LPFW STA 66 to POC

14-Feb-23, Hardscape

Place Bollards

Chain Link Fence West Ret. Basin

Chain Link Fence East Ret. Basin

01-Feb-23, Area 102

Place Walks 102

02-Feb-23, Area 103

Place Walks 103

13-Feb-23, Area 106

Rebar / Place Light Base 106

Form / Rebar Walks 106

Install Light Pole Base 106

07-Feb-23, Area 107

Rock Base Walks 107

Form / Rebar Walks 107

Place Walks 107

20-Feb-23, Landscape

Irrig. at Parking Lots

Irrig. at CBOC Bldg.

15-Mar-23, Community Based Outpatient Clinic

15-Feb-23, Enclosure

01-Feb-23, East Elevation

01-Feb-23, Gridlines 6 to 8 - Area A

Sealants East 6-8

07-Feb-23, North Elevation

01-Feb-23, Gridlines K to N - Area A

PRP System North K-N

Parapet Cap North K-N

03-Feb-23, Gridlines G to K - Area A

Metal Panels North G-K

PRP System North G-K

Parapet Cap North G-K

07-Feb-23, Gridlines D to G - Area A

PRP System North D-G

Parapet Cap North D-G

15-Feb-23, Roof

Roof Pavers

VA Livermore CBOC CUP - January 2023 Classic Schedule Layout 15-Feb-23 14:30

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 1 of 6 TASK filter: Planned Start / Finish.

