S02 - ATTACHMENT N - Construction Schedule.pdf
PDF 299 KB Posted
- Attached to
- Q702--Stockton CBOC Activation Contract Federal contract opportunity
- Solicitation number
- 36C77623Q0249
About this file
This document is an RFQ for the Stockton CBOC Activation Contract. The solicitation is seeking proposals for the activation of a new Community Based Outpatient Clinic in Stockton, California for the Department of Veterans Affairs Technology Acquisition Center Austin. Key requirements include construction and buildout services to prepare the new CBOC facility for operations. An attached schedule details the construction timeline and milestones spanning from May 2022 through July 2023, including site development, utilities installation, building enclosure, interior construction and finishes, elevators, central utility plant buildout, closeout activities, and warranty periods. Proposals are due by February 14, 2023, with contract award anticipated by March 29, 2023. The solicitation is designated for small business set-aside and targets SDVOSB/VOSB concerns.
View the file
Other files for this federal contract opportunity
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Activity ID Activity Name Original Duration Remaining Duration
Total Float Start Finish
VA Livermore CBOC & CUP - January 2023VA Livermore CBOC & CUP - January 2023 680 107 -43 13-May-20 A 03-Jul-23
Contract ModificationsContract Modifications 675 101 -37 13-May-20 A 23-Jun-23
CM0010-6 RFI 522 Site Security - BCD 37 / CPE 57 10 2 -21 13-May-20 A 02-Feb-23
CM0015-2 RFI 241 Added Waste Lines - BCD 39 / CPE 10 10 2 22 01-Jun-20 A 02-Feb-23
CM0016-1 RFP 22 Canopy Light Fixtures BCD 26 / CPE 51 10 3 16 01-Jun-20 A 03-Feb-23
CM0016-2 RFP 32 Fire Piping & Dr Hdwre 1A10P and 3A134A - BCD 50 / CPE 87 10 2 18 01-Jun-20 A 02-Feb-23
CM0025-1 RFP 26 Upgrade hardware/software of Video Surveillance - BCD 33 / CPE 60 Avigilon20 2 -21 17-Aug-22 A 03-Mar-23
CMP005-1 RFP 47 Manthey Rd Improvements - BCD 79 / CPE 140 80 10 -1 25-Aug-22 A 14-Feb-23
CM0020-2 RFP 38 EPPS Upgrade - BCD 61 / CPE 111 10 1 -10 12-Sep-22 A 02-Mar-23
CM0030-4 BCD 105 - CPE 144 Add REX to Doors 8 1 -37 07-Nov-22 A 01-Feb-23
CMP008 RFP 51 Pharmacy Redesign - Balance 1 101 -37 10-Nov-22 A 23-Jun-23
CM0029-6 BCD 104 Sub 28 16 00-2.1 Intrusion Detect. changes 10 1 -47 21-Nov-22 A 01-Feb-23
CM0028-1 RFP 52 upgrade door operators 1 1 5 01-Dec-22 A 01-Feb-23
CM0031-6 CPE 156 RFI 1062 RWL conflict at Spandrel Glass 10 2 -33 27-Dec-22 A 02-Feb-23
CM0031-9 CPE 195 RFP 65 rough-in for PGE antenna metering 15 10 -23 27-Dec-22 A 14-Feb-23
CMP003-1 RFP 28 City Water Tie-ins - BCD 38 / CPE 77 15 7 -5 23-Jan-23 A 09-Feb-23
Site DevelopmentSite Development 125 21 4 08-Jul-22 A 01-Mar-23
Utilities - Post Import SoilUtilities - Post Import Soil 8 4 -3 19-Dec-22 A 01-Mar-23
SD1720 JT. DW, FW & LPFW STA 66 to POC 8 4 -3 19-Dec-22 A 01-Mar-23
HardscapeHardscape 113 10 15 08-Jul-22 A 14-Feb-23
SD2310 Place Bollards 15 2 -19 08-Jul-22 A 02-Feb-23
SD3200 Chain Link Fence West Ret. Basin 10 3 -38 05-Dec-22 A 03-Feb-23
SD3190 Chain Link Fence East Ret. Basin 10 3 15 05-Dec-22 A 14-Feb-23
Area 102Area 102 10 1 -23 02-Sep-22 A 01-Feb-23
SD2950 Place Walks 102 10 1 -23 02-Sep-22 A 01-Feb-23
Area 103Area 103 10 1 -23 12-Sep-22 A 02-Feb-23
SD2960 Place Walks 103 10 1 -23 12-Sep-22 A 02-Feb-23
Area 106Area 106 54 9 -4 18-Jul-22 A 13-Feb-23
SD3060 Rebar / Place Light Base 106 10 2 -25 18-Jul-22 A 02-Feb-23
SD2920 Form / Rebar Walks 106 10 1 -20 25-Jul-22 A 01-Feb-23
SD3110 Install Light Pole Base 106 15 7 -4 12-Sep-22 A 13-Feb-23
Area 107Area 107 26 5 -20 01-Aug-22 A 07-Feb-23
SD2880 Rock Base Walks 107 10 2 -19 01-Aug-22 A 02-Feb-23
SD2930 Form / Rebar Walks 107 10 2 -20 02-Aug-22 A 03-Feb-23
SD2980 Place Walks 107 4 2 -20 05-Aug-22 A 07-Feb-23
LandscapeLandscape 89 12 -12 15-Aug-22 A 20-Feb-23
SD3540 Irrig. at Parking Lots 20 3 -23 15-Aug-22 A 07-Feb-23
SD3550 Irrig. at CBOC Bldg. 10 8 -12 10-Jan-23 A 20-Feb-23
Community Based Outpatient ClinicCommunity Based Outpatient Clinic 454 30 10 12-Apr-21 A 15-Mar-23
EnclosureEnclosure 194 11 18 12-Apr-21 A 15-Feb-23
East ElevationEast Elevation 3 1 18 10-Aug-22 A 01-Feb-23
