S02_Attachment-1_SOW.pdf
PDF 293 KB Posted
- Solicitation number
- 36C78621Q0146
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C78621Q0146 0002.docx | DOCX document | |
| 36C78621Q0146 0001.docx | DOCX document | |
| S02_Attachment-3_WD_HEAVY_El Paso_TX20210035.pdf | ||
| S02_Attachment-2_Drawings and Specs.pdf | ||
| S02_Attachment-4_Business Management-Past Performance Questionnaire.pdf | ||
| 36C78621Q0146.docx | DOCX document | |
| S02_Attachment-5_Contractor Cost Estimate Worksheet_2-10-20.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
REFURBISH IRRIGATION WELL
FORT BLISS NATIONAL CEMETERY
5200 FRED WILSON BLVD, EL PASO, TX 79916
A. The Contractor: Shall furnish all labor, material, equipment, and supervision necessary to pull and reinstall the irrigation submersible pump; video record the well casing; and refurbish the well casing at Fort Bliss National Cemetery in accordance with this Statement of Work, and per applicable standards and requirements.
B. System Description and Background:
1. See the “Existing Well Information” documentation for the original as-built information for the well, submersible pump and pump motor, and pitless adapter.
2. Irrigation Well: (refurbished in 2002)
a. The well was drilled approximately in 1995. The attached “Existing Well Information” document provides the construction cross section to include bore hole, casing, and liner, and column pipe dimensions. Total Depth (TD) is approximately 700 feet (per as-built information). The casing alternates between perforated screens and blank liners (at approximate intervals shown on the attached). The well is gravel packed the entire length from pump setting to TD.
b. The well was refurbished in 2002 with a new well casing and well screens along with the installation of a new submersible pump and pump motor including a new motor control panel.
c. Column pipe: 3-inch, SCH40 galvanized steel pipe. Estimated length: 483 feet.
d. Pitless Adapter: Baker Monitor, Model No. 3PS67NBWE03T3
3. Irrigation Pump and Motor: (replaced in 2019)
a. Pump: Goulds® Water Technology, Submersible Vertical Turbine, Model 5CLC, 14 Stages.
b. Pump Motor: Franklin® Model S55972, 25 HP, 3600 RPM, 460V, 3-phase, 60-cycle, Inverter Duty, Submersible Motor compatible with the existing motor control system.
c. Pump and Pump Motor Capacity: 120 gallons per minute (gpm) at 536.8 feet of total dynamic head (TDH).
d. The setting depth is approximately 400 feet to the top of the pump set.
C. Time Constraints on Performance of Work:
1. The Contractor is restricted to a maximum of five (5) continuous working days to pull the pump, refurbish the well, reinstall the submersible pump, and reassemble the pitless adaptor. This is required to minimize the stress on and damage to the turfgrass and landscaping. The work involves shutting down the entire active irrigation system which maintains 1.7 acres of turfgrass and 70 acres with landscaped areas, planting beds, and trees.
2. The Contractor shall have equipment, materials, and supplies needed to complete the work on-site and staged prior to starting work as described herein. The COR shall verify the Contractor is ready to perform the work and has coordinated the irrigation requirements as designated below.
3. Turfgrass areas are to be thoroughly irrigated the day prior to starting the well refurbishment under the direction of the COR and cemetery Gardener. Landscaped areas, planting beds and trees are to be irrigated the day before or as close to the day the well work begins as time allows under the direction of the COR and the cemetery Gardener.
4. If the Contractor fails to complete the work within the five (5) days as specified, the Contractor, at their own expense, shall provide the means to water the turfgrass, landscaped areas, planter beds, and trees until the work has been completed.
D. The Work: The refurbishment shall generally include three items: 1) Mechanically scrubbing the well casing to remove incrustation and air lifting of debris; 2) Controlled shape charge blasting; and 3) Acid treatment reconditioning. The Work shall include, but shall not be limited to the following (generally in the order indicated):
1. The Competent Professional identified in the Contractor’s accepted proposal must be on site during all reconditioning work and must directly supervise all reconditioning work.
2. The Contractor shall disassemble the pitless adaptor and discharge head, and pull the riser and pump. Hoisting and rigging access is open (i.e. not enclosed) in the walled-off well yard located in the southwest corner of the cemetery, with room for staging removed sections. The Contractor is responsible for inventorying all items removed from the well and securing anything left overnight. Inspect all equipment for corrosion and notify the COR of any discovered issues.
