S01 Attachment 1 Specifications.pdf

PDF 2 MB Posted

Attached to
EWP - Harlingen Irrigation Drainage Channel Stabilization Project - Cameron County, Texas
Solicitation number
12FPC321B0005
Issued by

About this file

This is a solicitation for a firm fixed price construction contract issued by the United States Department of Agriculture on behalf of the Natural Resources Conservation Service. The solicitation involves repair work along an existing drainage channel in Harlingen, Cameron County, Texas. Major work items include installing anchored steel sheet piles to stabilize the drainage channel toe and embankment slopes, excavating embankment slopes, installing drain prisms, backfilling slopes with earthfill, shaping areas to match existing structures, and vegetating disturbed areas. A site visit is scheduled for March 25, 2021. Bids are due under sealed bid procedures outlined in FAR Part 14, and bidders must provide a bid guarantee of 20% with each bid. Performance and payment bonds of 100% will be required within 5 days of award. The period of performance is 153 calendar days from notice to proceed. The estimated value is between $1,000,000 and $5,000,000. The solicitation is a total small business set-aside with a NAICS code of 237990 and size standard of $39.5M.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

12FPC321B0005 Attachment 1 Specifications Page 1

1. SPECIFICATIONS:

Construction Specification No.: Title: Date:

3 Structure Removal 5/01 4 Channel Clearing and Shaping 5/01 5 Pollution Control 1/14 6 Seeding, Sprigging and Mulching 9/18 7 Construction Surveys 1/09 8 Mobilization and Demobilization 5/01 9 Traffic Control 5/01

11 Removal of Water 5/01 13 Piling 5/01 21 Excavation 5/01 23 Earthfill 2/20 24 Drainfill 5/01 51 Corrugated Metal Pipe 5/01 61 Rock Riprap 9/18 81 Metal Fabrication and Installation 5/01 83 Timber Fabrication and Installation 1/09 92 Field Fence 1/09 94 Contractor Quality Control 1/09 95 Geotextile 1/14

424 Flowable Fill 8/20

Material Specification No.: Title: Date

511 Steel Piles 5/01 521 Aggregates for Drainfill and Filters 1/14 523 Rock for Riprap 9/18 531 Portland Cement 5/01 552 Aluminum Corrugated Pipe 5/01 581 Metal 11/05 582 Galvanizing 5/01 584 Structural Timber and Lumber 5/01 585 Wood Preservatives and Treatment 9/18 591 Field Fencing Materials 9/18 592 Geotextile 9/18

12FPC321B0005 Attachment 1 Specifications Page 2

2. DEFINITIONS:

Sponsor - Harlingen Irrigation District Cameron County No. 1 Contracting Officer (CO) – FPAC Acquisition Division - Section 3 Government – Natural Resources Conservation Service (NRCS) Service - NRCS Engineer - NRCS Construction Engineer Contracting Officer's Representative (COR) - NRCS Construction Engineer Government’s Representative (GR) – NRCS Construction Engineer Inspector – NRCS Construction Inspector (on-site) Quality Assurance (QA) – NRCS Construction Inspector (on-site) Quality Control (QC) – Contractor’s Construction Inspector (on-site) Owner – Harlingen Irrigation District Cameron County No. 1

3. DRAWINGS:

Site No. 44 Drawing No. TX-EN-0796, Cover plus Sheets 1 through 9.

4. LOCATION:

Site No. 44 is located approximately 3.5 miles south of Harlingen near Rangerville Road, Cameron County, Texas.

5. PERFORMANCE TIME:

Time to be allowed for completion of both sites in this contract is 153 calendar days (holidays and weather days not included).

12FPC321B0005 Attachment 1 Specifications Page 3

(210-VI-NEH, May 2001) 3-1

Construction Specification 3—Structure Removal

1. Scope The work shall consist of the removal, salvage, and disposal of structures (including fences) from the designated areas.

2. Marking Method 1—Each structure or structure part to be removed will be marked with stakes, flags, paint, or other suitable method.

Method 2—The area boundaries from which structures must be removed will be marked using stakes, flags, paint, or other suitable method. Structures to remain undisturbed or to be salvaged will be designated by special markings.

3. Removal Method 1—All structures designated for removal in the contract shall be removed to the specified extent and depth.

Method 2—Within the areas so marked, all visible and buried structures identified shall be removed to the specified extent and depth.

4. Salvage Structures or structure parts that are designated to be salvaged shall be carefully removed and neatly placed in the specified or approved storage location. Salvaged structures that are capable of being disassembled shall be dismantled into individual members or sections. Such structures shall be neatly and systematically match marked with paint before disassembly. All connectors and other parts shall be marked to indicate their proper location within the structure and shall be fastened to the appropriate structural member or packed in suitable containers.

Material from fences designated to be salvaged shall be placed outside the work area on the property on which the fence was originally located. Fence wire shall be rolled into uniform rolls of suitable size and neatly piled with other salvaged materials. Posts and rails shall be neatly stacked.