© Oracle Corporation

Total Float Start Finish

CBOC-3860 Sht Mtl Flashing at TS 5 2 18 01-Dec-22 A 02-Feb-23

CBOC-3900 Flashing at Pipe Pentrations 5 3 18 01-Dec-22 A 15-Feb-23

CBOC-3910 RWL at High Roof 5 3 18 01-Dec-22 A 15-Feb-23

CBOC-3870 Flashing at Conc./Equp Pads 5 2 18 08-Dec-22 A 06-Feb-23

CBOC-3880 Flashing / Membrane 5 2 18 08-Dec-22 A 08-Feb-23

CBOC-3890 Flashing at Scuppers 5 2 18 08-Dec-22 A 10-Feb-23

Roof Rough-InRoof Rough-In 194 7 22 12-Apr-21 A 09-Feb-23

Area A - Roof Ro-InArea A - Roof Ro-In 194 5 19 12-Apr-21 A 07-Feb-23

CBOC-4030 Install Lightning Protection - Area A 10 2 22 12-Apr-21 A 02-Feb-23

CBOC-4520 Term. Branch Elec & Lighting - Area A 10 5 -1 06-Jan-23 A 07-Feb-23

Area C - Roof Ro-InArea C - Roof Ro-In 32 7 22 01-Dec-22 A 09-Feb-23

CBOC-4270 Pull Feeders to Equip - Area C 10 7 -14 01-Dec-22 A 09-Feb-23

CBOC-4360 Term. Branch Elec & Lighting - Area C 10 5 24 04-Jan-23 A 07-Feb-23

Roof FinishesRoof Finishes 12 4 -10 23-Dec-22 A 06-Feb-23

CBOC-5080 Paint - PH / Elev Lobby 5 2 -10 23-Dec-22 A 02-Feb-23

CBOC-5100 Lighting - PH / Elev Lobby 4 2 -10 06-Jan-23 A 06-Feb-23

CBOC InteriorCBOC Interior 454 30 10 12-Apr-21 A 15-Mar-23

Level 1 - Rough-InLevel 1 - Rough-In 188 30 10 02-May-22 A 15-Mar-23

L1-1190 Pull LV Wire 5 1 -12 06-Sep-22 A 01-Feb-23

Level 1 Ro-In Area A4Level 1 Ro-In Area A4 188 30 10 02-May-22 A 15-Mar-23

RFP 51 Pharmacy RedesignRFP 51 Pharmacy Redesign 188 30 10 02-May-22 A 15-Mar-23

Finishes - RFP 51Finishes - RFP 51 3 1 -37 24-Jan-23 A 08-Feb-23

RFP51-2120 Drywall 2-side 3 1 -37 24-Jan-23 A 08-Feb-23

Procurement - RFP 51Procurement - RFP 51 188 30 10 02-May-22 A 15-Mar-23

RFP51-4060 Booster Fan - Procure 50 5 -17 02-May-22 A 07-Feb-23

RFP51-4130 Vault Door - Procure 50 5 29 01-Aug-22 A 07-Feb-23

RFP51-4000 Scrub Sink - Procure 50 25 15 30-Sep-22 A 08-Mar-23

RFP51-4010 Eyewash - Procure 50 25 15 30-Sep-22 A 08-Mar-23

RFP51-4030 VFD - Procure 30 5 33 30-Sep-22 A 07-Feb-23

RFP51-4220 Breakers / Gear Changes - Procure 60 10 6 03-Oct-22 A 14-Feb-23

RFP51-4100 Doors & Hardware - Procure 50 20 11 10-Oct-22 A 01-Mar-23

RFP51-4170 Casework - Procure 60 30 -14 31-Oct-22 A 15-Mar-23

Level 2 - Rough-InLevel 2 - Rough-In 5 1 2 11-Jul-22 A 01-Feb-23

L2-1180 Pull LV Wire 5 1 2 11-Jul-22 A 01-Feb-23

Level 3 - Rough-InLevel 3 - Rough-In 5 2 1 11-Jul-22 A 02-Feb-23

L3-1180 Pull LV Wire 5 2 1 11-Jul-22 A 02-Feb-23

Level 4 - Rough-InLevel 4 - Rough-In 20 2 9 01-Nov-22 A 02-Feb-23

L4-1180 Pull LV Wire 5 1 2 01-Nov-22 A 01-Feb-23

L4-1190 Pull Control Wire 20 2 9 01-Nov-22 A 02-Feb-23

FinishesFinishes 453 29 -20 12-Apr-21 A 14-Mar-23

Level 1 FinishesLevel 1 Finishes 447 23 -30 12-Apr-21 A 06-Mar-23

L1 Area A Finishes Gridlines 2 to 5L1 Area A Finishes Gridlines 2 to 5 221 6 -48 12-Apr-21 A 08-Feb-23

L1-1300 Drywall 1st Side - 2 to 5 10 1 -48 12-Apr-21 A 01-Feb-23

L1-1330 Tape Walls - 2 to 5 12 3 -48 19-Apr-21 A 08-Feb-23

L1-1310 Insulate Walls - 2 to 5 5 1 -48 28-Jun-21 A 02-Feb-23

L1-1320 Drywall 2nd Side - 2 to 5 10 1 -48 09-Aug-21 A 03-Feb-23

L1 Area A Finishes Gridlines 5 to 8L1 Area A Finishes Gridlines 5 to 8 250 13 -43 15-Apr-21 A 21-Feb-23

L1-1670 Drywall 1st Side - 5 to 8 10 1 -47 15-Apr-21 A 02-Feb-23

L1-1700 Tape Walls - 5 to 8 12 5 -43 19-Apr-21 A 21-Feb-23

L1-1680 Insulate Walls - 5 to 8 5 1 -40 29-Jun-21 A 06-Feb-23

L1-1690 Drywall 2nd Side - 5 to 8 10 2 -40 02-Aug-21 A 08-Feb-23

L1 Area B-D FinishesL1 Area B-D Finishes 208 23 -30 19-Apr-21 A 06-Mar-23

L1-2070 Tape Walls - B to D 12 1 -37 19-Apr-21 A 01-Feb-23

L1-2100 Prime Paint - B to D 5 1 -36 01-Nov-22 A 02-Feb-23

L1-2160 Finish Paint - B to D 7 3 -30 07-Nov-22 A 06-Mar-23

Level 2 FinishesLevel 2 Finishes 111 10 -25 29-Jul-22 A 14-Feb-23

L2 Area A Finishes Gridlines 2 to 5L2 Area A Finishes Gridlines 2 to 5 111 7 -32 29-Jul-22 A 09-Feb-23

L2-1360 Finish Paint - 2 to 5 7 3 -30 29-Jul-22 A 06-Feb-23

Jan Feb Mar Apr May Jun Jul Aug

Sht Mtl Flashing at TS

Flashing at Pipe Pentrations

RWL at High Roof

Flashing at Conc./Equp Pads

Flashing / Membrane

Flashing at Scuppers

09-Feb-23, Roof Rough-In

07-Feb-23, Area A - Roof Ro-In

Install Lightning Protection - Area A

Term. Branch Elec & Lighting - Area A

09-Feb-23, Area C - Roof Ro-In

Pull Feeders to Equip - Area C

Term. Branch Elec & Lighting - Area C

06-Feb-23, Roof Finishes

Paint - PH / Elev Lobby

Lighting - PH / Elev Lobby

15-Mar-23, CBOC Interior

15-Mar-23, Level 1 - Rough-In

Pull LV Wire

15-Mar-23, Level 1 Ro-In Area A4

15-Mar-23, RFP 51 Pharmacy Redesign

08-Feb-23, Finishes - RFP 51

Drywall 2-side

15-Mar-23, Procurement - RFP 51

Booster Fan - Procure

Vault Door - Procure

Scrub Sink - Procure

Eyewash - Procure

VFD - Procure

Breakers / Gear Changes - Procure

Doors & Hardware - Procure

Casework - Procure

01-Feb-23, Level 2 - Rough-In

Pull LV Wire

02-Feb-23, Level 3 - Rough-In

Pull LV Wire

02-Feb-23, Level 4 - Rough-In

Pull LV Wire

Pull Control Wire

14-Mar-23, Finishes

06-Mar-23, Level 1 Finishes

08-Feb-23, L1 Area A Finishes Gridlines 2 to 5

Drywall 1st Side - 2 to 5

Tape Walls - 2 to 5

Insulate Walls - 2 to 5

Drywall 2nd Side - 2 to 5

21-Feb-23, L1 Area A Finishes Gridlines 5 to 8

Drywall 1st Side - 5 to 8

Tape Walls - 5 to 8

Insulate Walls - 5 to 8

Drywall 2nd Side - 5 to 8

06-Mar-23, L1 Area B-D Finishes

Tape Walls - B to D

Prime Paint - B to D

Finish Paint - B to D

14-Feb-23, Level 2 Finishes

09-Feb-23, L2 Area A Finishes Gridlines 2 to 5

Finish Paint - 2 to 5

VA Livermore CBOC CUP - January 2023 Classic Schedule Layout 15-Feb-23 14:30

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 2 of 6 TASK filter: Planned Start / Finish.