3. Remove the existing submersible, vertical turbine pump and pump motor, drop pipe, and electrical cable from the well using a pump service rig and elevators of adequate capacity to safely handle the weight.
4. The drop pipe shall be unscrewed or torch cut at the Contractor’s discretion. Demolished drop pipe shall be disposed of off-site the same day that it is removed from the well.
5. Perform an initial video and camera survey to verify existing conditions: Verify the condition of the well casing/screen and percent blockage of the screened interval. Verify the static water depth. Provide two copies of the DVD with video and pictures: one to the COR and one to the District Engineer in Denver, CO.
6. Refurbishment Item #1: Initial Incrustation Removal
a. Remove the encrustation by mechanically scrubbing the length of well casing from pump setting height to TD using steel wire brushes.
b. Remove loosened material by air lift jetting, bailing, or other means. Collect and dispose of debris off site, and control discharge of wastewater to prevent site erosion.
c. Perform video and camera survey (provide copy to COR); determine locations of screened sections of well casing and make recommendations on follow-on rehabilitation method. There are an estimated 200 feet of screened sections.
Contractor shall notify the COR immediately and prior to blasting if the quantity of screened sections are found above this amount.
7. Refurbishment Item #2: Impulse Generation Rehabilitation
a. Include all labor, material, and equipment associated with reconditioning the well screen and aquifer using an approved impulse generation method such as controlled shape charge blasting using the SONAR-JET® system or other approved method to increase the capacity of the well as close to its original condition as possible.
8. Refurbishment Item #3: Acid Treatment Rehabilitation and Reconditioning
a. Include one acid treatment utilizing 2,000 gallons of 20% hydrochloric acid solution.
Introduce the mixed solution into the well through a double disk surge block in discrete intervals. Each section of the screen will be individually cleaned and redeveloped utilizing the disk surge block. The surging and swabbing operations will continue for a minimum 4 - 5 hour period. The solution will then be allowed to stand in the well overnight. The next day, the swabbing, pumping and re-injection operations will recommence for another 4 hour period. During this treatment phase the pH of the chemical solution will be monitored.
b. The pump off shall continue for 2 hours at a maximum rate, to thoroughly remove all loosened mineral deposits from the screen and surrounding gravel pack. Neutralize pumped solution and pump to natural drainage in an approved manner to avoid erosion.
c. The SDS for any acid(s) or chemicals shall be submitted to the COR for approval.
Chemicals shall be added to the well by a Competent Professional. The Contractor shall abide by the manufacturer’s recommended concentration, contact time, and shall monitor pH levels. If the pH rises above 4/5, the procedure will stop and the spent chemical will be neutralized and pumped to waste.
d. The well shall be developed to correct damage from the reconditioning process, remove fines from the aquifer, and increase local permeability until an insignificant amount of sand can be pumped.
9. Perform final video and camera survey (provide copy to COR) to determine effectiveness of rehabilitation.
10. Existing well equipment re-installation: The existing submersible pump and pump motor, drop pipe, and submersible pump electrical cable shall be reinstalled in the well using a pump service rig and elevators of adequate capacity to safely handle the weight.
Installation shall include all of the above listed major components and other associated components including but not limited to:
a. Mechanical and electrical connection of the pump, pump motor, drop pipe, and electrical cable assembly.
b. Hoisting/rigging for the installation of the pump, pump motor, and associated piping.
c. All labor, material, associated components, and equipment associated with testing the completed assembly.
11. Testing: After completion of all equipment, components, and material installations, perform a full system functional test and demonstrate to the COR the full operation/functionality of the irrigation pump, pump motor, and the irrigation pump motor control unit has been fully coordinated with the existing irrigation control system.
Verify no leaks and all other well components are functioning correctly.
E. General Conditions:
1. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
2. Thoroughly clean up the work area at the end of each day’s work, and at completion of the project. Leave premises clean and free of waste, scrap, used equipment, or other material intentionally or incidentally delivered to the site by Contractor or Contractor’s personnel. Haul away & dump debris and waste to an approved disposal site.
3. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site not to be removed and do not unreasonably interfere with the work required under this contract. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
4. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
5. All utilities required for the continuous operation of all existing facilities shall be maintained in service at all times except when disruptions are needed. The Contractor shall inform the Cemetery Director and the Contracting Officer (CO) in writing for such disruptions and obtain approval from the CO in writing at least 2 weeks prior to such need. When option exists, implement options to minimize interruption of services to the facilities.