5. Disposal of refuse materials Refuse materials resulting from structure removal shall be disposed of in a manner and at locations specified in section 7 of this specification or in an acceptable manner and at locations approved by the contracting officer. Disposal by burning shall be in accordance with local rules and regulations.

6. Measurement and payment Method 1—For items of work for which specific unit prices are established by the contract, payment for the removal of each structure unit, except fences, is made at the contract unit price. Fences removed or removed and salvaged are measured to the nearest linear foot. Payment for fence removal or removal and salvage is made at the contract unit prices for each type and size of fence.

Such payment will constitute full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and incidental to the completion of the work.

Method 2—For items of work for which specific lump sum prices are established by the contract, payment for structure removal is made at the contract lump sum price.

Such payment will constitute full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and incidental to the completion of the work.

All Methods—The following provisions apply to all methods of measurement and payment.

Compensation for any item of work described in the contract, but not listed as a contract line item number in the bid schedule, is included in the payment for the item of work to which it is made subsidiary. Such items and items to which they are made subsidiary are identified in section 7 of this specification.

7. Items of work and construction details

12FPC321B0005 Attachment 1 Specifications Page 4

NRCS – 8/18/2020 3-2

TX – HARLINGEN IRRIGATION DISTRICT EWP REPAIR

Items of work to be performed in conformance with this specification and the construction details therefore are:

a. Bid Item 1, Structure Removal, Vinyl Sheet Piles, Walers, Cables, Deadmen, Drain Pipe and Timber Pipe Supports

(1) In section 2, Marking, Method 2 shall apply.

(2) In section 3, Removal, Method 2 shall apply. The items shall be removed to the depth and/or cut to the length as indicated in the drawings.

(3) In section 4, Salvage, steel waler and cross drain conduit sections and set aside for reuse.

(4) All unusable material and rubble shall be disposed of at an offsite location of the contractor’s choosing as approved by the contracting officer and in accordance with all local and state regulations.

(5) In section 6, Measurement and payment, Method 1 shall apply.

b. Subsidiary Item, Structure Removal, Fence

(1) This item shall consist of the removal of fence as necessary to complete the work in the construction area as shown on the drawings.

(2) Separate payment will not be made for this item of work. Compensation for this item will be included in the payment for the bid items for Mobilization and Demobilization.

c. Subsidiary Item, Structure Removal, Rock Riprap

(1) The rock riprap in the channel shall be, removed, salvaged, and re-installed below the re-installed cross drains as shown on the drawings and in accordance with Construction Specification 61. The geotextile underlying the existing rock riprap shall be wasted.

(2) In section 2, Marking, Method 2 shall apply.

(3) In section 3, Removal, Method 2 shall apply.

(4) Separate payment will not be made for this item of work. Compensation for this item will be included in the payment for the bid items for Channel Clearing and Shaping.

12FPC321B0005 Attachment 1 Specifications Page 5

(210-VI-NEH, May 2001) 4-1

Construction Specification 4—Channel Clearing and Shaping

1. Scope The work consists of clearing designated areas by the removal and disposal of trees, logs, stumps, shrubs, brush, and rubbish, and the shaping of the channel.

2. Protection of existing vegetation Trees and other vegetation designated to remain undisturbed shall be protected from damage throughout the duration of the construction period. Any damages resulting from the contractor's operations or neglect shall be repaired by the contractor.

Earthfill, stockpiling of materials, vehicle or equipment parking, and excessive foot or vehicle traffic shall not be allowed within the drip line of vegetation designated to remain in place. Vegetation damaged by any of these or similar actions shall be replaced with viable vegetation of the same species, similar condition, and like size unless otherwise approved by the contracting officer.

Any cuts, skins, scrapes, or bruises to the bark of the vegetation shall be carefully trimmed and local nursery accepted procedures used to seal damaged bark.

Any limbs or branches 0.5 inch or larger in diameter that are broken, severed, or otherwise seriously damaged during construction shall be cut off at the base of the damaged limb or branch flush with the adjacent limb or tree trunk.

All roots 1 inch or larger in diameter that are cut, broken, or otherwise severed during channel shaping shall have the end smoothly cut perpendicular to the root. Roots exposed during channel shaping operations shall be covered with moist soil as soon as possible to prevent roots from drying out.

3. Marking The limits of the area(s) to be cleared and shaped are marked by stakes, flags, paint, tree markings, or other suitable methods or as specified in section 8 of this specification, or they will be shown on the drawings. Trees to remain standing, undisturbed, and uninjured are designated by special markings.

4. Clearing Trees and other vegetation marked for clearing shall be cut off as near the ground surface as conventional tools and equipment normally permit. All trees not marked for preservation and all snags, logs, brush, shrubs, stumps, and rubbish shall be cleared from within the area limits identified.

5. Disposal All woody material, vegetation, and rubbish resulting from clearing from designated areas shall be disposed of at the locations and in a manner shown on the drawings, or as specified in section 8 of this specification.

6. Shaping The channel bottom and side slopes shall be shaped as shown on the drawings. The resulting shaped channel surface shall be reasonably smooth. Material excavated during the channel shaping operation shall be removed from the channel and disposed of as specified in section 8 of this specification.