Total Float Start Finish

L2-1350 T-Bar Ceiling - 2 to 5 7 2 -32 11-Aug-22 A 03-Feb-23

L2-1380 Trim HVAC - 2 to 5 12 3 -31 15-Aug-22 A 08-Feb-23

L2-1390 Install Lighting - 2 to 5 7 4 -32 15-Aug-22 A 09-Feb-23

L2-1400 Fire Sprinkler Drops - 2 to 5 5 2 -30 03-Jan-23 A 07-Feb-23

L2-1650 Firestopping Sign-Off - 2 to 5 2 1 -32 03-Jan-23 A 01-Feb-23

L2-1660 Permiter Firestop Sign-Off - 2 to 5 2 1 -32 03-Jan-23 A 01-Feb-23

L2-2410 Above Ceiling Sign-Off - 2 to 5 3 1 -32 03-Jan-23 A 01-Feb-23

L2 Area A Finishes Gridlines 5 to 8L2 Area A Finishes Gridlines 5 to 8 103 10 -25 10-Aug-22 A 14-Feb-23

L2-1790 Finish Paint - 5 to 8 7 2 -19 10-Aug-22 A 03-Feb-23

L2-1740 T-Bar Ceiling - 5 to 8 7 3 -25 15-Aug-22 A 08-Feb-23

L2-1760 Trim HVAC - 5 to 8 10 2 -23 17-Aug-22 A 10-Feb-23

L2-1770 Install Lighting - 5 to 8 7 4 -25 22-Aug-22 A 14-Feb-23

L2-1780 Fire Sprinkler Drops - 5 to 8 5 2 -23 03-Jan-23 A 10-Feb-23

L2-1720 Firestopping Sign-Off - 5 to 8 2 1 -23 03-Jan-23 A 01-Feb-23

L2-1710 Permiter Firestop Sign-Off - 5 to 8 2 1 -23 03-Jan-23 A 01-Feb-23

L2-2420 Above Ceiling Sign-Off - 5 to 8 3 1 -23 03-Jan-23 A 01-Feb-23

Level 3 FinishesLevel 3 Finishes 111 17 -13 10-Aug-22 A 24-Feb-23

L3 Area A Finishes Gridlines 2 to 5L3 Area A Finishes Gridlines 2 to 5 108 8 -19 10-Aug-22 A 21-Feb-23

L3-1360 Finish Paint - 2 to 5 7 3 -19 10-Aug-22 A 21-Feb-23

L3-1350 T-Bar Ceiling - 2 to 5 7 3 -19 18-Aug-22 A 13-Feb-23

L3-1380 Trim HVAC - 2 to 5 12 4 -18 24-Aug-22 A 17-Feb-23

L3-1390 Install Lighting - 2 to 5 7 4 -18 29-Aug-22 A 17-Feb-23

L3-1400 Fire Sprinkler Drops - 2 to 5 5 2 -19 03-Jan-23 A 15-Feb-23

L3 Area A Finishes Gridlines 5 to 8L3 Area A Finishes Gridlines 5 to 8 100 17 10-Aug-22 A 24-Feb-23

L3-1790 Finish Paint - 5 to 8 7 3 -17 10-Aug-22 A 24-Feb-23

L3-1740 T-Bar Ceiling - 5 to 8 7 3 -17 22-Aug-22 A 16-Feb-23

L3-1720 Firestopping Sign-Off - 5 to 8 2 1 -9 03-Jan-23 A 01-Feb-23

L3-1710 Permiter Firestop Sign-Off - 5 to 8 2 1 -9 03-Jan-23 A 01-Feb-23

L3-2420 Above Ceiling Sign-Off - 5 to 8 3 1 -9 03-Jan-23 A 01-Feb-23

L3-1770 Install Lighting - 5 to 8 7 4 -12 17-Jan-23 A 23-Feb-23

L3-1780 Fire Sprinkler Drops - 5 to 8 5 2 -17 24-Jan-23 A 21-Feb-23

Level 4 FinishesLevel 4 Finishes 134 29 -27 06-Jun-22 A 14-Mar-23

L4 Area A Finishes Gridlines 2 to 5L4 Area A Finishes Gridlines 2 to 5 133 14 -20 06-Jun-22 A 21-Feb-23

L4-1330 Tape Walls - 2 to 5 12 1 -21 06-Jun-22 A 01-Feb-23

L4-1340 Prime Paint - 2 to 5 5 3 -21 07-Nov-22 A 07-Feb-23

L4-1360 Finish Paint - 2 to 5 7 3 -19 14-Nov-22 A 17-Feb-23

L4-1350 T-Bar Ceiling - 2 to 5 7 3 -21 17-Nov-22 A 10-Feb-23

L4-1380 Trim HVAC - 2 to 5 12 6 -21 28-Nov-22 A 21-Feb-23

L4-1660 Permiter Firestop Sign-Off - 2 to 5 2 1 -17 03-Jan-23 A 01-Feb-23

L4-2410 Above Ceiling Sign-Off - 2 to 5 3 1 -17 03-Jan-23 A 01-Feb-23

L4-1650 Firestopping Sign-Off - 2 to 5 2 1 -21 04-Jan-23 A 02-Feb-23

L4-1390 Install Lighting - 2 to 5 7 4 -19 17-Jan-23 A 16-Feb-23

L4-1400 Fire Sprinkler Drops - 2 to 5 5 2 -19 17-Jan-23 A 14-Feb-23

L4 Area A Finishes Gridlines 5 to 8L4 Area A Finishes Gridlines 5 to 8 122 13 -27 13-Jun-22 A 14-Mar-23

