This document is an Invitation for Bid (IFB) issued by the Arkansas Department of Transformation and Shared Services Office of State Procurement to obtain pricing and contracts for Switched Ethernet and Dark Fiber Service to serve various Arkansas state parks, heritage sites, and tourism locations. The IFB seeks bids for Ethernet connectivity from selected parks to contractor aggregation locations and between contractor aggregation locations and state aggregation locations. It also seeks bids for dark fiber connections at several state parks. The bid opening is scheduled for August 31, 2021, and the contract term is for three years with up to four one-year renewal options.
The IFB provides detailed technical requirements for the Ethernet and dark fiber services, including network handoff specifications, latency and loss requirements, and support and installation details. Pricing is to be submitted on the provided official bid price sheet, which includes tables for the various service locations and requirements. The contracts will be awarded on a per-site basis, except for certain park locations that will be awarded to the contractor with the lowest combined cost. The state will utilize up to eight geographically dispersed aggregation sites and seeks the most cost-effective solutions from bidders.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF ARKANSAS
DEPARTMENT OF TRANSFORMATION AND SHARED SERVICES
OFFICE OF STATE PROCUREMENT
501 Woodlane St., Ste. 220 Little Rock, Arkansas 72201-1023
INVITATION FOR BID
SOLICITATION DOCUMENT
SOLICITATION INFORMATION
| Solicitation Number: |
| S000000033 |
| Solicitation Issued: |
| 08/03/2021 |
| Description: |
| Ethernet & Dark Fiber for State Parks |
| Department: |
| OSP |
SUBMISSION DEADLINE AND DELIVERY OF RESPONSE DOCUMENTS
| Bid Opening Date: |
| August 31, 2021 |
| Bid Opening Time: |
| 02:00:00 PM, Central Time |
Bid responses for this Invitation for Bid must be submitted through ARBuy, the State’s eProcurement system. It can be accessed at https://arbuy.arkansas.gov. Bids received after the submission deadline may be rejected as untimely. See section 1.2 for information regarding Live Bid Openings.
TSS OFFICE OF STATE PROCUREMENT CONTACT INFORMATION
| TSS OSP Buyer: |
| Shane Phillips |
| Buyer’s Direct Phone Number: |
| 501-324-9322 |
| Email Address: |
| Jordan.Phillips@arkansas.gov |
| TSS OSP’s Main Number: |
| 501-324-9316 |
| TSS OSP Website: |
| https://www.transform.ar.gov/procurement/ |
SECTION 1 – REQUIREMENTS
· Do not provide responses to items in this section unless specifically and expressly required.
1.1 INTRODUCTION
This Invitation for Bid (IFB) is issued by the TSS Office of State Procurement (TSS OSP) for the OSP to obtain pricing and contracts for Switched Ethernet & Dark Fiber Service to Serve Parks, Heritage, and Tourism Sites. Direct all questions, comments, or concerns you may have regarding this solicitation to the TSS Office of State Procurement, not DIS.
1.2 LIVE BID OPENING
Use the information below to view the bid opening online.
| Zoom Meeting Link: https://arkansas-gov.zoom.us/j/87935423023?pwd=QTIzanNnb2EzNloxK0lVUnlEVWttUT09 | |
| Meeting ID: 879 3542 3023 | |
| Meeting Password: 974374 | |
| Dial-In Information: 877 853 5257 US Toll-free | |
| 888 475 4499 US Toll-free |
1.3 CLARIFICATION OF SOLICITATION
A. Submit any questions requesting clarification of information contained in this Solicitation via the solicitation posting in ARBuy by midnight, Central Time on or before 08/10/2021.
1. For each question submitted, Prospective Contractor should reference the specific solicitation item number to which the question refers.
2. Prospective Contractors’ written questions will be consolidated and answered by the State as deemed appropriate. The State’s consolidated written response is anticipated to be posted to the solicitation posting in ARBuy by the close of business on 08/17/2021. If Prospective Contractor questions are unclear or non-substantive in nature, the State may request clarification of a question(s) or decline to answer.
B. The Prospective Contractor should notify the TSS OSP buyer of any term, condition, etc., that precludes the Prospective Contractor from submitting a compliant, Responsive Bid. Prospective Contractors should note that it is the responsibility of the Prospective Contractor to seek resolution of all such issues, including those relating to the terms and conditions of the contract, prior to the submission of a bid.
C. Prospective Contractors may contact the TSS OSP buyer with non-substantive questions at any time prior to the bid opening.
