523A5-22-003 VISN 1 RCx Repairs BR SOW 230330sm.pdf
PDF 70 KB Posted
- Solicitation number
- 36C24123B0009
About this file
This statement of work outlines repairs and upgrades to be completed at the Brockton VA Medical Center in Brockton, Massachusetts. The project involves implementing recommendations from a previous retro-commissioning assessment to improve energy efficiency and operations. Work includes installing clean steam generators for six humidification systems, adding a bypass to allow chilled water flow through piping at the 46 building without flowing through coils, and installing a variable frequency drive for an air handling unit supply fan and reprogramming its sequence of operation. The performance period is 180 calendar days from notice to proceed. All contractors must comply with VA security requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| S06 - Site Visit Sign In Sheet Brockton RCx Repairs.pdf | ||
| S06 - Bid Opening Conference Line 36C24123B0009.docx | DOCX document | |
| S05 - RFI Questions and Answers 523A5-22-003 RCx Repairs Brockton.docx | DOCX document | |
| 36C24123B0009 0003.docx | DOCX document | |
| 36C24123B0009 0002.docx | DOCX document | |
| 1 35 26 SAFETY REQUIREMENTS.pdf | ||
| 36C24123B0009 0001.docx | DOCX document | |
| 01 00 00 GENERAL REQUIREMENTS.pdf | ||
| 01 33 23 SHOP DRAWINGS PRODUCT DATA AND SAMPLES.pdf | ||
| WD MA20230001 16 June 2023.pdf | ||
| 36C24123B0009.pdf | ||
| S02 523A5-23-003.pdf | ||
| 36C24123B0009.docx | DOCX document | |
| S02 01 33 23 SHOP DRAWINGS PRODUCT DATA AND SAMPLES.pdf | ||
| S02 1 35 26 SAFETY REQUIREMENTS.pdf | ||
| S02 01 00 00 GENERAL REQUIREMENTS.pdf | ||
| S02 WD MA20230001 16 June 2023.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
VISN 1 RETRO-COMMISSIONING (RCx) REPAIRS AT BROCKTON
PROJECT #523A5-22-003
This project will implement recommendations identified by previously completed retro-commissioning (RCx) activities as included as individual item repairs from a RCx Master Issues Log (MIL). This project will include equipment repairs, equipment replacement, and/or upgrading or optimizing Siemens controls. All work will be done at the Brockton VA Medical Center in Brockton, Massachusetts. In general, work shall include all labor, material, equipment, and supervision to perform the required mechanical, electrical, and programmatic work discussed below.
All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
The Period of Performance for this project is 180 calendar days from the Notice to Proceed.
The goal of this work is to make corrections to existing equipment and systems to improve energy efficiency and facility operations. All issues within the scope of work are shown below as they are represented in the
MIL.
The Contractor shall assume responsibility for all temporary measures adopted during the construction period, to maintain operation of the hospital. This shall include but not be limited to temporary heating/cooling/ventilation, coordinating with the COR to relocate personnel, and/or ensuring that adequate facilities are provided, where deemed necessary.
The Brockton VA Medical Center utilizes Siemens as the building automation system vendor.
MIL
Issue No.
Survey Date
Equipment Name
Equipment Building Location;
Room, Roof, or Wing;
and Area Served Issue Description Resolution
7 2/1/2021 A1 Bldg 2
PHA-02 Penthouse A Section
During functional testing the humidifier was supplied by the low-pressure steam from the boiler plant.
Install a clean steam generator.
13 2/1/2021 A2 Bldg 2
B-001A B Section Basement, 1st/2nd Floors
During functional testing the humidifier was supplied by the low-pressure steam from the boiler plant.
Install a clean steam generator.
17 2/1/2021 A3 Bldg 2
B-001 B Section Day Rooms
During functional testing the humidifier was supplied by the low-pressure steam from the boiler plant.
Install a clean steam generator.
25 2/1/2021 A4 Bldg 2
PHB-02 Penthouse B Section 3rd/4th Floors
During functional testing the humidifier was supplied by the low-pressure steam from the boiler plant.
Install a clean steam generator.
35 2/1/2021 A5 Bldg 2
C-001A C Section Basement, 1st/2nd Floors
During functional testing the humidifier was supplied by the low-pressure steam from the boiler plant.
Install a clean steam generator.
41 2/1/2021 A6 Bldg 2
C-001A C Section Day Rooms
During functional testing the humidifier was supplied by the low-pressure steam from the boiler plant.
Install a clean steam generator.
235 2/4/2021 3 AHUs for Bldg 46 Bldg 46 Outside
During testing the AC Shop indicated that the chilled water valve was set open to allow flow through the pipes to prevent freezing. They indicated that they were waiting on globe valves to put in place as a bypass so chilled water did not need to pass through the cooling coils.
Add a bypass to allow for chilled water flow through the system piping during winter but prevent flow through the coils.
248 2/2/2021 A23 5 - Outpatient Psychiatry
Penthouse
PHA-05
The air handling unit's supply fan is not equipped with a variable frequency drive. (Priority: 3 - Energy Conservation)
Install a variable frequency drive and reprogram the sequence of operation for airflow control. Run the unit through point-to-point and functional performance testing.
File details come from the government source that posted it. Updated .