L4-1700 Tape Walls - 5 to 8 12 1 -28 13-Jun-22 A 24-Feb-23

L4-1730 Prime Paint - 5 to 8 5 3 -28 07-Nov-22 A 02-Mar-23

L4-1740 T-Bar Ceiling - 5 to 8 7 4 -28 17-Nov-22 A 08-Mar-23

L4-1720 Firestopping Sign-Off - 5 to 8 2 1 -28 03-Jan-23 A 27-Feb-23

L4-1710 Permiter Firestop Sign-Off - 5 to 8 2 1 -24 03-Jan-23 A 24-Feb-23

L4-2420 Above Ceiling Sign-Off - 5 to 8 3 1 -24 03-Jan-23 A 24-Feb-23

L4-1770 Install Lighting - 5 to 8 7 4 -27 17-Jan-23 A 14-Mar-23

L4-1780 Fire Sprinkler Drops - 5 to 8 5 2 -26 17-Jan-23 A 10-Mar-23

Specialty FinishesSpecialty Finishes 85 6 1 26-Sep-22 A 10-Feb-23

CBOC-5640 Install Audiometric Rooms 20 3 -8 26-Sep-22 A 10-Feb-23

CBOC-5680 Coiling Counter Doors - Level 1 10 1 2 15-Dec-22 A 09-Feb-23

CBOC-5670 Coiling Grille - Level 1 10 1 -1 05-Jan-23 A 03-Feb-23

Jan Feb Mar Apr May Jun Jul Aug

T-Bar Ceiling - 2 to 5

Trim HVAC - 2 to 5

Install Lighting - 2 to 5

Fire Sprinkler Drops - 2 to 5

Firestopping Sign-Off - 2 to 5

Permiter Firestop Sign-Off - 2 to 5

Above Ceiling Sign-Off - 2 to 5

14-Feb-23, L2 Area A Finishes Gridlines 5 to 8

Finish Paint - 5 to 8

T-Bar Ceiling - 5 to 8

Trim HVAC - 5 to 8

Install Lighting - 5 to 8

Fire Sprinkler Drops - 5 to 8

Firestopping Sign-Off - 5 to 8

Permiter Firestop Sign-Off - 5 to 8

Above Ceiling Sign-Off - 5 to 8

24-Feb-23, Level 3 Finishes

21-Feb-23, L3 Area A Finishes Gridlines 2 to 5

Finish Paint - 2 to 5

T-Bar Ceiling - 2 to 5

Trim HVAC - 2 to 5

Install Lighting - 2 to 5

Fire Sprinkler Drops - 2 to 5

24-Feb-23, L3 Area A Finishes Gridlines 5 to 8

Finish Paint - 5 to 8

T-Bar Ceiling - 5 to 8

Firestopping Sign-Off - 5 to 8

Permiter Firestop Sign-Off - 5 to 8

Above Ceiling Sign-Off - 5 to 8

Install Lighting - 5 to 8

Fire Sprinkler Drops - 5 to 8

14-Mar-23, Level 4 Finishes

21-Feb-23, L4 Area A Finishes Gridlines 2 to 5

Tape Walls - 2 to 5

Prime Paint - 2 to 5

Finish Paint - 2 to 5

T-Bar Ceiling - 2 to 5

Trim HVAC - 2 to 5

Permiter Firestop Sign-Off - 2 to 5

Above Ceiling Sign-Off - 2 to 5

Firestopping Sign-Off - 2 to 5

Install Lighting - 2 to 5

Fire Sprinkler Drops - 2 to 5

14-Mar-23, L4 Area A Finishes Gridlines 5 to 8

Tape Walls - 5 to 8

Prime Paint - 5 to 8

T-Bar Ceiling - 5 to 8

Firestopping Sign-Off - 5 to 8

Permiter Firestop Sign-Off - 5 to 8

Above Ceiling Sign-Off - 5 to 8

Install Lighting - 5 to 8

Fire Sprinkler Drops - 5 to 8

10-Feb-23, Specialty Finishes

Install Audiometric Rooms

Coiling Counter Doors - Level 1

Coiling Grille - Level 1

VA Livermore CBOC CUP - January 2023 Classic Schedule Layout 15-Feb-23 14:30

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 3 of 6 TASK filter: Planned Start / Finish.