7. Measurement and payment Method 1—For items of work for which specific unit prices are established by the contract, the designated cleared and shaped area is measured and the area determined to the nearest 0.1 acre. Payment

12FPC321B0005 Attachment 1 Specifications Page 6

(210-VI-NEH, May 2001) 4-2 for clearing and shaping is made at the contract unit price for the item and shall constitute full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and incidental to the satisfactory completion of the work.

Method 2—For items of work for which specific unit prices are established by the contract, the length of the cleared and shaped channel designated is measured to the nearest 100 feet. Payment for clearing and shaping is made at the contract unit price for the item and shall constitute full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and incidental to the satisfactory performance of the work.

Method 3—For items of work for which specific unit prices are established by the contract, the cleared and shaped area(s) is measured and the area determined to the nearest 0.1 acre. The designated cleared and shaped area(s) is determined from the measured width at representative sections and the distance between the sections. Payment for clearing and shaping is made at the contract unit price for the item and shall constitute full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and incidental to the satisfactory completion of the work.

Method 4—For items of work for which specific lump sum prices are established by the contract, the extent of clearing and shaping is not measured or determined for payment. Payment for clearing and shaping is made at the contract lump sum price for the item and shall constitute full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and incidental to the satisfactory completion of the work.

All Methods—The following provisions apply to all methods of measurement and payment.

Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items and items to which they have been made subsidiary are identified in section 8 of this specification.

8. Items of work and construction details

12FPC321B0005 Attachment 1 Specifications Page 7

NRCS – 8/18/2020 3-3

Section 2, Protection of existing vegetation shall not apply.

In section 6, Shaping, the shaping shall consist of removing and disposal of the sediment from the channel as shown on the drawings. The disposal of the sediment materials shall include transporting, depositing, and spreading the materials at an offsite location of the contractor’s choosing as approved by the COR. The finished surfaces of the waste area shall be uniform and conform to the topography. Additional compensation for disposal of sediment materials and dressing of the surface of the waste area will not be made.

In section 7, Measurement and payment, Method 4 shall apply.

Brush and debris shall be disposed of at an offsite location of the contractor’s choosing as approved by the COR.

Items of work to be performed in conformance with this specification and the construction details therefore are:

a. Bid Item 2, Channel Clearing and Shaping

(1) This item shall consist of the removal and disposal of all brush and debris in the construction area and the removal of the sediment as shown on the drawings.

(2) The items of work subsidiary to this bid item are: Structure Removal, Rock Riprap as specified in Construction Specification 3.

12FPC321B0005 Attachment 1 Specifications Page 8

(210-VI-NEH, January 2014) 5-1

Construction Specification 5—Pollution Control

1. Scope

The work consists of installing measures or performing work to control erosion and minimize the production of sediment and other pollutants to water and air from construction activities.

The following BioPreferred® product categories are applicable to this specification: — mulch and compost materials erosion control materials fertilizers dust suppressants agricultural spray adjuvants

2. Material

Silt fence shall conform to the requirement of Materials Specification 592, Geotextile. All other material furnished shall meet the requirements of the material specifications listed in section 8 of this specification.

3. Erosion and sediment control measures and works

The measures and works shall include, but are not limited to, the following:

Staging of earthwork activities—The excavation and moving of soil materials shall be scheduled to minimize the size of areas disturbed and unprotected from erosion for the shortest reasonable time.

Seeding—Seeding to protect disturbed areas shall occur as soon as reasonably possible following completion of that earthwork activity.

Mulching—Mulching to provide temporary protection of the soil surface from erosion.

Diversions—Diversions to divert water from work areas and to collect water from work areas for treatment and safe disposition. They are temporary and shall be removed and the area restored to its near original condition when the diversions are no longer required or when permanent measures are installed.

Stream crossings—Culverts or bridges where equipment must cross streams. They are temporary and shall be removed and the area restored to its near original condition when the crossings are no longer required or when permanent measures are installed.

Sediment basins—Sediment basins collect, settle, and eliminate sediment from eroding areas from impacting properties and streams below the construction site(s). These basins are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.

Sediment filters—Straw bale filters or geotextile silt fences trap sediment from areas of limited runoff.

Sediment filters shall be properly anchored to prevent erosion under or around them. Silt fences shall be installed and maintained in accordance with ASTM D6462. These filters are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.

Waterways—Waterways for the safe disposal of runoff from fields, diversions, and other structures or measures. These works are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.

Other—Additional protection measures as specified in section 8 of this specification or required by Federal, State, or local government.

4. Chemical pollution

12FPC321B0005 Attachment 1 Specifications Page 9

(210-VI-NEH, January 2014) 5-2

The contractor shall provide watertight tanks or barrels or construct a sump sealed with plastic sheets to collect and temporarily contain chemical pollutants, such as drained lubricating or transmission fluids, grease, soaps, concrete mixer washwater, or asphalt, produced as a by-product of the construction activities. Pollutants shall be disposed of in accordance with appropriate state and Federal regulations. At the completion of the construction work, tanks, barrels, and sumps shall be removed and the area restored to its original condition as specified in section 8 of this specification. Sump removal shall be conducted without causing pollution.