D. An oral statement by TSS OSP will not be part of any contract resulting from this solicitation and may not reasonably be relied on by any Prospective Contractor as an aid to interpretation unless it is reduced to writing and expressly adopted by TSS OSP.
1.4 DEFINITION OF TERMS
A. Unless otherwise defined herein, all terms defined in Arkansas Procurement Law have the same meaning herein.
B. “Prospective Contractor” means a responsible bidder who submits a Responsive Bid in response to this solicitation.
C. The terms “Invitation For Bid”, “IFB” and “Solicitation” are used synonymously in this document.
D. “Responsive Bid” means a bid submitted in response to this solicitation that conforms in all material respects to this IFB.
E. “Shall” and “Must” mean the imperative and are used to identify requirements.
F. “Requirement” means something required.
G. “Specification” means any technical or purchase description or other description of the physical or functional characteristics, or of the nature, of a commodity or service. “Specification” may include a description of any requirement for inspecting, testing, or preparing a commodity or service for delivery.
H. “State” means the State of Arkansas. When the term “State” is used herein to reference any obligation of the State under a contract that results from this solicitation, that obligation is limited to the Department using such a contract.
1.5 BACKGROUND FOR ETHERNET SERVICES
A. Consistent with the State of Arkansas’ commitment to public-private partnerships, DIS seeks bids for Ethernet connectivity from selected parks to Contractor aggregation locations and between Contractor aggregation locations and State aggregation locations. IFB SP-20-0060 for High Bandwidth Transport and Internet was issued and awarded a year ago and contains the majority of the network needed to serve K12 schools, including the vendor aggregation circuits to State aggregation sites, the backbone connecting State aggregation sites, and internet access. IFB SP-18-0098 and SP-18-0116 for agency locations were issued and awarded three years ago. The circuits being bid here supplement what was included in the SP-20-0060, SP-18-0098, and SP-18-0116 solicitations. DIS intends to design the services that are bid here and award in the most cost-effective configuration utilizing any Ethernet connectivity awarded from the SP-20-0060, SP-18-0098, and SP-18-0116.
B. DIS will utilize up to eight (8) State aggregation sites, geographically dispersed throughout Arkansas. These State aggregation sites include two (2) State data centers and six (6) Arkansas Research & Education Optical Network (ARE-ON) huts. The ARE- ON huts are State assets with environmental controls, physical security, battery power, emergency generators, 24-hour access, and other elements needed for the latest technology and network designs. The eight (8) State aggregation sites are listed in Figure A:
Figure A, State Aggregation Sites
| Location Code |
| Location Name |
| Address |
| City |
| Zip |
| NPA/NXX |
| ALMA |
| ARE-ON Alma |
| 6803 Alma Hwy |
| Van Buren |
| 72956 |
| 479/474 |
| HOPE |
| ARE-ON Hope |
| #1 358 Hwy 174 N |
| Hope |
| 71801 |
| 870/777 |
| LTRKARXZ |
| Little Rock Datacenter -West (DIS) |
| 11025 Anderson Drive |
| Little Rock |
| 72212 |
| 501/225 |
| LWLLAR66 |
| Arkansas State Police Datacenter (ASP) |
| 1120 Monroe Avenue |
| Lowell |
| 72745 |
| 479/751 |
| MTHO |
| ARE-ON Mountain Home |
| 195 High Avenue |
| Mountain Home |
| 72653 |
| 870/425 |
| NLRK |
| ARE-ON North Little Rock |
| 2809 Eanes Road |
| North Little Rock |
| 72117 |
| 501/758 |
| NWPT |
| ARE-ON Newport |
| 3714 Comet |
| Newport |
| 72212 |
| 870/523 |
| PNBL |
| ARE-ON Pine Bluff |
| 2300 W 18th Ave |
| Pine Bluff |
| 71603 |
| 870/534 |
C. Six (6) of the State aggregation sites are owned by the Arkansas Research & Education Optical Network (ARE-ON). These locations were funded by the Broadband Technology Opportunities Program (BTOP) grant money, and therefore are subject to the following program requirement: “Recipients should allow colocation by interconnecting parties, on a first-come, first-served basis, in any equipment or facilities funded by BTOP, where and when possible. Recipients should expect customers to request a variety of colocation services, including secured space separated from the owner’s equipment, 24-hour access, escorted or unescorted access, and AC and/or DC.” The AREON sites can only provide -48volt DC power.
D. Prospective Contractors may find additional information regarding the BTOP program and applicable rules at the following link: http://www.ntia.doc.gov/files/ntia/publications/fr_bbnofa_090709.pdf.