Gridlines 6 to 8 - Area AGridlines 6 to 8 - Area A 3 1 18 10-Aug-22 A 01-Feb-23
CBOC-2890 Sealants East 6-8 3 1 18 10-Aug-22 A 01-Feb-23
North ElevationNorth Elevation 113 5 25 27-Jun-22 A 07-Feb-23
Gridlines K to N - Area AGridlines K to N - Area A 51 1 27 09-Sep-22 A 01-Feb-23
CBOC-2200 PRP System North K-N 5 1 -1 09-Sep-22 A 01-Feb-23
CBOC-3470 Parapet Cap North K-N 5 1 27 31-Oct-22 A 01-Feb-23
Gridlines G to K - Area AGridlines G to K - Area A 108 2 26 27-Jun-22 A 03-Feb-23
CBOC-2130 Metal Panels North G-K 12 1 -1 27-Jun-22 A 02-Feb-23
CBOC-2190 PRP System North G-K 5 1 -1 06-Sep-22 A 03-Feb-23
CBOC-3460 Parapet Cap North G-K 5 1 26 31-Oct-22 A 03-Feb-23
Gridlines D to G - Area AGridlines D to G - Area A 50 2 25 12-Sep-22 A 07-Feb-23
CBOC-2180 PRP System North D-G 5 1 25 12-Sep-22 A 06-Feb-23
CBOC-3450 Parapet Cap North D-G 5 1 25 31-Oct-22 A 07-Feb-23
RoofRoof 194 11 18 12-Apr-21 A 15-Feb-23
CBOC-3850 Roof Pavers 5 3 26 01-Sep-22 A 03-Feb-23
Jan Feb Mar Apr May Jun Jul Aug
03-Jul-23, VA Livermore CBOC & CUP - January 2023
23-Jun-23, Contract Modifications
RFI 522 Site Security - BCD 37 / CPE 57
RFI 241 Added Waste Lines - BCD 39 / CPE 10
RFP 22 Canopy Light Fixtures BCD 26 / CPE 51
RFP 32 Fire Piping & Dr Hdwre 1A10P and 3A134A - BCD 50 / CPE 87
RFP 26 Upgrade hardware/software of Video Surveillance - BCD 33 / CPE 60 Avigilon
RFP 47 Manthey Rd Improvements - BCD 79 / CPE 140
RFP 38 EPPS Upgrade - BCD 61 / CPE 111
BCD 105 - CPE 144 Add REX to Doors
RFP 51 Pharmacy Redesign - Balance
BCD 104 Sub 28 16 00-2.1 Intrusion Detect. changes
RFP 52 upgrade door operators
CPE 156 RFI 1062 RWL conflict at Spandrel Glass
CPE 195 RFP 65 rough-in for PGE antenna metering
RFP 28 City Water Tie-ins - BCD 38 / CPE 77
01-Mar-23, Site Development
01-Mar-23, Utilities - Post Import Soil
JT. DW, FW & LPFW STA 66 to POC
14-Feb-23, Hardscape
Place Bollards
Chain Link Fence West Ret. Basin
Chain Link Fence East Ret. Basin
01-Feb-23, Area 102
Place Walks 102
02-Feb-23, Area 103
Place Walks 103
13-Feb-23, Area 106
Rebar / Place Light Base 106
Form / Rebar Walks 106
Install Light Pole Base 106
07-Feb-23, Area 107
Rock Base Walks 107
Form / Rebar Walks 107
Place Walks 107
20-Feb-23, Landscape
Irrig. at Parking Lots
Irrig. at CBOC Bldg.
15-Mar-23, Community Based Outpatient Clinic
15-Feb-23, Enclosure
01-Feb-23, East Elevation
01-Feb-23, Gridlines 6 to 8 - Area A
Sealants East 6-8
07-Feb-23, North Elevation
01-Feb-23, Gridlines K to N - Area A
PRP System North K-N
Parapet Cap North K-N
03-Feb-23, Gridlines G to K - Area A
Metal Panels North G-K
PRP System North G-K
Parapet Cap North G-K
07-Feb-23, Gridlines D to G - Area A
PRP System North D-G
Parapet Cap North D-G
15-Feb-23, Roof
Roof Pavers
VA Livermore CBOC CUP - January 2023 Classic Schedule Layout 15-Feb-23 14:30
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 1 of 6 TASK filter: Planned Start / Finish.
© Oracle Corporation
Total Float Start Finish
CBOC-3860 Sht Mtl Flashing at TS 5 2 18 01-Dec-22 A 02-Feb-23
CBOC-3900 Flashing at Pipe Pentrations 5 3 18 01-Dec-22 A 15-Feb-23
CBOC-3910 RWL at High Roof 5 3 18 01-Dec-22 A 15-Feb-23
CBOC-3870 Flashing at Conc./Equp Pads 5 2 18 08-Dec-22 A 06-Feb-23
CBOC-3880 Flashing / Membrane 5 2 18 08-Dec-22 A 08-Feb-23
CBOC-3890 Flashing at Scuppers 5 2 18 08-Dec-22 A 10-Feb-23
Roof Rough-InRoof Rough-In 194 7 22 12-Apr-21 A 09-Feb-23
Area A - Roof Ro-InArea A - Roof Ro-In 194 5 19 12-Apr-21 A 07-Feb-23
CBOC-4030 Install Lightning Protection - Area A 10 2 22 12-Apr-21 A 02-Feb-23
CBOC-4520 Term. Branch Elec & Lighting - Area A 10 5 -1 06-Jan-23 A 07-Feb-23
Area C - Roof Ro-InArea C - Roof Ro-In 32 7 22 01-Dec-22 A 09-Feb-23
CBOC-4270 Pull Feeders to Equip - Area C 10 7 -14 01-Dec-22 A 09-Feb-23
CBOC-4360 Term. Branch Elec & Lighting - Area C 10 5 24 04-Jan-23 A 07-Feb-23
Roof FinishesRoof Finishes 12 4 -10 23-Dec-22 A 06-Feb-23
CBOC-5080 Paint - PH / Elev Lobby 5 2 -10 23-Dec-22 A 02-Feb-23
CBOC-5100 Lighting - PH / Elev Lobby 4 2 -10 06-Jan-23 A 06-Feb-23
CBOC InteriorCBOC Interior 454 30 10 12-Apr-21 A 15-Mar-23
Level 1 - Rough-InLevel 1 - Rough-In 188 30 10 02-May-22 A 15-Mar-23
L1-1190 Pull LV Wire 5 1 -12 06-Sep-22 A 01-Feb-23
Level 1 Ro-In Area A4Level 1 Ro-In Area A4 188 30 10 02-May-22 A 15-Mar-23