Sanitary facilities, such as chemical toilets, or septic tanks shall not be located next to live streams, wells, or springs. They shall be located at a distance sufficient to prevent contamination of any water source. At the completion of construction activities, facilities shall be disposed of without causing pollution as specified in section 8 of this specification.

5. Air pollution

The burning of brush or slash and the disposal of other materials shall adhere to state and local regulations.

Fire prevention measures shall be taken to prevent the start or spreading of wildfires that may result from project activities. Firebreaks or guards shall be constructed and maintained at locations shown on the drawings.

All public access or haul roads used by the contractor during construction of the project shall be sprinkled or otherwise treated to fully suppress dust. All dust control methods shall ensure safe construction operations at all times. If chemical dust suppressants are applied, the material shall be a commercially available product specifically designed for dust suppression and the application shall follow manufacturer's requirements and recommendations. A copy of the product data sheet and manufacturer's recommended application procedures shall be provided to the engineer 5 working days before the first application.

6. Maintenance, removal, and restoration

All pollution control measures and temporary works shall be adequately maintained in a functional condition for the duration of the construction period. All temporary measures shall be removed and the site restored to near original condition.

7. Measurement and payment

Method 1—For items of work for which specific unit prices are established in the contract, each item is measured to the nearest unit applicable. Payment for each item is made at the contract unit price for that item. For water or chemical suppressant items used for dust control for which items of work are established in section 8 of this specification, measurement for payment will not include water or chemical suppressants that are used inappropriately or excessive to need. Such payment will constitute full compensation for the completion of the work.

Method 2—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds and supported by invoices presented by the contractor that reflect actual costs. If the total of all progress payments is less than the lump sum contract price for this item, the balance remaining for this item will be included in the final contract payment. Payment of the lump sum contract price will constitute full compensation for completion of the work.

Method 3—For items of work for which lump sum prices are established in the contract, payment will be prorated and provided in equal amounts on each monthly progress payment estimate. The number of months used for prorating shall be the number estimated to complete the work as outlined in the contractor's approved construction schedule. The final month's prorate amount will be provided with the final contract payment. Payment as described will constitute full compensation for completion of the work.

12FPC321B0005 Attachment 1 Specifications Page 10

(210-VI-NEH, January 2014) 5-3

All Methods—The following provisions apply to all methods of measurement and payment.

Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items, and the items to which they are made subsidiary, are identified in section 8 of this specification.

12FPC321B0005 Attachment 1 Specifications Page 11

NRCS – 8/18/2020 5-4

The construction site is greater than five (5) acres in area and is subject to the Texas Pollutant Discharge Elimination System (TPDES) requirements administered by the Texas Commission on Environmental Quality (TCEQ). Rules for the TPDES process relative to construction sites are contained in the TPDES General Permit NO. TXR150000. A copy of General permit No.

TXR150000 may be found at the TCEQ website.

In conformance with TPDES General Permit TXR150000, a Storm Water Pollution Prevention Plan (SWP3) is required for the construction site. A SWP3 prepared by NRCS is provided. The Contractor shall review the SWP3, and shall amend the plan with a detailed work sequence outline which defines and delineates the proposed construction operation. The amended SWP3 shall be signed by the Contractor and submitted to the Contracting Officer prior to issuance of the Notice to Proceed. A copy of the approved SWP3, as amended, will be maintained at the construction site by the Contractor. A copy of the permit shall be attached to the SWP3.

A copy of the Notice of Intent (NOI) shall be posted at the site until the TPDES permit number is issued for the site. An 8 ½” x 11” notice shall be posted at the site giving the following information about the permit: permit number, contact name, contact phone and project description. If a permit number has not been issued, a copy of the NOI shall be posted with the notice.

If the Contractor identifies sediment control items, which are considered essential to the anticipated construction operation but which are not reflected by the contract bid schedule, a written request for a contract modification will be provided to the Contracting Officer. The request will identify the items, operation, and provide an assessment of changes to the contract cost and performance time.

TPDES also requires an NOI and Notice of Termination (NOT) to be filed with TCEQ. The Contractor will be responsible for submitting the Contractor’s copy of the NOI to the Engineer at least five business days before work begins. When the contract is completed, the Contractor shall provide the NRCS Project Engineer a copy of the NOT that he/she will file with the TCEQ.

In conformance with TPDES requirements, the Inspector and the Contractor (or the Contractor’s Quality Control person) shall perform periodic inspections of the sediment control practices.

Inspections will be conducted bi-weekly (first work day of each week) and within 24 hours of any rainfall event of more than 0.5 inches at the construction site. After each inspection, a written report will be prepared which summarizes the status of inspected items. The reports will (a) evaluate effectiveness, (b) identify maintenance needs and/or (c) recommend remedial corrective action and will be prepared and signed by the COR and the Contractor. The report shall be filed on site in the same location as the SWP3. The Contractor shall be responsible for identified corrective maintenance needs.