E. The Prospective Contractor may bid on any or all addresses and services in the Official Bid Price Sheet. For connectivity services in Table 3 the contractor must bid all bandwidth for each address bid, If the Prospective Contractor does not desire to bid service in an address, the Prospective Contractor may show “no bid” on the price sheet. Leaving a line blank on the price sheet will be interpreted as no bid. The bid will be awarded on a per site basis except for the two Mount Magazine State Park sites and the two Village Creek State Park sites. The Mount Magazine and Village Creek sites will be awarded to the Contractor with the lowest combined cost for the two sites in the respective park. In the price sheet Table 3 each pair as shown will be awarded to a single contractor.
1.6 DARK FIBER SERVICES
A. DIS seeks bids for dark fiber to connect the cabins at the Lake Ouachita State Park, the Crowley’s Ridge State Park, the Lake Chicot State Park, and the Village Creek State Park back to the Visitor Information Center at each park. The contractor responses are to be shown in Table 10 of the Official Bid Price Sheet. Also, we are bidding point to point dark fiber between the Mississippi River State Park Visitor Center and the Maintenance Shop and between the Parkin Archeological State Park Visitor Center and the Parkin Archeological State Park Maintenance Shop. The contractor responses for these locations are to be shown in Table 11 of the Official Bid Price Sheet.
B. At the Lake Ouachita State Park, the Prospective Contractor must install 48 strand single mode (SM) fiber from the Visitor Information Center (VIC) to a Splice Junction Box located in front of the cabins in a 2” conduit system. Total footage of 48 strands is approximately 2000’. A 48 port Wall Mount LIU will need to be installed in the VIC to terminate the fiber. Six (6) Quazite pull boxes will be needed at a minimum, one (1) 150’ road bore, and 6 driveways will need to be cut and repatched. From the junction box in front of the cabins a conduit system will need to be installed to each of the eight (8) cabins. A six (6) strand Single Mode Fiber is to be installed in each cabin. All cabins will need a wall mount LIU installed. All fiber is to be Outdoor Rated OS1-2 Single mode 1310 or 1550nm. All Fiber is to be terminated with ST Connectors. Attachment A provides a brochure with a high-level view of the park. All road bores, street cuts and patching must be covered in pricing provided on the Official Bid Price Sheet. Contractor must provide test reports on all strands of fiber after completion.
C. At the Lake Chicot State Park, the Prospective Contractor must provide labor and materials to install a 48-strand single mode (SM) fiber from the Visitor Information Center (VIC) to the splice point Quazite box at approximately 1000’ in a conduit system. Install from the splice point box 6 strand single mode fiber in a conduit system to each of the seven (7) pairs of cabins (each pair gets 6 strands). All fiber is to be Outdoor Rated OS1-2 Single mode 1310 or 1550nm. Provide all trenching, Quazite pull boxes, and conduit system from the VIC to each of the cabins. Install all fiber LIU’s as needed and terminate with ST connectors. Total splice boxes are expected to be eight (8). One (1) road bore may be required if the park doesn’t want the street cut. Attachment B provides a high-level view of the park. All road bores, street cuts and patching must be covered in pricing provided on the Official Bid Price Sheet. Contractor must provide test reports on all strands of fiber after completion.
D. At the Crowley’s Ridge State Park the Prospective Contractor must provide labor and materials to install a 24 strand single mode (SM) fiber from the Visitor Information Center (VIC) to the new Snack Bar/Bathhouse IDF location at approx.1500ft. Provide trenching, 2” PVC conduit and Quazite pull boxes as needed. Install a 6-strand single mode (SM) fiber from Bathhouse IDF to the Group Lodging main building at approx.1600ft. Provide trenching, 2” PVC conduit and Quazite pull boxes as needed. Provide road bore under Hwy.168 going to Group Lodging main building. Install a small network cabinet at the main building in Group Lodging to terminate the fiber. Install a 6-strand single mode fiber from Bathhouse IDF to the two pairs of cabins at approx.1650ft (each pair of cabins get 6 strands). All fiber is to be Outdoor Rated OS1-2 Single mode 1310 or 1550nm. Provide trenching, 2” PVC conduit and Quazite boxes as needed. Provide external conduit work at cabin #2 to enter the network closet. Provide wall mounted LIUs each location and terminate all strands of fiber in ST connectors. Attachment C provides the layout of the park. All cost associated with the work described in this section must be included on the Official Bid Price Sheet. Contractor must provide test reports on all strands of fiber after completion.
