This document provides details for a federal construction contract opportunity with the Department of Veterans Affairs. The solicitation will correct water infiltration issues and repair water damage at connecting corridors and modular buildings 1, 3, 60, and 54 at the Veterans Affairs North Texas Health Care System in Dallas, Texas. The design-build project scope includes investigating infiltration points, developing a phasing plan, repairing or adding gutters and downspouts, testing and cleaning drains, sealing wall penetrations, and applying waterproofing materials. The contractor must provide design drawings at 65%, 95%, and 100% completion for a two-week government review period prior to construction. The estimated value is between $1,000,000 and $2,000,000. The solicitation will be issued on March 20, 2020 as a total SDVOSB set-aside with a 270-day period of performance.

View the file

Other files

File Type Posted
S02 - Attachment 12 - Section 01 42 19 Reference Standards SCE 11-19-2018.docx DOCX document
S02 - Attachment 5 - Construction Wage Determinations (Dallas County).pdf PDF
S02 - Attachment 6 - Labor Standard Wage Determination (Dallas County).pdf PDF
S02 - Attachment 13 - Section 01 33 23 Shop Drawings SCE 11-19-2018.docx DOCX document
S02 - Attachment 8 - Past Performance Questionnaire.docx DOCX document
S02 - Attachment 2 - Statement of Work - Water Infiltration Bldgs 1_3 and 60 - (5-13-2020 YMR) - Final.pdf PDF
36E77620R0025.docx DOCX document
S02 - Attachment 9 - Release of Claims.docx DOCX document
S02 - Attachment 11 - 01 32 16 16 - Project Schedule.docx DOCX document
S02 - Attachment 1 - Specification 00 11 21 RFP to DB Spec - Water Filtration Project (5-13-2020 YMR).doc DOC document
S02 - Attachment 10 -VHA Master Specifications.docx DOCX document
S02 - Attachment 16 - Quality Control Requirements Plan SCE 11-19-2018.docx DOCX document
S02 - Attachment 4 - Water Intrusion and Mold Management (WIMM).pdf PDF
S02 - Attachment 14 - Section 01 35 26 Safety Requirements SCE 11-19-2018.docx DOCX document
S02 - Attachment 7 - Contractor Safety and Environmental Record Evaluation Form.docx DOCX document
S02 - Attachment 3 - Mold and Moisture Control Program.doc DOC document
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01-11

SECTION 01 57 19

TEMPORARY ENVIRONMENTAL CONTROLS

PART 1 - GENERAL

1.1 DESCRIPTION

A.

This section specifies the control of environmental pollution and damage that the Contractor must consider for air, water, and land resources. It includes management of visual aesthetics, noise, solid waste, radiant energy, and radioactive materials, as well as other pollutants and resources encountered or generated by the Contractor. The Contractor is obligated to consider specified control measures with the costs included within the various contract items of work.

B.

Environmental pollution and damage is defined as the presence of chemical, physical, or biological elements or agents which:

1.

Adversely effect human health or welfare, 2.

Unfavorably alter ecological balances of importance to human life, 3.

Effect other species of importance to humankind, or;

4.

Degrade the utility of the environment for aesthetic, cultural, and historical purposes.

C.

Definitions of Pollutants:

1.

Chemical Waste: Petroleum products, bituminous materials, salts, acids, alkalis, herbicides, pesticides, organic chemicals, and inorganic wastes.

2.

Debris: Combustible and noncombustible wastes, such as leaves, tree trimmings, ashes, and waste materials resulting from construction or maintenance and repair work.

3.

Sediment: Soil and other debris that has been eroded and transported by runoff water.

4.

Solid Waste: Rubbish, debris, garbage, and other discarded solid materials resulting from industrial, commercial, and agricultural operations and from community activities.

5.

Surface Discharge: The term "Surface Discharge" implies that the water is discharged with possible sheeting action and subsequent soil erosion may occur. Waters that are surface discharged may terminate in drainage ditches, storm sewers, creeks, and/or "water of the United States" and would require a permit to discharge water from the governing agency.

