523A5-22-003 VISN 1 RCx Repairs BR SOW 230330sm.pdf

PDF 70 KB Posted

Attached to
Z1DA--523A5-22-003 VISN 1 RCx Repairs Brockton (VA-23-00060805)
Solicitation number
36C24123B0009
Issued by

About this file

This statement of work outlines repairs and upgrades to be completed at the Brockton VA Medical Center in Brockton, Massachusetts. The project involves implementing recommendations from a previous retro-commissioning assessment to improve energy efficiency and operations. Work includes installing clean steam generators for six humidification systems, adding a bypass to allow chilled water flow through piping at the 46 building without flowing through coils, and installing a variable frequency drive for an air handling unit supply fan and reprogramming its sequence of operation. The performance period is 180 calendar days from notice to proceed. All contractors must comply with VA security requirements.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

VISN 1 RETRO-COMMISSIONING (RCx) REPAIRS AT BROCKTON

PROJECT #523A5-22-003

This project will implement recommendations identified by previously completed retro-commissioning (RCx) activities as included as individual item repairs from a RCx Master Issues Log (MIL). This project will include equipment repairs, equipment replacement, and/or upgrading or optimizing Siemens controls. All work will be done at the Brockton VA Medical Center in Brockton, Massachusetts. In general, work shall include all labor, material, equipment, and supervision to perform the required mechanical, electrical, and programmatic work discussed below.

All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

The Period of Performance for this project is 180 calendar days from the Notice to Proceed.

The goal of this work is to make corrections to existing equipment and systems to improve energy efficiency and facility operations. All issues within the scope of work are shown below as they are represented in the

MIL.

The Contractor shall assume responsibility for all temporary measures adopted during the construction period, to maintain operation of the hospital. This shall include but not be limited to temporary heating/cooling/ventilation, coordinating with the COR to relocate personnel, and/or ensuring that adequate facilities are provided, where deemed necessary.

The Brockton VA Medical Center utilizes Siemens as the building automation system vendor.

MIL

Issue No.

Survey Date

Equipment Name

Equipment Building Location;

Room, Roof, or Wing;

and Area Served Issue Description Resolution

7 2/1/2021 A1 Bldg 2

PHA-02 Penthouse A Section

During functional testing the humidifier was supplied by the low-pressure steam from the boiler plant.

Install a clean steam generator.

13 2/1/2021 A2 Bldg 2

B-001A B Section Basement, 1st/2nd Floors

During functional testing the humidifier was supplied by the low-pressure steam from the boiler plant.

Install a clean steam generator.

17 2/1/2021 A3 Bldg 2

B-001 B Section Day Rooms

During functional testing the humidifier was supplied by the low-pressure steam from the boiler plant.

Install a clean steam generator.

25 2/1/2021 A4 Bldg 2

PHB-02 Penthouse B Section 3rd/4th Floors

During functional testing the humidifier was supplied by the low-pressure steam from the boiler plant.

Install a clean steam generator.

35 2/1/2021 A5 Bldg 2

C-001A C Section Basement, 1st/2nd Floors

During functional testing the humidifier was supplied by the low-pressure steam from the boiler plant.

Install a clean steam generator.

41 2/1/2021 A6 Bldg 2

C-001A C Section Day Rooms

During functional testing the humidifier was supplied by the low-pressure steam from the boiler plant.

Install a clean steam generator.

235 2/4/2021 3 AHUs for Bldg 46 Bldg 46 Outside

During testing the AC Shop indicated that the chilled water valve was set open to allow flow through the pipes to prevent freezing. They indicated that they were waiting on globe valves to put in place as a bypass so chilled water did not need to pass through the cooling coils.

Add a bypass to allow for chilled water flow through the system piping during winter but prevent flow through the coils.

248 2/2/2021 A23 5 - Outpatient Psychiatry

Penthouse

PHA-05

The air handling unit's supply fan is not equipped with a variable frequency drive. (Priority: 3 - Energy Conservation)

Install a variable frequency drive and reprogram the sequence of operation for airflow control. Run the unit through point-to-point and functional performance testing.