6. The Contractor shall coordinate with the Cemetery Director for parking, material storage, temporary portable restroom facilities, and any other needs for the work. Public access to the National Cemetery shall not be impaired.
7. The Contractor shall assume sole responsibility for safety of all persons on or about the construction site, in accordance with applicable laws and codes. Guard all materials in accordance with the safety provisions according to OSHA and Associated General Contractors of America (AGC).
F. Standards of Employee Conduct:
1. The National Cemetery Administration honors veterans with a final resting place and lasting memorials that commemorate their service to our Nation. National Cemeteries are national shrines. The standards of work, appearance, and procedures performed by the contractor at this cemetery shall reflect this nation’s concern for those interred there. Due to the sensitive mission of the cemetery, contractor personnel must exercise and exhibit absolute decorum, composure, and stability at all times.
2. Contractor personnel shall be required to adhere to the following standards of dress and conduct, as briefly mentioned here, while performing work in the National Cemetery.
These standards and regulations are enforceable under Title 38, U.S.C., Part I, Chapter 9, Section 5901.
3. Clothing shall be presentable and suitable to the work while maintaining proper appearance and decorum indicative for a National Shrine. Uniform shirts and hats are preferred. Clothing shall be clean and cleanliness and personal hygiene are imperative. T-shirts and/or tank tops as outer garments are prohibited. Protective/safety clothing and shoes shall meet or exceed OSHA and state requirements.
4. Behavior and language must be appropriate, reverent, and respectful at all times.
5. Eating and drinking (except water) is prohibited in the work areas and within sight of a committal shelter during a service.
6. Use of intoxicating beverages, any tobacco products, and illegal drugs on the Cemetery premises is strictly prohibited.
7. Contractor personnel shall not lean, sit, or stand on or against headstones or monuments.
No tools, equipment or other items will be placed or leaned on headstones or monuments.
8. The Contractor shall be responsible for maintaining satisfactory standards of personnel conduct and work performance and shall administer disciplinary action as required. The Contractor is expected to remove any employees from the Cemetery for cause, to include, but not limited to, safety violations, other misconduct in performance of duty under these specifications and/or conduct contrary to the best interests of the Government. If the Contractor fails to act in this regard, or the reason for a removal is immediately required to protect the interests of the Government, the COR may direct the removal of an employee from the premises. Contractor objections to any such action will be referred to the Contacting Officer (CO) for final resolution; however, the Contractor will first immediately comply with COR direction pending any CO final resolution at a later time or date. The Contractor will not be due any type of compensation for their costs incurred as a result of an employee being removed for cause; unless the removal is directed by the COR and is later found invalid and/or unreasonable by the Contracting Officer.
G. Time of Completion: The project shall be completed within 30 calendar days after Award, to include equipment mobilization. Work outside of the Cemetery’s normal operating hours of 7 am to 4:30 pm CT, Monday through Friday, may be permitted only by prior approval of the COR. Requests shall be submitted at least three (3) working days in advance.
H. Code Compliance: All work shall be performed in accordance with the specifications. It shall be the Contractor's responsibility to comply with all the applicable local, state and federal laws and regulations. The Contractor shall apply and obtain all applicable permits to comply with local, State and Federal regulations and requirements. The Contractor shall remove and dispose of all waste materials and construction debris and comply with all applicable local, State and Federal regulations and requirements. All waste materials and debris specified shall be removed from the Cemetery grounds by the Contractor at its own expenses, including all applicable permits and fees.
I. Contractor Quality Control:
1. The Contractor shall guarantee that all work done under this contract shall be free from defaults and no faulty materials or workmanship with one (1) year warranty. The Contractor hereby agrees to repair or replace deficiencies within the specified time frame by the direction of the CO at Contractor's own expense and shall be corrected to the satisfaction of the Government.
2. A competent and experienced English-speaking Contractor Supervisor/Superintendent shall be provided by the Contractor whenever work is being performed, other than trash and debris pick-up. The Contractor Supervisor shall review and approve submittals, ensure all specifications are being met, inspect the quality of work performed, ensure contract work does not conflict with ceremonies and funerals, ensure employees are is adequately supervised and proper conduct maintained, and certify the completed work for payment and other purposes.
J. Submittals After Award: Submit manufacture’s literature for all products and materials to the COR for review/approval.
K. Attachments:
1. Attachment 1, Existing Well Information;
L. Project completion: The project site shall be protected and/or restored to a condition equal to that existing prior to the commencement of work. Upon completion of contract, deliver work complete and undamaged. Existing work disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
END OF STATEMENT OF WORK