Total Float Start Finish

CBOC-5720 Alum Framed Entrance - Level 1 10 5 -1 17-Jan-23 A 10-Feb-23

ElevatorsElevators 104 21 -28 15-Aug-22 A 02-Mar-23

Service ElevatorService Elevator 81 3 -35 12-Sep-22 A 03-Feb-23

CBOC-8400 Install Raceways S-1 5 1 -35 12-Sep-22 A 03-Feb-23

CBOC-8390 Install Car Fronts S-1 5 2 -35 03-Jan-23 A 02-Feb-23

Passenger Elevator P-1Passenger Elevator P-1 104 3 -28 15-Aug-22 A 03-Feb-23

CBOC-8040 Install Raceways P-1 5 1 -28 15-Aug-22 A 03-Feb-23

CBOC-8030 Install Car Fronts P-1 5 2 -28 03-Jan-23 A 02-Feb-23

Passenger Elevator P-2Passenger Elevator P-2 80 5 -28 29-Aug-22 A 02-Mar-23

CBOC-8160 Install Raceways P-2 5 3 -28 29-Aug-22 A 02-Mar-23

CBOC-8150 Install Car Fronts P-2 5 2 -28 03-Jan-23 A 27-Feb-23

Central Utility PlantCentral Utility Plant 451 20 30 05-Apr-21 A 01-Mar-23

EnclosureEnclosure 10 1 49 22-Aug-22 A 01-Feb-23

CUP-580 Caged Ladder 10 1 49 22-Aug-22 A 01-Feb-23

Rough-InRough-In 230 15 -20 25-Aug-21 A 22-Feb-23

CUP-1150 HHW Piping at Boilers 21 2 -15 25-Aug-21 A 07-Feb-23

CUP-1460 Ro-In Controls 20 1 -9 30-Aug-21 A 01-Feb-23

CUP-1420 Terminate Wire at Water/Fire Pumps 4 1 -19 25-Jul-22 A 01-Feb-23

CUP-1190 Fuel Piping & Equipment 20 15 -20 31-Oct-22 A 22-Feb-23

CUP-1040 Set Boiler & Pumps 10 3 -16 28-Nov-22 A 03-Feb-23

CUP-1465 Pull / Term. Control Wire 10 3 -9 16-Dec-22 A 06-Feb-23

CUP-1410 Terminate Wire at CT Equip. 4 1 -19 21-Dec-22 A 01-Feb-23

Finishes 451 20 10 05-Apr-21 A 01-Mar-23

CUP-930 Resinous Flooring 20 10 10 05-Apr-21 A 01-Mar-23

CUP-840 Doors & Hardware 5 1 29 20-Oct-21 A 01-Feb-23

CUP-910 Terminate & Trim Controls 20 5 25 18-Jul-22 A 07-Feb-23

CUP-860 Trim Plumbing 4 2 28 03-Jan-23 A 02-Feb-23

CUP-900 Trim Fire Alarm 10 5 25 03-Jan-23 A 07-Feb-23

CUP-970 Trim Telecom 10 5 25 03-Jan-23 A 07-Feb-23

CUP-850 Trim Electrical 10 5 25 04-Jan-23 A 07-Feb-23

Mock-UpsMock-Ups 5 1 -30 29-Jul-22 A 01-Feb-23

MU270 Single Stall Toil. Rm - Mock-up Review 5 1 -30 29-Jul-22 A 01-Feb-23

CloseoutCloseout 129 77 -43 20-Jun-22 A 03-Jul-23

Warranty, Spare-Parts and As-BuiltsWarranty, Spare-Parts and As-Builts 129 77 -43 20-Jun-22 A 03-Jul-23