Items of work to be performed in conformance with this specification and the construction details therefore are:

a. Bid Item 3, Pollution Control

(1) This item shall consist of performing all work and furnishing all materials necessary to accomplish the work defined in section 1 of this specification, including all works required to implement the Storm Water Pollution Prevention Plan, installation of the rock sediment filter and maintenance of all silt fence, but not the installation of silt fence.

12FPC321B0005 Attachment 1 Specifications Page 12

NRCS – 8/18/2020 5-5

(2) In section 3, Other, a stabilized construction entrance shall be installed on the access road where it intersects with an improved road as shown on the drawings. Geotextile shall be non-woven and conform to the requirements of Material Specification 592.

(3) In section 5, Air pollution, firebreaks or guards are not shown on the drawing.

(4) In section 7, Measurement and payment, Method 3 shall apply.

(5) The item of work subsidiary to this bid item is Sediment Silt Fence as specified in this specification.

b. Subsidiary Item, Sediment Silt Fence

(1) This item shall consist of furnishing and installing sediment silt fence to the lengths and locations designated on the drawings and otherwise needed to control sediment from leaving the construction site. Maintenance of installed silt fence shall be paid for under the bid item for Pollution Control.

(2) In section 3, Erosion and sediment control measures and works, sediment filters shall be limited to geotextile sediment silt fence.

(3) The silt fence material shall meet the requirements of Material Specification 592.

(4) Separate payment shall not be made for this item of work. Compensation for this item will be included in the payment for the bid item Pollution Control.

12FPC321B0005 Attachment 1 Specifications Page 13

(210-VI-NEH, Amend. 2, Sept. 2018) 6-1

Construction Specification 6—Seeding, Sprigging, and Mulching

1. Scope

The work consists of preparing the area for treatment; furnishing and placing seed, sprigs, mulch, fertilizer, inoculant, lime, and other soil amendments; and anchoring mulch in designated areas as specified.

The following BioPreferred® product categories are applicable to this specification:

— Mulch and compost materials

— Erosion control materials

— Fertilizers

— Agricultural spray adjuvants

2. Material

Seed—All seed must conform to the current rules and regulations of the State where it is being used and must be from the latest crop available. It must meet or exceed the standard for purity and germination listed in section 7.

Seed must be labeled in accordance with State laws and U.S. Department of Agriculture rules and regulations under the Federal Seed Act in effect on the date of invitations for bids. Bag tag figures are evidence of purity and germination. No seed may be accepted with a test date of more than 9 months before the date of delivery to the site.

Seed that has become wet, moldy, or otherwise damaged in transit or storage will not be accepted. The percent of noxious weed seed allowable must be as defined in the current State laws relating to agricultural seeds. Each type of seed must be delivered in separate sealed containers and fully tagged unless an exception is granted in writing by the contracting officer.

Fertilizer—Unless otherwise specified, the fertilizer must be a commercial-grade fertilizer. It must meet the standard for grade and quality specified by State law. Where fertilizer is furnished from bulk storage, the contractor must furnish a supplier’s certification of analysis and weight. When required by the contract, a representative sample of the fertilizer must be furnished to the contracting officer for chemical analysis.

Inoculants—The inoculant for treating legume seeds must be a pure culture of nitrogen-fixing bacteria prepared specifically for the species and must not be used later than the date indicated on the container or as otherwise specified. A mixing medium, as recommended by the manufacturer, must be used to bond the inoculant to the seed. Two times the amount of the inoculant recommended by the manufacturer must be used, except that four times the amount must be used when seed is applied using a hydraulic seeder.

Seed must be sown within 24 hours of treatment and must not remain in the hydraulic seeder longer than 4 hours.

Lime and other soil amendments—Lime must consist of standard ground agriculture limestone, or approved equivalent. Standard ground agriculture limestone is defined as ground limestone meeting current requirements of the State department of agriculture. Other soil amendments must meet quality criteria and application requirements specified in section 7.

12FPC321B0005 Attachment 1 Specifications Page 14

(210-VI-NEH, Amend. 2, Sept. 2018) 6-2

Mulch tackifiers—Asphalt emulsion tackifiers must conform to the requirements of ASTM D977, Specification for Emulsified Asphalt. The emulsified asphalt may be rapid setting, medium setting, or slow setting. Nonasphaltic tackifiers required because of environmental considerations must be as specified in section 7.

Straw mulch material—Straw mulch must consist of wheat, barley, oat or rye straw, hay, grass cut from native grasses, or other plants as specified in section 7. The mulch material must be air-dry, reasonably light in color, and must not be musty, moldy, caked, or otherwise of low quality. The use of mulch that contains noxious weeds is not permitted. The contractor must provide a method satisfactory to the contracting officer for determining weight of mulch furnished.

Other mulch materials—Mulching materials, such as wood cellulose fiber mulch, mulch tackifiers, synthetic fiber mulch, netting, and mesh may be required for specialized locations and conditions. These materials, when specified, must be accompanied by the manufacturer’s recommendations for methods of application.

