The file is a Base Offer Price Breakdown spreadsheet for the VA project "Renovate Lake Nona Building 1 Women's Health" (Solicitation Number: 36C24825R0058). The template is designed for contractors to itemize labor and material costs across 34 construction divisions, including general requirements, earthwork, electrical, HVAC, plumbing, and other building systems. The spreadsheet allows for calculating overhead, profit, and bonding percentages, with spaces to input specific costs for each division.

The associated federal contract opportunity involves renovating approximately 8,272 square feet of administrative space in Building 1, Level 4, at the Orlando Veterans Affairs Healthcare System (OVAHCS). The project requires professional bid-build construction services, encompassing architectural, structural, mechanical, plumbing, electrical, and low-voltage work. The renovation will be completed at the Lake Nona facility located at 13800 Veterans Way, Orlando, FL 32827, and will specifically focus on creating a Women's Health Clinic space.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Base Offer Base Offer Cost Breakdown

Project Number:

Edward L Roy: VA assigned project #

Date:
Project Title
Edward L Roy: VA assigned Project TitleProject Location
Offeror Name
Offeror Street
Offeror CityStateZip

Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division

Material Cost
Edward L Roy: Enter all Material Costs by DivisionTotal Cost

Edward L Roy: This Column is the sum of the Division's Labor and Material Costs

Division 1General Requirements$ - 0$ - 0$ - 0
Division 2Existing Conditions- 0- 0- 0
Division 3Concrete- 0- 0- 0
Division 4Masonry- 0- 0- 0
Division 5Metals- 0- 0- 0
Division 6Wood and Plastic- 0- 0- 0
Division 7Thermal & Moisture Protect- 0- 0- 0
Division 8Doors and Windows- 0- 0- 0
Division 9Finishes- 0- 0- 0
Division 10Specialties- 0- 0- 0
Division 11Equipment- 0- 0- 0
Division 12Furnishings- 0- 0- 0
Division 13Special Construction- 0- 0- 0
Division 14Conveying Equipment- 0- 0- 0
Division 21Fire Suppression- 0- 0- 0
Division 22Plumbing- 0- 0- 0
Division 23HVAC- 0- 0- 0
Division 26Electrical- 0- 0- 0
Division 27Communications- 0- 0- 0
Division 28Electronic Safety & Security- 0- 0- 0
Division 31Earthwork- 0- 0- 0
Division 32Exterior Improvements- 0- 0- 0
Division 33Utilities- 0- 0- 0
Division 34Transportation Subtotal- 0- 0- 0
Division Subtotals :$ - 0$ - 0$ - 0

Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).

Edward L Roy: Date Offer Prepared/Submitted

- 0
Profit %0.00%
Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38).- 0
Bond %0.00%

Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).

Edward L Roy: Enter all Labor Costs by Division

- 0
Overhead/Profit Subtotals :$ - 0

Edward L Roy: Sum of Overhead, Profit and Bond %.

Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Base Offer Cost $ - 0 $ - 0 $ - 0

Offerors shall provide additional price breakdown to avoiding lump sum, etc. This price offer breakdown is the overall base offer price for Government price analysis

File details come from the government source that posted it. Updated .