CL1000 Air Barrier - Warranty 20 5 -17 20-Jun-22 A 25-May-23

CL1010 Wall Panels - Warranty 20 5 -17 20-Jun-22 A 25-May-23

CL1020 Rainscreen Panel - Warranty 20 5 -17 20-Jun-22 A 25-May-23

CL1030 HPL / EGP Wall Panels - Warranty 20 5 -17 20-Jun-22 A 25-May-23

CL1040 EPDM Roofing - Warranty 20 5 -17 20-Jun-22 A 25-May-23

CL1050 Firestopping - Warranty 20 5 -15 20-Jun-22 A 23-May-23

CL1060 Wood Doors - Warranty 20 5 -15 20-Jun-22 A 23-May-23

CL1070 Coiling Counter Doors - Warranty 20 5 -15 20-Jun-22 A 23-May-23

CL1080 Vert. Folding Wall - Warranty 20 5 16 20-Jun-22 A 10-Apr-23

CL1090 Alum. Entry & Storefronts - Warranty 20 5 -27 20-Jun-22 A 09-Jun-23

CL1100 Curtain Wall - Warranty 20 5 -27 20-Jun-22 A 09-Jun-23

CL1110 Door Hardware - Warranty 20 5 -15 20-Jun-22 A 23-May-23

CL1130 Glazing - Warranty 20 5 -27 20-Jun-22 A 09-Jun-23

CL1120 Low-E Pwr Operators - Warranty 20 5 -15 20-Jun-22 A 23-May-23

CL1140 Ceramic / Porcelain Tile - Warranty 20 5 -15 20-Jun-22 A 23-May-23

CL1150 Wood Clg System - Warranty 20 5 -15 20-Jun-22 A 23-May-23

CL1160 Static Control Flrng - Warranty 20 5 -15 20-Jun-22 A 23-May-23

CL1170 Resilient Flooring - Warranty 20 5 -15 20-Jun-22 A 23-May-23

CL1180 Athletic Flrng - Warranty 20 5 -15 20-Jun-22 A 23-May-23

CL1190 Carpet Tile - Warranty 20 5 -15 20-Jun-22 A 23-May-23

CL1200 Signage - Warranty 20 5 -15 20-Jun-22 A 23-May-23

Jan Feb Mar Apr May Jun Jul Aug

Alum Framed Entrance - Level 1

02-Mar-23, Elevators

03-Feb-23, Service Elevator

Install Raceways S-1

Install Car Fronts S-1

03-Feb-23, Passenger Elevator P-1

Install Raceways P-1

Install Car Fronts P-1

02-Mar-23, Passenger Elevator P-2

Install Raceways P-2

Install Car Fronts P-2

01-Mar-23, Central Utility Plant

01-Feb-23, Enclosure

Caged Ladder

22-Feb-23, Rough-In

HHW Piping at Boilers

Ro-In Controls

Terminate Wire at Water/Fire Pumps

Fuel Piping & Equipment

Set Boiler & Pumps

Pull / Term. Control Wire

Terminate Wire at CT Equip.

01-Mar-23, Finishes

Resinous Flooring

Doors & Hardware

Terminate & Trim Controls

Trim Plumbing

Trim Fire Alarm

Trim Telecom

Trim Electrical

01-Feb-23, Mock-Ups

Single Stall Toil. Rm - Mock-up Review

03-Jul-23, Closeout

03-Jul-23, Warranty, Spare-Parts and As-Builts

Air Barrier - Warranty

Wall Panels - Warranty

Rainscreen Panel - Warranty

HPL / EGP Wall Panels - Warranty

EPDM Roofing - Warranty

Firestopping - Warranty

Wood Doors - Warranty

Coiling Counter Doors - Warranty

Vert. Folding Wall - Warranty

Alum. Entry & Storefronts - Warranty

Curtain Wall - Warranty

Door Hardware - Warranty

Glazing - Warranty

Low-E Pwr Operators - Warranty

Ceramic / Porcelain Tile - Warranty

Wood Clg System - Warranty

Static Control Flrng - Warranty

Resilient Flooring - Warranty

Athletic Flrng - Warranty

Carpet Tile - Warranty

Signage - Warranty

VA Livermore CBOC CUP - January 2023 Classic Schedule Layout 15-Feb-23 14:30

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 4 of 6 TASK filter: Planned Start / Finish.