3. Seeding mixtures, sod, sprigs, and dates of planting

The application rate per acre for seed mixtures, sprigs, or sod and date of seeding or planting must be as shown on the plans or as specified in section 7.

4. Seedbed preparation and treatment

Areas to be treated must be dressed to a smooth, firm surface. On sites where equipment can operate on slopes safely, the seedbed must be adequately loosened (4 to 6 inches deep) and smoothed. Depending on soil and moisture conditions, disking or cultipacking, or both, may be necessary to properly prepare a seedbed. Where equipment cannot operate safely, the seedbed must be prepared by hand methods by scarifying to provide a roughened soil surface so that broadcast seed will remain in place.

If seeding is to be accomplished immediately following construction operations, seedbed preparation may not be required except on a compacted, polished, or freshly cut soil surface.

Rocks larger than 6 inches in diameter, trash, weeds, and other debris that will interfere with seeding or maintenance operations must be removed or disposed of as specified in section 7.

Seedbed preparation must be discontinued when soil moisture conditions are not suitable for the preparation of a satisfactory seedbed as determined by the responsible engineer.

5. Seeding, sprigging, fertilizing, mulching, and stabilizing

All seeding or sprigging operations must be performed in such a manner that the seed or sprigs are applied in the specified quantities uniformly in the designated areas. The method and rate of seed application must be as specified in section 7. Unless otherwise specified, seeding or sprigging must be accomplished within 2 days after final grading is completed and approved.

Fertilizer, lime, and other soil amendments must be applied as specified in section 7. When specified, the fertilizer and soil amendments must be thoroughly incorporated into the soil immediately following surface application.

The rate, amount, and kind of mulching or mesh must be as specified in section 7. Mulches must be applied uniformly to the designated areas. They must be applied to areas seeded not later than 2 working

12FPC321B0005 Attachment 1 Specifications Page 15

(210-VI-NEH, Amend. 2, Sept. 2018) 6-3 days after seeding has been performed. Straw mulch material must be stabilized within 24 hours of application using a mulch crimper or equivalent anchoring tool or by a suitable tackifier. When the mulch crimper or equivalent anchoring tool is used, it must have straight blades and be the type manufactured expressly for and capable of firmly punching the mulch into the soil. Where the equipment can be safely operated, it must be operated on the contour. Hand methods must be used where equipment cannot safely operate to perform the work required.

The tackifier must be applied uniformly over the mulch material at the specified rate, or it must be injected into the mulch material as it is being applied. Mesh or netting stabilizing materials must be applied smoothly but loosely on the designated areas. The edges of these materials must be buried or securely anchored using spikes or staples as specified in section 7.

The contractor must maintain the mesh or netting areas until all work under the contract has been completed and accepted. Maintenance must consist of the repair of areas damaged by water erosion, wind, fire, or other causes. Such areas must be repaired to reestablish the intended condition and to the design lines and grades required by the contract. The areas must be refertilized, reseeded, and remulched before the new application of the mesh or netting.

6. Measurement and payment

Method 1—For items of work for which specific unit prices are established in the contract, each area treated is measured as specified in section 7 and the area is calculated to the nearest 0.1 acre. Payment for treatment is made at the contract unit price for the designated treatment, which will constitute full compensation for completion of the work.

When specified as an item of work, mesh or netting is measured to the nearest square yard of surface area covered and accepted. Payment is made at the contract unit price and will constitute full compensation for completion of the work.

Method 2—For items of work for which specific lump-sum prices are established in the contract, the quantity of work will not be measured for payment. Payment for this item is made at the contract lump-sum price for the item and constitutes full compensation for the completion of the work.

Method 3—For items of work for which lump-sum prices are established in the contract, payment is made as the work proceeds. Progress payments are determined as specified in section 7. Payment of the lump sum contract price constitutes full compensation for completion of the work.

All Methods—The following provisions apply to all methods of measurement and payment.

Compensation for any item of work described in the contract but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items and the items to which they are made subsidiary are identified in section 7.

12FPC321B0005 Attachment 1 Specifications Page 16

NRCS – 8/18/2020 6-4

Vegetation shall be performed by seeding using a hydro mulch.

In section 5, mulch material shall consist of 100% wood fiber mulch and containing an organic tackifier of 40 pounds per acre. The mulch shall be applied at a rate of 2,300 lb per acre. The fiber mulch shall be a mix with a minimum thirty-five (35) pounds of mulch material per 100 gallons of water. The seed and fertilizer shall be uniformly combined in the hydro mulch. The mulch and tackifier shall be approved by the COR prior to placement.

No site preparation shall be required prior to application of the materials.

The seed shall consist of common bermudagrass applied at a rate of 5 pounds pure live seed per acre and can be applied year-round in Cameron County, Texas.

The rate of application of the fertilizer shall be fifty (50) pounds of nitrogen (N) or to the nitrogen (N)/phosphorous (P)/potassium (K) mix and application rate as prescribed by the Cameron County NRCS District Conservationist.