6.

Rubbish: Combustible and noncombustible wastes such as paper, boxes, glass and crockery, metal and lumber scrap, tin cans, and bones.

7.

Sanitary Wastes:

a.

Sewage: Domestic sanitary sewage and human and animal waste.

b.

Garbage: Refuse and scraps resulting from preparation, cooking, dispensing, and consumption of food.

1.2 QUALITY CONTROL

A.

Establish and maintain quality control for the environmental protection of all items set forth herein.

B.

Record on daily reports any problems in complying with laws, regulations, and ordinances. Note any corrective action taken.

1.3 references

A.

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

B.

U.S. National Archives and Records Administration (NARA):

33 CFR 328

Definitions

1.4 SUBMITTALS

A.

In accordance with Section, 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES, furnish the following:

1.

Environmental Protection Plan: After the contract is awarded and prior to the commencement of the work, the Contractor shall meet with the COR to discuss the proposed Environmental Protection Plan and to develop mutual understanding relative to details of environmental protection. Not more than 20 days after the meeting, the Contractor shall prepare and submit to the COR and Contracting Officer for approval, a written and/or graphic Environmental Protection Plan including, but not limited to, the following:

a.

Name(s) of person(s) within the Contractor's organization who is (are) responsible for ensuring adherence to the Environmental Protection Plan.

b.

Name(s) and qualifications of person(s) responsible for manifesting hazardous waste to be removed from the site.

c.

Name(s) and qualifications of person(s) responsible for training the Contractor's environmental protection personnel.

d.

Description of the Contractor's environmental protection personnel training program.

e.

A list of Federal, State, and local laws, regulations, and permits concerning environmental protection, pollution control, noise control and abatement that are applicable to the Contractor's proposed operations and the requirements imposed by those laws, regulations, and permits.

f.

Methods for protection of features to be preserved within authorized work areas including trees, shrubs, vines, grasses, ground cover, landscape features, air and water quality, fish and wildlife, soil, historical, and archeological and cultural resources.

g.

Procedures to provide the environmental protection that comply with the applicable laws and regulations. Describe the procedures to correct pollution of the environment due to accident, natural causes, or failure to follow the procedures as described in the Environmental Protection Plan.

h.

Permits, licenses, and the location of the solid waste disposal area.

B.

Approval of the Contractor's Environmental Protection Plan will not relieve the Contractor of responsibility for adequate and continued control of pollutants and other environmental protection measures.

1.5 PROTECTION OF ENVIRONMENTAL RESOURCES

A.

Protect environmental resources within the project boundaries and those affected outside the limits of permanent work during the entire period of this contract. Confine activities to areas defined by the specifications and drawings.

B.

Reduction of Noise: Minimize noise using every action possible. Perform noise-producing work in less sensitive hours of the day or week as directed by the Resident Engineer. Maintain noise-produced work at or below the decibel levels and within the time periods specified.

1.

Perform construction activities involving repetitive, high-level impact noise only between 8:00 a.m. and 6:00 p.m unless otherwise permitted by local ordinance or the Resident Engineer. Repetitive impact noise on the property shall not exceed the following dB limitations:

Time Duration of Impact Noise
Sound Level in dB
More than 12 minutes in any hour
70
Less than 30 seconds of any hour
85
Less than three minutes of any hour
80
Less than 12 minutes of any hour
75

C.

Restoration of Damaged Property: If any direct or indirect damage is done to public or private property resulting from any act, omission, neglect, or misconduct, the Contractor shall restore the damaged property to a condition equal to that existing before the damage at no additional cost to the Government. Repair, rebuild, or restore property as directed or make good such damage in an acceptable manner.

D.

Final Clean‑up: On completion of project and after removal of all debris, rubbish, and temporary construction, Contractor shall leave the construction area in a clean condition satisfactory to the Resident Engineer. Cleaning shall include off the station disposal of all items and materials not required to be salvaged, as well as all debris and rubbish resulting from demolition and new work operations.