Total Float Start Finish

CL1210 Cubicle Curtain - Warranty 20 5 -15 20-Jun-22 A 23-May-23

CL1220 Wire Mesh Partitions - Warranty 20 5 -15 20-Jun-22 A 23-May-23

CL1230 Wall & Door Protection - Warranty 20 5 -15 20-Jun-22 A 23-May-23

CL1240 Bullet Fiberglass Sht - Warranty 20 5 -15 20-Jun-22 A 23-May-23

CL1250 Toilet Access. - Warranty 20 5 -15 20-Jun-22 A 23-May-23

CL1260 Dock Levelers - Warranty 20 8 -16 20-Jun-22 A 24-May-23

CL1270 Window Tie Backs - Warranty 20 5 -27 20-Jun-22 A 09-Jun-23

CL1280 Food Service Equip - Warranty 20 5 -15 20-Jun-22 A 23-May-23

CL1290 Wood Casework - Warranty 20 5 -15 20-Jun-22 A 23-May-23

CL1300 Solid Surfaces - Warranty 20 5 -15 20-Jun-22 A 23-May-23

CL1310 Elevators - Warranty 20 5 -11 20-Jun-22 A 17-May-23

CL1320 HVAC Controls - Warranty 20 5 -33 20-Jun-22 A 19-Jun-23

CL1330 Boilers - Warranty 20 5 -18 20-Jun-22 A 26-May-23

CL1340 Chillers - Warranty 20 5 19 20-Jun-22 A 05-Apr-23

CL1350 FCU's - Warranty 20 5 -15 20-Jun-22 A 23-May-23

CL1360 Elec. Humidifiers - Warranty 20 5 -15 20-Jun-22 A 23-May-23

CL1035 Joint Sealant - Warranty 20 5 -27 20-Jun-22 A 09-Jun-23

CL1265 Detention Equip - Waranty 20 5 -15 20-Jun-22 A 23-May-23

CL1370 Utility Metering System - Warranty 20 5 -33 20-Jun-22 A 19-Jun-23

CL1510 Fire Sprinklers - As-Builts 20 5 -15 20-Jun-22 A 23-May-23

CL1520 Fire Pumps - As-Builts 20 5 19 20-Jun-22 A 05-Apr-23

CL1530 Plumbing Motors - Certs 20 5 19 20-Jun-22 A 05-Apr-23

CL1540 Meters & Guages - As-Builts 20 5 -15 20-Jun-22 A 23-May-23

CL1550 Plumbing Insulation - As-Builts 20 5 -15 20-Jun-22 A 23-May-23

CL1560 Water Distribution - As-Builts 20 5 -15 20-Jun-22 A 23-May-23

CL1570 DW Pumps - As-Builts 20 5 -15 20-Jun-22 A 23-May-23

CL1580 Sanitary & Vent Piping - As-Builts 20 5 -15 20-Jun-22 A 23-May-23

CL1590 SS Pumps - As-Builts 20 10 -20 20-Jun-22 A 31-May-23

CL1600 Facility Storm Drain - As-Builts 20 5 -15 20-Jun-22 A 23-May-23

CL1610 Water Softener - As-Builts 20 5 -15 20-Jun-22 A 23-May-23

CL1620 DW Water Heaters - As-Builts 20 5 -15 20-Jun-22 A 23-May-23

CL1500 Dental Air Piping - As-Builts 20 5 -15 20-Jun-22 A 23-May-23

CL1630 Vacuum System - As-Builts 20 5 -15 20-Jun-22 A 23-May-23

CL1640 HVAC Controls - As-Builts 20 5 -15 20-Jun-22 A 23-May-23

CL1650 Cooling Towers - Certs 20 10 14 20-Jun-22 A 12-Apr-23

CL1660 Utility Metering System - As-Builts 30 15 -43 20-Jun-22 A 03-Jul-23

CL1670 Transformers - Spare Parts 30 15 9 20-Jun-22 A 19-Apr-23

CL1680 Switches & C.B.'s - Spare Parts 30 15 -15 20-Jun-22 A 23-May-23

CL1690 Generators - Spare Parts 30 15 9 20-Jun-22 A 19-Apr-23

CL1525 Plumbing - As-Builts 20 5 -15 20-Jun-22 A 23-May-23

CL1700 Comm. System - Warranty 30 15 -15 20-Jun-22 A 23-May-23

CL1710 PA System - Warranty 30 15 -15 20-Jun-22 A 23-May-23

CL1720 Nurse Call System - Warranty 30 15 -15 20-Jun-22 A 23-May-23

CL1730 Radio Equip - Warranty 30 15 -15 20-Jun-22 A 23-May-23

CL1740 Comm. System - As-Builts 30 15 -15 20-Jun-22 A 23-May-23

CL1750 PA System - As-Builts 30 15 -15 20-Jun-22 A 23-May-23

CL1760 Nurse Call System - As-Builts 30 15 -15 20-Jun-22 A 23-May-23

CL1770 Radio Equip - As-Builts 30 15 -15 20-Jun-22 A 23-May-23

CL1780 Security System - Warranty 30 15 -15 20-Jun-22 A 23-May-23

CL1790 Fire Alarm System - Warranty 30 15 -15 20-Jun-22 A 23-May-23

CL1860 Sanitary Sewer Utilities - Warranty 20 8 -16 20-Jun-22 A 24-May-23

CL1870 Storm Sewer Utilities - Warranty 20 8 -16 20-Jun-22 A 24-May-23

CL1880 Site Gas Utilities - Warranty 20 8 -16 20-Jun-22 A 24-May-23

CL1800 Porous Flexible Paving - Warranty 20 8 -16 20-Jun-22 A 24-May-23

CL1810 Gate Operators - Warranty 20 8 -16 20-Jun-22 A 24-May-23

CL1820 Steel Fence & Gates - Warranty 20 8 -16 20-Jun-22 A 24-May-23

Jan Feb Mar Apr May Jun Jul Aug

Cubicle Curtain - Warranty

Wire Mesh Partitions - Warranty

Wall & Door Protection - Warranty

Bullet Fiberglass Sht - Warranty

Toilet Access. - Warranty

Dock Levelers - Warranty

Window Tie Backs - Warranty

Food Service Equip - Warranty

Wood Casework - Warranty

Solid Surfaces - Warranty

Elevators - Warranty

HVAC Controls - Warranty

Boilers - Warranty

Chillers - Warranty

FCU's - Warranty

Elec. Humidifiers - Warranty

Joint Sealant - Warranty

Detention Equip - Waranty

Utility Metering System - Warranty

Fire Sprinklers - As-Builts

Fire Pumps - As-Builts

Plumbing Motors - Certs

Meters & Guages - As-Builts

Plumbing Insulation - As-Builts

Water Distribution - As-Builts

DW Pumps - As-Builts

Sanitary & Vent Piping - As-Builts

SS Pumps - As-Builts

Facility Storm Drain - As-Builts

Water Softener - As-Builts

DW Water Heaters - As-Builts

Dental Air Piping - As-Builts

Vacuum System - As-Builts

HVAC Controls - As-Builts

Cooling Towers - Certs

Utility Metering System - As-Builts

Transformers - Spare Parts

Switches & C.B.'s - Spare Parts

Generators - Spare Parts

Plumbing - As-Builts

Comm. System - Warranty

PA System - Warranty

Nurse Call System - Warranty

Radio Equip - Warranty

Comm. System - As-Builts

PA System - As-Builts

Nurse Call System - As-Builts

Radio Equip - As-Builts

Security System - Warranty

Fire Alarm System - Warranty

Sanitary Sewer Utilities - Warranty

Storm Sewer Utilities - Warranty

Site Gas Utilities - Warranty

Porous Flexible Paving - Warranty

Gate Operators - Warranty

Steel Fence & Gates - Warranty

VA Livermore CBOC CUP - January 2023 Classic Schedule Layout 15-Feb-23 14:30

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 5 of 6 TASK filter: Planned Start / Finish.