RFP 51 Pharmacy RedesignRFP 51 Pharmacy Redesign 188 30 10 02-May-22 A 15-Mar-23
Finishes - RFP 51Finishes - RFP 51 3 1 -37 24-Jan-23 A 08-Feb-23
RFP51-2120 Drywall 2-side 3 1 -37 24-Jan-23 A 08-Feb-23
Procurement - RFP 51Procurement - RFP 51 188 30 10 02-May-22 A 15-Mar-23
RFP51-4060 Booster Fan - Procure 50 5 -17 02-May-22 A 07-Feb-23
RFP51-4130 Vault Door - Procure 50 5 29 01-Aug-22 A 07-Feb-23
RFP51-4000 Scrub Sink - Procure 50 25 15 30-Sep-22 A 08-Mar-23
RFP51-4010 Eyewash - Procure 50 25 15 30-Sep-22 A 08-Mar-23
RFP51-4030 VFD - Procure 30 5 33 30-Sep-22 A 07-Feb-23
RFP51-4220 Breakers / Gear Changes - Procure 60 10 6 03-Oct-22 A 14-Feb-23
RFP51-4100 Doors & Hardware - Procure 50 20 11 10-Oct-22 A 01-Mar-23
RFP51-4170 Casework - Procure 60 30 -14 31-Oct-22 A 15-Mar-23
Level 2 - Rough-InLevel 2 - Rough-In 5 1 2 11-Jul-22 A 01-Feb-23
L2-1180 Pull LV Wire 5 1 2 11-Jul-22 A 01-Feb-23
Level 3 - Rough-InLevel 3 - Rough-In 5 2 1 11-Jul-22 A 02-Feb-23
L3-1180 Pull LV Wire 5 2 1 11-Jul-22 A 02-Feb-23
Level 4 - Rough-InLevel 4 - Rough-In 20 2 9 01-Nov-22 A 02-Feb-23
L4-1180 Pull LV Wire 5 1 2 01-Nov-22 A 01-Feb-23
L4-1190 Pull Control Wire 20 2 9 01-Nov-22 A 02-Feb-23
FinishesFinishes 453 29 -20 12-Apr-21 A 14-Mar-23
Level 1 FinishesLevel 1 Finishes 447 23 -30 12-Apr-21 A 06-Mar-23
L1 Area A Finishes Gridlines 2 to 5L1 Area A Finishes Gridlines 2 to 5 221 6 -48 12-Apr-21 A 08-Feb-23
L1-1300 Drywall 1st Side - 2 to 5 10 1 -48 12-Apr-21 A 01-Feb-23
L1-1330 Tape Walls - 2 to 5 12 3 -48 19-Apr-21 A 08-Feb-23
L1-1310 Insulate Walls - 2 to 5 5 1 -48 28-Jun-21 A 02-Feb-23
L1-1320 Drywall 2nd Side - 2 to 5 10 1 -48 09-Aug-21 A 03-Feb-23
L1 Area A Finishes Gridlines 5 to 8L1 Area A Finishes Gridlines 5 to 8 250 13 -43 15-Apr-21 A 21-Feb-23
L1-1670 Drywall 1st Side - 5 to 8 10 1 -47 15-Apr-21 A 02-Feb-23
L1-1700 Tape Walls - 5 to 8 12 5 -43 19-Apr-21 A 21-Feb-23
L1-1680 Insulate Walls - 5 to 8 5 1 -40 29-Jun-21 A 06-Feb-23
L1-1690 Drywall 2nd Side - 5 to 8 10 2 -40 02-Aug-21 A 08-Feb-23
L1 Area B-D FinishesL1 Area B-D Finishes 208 23 -30 19-Apr-21 A 06-Mar-23
L1-2070 Tape Walls - B to D 12 1 -37 19-Apr-21 A 01-Feb-23
L1-2100 Prime Paint - B to D 5 1 -36 01-Nov-22 A 02-Feb-23
L1-2160 Finish Paint - B to D 7 3 -30 07-Nov-22 A 06-Mar-23
Level 2 FinishesLevel 2 Finishes 111 10 -25 29-Jul-22 A 14-Feb-23
L2 Area A Finishes Gridlines 2 to 5L2 Area A Finishes Gridlines 2 to 5 111 7 -32 29-Jul-22 A 09-Feb-23
L2-1360 Finish Paint - 2 to 5 7 3 -30 29-Jul-22 A 06-Feb-23
Jan Feb Mar Apr May Jun Jul Aug
Sht Mtl Flashing at TS
Flashing at Pipe Pentrations
RWL at High Roof
Flashing at Conc./Equp Pads
Flashing / Membrane
Flashing at Scuppers
09-Feb-23, Roof Rough-In
07-Feb-23, Area A - Roof Ro-In
Install Lightning Protection - Area A
Term. Branch Elec & Lighting - Area A
09-Feb-23, Area C - Roof Ro-In
Pull Feeders to Equip - Area C
Term. Branch Elec & Lighting - Area C
06-Feb-23, Roof Finishes
Paint - PH / Elev Lobby
Lighting - PH / Elev Lobby
15-Mar-23, CBOC Interior
15-Mar-23, Level 1 - Rough-In
Pull LV Wire
15-Mar-23, Level 1 Ro-In Area A4
15-Mar-23, RFP 51 Pharmacy Redesign
08-Feb-23, Finishes - RFP 51
Drywall 2-side
15-Mar-23, Procurement - RFP 51
Booster Fan - Procure
Vault Door - Procure
Scrub Sink - Procure
Eyewash - Procure
VFD - Procure
Breakers / Gear Changes - Procure
Doors & Hardware - Procure
Casework - Procure
01-Feb-23, Level 2 - Rough-In
Pull LV Wire
02-Feb-23, Level 3 - Rough-In
Pull LV Wire
02-Feb-23, Level 4 - Rough-In
Pull LV Wire
Pull Control Wire
14-Mar-23, Finishes
06-Mar-23, Level 1 Finishes
08-Feb-23, L1 Area A Finishes Gridlines 2 to 5
Drywall 1st Side - 2 to 5
Tape Walls - 2 to 5
Insulate Walls - 2 to 5
Drywall 2nd Side - 2 to 5
21-Feb-23, L1 Area A Finishes Gridlines 5 to 8
Drywall 1st Side - 5 to 8
Tape Walls - 5 to 8
Insulate Walls - 5 to 8
Drywall 2nd Side - 5 to 8
06-Mar-23, L1 Area B-D Finishes
Tape Walls - B to D
Prime Paint - B to D
Finish Paint - B to D
14-Feb-23, Level 2 Finishes
09-Feb-23, L2 Area A Finishes Gridlines 2 to 5
Finish Paint - 2 to 5
VA Livermore CBOC CUP - January 2023 Classic Schedule Layout 15-Feb-23 14:30
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 2 of 6 TASK filter: Planned Start / Finish.