The contractor shall furnish weight tickets for the seed, fertilizer, and mulch materials applied.

When working on slopes which are steeper than 3:1 horizontal to vertical, all rubber tire equipment on the slope will be held with truck or tractor and winch line with the truck or tractor operating along the crown of the embankment or other suitable flat surface. As an alternative, track (crawler) equipment with a low center of gravity may be used to perform work on slopes without a winch line requirement when operated in accordance with applicable OSHA requirements.

In section 6, Measurement and payment, Method 1 shall apply, the area shall be surface measured.

Items of work to be performed in conformance with this specification and the construction details therefore are:

a. Bid Item 4, Vegetation

(1) This item shall consist of furnishing and applying hydro mulch mix to all areas designated for vegetation.

12FPC321B0005 Attachment 1 Specifications Page 17

(210-VI-NEH, January 2009) 7-1

Construction Specification 7—Construction Surveys

1. Scope The work consists of performing all surveys, measurements, and computations required by this specification.

2. Equipment and material Equipment for construction surveys shall be of a quality and condition to provide the required accuracy.

The equipment shall be maintained in good working order and in proper adjustment at all times. Records of repairs, calibration tests, accuracy checks, and adjustments shall be maintained and be available for inspection by the engineer. Equipment shall be checked, tested, and adjusted as necessary in conformance with manufacturer's recommendations.

Material is field notebooks, stakes, templates, platforms, equipment, spikes, steel pins, tools, and all other items necessary to perform the work specified.

3. Quality of work All work shall follow recognized professional practice and the standards of the industry unless otherwise specified in section 9 of this specification. The work shall be performed to the accuracy and detail appropriate for the type of job. Notes, sketches, and other data shall be complete, recorded neatly, legible, reproducible and organized to facilitate ease in review and allow reproduction of copies for job documentation. Survey equipment that requires little or no manual recording of field data shall have survey information documented as outlined in section 9 of this specification.

All computations shall be mathematically correct and shall include information to identify the bid item, date, and who performed, checked, and approved the computations. Computations shall be legible, complete, and clearly document the source of all information used including assumptions and measurements collected.

If a computer program is used to perform the computations, the contractor shall provide the engineer with the software identification, vendor's name, version number, and other pertinent data before beginning survey activities. Computer generated computations shall show all input data including values assigned and assumptions made.

The elevations of permanent and temporary bench marks shall be determined and recorded to the nearest

0.01 foot. Differential leveling and transit traverses shall be of such precision that the error of vertical closure in feet shall not exceed plus or minus 0.1 times the square root of the traverse distance in miles.

Linear measurements shall be accurate to within 1 foot in 5,000 feet, unless otherwise specified in section 9 of this specification. The angular error of closure for transit traverses shall not exceed 1 minute times the square root of the number of angles turned.

The minimum requirements for placing slope stakes shall be at 100-foot stations for tangents, as little as 25 feet for sharp curves, breaks in the original ground surface and at any other intermediate stations necessary to ensure accurate location for construction layout and measurement. Slope stakes and cross sections shall be perpendicular to the centerline. Significant breaks in grade shall be determined for cross sections. Distances shall be measured horizontally and recorded to the nearest 0.1 foot. Side shots for interim construction stakes may be taken with a hand level.

Unless otherwise specified in section 9 of this specification, measurements for stationing and establishing the location of structures shall be made to the nearest 0.1 foot.

Elevations for concrete work, pipes, and mechanical equipment shall be determined and recorded to the nearest 0.01 foot. Elevations for earth work shall be determined and recorded to the nearest 0.1 foot.

12FPC321B0005 Attachment 1 Specifications Page 18

(210-VI-NEH, January 2009) 7-2

4. Primary control The baselines and bench marks for primary control, necessary to establish lines and grades needed for construction, are shown on the drawings and have been located on the job site.

These baselines and bench marks shall be used as the origin of all surveys, layouts, and measurements to establish construction lines and grades. The contractor shall take all necessary precautions to prevent the loss or damage of primary control points. Any stakes or control points lost or damaged by construction activity will be reestablished by the contractor or at contractor expense

5. Construction surveys Before work starts that requires contractor performed surveys, the contractor shall submit in writing for the engineer's review: the name, qualifications, and experience of the individuals to be assigned to the survey tasks.

Method 1—Contractor performed surveys shall include:

• checking and any supplemental or interim staking

• performing quantity surveys, measurements, and computations for progress payment

• other surveys as described in section 9 of this specification

Method 2—Contractor performed surveys shall consist of all work necessary for:

• establishing line and grade for all work

• setting slope stakes for all work

• checking and any supplemental or interim staking

• establishing final grade stakes

• performing quantity surveys, measurements, and computations for progress payment

• other surveys as described in section 9 of this specification

Method 3—Contractor performed surveys shall consist of all work necessary for:

• establishing line and grade for all work

• setting slope stakes for all work

• checking and any supplemental or interim staking

• establishing final grade stakes

• performing quantity surveys, measurements, and computations for progress payments

• performing original (initial) and final surveys for determinations of final quantities

• other surveys as described in section 9 of this specification.