Total Float Start Finish

CL1830 Loop Vehicle Detector - Warranty 20 8 -16 20-Jun-22 A 24-May-23

CL1840 Planting - Warranty 20 8 -16 20-Jun-22 A 24-May-23

CL1850 Hydroseeding - Warranty 20 8 -16 20-Jun-22 A 24-May-23

CL1890 Solar PV System - Warranty 30 15 19 20-Jun-22 A 05-Apr-23

SubmittalsSubmittals 565 40 13 01-Sep-20 A 29-Mar-23

SubmitSubmit 346 10 -25 01-Sep-20 A 14-Feb-23

S230811 Demo & Test Boiler - Submit 159 1 -16 01-Sep-20 A 01-Feb-23

S251010 Utility Metering System - Submit 109 10 -39 01-Sep-21 A 14-Feb-23

ReviewReview 30 8 -42 27-May-21 A 08-Feb-23

R226119.74 Dental Air Equip - Review 30 8 -42 27-May-21 A 08-Feb-23

ProcureProcure 205 40 13 01-Feb-22 A 29-Mar-23

P281300 Access Control System - Procure 50 20 -19 01-Feb-22 A 01-Mar-23

P281600 Intrusion Detection - Procure 50 20 -19 01-Feb-22 A 01-Mar-23

P226119.74 Dental Air Equip - Procure 40 10 -28 28-Feb-22 A 23-Feb-23

P260573 Arc Flash Labels - Procure 40 15 -33 01-Mar-22 A 22-Feb-23

P329300 Site Furnishings - Procure 40 10 -33 01-Mar-22 A 14-Feb-23

P097761 FRP Panels - Procure 40 15 -25 07-Mar-22 A 22-Feb-23

P074113 Metal Roofing - Procure 40 25 -21 28-Mar-22 A 08-Mar-23

P083506 Operable Wall - Procure 51 15 8 31-Mar-22 A 22-Feb-23

P084229 Auto Sliding Doors - Procure 75 20 -13 01-Jun-22 A 01-Mar-23

P101400 Signage - Procure 40 10 1 01-Jun-22 A 14-Feb-23

P102123 Cubicle Curtain - Procure 40 10 0 01-Jun-22 A 14-Feb-23

P102213 Wire Mesh Partitions - Procure 40 20 -11 01-Jun-22 A 01-Mar-23

P102600 Wall & Door Protection - Procure 40 20 -9 01-Jun-22 A 01-Mar-23

P230593 HVAC TAB - Procure 40 20 7 01-Jun-22 A 01-Mar-23

P260913 Power Monitoring System - Procure 40 40 13 01-Jun-22 A 29-Mar-23

P274131 Antenna TV System - Procure 40 20 14 01-Jun-22 A 01-Mar-23

P275116 PA & Mass Notification - Procure 40 20 -26 01-Jun-22 A 01-Mar-23

P275223 Nurse Call System - Procure 40 20 -26 01-Jun-22 A 01-Mar-23

P275319 Radio Eqiup System - Procure 50 20 12 01-Jun-22 A 01-Mar-23

P282800 Video Surveillance - Procure 50 20 -21 01-Jun-22 A 01-Mar-23

P282600 Personal Protection System - Procure 50 20 -19 01-Jun-22 A 01-Mar-23

P283100 Fire Alarm - Procure 40 20 -31 01-Jun-22 A 01-Mar-23

P321723 Pavement Markings - Procure 40 5 9 01-Jun-22 A 07-Feb-23

P329000 Planting - Procure 60 20 -24 01-Jun-22 A 14-Mar-23

P329010 Agg. Paving - Procure 40 10 -15 01-Jun-22 A 14-Feb-23

P329219 Hydroseeding - Procure 40 10 -10 01-Jun-22 A 14-Feb-23

P329223 Sodding - Procure 40 10 9 01-Jun-22 A 14-Feb-23

P330800 Cx Site Utilities - Procure 40 15 2 01-Jun-22 A 22-Feb-23

P088000-2 Interior Glazing - Procure 20 10 1 01-Jun-22 A 14-Feb-23

P226219.74 Dental Vacuum Sys - Procure 40 39 -6 30-Sep-22 A 28-Mar-23

Jan Feb Mar Apr May Jun Jul Aug

Loop Vehicle Detector - Warranty

Planting - Warranty

Hydroseeding - Warranty

Solar PV System - Warranty

29-Mar-23, Submittals

14-Feb-23, Submit

Demo & Test Boiler - Submit

Utility Metering System - Submit

08-Feb-23, Review

Dental Air Equip - Review

29-Mar-23, Procure

Access Control System - Procure

Intrusion Detection - Procure

Dental Air Equip - Procure

Arc Flash Labels - Procure

Site Furnishings - Procure

FRP Panels - Procure

Metal Roofing - Procure

Operable Wall - Procure

Auto Sliding Doors - Procure

Signage - Procure

Cubicle Curtain - Procure

Wire Mesh Partitions - Procure

Wall & Door Protection - Procure

HVAC TAB - Procure

Power Monitoring System - Procure

Antenna TV System - Procure

PA & Mass Notification - Procure

Nurse Call System - Procure

Radio Eqiup System - Procure

Video Surveillance - Procure

Personal Protection System - Procure

Fire Alarm - Procure

Pavement Markings - Procure

Planting - Procure

Agg. Paving - Procure

Hydroseeding - Procure

Sodding - Procure

Cx Site Utilities - Procure

Interior Glazing - Procure

Dental Vacuum Sys - Procure

VA Livermore CBOC CUP - January 2023 Classic Schedule Layout 15-Feb-23 14:30

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 6 of 6 TASK filter: Planned Start / Finish.