Total Float Start Finish
L2-1350 T-Bar Ceiling - 2 to 5 7 2 -32 11-Aug-22 A 03-Feb-23
L2-1380 Trim HVAC - 2 to 5 12 3 -31 15-Aug-22 A 08-Feb-23
L2-1390 Install Lighting - 2 to 5 7 4 -32 15-Aug-22 A 09-Feb-23
L2-1400 Fire Sprinkler Drops - 2 to 5 5 2 -30 03-Jan-23 A 07-Feb-23
L2-1650 Firestopping Sign-Off - 2 to 5 2 1 -32 03-Jan-23 A 01-Feb-23
L2-1660 Permiter Firestop Sign-Off - 2 to 5 2 1 -32 03-Jan-23 A 01-Feb-23
L2-2410 Above Ceiling Sign-Off - 2 to 5 3 1 -32 03-Jan-23 A 01-Feb-23
L2 Area A Finishes Gridlines 5 to 8L2 Area A Finishes Gridlines 5 to 8 103 10 -25 10-Aug-22 A 14-Feb-23
L2-1790 Finish Paint - 5 to 8 7 2 -19 10-Aug-22 A 03-Feb-23
L2-1740 T-Bar Ceiling - 5 to 8 7 3 -25 15-Aug-22 A 08-Feb-23
L2-1760 Trim HVAC - 5 to 8 10 2 -23 17-Aug-22 A 10-Feb-23
L2-1770 Install Lighting - 5 to 8 7 4 -25 22-Aug-22 A 14-Feb-23
L2-1780 Fire Sprinkler Drops - 5 to 8 5 2 -23 03-Jan-23 A 10-Feb-23
L2-1720 Firestopping Sign-Off - 5 to 8 2 1 -23 03-Jan-23 A 01-Feb-23
L2-1710 Permiter Firestop Sign-Off - 5 to 8 2 1 -23 03-Jan-23 A 01-Feb-23
L2-2420 Above Ceiling Sign-Off - 5 to 8 3 1 -23 03-Jan-23 A 01-Feb-23
Level 3 FinishesLevel 3 Finishes 111 17 -13 10-Aug-22 A 24-Feb-23
L3 Area A Finishes Gridlines 2 to 5L3 Area A Finishes Gridlines 2 to 5 108 8 -19 10-Aug-22 A 21-Feb-23
L3-1360 Finish Paint - 2 to 5 7 3 -19 10-Aug-22 A 21-Feb-23
L3-1350 T-Bar Ceiling - 2 to 5 7 3 -19 18-Aug-22 A 13-Feb-23
L3-1380 Trim HVAC - 2 to 5 12 4 -18 24-Aug-22 A 17-Feb-23
L3-1390 Install Lighting - 2 to 5 7 4 -18 29-Aug-22 A 17-Feb-23
L3-1400 Fire Sprinkler Drops - 2 to 5 5 2 -19 03-Jan-23 A 15-Feb-23
L3 Area A Finishes Gridlines 5 to 8L3 Area A Finishes Gridlines 5 to 8 100 17 10-Aug-22 A 24-Feb-23
L3-1790 Finish Paint - 5 to 8 7 3 -17 10-Aug-22 A 24-Feb-23
L3-1740 T-Bar Ceiling - 5 to 8 7 3 -17 22-Aug-22 A 16-Feb-23
L3-1720 Firestopping Sign-Off - 5 to 8 2 1 -9 03-Jan-23 A 01-Feb-23
L3-1710 Permiter Firestop Sign-Off - 5 to 8 2 1 -9 03-Jan-23 A 01-Feb-23
L3-2420 Above Ceiling Sign-Off - 5 to 8 3 1 -9 03-Jan-23 A 01-Feb-23
L3-1770 Install Lighting - 5 to 8 7 4 -12 17-Jan-23 A 23-Feb-23
L3-1780 Fire Sprinkler Drops - 5 to 8 5 2 -17 24-Jan-23 A 21-Feb-23
Level 4 FinishesLevel 4 Finishes 134 29 -27 06-Jun-22 A 14-Mar-23
L4 Area A Finishes Gridlines 2 to 5L4 Area A Finishes Gridlines 2 to 5 133 14 -20 06-Jun-22 A 21-Feb-23
L4-1330 Tape Walls - 2 to 5 12 1 -21 06-Jun-22 A 01-Feb-23
L4-1340 Prime Paint - 2 to 5 5 3 -21 07-Nov-22 A 07-Feb-23
L4-1360 Finish Paint - 2 to 5 7 3 -19 14-Nov-22 A 17-Feb-23
L4-1350 T-Bar Ceiling - 2 to 5 7 3 -21 17-Nov-22 A 10-Feb-23
L4-1380 Trim HVAC - 2 to 5 12 6 -21 28-Nov-22 A 21-Feb-23
L4-1660 Permiter Firestop Sign-Off - 2 to 5 2 1 -17 03-Jan-23 A 01-Feb-23
L4-2410 Above Ceiling Sign-Off - 2 to 5 3 1 -17 03-Jan-23 A 01-Feb-23
L4-1650 Firestopping Sign-Off - 2 to 5 2 1 -21 04-Jan-23 A 02-Feb-23
L4-1390 Install Lighting - 2 to 5 7 4 -19 17-Jan-23 A 16-Feb-23
L4-1400 Fire Sprinkler Drops - 2 to 5 5 2 -19 17-Jan-23 A 14-Feb-23
L4 Area A Finishes Gridlines 5 to 8L4 Area A Finishes Gridlines 5 to 8 122 13 -27 13-Jun-22 A 14-Mar-23
L4-1700 Tape Walls - 5 to 8 12 1 -28 13-Jun-22 A 24-Feb-23
L4-1730 Prime Paint - 5 to 8 5 3 -28 07-Nov-22 A 02-Mar-23
L4-1740 T-Bar Ceiling - 5 to 8 7 4 -28 17-Nov-22 A 08-Mar-23
L4-1720 Firestopping Sign-Off - 5 to 8 2 1 -28 03-Jan-23 A 27-Feb-23
L4-1710 Permiter Firestop Sign-Off - 5 to 8 2 1 -24 03-Jan-23 A 24-Feb-23
L4-2420 Above Ceiling Sign-Off - 5 to 8 3 1 -24 03-Jan-23 A 24-Feb-23
L4-1770 Install Lighting - 5 to 8 7 4 -27 17-Jan-23 A 14-Mar-23
L4-1780 Fire Sprinkler Drops - 5 to 8 5 2 -26 17-Jan-23 A 10-Mar-23
