S02 523A5-23-003.pdf

PDF 105 KB Posted

Attached to
Z1DA--523A5-22-003 VISN 1 RCx Repairs Brockton (VA-23-00060805)
Solicitation number
36C24123B0009
Issued by

About this file

This document outlines maintenance issues and resolutions for various buildings and equipment at a Veterans Affairs medical center. It identifies six humidification systems across multiple buildings and floors that were supplied by low pressure steam from the boiler plant during functional testing, and specifies installing clean steam generators to resolve the issue. It also notes two additional issues - an air handling unit lacking a variable frequency drive, which should be installed along with reprogramming the sequence of operation for airflow control, and chilled water valves open to allow flow to prevent freezing while awaiting bypass valves, with adding the bypass valves listed as the resolution. The related federal contract opportunity is for repairs at the specified Veterans Affairs medical center located in Brockton, Massachusetts, under Solicitation Number 36C24123B0009, issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 1.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MIL

Issue No.

Survey Date

Equipment Name

Equipment Building Location;

Room, Roof, or Wing;

and Area Served

Issue Description Resolution

7 2/1/2021 A1 Bldg 2 PHA‐02 Penthouse A Section

During functional testing the humidifier was supplied by the low‐ pressure steam from the boiler plant.

Install a clean steam generator.

13 2/1/2021 A2 Bldg 2 B‐001A B Section Basement, 1st/2nd Floors

During functional testing the humidifier was supplied by the low‐ pressure steam from the boiler plant.

Install a clean steam generator.

17 2/1/2021 A3 Bldg 2 B‐001 B Section Day Rooms

During functional testing the humidifier was supplied by the low‐ pressure steam from the boiler plant.

Install a clean steam generator.

25 2/1/2021 A4 Bldg 2 PHB‐02 Penthouse B Section 3rd/4th Floors

During functional testing the humidifier was supplied by the low‐ pressure steam from the boiler plant.

Install a clean steam generator.

35 2/1/2021 A5 Bldg 2 C‐001A C Section Basement, 1st/2nd Floors

During functional testing the humidifier was supplied by the low‐ pressure steam from the boiler plant.

Install a clean steam generator.

41 2/1/2021 A6 Bldg 2 C‐001A C Section Day Rooms

During functional testing the humidifier was supplied by the low‐ pressure steam from the boiler plant.

Install a clean steam generator.

MIL

Issue No.

Survey Date

Equipment Name

Equipment Building Location;

Room, Roof, or Wing;

and Area Served

Issue Description Resolution

235 2/4/2021 3 AHUs for Bldg 46

Bldg 46 Outside

During testing the AC Shop indicated that the chilled water valve was set open to allow flow through the pipes to prevent freezing. They indicated that they were waiting on globe valves to put in place as a bypass so chilled water did not need to pass through the cooling coils.

Add a bypass to allow for chilled water flow through the system piping during winter but prevent flow through the coils.

248 2/2/2021 A23 5 ‐ Outpatient Psychiatry Penthouse

PHA‐05

The air handling unit's supply fan is not equipped with a variable frequency drive. (Priority: 3 ‐ Energy Conservation)

Install a variable frequency drive and reprogram the sequence of operation for airflow control. Run the unit through point‐to‐point and functional performance testing.