6. Staking The construction staking required for the item shall be completed before work on any item starts.

Construction staking shall be completed as follows or as otherwise specified in section 9 of this specification:

Clearing and grubbing—The boundary of the area(s) to be cleared and grubbed shall be staked or flagged at a maximum interval of 200 feet, closer if needed, to clearly mark the limits of work. When contractor staking is the basis for determining the area for final payment, all boundary stakes will be reviewed by the engineer before start of this work item.

Excavation and fill—Slope stakes shall be placed at the intersection of the specified slopes and ground line. Slope stakes and the reference stakes for slopes shall be marked with the stationing, required cut or fill, slope ratio, and horizontal distance from the centerline or other control line. The minimum

12FPC321B0005 Attachment 1 Specifications Page 19

(210-VI-NEH, January 2009) 7-3 requirements for placing slope stakes is outlined in section 3, Quality of work.

Structures—Centerline and offset reference line stakes for location, alignment, and elevation shall be placed for all structures.

7. Records All survey data shall be recorded in fully identified standard hard-bound engineering survey field notebooks with consecutively numbered pages. All field notes and printed data shall include the purpose or description of the work, the date the work was performed, weather data, sketches, and the personnel who performed and checked the work. Electronically generated survey data and computations shall be bound, page numbered, and cross referenced in a bound field notebook containing the index for all survey activities. All work shall follow recognized professional practice.

The construction survey records shall be available at all times during the progress of the work for examination and use by the engineer and when requested, copies shall be made available. The original field notebooks and other records shall be provided to and become the property of the owner before final payment and acceptance of all work.

Complete documentation of computations and supporting data for progress payments shall be submitted to the engineer with each invoice for payment as specified in section 9 of the specification. When the contractor is required to conduct initial and final surveys as outlined in section 5, Construction Surveys, notes shall be provided as soon as possible after completion to the engineer for the purpose of determining final payment quantities.

8. Payment Method 1—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds, after presentation of correct and accurate invoices by the contractor showing related costs and evidence of the charges of suppliers, subcontractors, and others for supplies furnished and work performed. Invoices for the total amount of the contract price will not be accepted until all surveys are complete and required documentation has been determined complete. If the total of such payments is less than the lump sum contract price for this item, the unpaid balance will be included in the final contract payment. Payment of the lump sum contract price will constitute full compensation for completion of all work under the bid item.

Method 2—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds with progress payment amounts determined as a percentage of the total work planned as projected from the contractor's approved construction schedule. Payment of the lump sum contract price will constitute full compensation for completion of all work under this bid item.

All Methods—Payment will not be provided under this item for the purchase price of materials or equipment having a residual value.

Compensation for any item of work described in the contract, but not listed in the bid schedule will be included in the payment for the item of work to which it is made subsidiary. Such items and the item to which they are made subsidiary are identified in section 9 of this specification.

9. Items of work and construction details

12FPC321B0005 Attachment 1 Specifications Page 20

NRCS – 8/18/2020 7-4

9. Items of work and construction details

In section 5, Construction Surveys, Method 2 shall apply. The surveys conducted by the Contractor shall include but not be limited to: (1) Those required to check all piling, excavation and earthfill slopes as work progresses to ensure such piling, excavation and slopes are maintained at those elevations specified. (2) Piling and Earthfill slopes shall be checked at least each five feet vertical interval and corrected to planned elevation and slope. (3) Those required to set “bluetops” for subgrades and finished grades of all excavations, earthfills, and appurtenances to the works.

All surveys shall proceed from benchmarks; reference points and/or stakes set or established by the Government. The benchmarks are shown on the drawings.

Initial and final surveys for determinations of final quantities will be performed by the Government.

In section 8, Payment, Method 2 shall apply.

Items of work to be performed in conformance with this specification and the construction details therefore are:

a. Bid Item 5, Construction Surveys

(1) This item shall consist of all work required by section 1 of this specification.

12FPC321B0005 Attachment 1 Specifications Page 21

(210-VI-NEH, May 2001) 8-1

Construction Specification 8—Mobilization and Demobilization

1. Scope The work consists of the mobilization and demobilization of the contractor's forces and equipment necessary for performing the work required under the contract. It does not include mobilization and demobilization for specific items of work for which payment is provided elsewhere in the contract.

Mobilization will not be considered as work in fulfilling the contract requirements for commencement of work.

2. Equipment and material Mobilization shall include all activities and associated costs for transportation of contractor's personnel, equipment, and operating supplies to the site; establishment of offices, buildings, and other necessary general facilities for the contractor's operations at the site; premiums paid for performance and payment bonds including coinsurance and reinsurance agreements as applicable; and other items specified in section 4 of this specification.

Demobilization shall include all activities and costs for transportation of personnel, equipment, and supplies not required or included in the contract from the site; including the disassembly, removal, and site cleanup of offices, buildings, and…