Specialty FinishesSpecialty Finishes 85 6 1 26-Sep-22 A 10-Feb-23
CBOC-5640 Install Audiometric Rooms 20 3 -8 26-Sep-22 A 10-Feb-23
CBOC-5680 Coiling Counter Doors - Level 1 10 1 2 15-Dec-22 A 09-Feb-23
CBOC-5670 Coiling Grille - Level 1 10 1 -1 05-Jan-23 A 03-Feb-23
Jan Feb Mar Apr May Jun Jul Aug
T-Bar Ceiling - 2 to 5
Trim HVAC - 2 to 5
Install Lighting - 2 to 5
Fire Sprinkler Drops - 2 to 5
Firestopping Sign-Off - 2 to 5
Permiter Firestop Sign-Off - 2 to 5
Above Ceiling Sign-Off - 2 to 5
14-Feb-23, L2 Area A Finishes Gridlines 5 to 8
Finish Paint - 5 to 8
T-Bar Ceiling - 5 to 8
Trim HVAC - 5 to 8
Install Lighting - 5 to 8
Fire Sprinkler Drops - 5 to 8
Firestopping Sign-Off - 5 to 8
Permiter Firestop Sign-Off - 5 to 8
Above Ceiling Sign-Off - 5 to 8
24-Feb-23, Level 3 Finishes
21-Feb-23, L3 Area A Finishes Gridlines 2 to 5
Finish Paint - 2 to 5
T-Bar Ceiling - 2 to 5
Trim HVAC - 2 to 5
Install Lighting - 2 to 5
Fire Sprinkler Drops - 2 to 5
24-Feb-23, L3 Area A Finishes Gridlines 5 to 8
Finish Paint - 5 to 8
T-Bar Ceiling - 5 to 8
Firestopping Sign-Off - 5 to 8
Permiter Firestop Sign-Off - 5 to 8
Above Ceiling Sign-Off - 5 to 8
Install Lighting - 5 to 8
Fire Sprinkler Drops - 5 to 8
14-Mar-23, Level 4 Finishes
21-Feb-23, L4 Area A Finishes Gridlines 2 to 5
Tape Walls - 2 to 5
Prime Paint - 2 to 5
Finish Paint - 2 to 5
T-Bar Ceiling - 2 to 5
Trim HVAC - 2 to 5
Permiter Firestop Sign-Off - 2 to 5
Above Ceiling Sign-Off - 2 to 5
Firestopping Sign-Off - 2 to 5
Install Lighting - 2 to 5
Fire Sprinkler Drops - 2 to 5
14-Mar-23, L4 Area A Finishes Gridlines 5 to 8
Tape Walls - 5 to 8
Prime Paint - 5 to 8
T-Bar Ceiling - 5 to 8
Firestopping Sign-Off - 5 to 8
Permiter Firestop Sign-Off - 5 to 8
Above Ceiling Sign-Off - 5 to 8
Install Lighting - 5 to 8
Fire Sprinkler Drops - 5 to 8
10-Feb-23, Specialty Finishes
Install Audiometric Rooms
Coiling Counter Doors - Level 1
Coiling Grille - Level 1
VA Livermore CBOC CUP - January 2023 Classic Schedule Layout 15-Feb-23 14:30
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 3 of 6 TASK filter: Planned Start / Finish.
Total Float Start Finish
CBOC-5720 Alum Framed Entrance - Level 1 10 5 -1 17-Jan-23 A 10-Feb-23
ElevatorsElevators 104 21 -28 15-Aug-22 A 02-Mar-23
Service ElevatorService Elevator 81 3 -35 12-Sep-22 A 03-Feb-23
CBOC-8400 Install Raceways S-1 5 1 -35 12-Sep-22 A 03-Feb-23
CBOC-8390 Install Car Fronts S-1 5 2 -35 03-Jan-23 A 02-Feb-23
Passenger Elevator P-1Passenger Elevator P-1 104 3 -28 15-Aug-22 A 03-Feb-23
CBOC-8040 Install Raceways P-1 5 1 -28 15-Aug-22 A 03-Feb-23
CBOC-8030 Install Car Fronts P-1 5 2 -28 03-Jan-23 A 02-Feb-23
Passenger Elevator P-2Passenger Elevator P-2 80 5 -28 29-Aug-22 A 02-Mar-23
CBOC-8160 Install Raceways P-2 5 3 -28 29-Aug-22 A 02-Mar-23
CBOC-8150 Install Car Fronts P-2 5 2 -28 03-Jan-23 A 27-Feb-23
Central Utility PlantCentral Utility Plant 451 20 30 05-Apr-21 A 01-Mar-23
EnclosureEnclosure 10 1 49 22-Aug-22 A 01-Feb-23
CUP-580 Caged Ladder 10 1 49 22-Aug-22 A 01-Feb-23
Rough-InRough-In 230 15 -20 25-Aug-21 A 22-Feb-23
CUP-1150 HHW Piping at Boilers 21 2 -15 25-Aug-21 A 07-Feb-23
CUP-1460 Ro-In Controls 20 1 -9 30-Aug-21 A 01-Feb-23
CUP-1420 Terminate Wire at Water/Fire Pumps 4 1 -19 25-Jul-22 A 01-Feb-23
CUP-1190 Fuel Piping & Equipment 20 15 -20 31-Oct-22 A 22-Feb-23
CUP-1040 Set Boiler & Pumps 10 3 -16 28-Nov-22 A 03-Feb-23
CUP-1465 Pull / Term. Control Wire 10 3 -9 16-Dec-22 A 06-Feb-23
CUP-1410 Terminate Wire at CT Equip. 4 1 -19 21-Dec-22 A 01-Feb-23
Finishes 451 20 10 05-Apr-21 A 01-Mar-23
CUP-930 Resinous Flooring 20 10 10 05-Apr-21 A 01-Mar-23
CUP-840 Doors & Hardware 5 1 29 20-Oct-21 A 01-Feb-23
CUP-910 Terminate & Trim Controls 20 5 25 18-Jul-22 A 07-Feb-23
CUP-860 Trim Plumbing 4 2 28 03-Jan-23 A 02-Feb-23
CUP-900 Trim Fire Alarm 10 5 25 03-Jan-23 A 07-Feb-23
CUP-970 Trim Telecom 10 5 25 03-Jan-23 A 07-Feb-23
CUP-850 Trim Electrical 10 5 25 04-Jan-23 A 07-Feb-23
Mock-UpsMock-Ups 5 1 -30 29-Jul-22 A 01-Feb-23
MU270 Single Stall Toil. Rm - Mock-up Review 5 1 -30 29-Jul-22 A 01-Feb-23
CloseoutCloseout 129 77 -43 20-Jun-22 A 03-Jul-23
Warranty, Spare-Parts and As-BuiltsWarranty, Spare-Parts and As-Builts 129 77 -43 20-Jun-22 A 03-Jul-23
CL1000 Air Barrier - Warranty 20 5 -17 20-Jun-22 A 25-May-23
CL1010 Wall Panels - Warranty 20 5 -17 20-Jun-22 A 25-May-23
CL1020 Rainscreen Panel - Warranty 20 5 -17 20-Jun-22 A 25-May-23
CL1030 HPL / EGP Wall Panels - Warranty 20 5 -17 20-Jun-22 A 25-May-23
CL1040 EPDM Roofing - Warranty 20 5 -17 20-Jun-22 A 25-May-23
CL1050 Firestopping - Warranty 20 5 -15 20-Jun-22 A 23-May-23
CL1060 Wood Doors - Warranty 20 5 -15 20-Jun-22 A 23-May-23
CL1070 Coiling Counter Doors - Warranty 20 5 -15 20-Jun-22 A 23-May-23
CL1080 Vert. Folding Wall - Warranty 20 5 16 20-Jun-22 A 10-Apr-23
CL1090 Alum. Entry & Storefronts - Warranty 20 5 -27 20-Jun-22 A 09-Jun-23
CL1100 Curtain Wall - Warranty 20 5 -27 20-Jun-22 A 09-Jun-23
CL1110 Door Hardware - Warranty 20 5 -15 20-Jun-22 A 23-May-23
CL1130 Glazing - Warranty 20 5 -27 20-Jun-22 A 09-Jun-23
CL1120 Low-E Pwr Operators - Warranty 20 5 -15 20-Jun-22 A 23-May-23
CL1140 Ceramic / Porcelain Tile - Warranty 20 5 -15 20-Jun-22 A 23-May-23
CL1150 Wood Clg System - Warranty 20 5 -15 20-Jun-22 A 23-May-23
CL1160 Static Control Flrng - Warranty 20 5 -15 20-Jun-22 A 23-May-23
CL1170 Resilient Flooring - Warranty 20 5 -15 20-Jun-22 A 23-May-23
CL1180 Athletic Flrng - Warranty 20 5 -15 20-Jun-22 A 23-May-23
CL1190 Carpet Tile - Warranty 20 5 -15 20-Jun-22 A 23-May-23
CL1200 Signage - Warranty 20 5 -15 20-Jun-22 A 23-May-23
Jan Feb Mar Apr May Jun Jul Aug
Alum Framed Entrance - Level 1
02-Mar-23, Elevators
03-Feb-23, Service Elevator
Install Raceways S-1
Install Car Fronts S-1
03-Feb-23, Passenger Elevator P-1
Install Raceways P-1
Install Car Fronts P-1
02-Mar-23, Passenger Elevator P-2
Install Raceways P-2
Install Car Fronts P-2
01-Mar-23, Central Utility Plant
01-Feb-23, Enclosure
Caged Ladder
22-Feb-23, Rough-In
HHW Piping at Boilers
Ro-In Controls
Terminate Wire at Water/Fire Pumps
Fuel Piping & Equipment
Set Boiler & Pumps
Pull / Term. Control Wire
Terminate Wire at CT Equip.
01-Mar-23, Finishes
Resinous Flooring
Doors & Hardware
Terminate & Trim Controls
Trim Plumbing
Trim Fire Alarm
Trim Telecom
Trim Electrical
01-Feb-23, Mock-Ups
Single Stall Toil. Rm - Mock-up Review
03-Jul-23, Closeout
03-Jul-23, Warranty, Spare-Parts and As-Builts
Air Barrier - Warranty
Wall Panels - Warranty
Rainscreen Panel - Warranty
HPL / EGP Wall Panels - Warranty
EPDM Roofing - Warranty
Firestopping - Warranty
Wood Doors - Warranty
Coiling Counter Doors - Warranty
Vert. Folding Wall - Warranty
Alum. Entry & Storefronts - Warranty
Curtain Wall - Warranty
Door Hardware - Warranty
Glazing - Warranty
Low-E Pwr Operators - Warranty
Ceramic / Porcelain Tile - Warranty
Wood Clg System - Warranty
Static Control Flrng - Warranty
Resilient Flooring - Warranty
Athletic Flrng - Warranty
Carpet Tile - Warranty
Signage - Warranty
VA Livermore CBOC CUP - January 2023 Classic Schedule Layout 15-Feb-23 14:30
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 4 of 6 TASK filter: Planned Start / Finish.
Total Float Start Finish
CL1210 Cubicle Curtain - Warranty 20 5 -15 20-Jun-22 A 23-May-23
CL1220 Wire Mesh Partitions - Warranty 20 5 -15 20-Jun-22 A 23-May-23
CL1230 Wall & Door Protection - Warranty 20 5 -15 20-Jun-22 A 23-May-23
CL1240 Bullet Fiberglass Sht - Warranty 20 5 -15 20-Jun-22 A 23-May-23
CL1250 Toilet Access. - Warranty 20 5 -15 20-Jun-22 A 23-May-23
CL1260 Dock Levelers - Warranty 20 8 -16 20-Jun-22 A 24-May-23
CL1270 Window Tie Backs - Warranty 20 5 -27 20-Jun-22 A 09-Jun-23
CL1280 Food Service Equip - Warranty 20 5 -15 20-Jun-22 A 23-May-23
CL1290 Wood Casework - Warranty 20 5 -15 20-Jun-22 A 23-May-23
CL1300 Solid Surfaces - Warranty 20 5 -15 20-Jun-22 A 23-May-23
CL1310 Elevators - Warranty 20 5 -11 20-Jun-22 A 17-May-23
CL1320 HVAC Controls - Warranty 20 5 -33 20-Jun-22 A 19-Jun-23
CL1330 Boilers - Warranty 20 5 -18 20-Jun-22 A 26-May-23
CL1340 Chillers - Warranty 20 5 19 20-Jun-22 A 05-Apr-23
CL1350 FCU's - Warranty 20 5 -15 20-Jun-22 A 23-May-23
CL1360 Elec. Humidifiers - Warranty 20 5 -15 20-Jun-22 A 23-May-23
CL1035 Joint Sealant - Warranty 20 5 -27 20-Jun-22 A 09-Jun-23
CL1265 Detention Equip - Waranty 20 5 -15 20-Jun-22 A 23-May-23
CL1370 Utility Metering System - Warranty 20 5 -33 20-Jun-22 A 19-Jun-23
CL1510 Fire Sprinklers - As-Builts 20 5 -15 20-Jun-22 A 23-May-23
CL1520 Fire Pumps - As-Builts 20 5 19 20-Jun-22 A 05-Apr-23
CL1530 Plumbing Motors - Certs 20 5 19 20-Jun-22 A 05-Apr-23
CL1540 Meters & Guages - As-Builts 20 5 -15 20-Jun-22 A 23-May-23
CL1550 Plumbing Insulation - As-Builts 20 5 -15 20-Jun-22 A 23-May-23
CL1560 Water Distribution - As-Builts 20 5 -15 20-Jun-22 A 23-May-23
CL1570 DW Pumps - As-Builts 20 5 -15 20-Jun-22 A 23-May-23
CL1580 Sanitary & Vent Piping - As-Builts 20 5 -15 20-Jun-22 A 23-May-23
CL1590 SS Pumps - As-Builts 20 10 -20 20-Jun-22 A 31-May-23
CL1600 Facility Storm Drain - As-Builts 20 5 -15 20-Jun-22 A 23-May-23
CL1610 Water Softener - As-Builts 20 5 -15 20-Jun-22 A 23-May-23
CL1620 DW Water Heaters - As-Builts 20 5 -15 20-Jun-22 A 23-May-23
CL1500 Dental Air Piping - As-Builts 20 5 -15 20-Jun-22 A 23-May-23
CL1630 Vacuum System - As-Builts 20 5 -15 20-Jun-22 A 23-May-23
CL1640 HVAC Controls - As-Builts 20 5 -15 20-Jun-22 A 23-May-23
CL1650 Cooling Towers - Certs 20 10 14 20-Jun-22 A 12-Apr-23
CL1660 Utility Metering System - As-Builts 30 15 -43 20-Jun-22 A 03-Jul-23
CL1670 Transformers - Spare Parts 30 15 9 20-Jun-22 A 19-Apr-23
CL1680 Switches & C.B.'s - Spare Parts 30 15 -15 20-Jun-22 A 23-May-23
CL1690 Generators - Spare Parts 30 15 9 20-Jun-22 A 19-Apr-23
CL1525 Plumbing - As-Builts 20 5 -15 20-Jun-22 A 23-May-23
CL1700 Comm. System - Warranty 30 15 -15 20-Jun-22 A 23-May-23
CL1710 PA System - Warranty 30 15 -15 20-Jun-22 A 23-May-23
CL1720 Nurse Call System - Warranty 30 15 -15 20-Jun-22 A 23-May-23
CL1730 Radio Equip - Warranty 30 15 -15 20-Jun-22 A 23-May-23
CL1740 Comm. System - As-Builts 30 15 -15 20-Jun-22 A 23-May-23
CL1750 PA System - As-Builts 30 15 -15 20-Jun-22 A 23-May-23
CL1760 Nurse Call System - As-Builts 30 15 -15 20-Jun-22 A 23-May-23
CL1770 Radio Equip - As-Builts 30 15 -15 20-Jun-22 A 23-May-23
CL1780 Security System - Warranty 30 15 -15 20-Jun-22 A 23-May-23
CL1790 Fire Alarm System - Warranty 30 15 -15 20-Jun-22 A 23-May-23
CL1860 Sanitary Sewer Utilities - Warranty 20 8 -16 20-Jun-22 A 24-May-23
CL1870 Storm Sewer Utilities - Warranty 20 8 -16 20-Jun-22 A 24-May-23
CL1880 Site Gas Utilities - Warranty 20 8 -16 20-Jun-22 A 24-May-23
CL1800 Porous Flexible Paving - Warranty 20 8 -16 20-Jun-22 A 24-May-23
CL1810 Gate Operators - Warranty 20 8 -16 20-Jun-22 A 24-May-23
CL1820 Steel Fence & Gates - Warranty 20 8 -16 20-Jun-22 A 24-May-23
Jan Feb Mar Apr May Jun Jul Aug
Cubicle Curtain - Warranty
Wire Mesh Partitions - Warranty
Wall & Door Protection - Warranty
Bullet Fiberglass Sht - Warranty
Toilet Access. - Warranty
Dock Levelers - Warranty
Window Tie Backs - Warranty
Food Service Equip - Warranty
Wood Casework - Warranty
Solid Surfaces - Warranty
Elevators - Warranty
HVAC Controls - Warranty
Boilers - Warranty
Chillers - Warranty
FCU's - Warranty
Elec. Humidifiers - Warranty
Joint Sealant - Warranty
Detention Equip - Waranty
Utility Metering System - Warranty
Fire Sprinklers - As-Builts
Fire Pumps - As-Builts
Plumbing Motors - Certs
Meters & Guages - As-Builts
Plumbing Insulation - As-Builts
Water Distribution - As-Builts
DW Pumps - As-Builts
Sanitary & Vent Piping - As-Builts
SS Pumps - As-Builts
Facility Storm Drain - As-Builts
Water Softener - As-Builts
DW Water Heaters - As-Builts
Dental Air Piping - As-Builts
Vacuum System - As-Builts
HVAC Controls - As-Builts
Cooling Towers - Certs
Utility Metering System - As-Builts
Transformers - Spare Parts
Switches & C.B.'s - Spare Parts
Generators - Spare Parts
Plumbing - As-Builts
Comm. System - Warranty
PA System - Warranty
Nurse Call System - Warranty
Radio Equip - Warranty
Comm. System - As-Builts
PA System - As-Builts
Nurse Call System - As-Builts
Radio Equip - As-Builts
Security System - Warranty
Fire Alarm System - Warranty
Sanitary Sewer Utilities - Warranty
Storm Sewer Utilities - Warranty
Site Gas Utilities - Warranty
Porous Flexible Paving - Warranty
Gate Operators - Warranty
Steel Fence & Gates - Warranty
VA Livermore CBOC CUP - January 2023 Classic Schedule Layout 15-Feb-23 14:30
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 5 of 6 TASK filter: Planned Start / Finish.
Total Float Start Finish
CL1830 Loop Vehicle Detector - Warranty 20 8 -16 20-Jun-22 A 24-May-23
CL1840 Planting - Warranty 20 8 -16 20-Jun-22 A 24-May-23
CL1850 Hydroseeding - Warranty 20 8 -16 20-Jun-22 A 24-May-23
CL1890 Solar PV System - Warranty 30 15 19 20-Jun-22 A 05-Apr-23
SubmittalsSubmittals 565 40 13 01-Sep-20 A 29-Mar-23
SubmitSubmit 346 10 -25 01-Sep-20 A 14-Feb-23
S230811 Demo & Test Boiler - Submit 159 1 -16 01-Sep-20 A 01-Feb-23
S251010 Utility Metering System - Submit 109 10 -39 01-Sep-21 A 14-Feb-23
ReviewReview 30 8 -42 27-May-21 A 08-Feb-23
R226119.74 Dental Air Equip - Review 30 8 -42 27-May-21 A 08-Feb-23
ProcureProcure 205 40 13 01-Feb-22 A 29-Mar-23
P281300 Access Control System - Procure 50 20 -19 01-Feb-22 A 01-Mar-23
P281600 Intrusion Detection - Procure 50 20 -19 01-Feb-22 A 01-Mar-23
P226119.74 Dental Air Equip - Procure 40 10 -28 28-Feb-22 A 23-Feb-23
P260573 Arc Flash Labels - Procure 40 15 -33 01-Mar-22 A 22-Feb-23
P329300 Site Furnishings - Procure 40 10 -33 01-Mar-22 A 14-Feb-23
P097761 FRP Panels - Procure 40 15 -25 07-Mar-22 A 22-Feb-23
P074113 Metal Roofing - Procure 40 25 -21 28-Mar-22 A 08-Mar-23
P083506 Operable Wall - Procure 51 15 8 31-Mar-22 A 22-Feb-23
P084229 Auto Sliding Doors - Procure 75 20 -13 01-Jun-22 A 01-Mar-23
P101400 Signage - Procure 40 10 1 01-Jun-22 A 14-Feb-23
P102123 Cubicle Curtain - Procure 40 10 0 01-Jun-22 A 14-Feb-23
P102213 Wire Mesh Partitions - Procure 40 20 -11 01-Jun-22 A 01-Mar-23
P102600 Wall & Door Protection - Procure 40 20 -9 01-Jun-22 A 01-Mar-23
P230593 HVAC TAB - Procure 40 20 7 01-Jun-22 A 01-Mar-23
P260913 Power Monitoring System - Procure 40 40 13 01-Jun-22 A 29-Mar-23
P274131 Antenna TV System - Procure 40 20 14 01-Jun-22 A 01-Mar-23
P275116 PA & Mass Notification - Procure 40 20 -26 01-Jun-22 A 01-Mar-23
P275223 Nurse Call System - Procure 40 20 -26 01-Jun-22 A 01-Mar-23
P275319 Radio Eqiup System - Procure 50 20 12 01-Jun-22 A 01-Mar-23
P282800 Video Surveillance - Procure 50 20 -21 01-Jun-22 A 01-Mar-23
P282600 Personal Protection System - Procure 50 20 -19 01-Jun-22 A 01-Mar-23
P283100 Fire Alarm - Procure 40 20 -31 01-Jun-22 A 01-Mar-23
P321723 Pavement Markings - Procure 40 5 9 01-Jun-22 A 07-Feb-23
P329000 Planting - Procure 60 20 -24 01-Jun-22 A 14-Mar-23
P329010 Agg. Paving - Procure 40 10 -15 01-Jun-22 A 14-Feb-23
P329219 Hydroseeding - Procure 40 10 -10 01-Jun-22 A 14-Feb-23
P329223 Sodding - Procure 40 10 9 01-Jun-22 A 14-Feb-23
P330800 Cx Site Utilities - Procure 40 15 2 01-Jun-22 A 22-Feb-23
P088000-2 Interior Glazing - Procure 20 10 1 01-Jun-22 A 14-Feb-23
P226219.74 Dental Vacuum Sys - Procure 40 39 -6 30-Sep-22 A 28-Mar-23
Jan Feb Mar Apr May Jun Jul Aug
Loop Vehicle Detector - Warranty
Planting - Warranty
Hydroseeding - Warranty
Solar PV System - Warranty
29-Mar-23, Submittals
14-Feb-23, Submit
Demo & Test Boiler - Submit
Utility Metering System - Submit
08-Feb-23, Review
Dental Air Equip - Review
29-Mar-23, Procure
Access Control System - Procure
Intrusion Detection - Procure
Dental Air Equip - Procure
Arc Flash Labels - Procure
Site Furnishings - Procure
FRP Panels - Procure
Metal Roofing - Procure
Operable Wall - Procure
Auto Sliding Doors - Procure
Signage - Procure
Cubicle Curtain - Procure
Wire Mesh Partitions - Procure
Wall & Door Protection - Procure
HVAC TAB - Procure
Power Monitoring System - Procure
Antenna TV System - Procure
PA & Mass Notification - Procure
Nurse Call System - Procure
Radio Eqiup System - Procure
Video Surveillance - Procure
Personal Protection System - Procure
Fire Alarm - Procure
Pavement Markings - Procure
Planting - Procure
Agg. Paving - Procure
Hydroseeding - Procure
Sodding - Procure
Cx Site Utilities - Procure
Interior Glazing - Procure
Dental Vacuum Sys - Procure
VA Livermore CBOC CUP - January 2023 Classic Schedule Layout 15-Feb-23 14:30
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 6 of 6 TASK filter: Planned Start / Finish.