E. At the Village Creek State Park, the Prospective Contractor is asked to provide 24 strands of single mode (SM) fiber from the Village Creek Golf Pro Shop to Cabin #6. From Cabin #6 take four (4) strands to each of Cabins # 2, 3, 4, 5, and 7. Provide 24 strands of single SM fiber from Cabin #6 across the road to Cabin #1. From Cabin #1 provide four (4) strand SM fiber to each of Cabins # 8, 9, and 10. The total 48 strand footage is approximately 300 feet, and the 24-strand footage is approximately 200 feet. The total four (4) strand footage is approximately 1500 feet. Any access roads will need to be cut and patched. All fiber to be single mode outdoor rated and placed in a conduit no less 2” in diameter. All fiber to be placed in Wall Mount LIU’s and terminated with ST connectors. Quazite boxes should be placed every 200’ or as needed. Attachment D provides a brochure that includes a high-level view of the park. All cost associated with the work described in this section must be included on the Official Bid Price Sheet. Contractor must provide test reports on all strands of fiber after completion.
F. Between the Mississippi River State Park Visitor Center and the Mississippi River State Park Maintenance Shop install 24 strands of single mode (SM) dark fiber. Provide trenching, 2” PVC conduit and Quazite pull boxes at every 200 feet and as needed. The total distance for trenching, fiber, and conduit is approximately 2300 feet. Terminate all strands of fiber with ST connectors in wall mounted LIUs. Provide test reports on all strands of fiber after completion. Attachment E (1) provides the park brochure, and Attachment E (2) shows a proposed fiber route. All cost associated with the work described in this section must be included on the Official Bid Price Sheet. Contractor must provide test reports on all strands of fiber after completion.
G. Between the Parkin Archeological State Park Visitors Center and the Parkin Archeological State Park Maintenance Shop install 24 strands of single mode (SM) dark fiber. Provide trenching, 2” PVC conduit and Quazite pull boxes every 200 feet and as needed. The total distance for trenching, fiber, and conduit is approximately 2300 feet. A 125-foot road bore will be required to get under the highway. Terminate all strands of fiber with ST connectors in wall mounted LIUs. Provide test reports on all strands of fiber after completion. Attachment F(1) provides the park brochure, and Attachment F(2) shows a proposed fiber route. All cost associated with the work described in this section must be included on the Official Bid Price Sheet. Contractor must provide test reports on all strands of fiber after completion.
1.7 SERVICE TECHNICAL REQUIREMENTS
A. The proposed Ethernet services must support the transport of the existing applications and related data currently being utilized by the Arkansas parks community. This normally requires three (3) VLANs at each park. The Contractor’s proposed solutions(s) must allow the existing applications to function normally and perform properly, including but not limited to:
· Internet access for Parks employees and guests
· Parks administrative applications
· Credit card transactions
· Network Monitoring
· Security Monitoring
· Internet Content Filtering
The service proposed and provided by the Contractor(s) must support virtual private network (VPN) traffic between the parks and the State aggregation sites for some of the above applications as determined by DIS. At a State Parks site three (3) VLANs are normal.
B. The network handoff for all Ethernet connections must meet the following requirements:
· 100Mbps and below must be 100BaseT (copper) connections.
· Between 100Mbps and 1Gbps must be 1000BaseSX unless specified differently by the customer when the service is ordered.
· Greater than 1Gbps must be 10GBase-SR unless specified differently by the customer when the service is ordered.
· Greater than 10G must be 100GBase-SR single mode unless specified differently by the customer when the service is ordered.
C. The Contractor’s provided telecommunications services must be compatible with customer public or private IPv4 and IPv6 addressing.
D. The basic design for this network is one that will, at some sites, support applications that require minimal loss and low latency. The Ethernet Class of Service (CoS) must be provisioned as Business Critical – Medium. DIS is currently utilizing only two priority queues, “EF” and “AF31” along with the standard “Best Effort” class. Future applications may require utilization of additional priority queues. The Contractor’s infrastructure must honor and act upon packets or frames with traditional QoS or CoS markings. The Contractor shall support a minimum of four (4) priority queues and the “best effort” class. Official Price Sheet Table 8 may be expanded and modified by the Contractor to show all the options and cost for the features associated with the service bid.
E. DIS prefers Layer 2 switched connectivity. Where a Contractor must provide Layer 3 services inside their network, the hand-offs to the State must be Layer 2.
F. If an agency needs a private network address as specified in Request for Comments RFC 1918 (Network Address Translation), the State will allocate IP addresses out of the RFC 1918 address space. In this case, Contractor(s) must support private and public IP addresses equally. If RFC 1918 addresses must traverse the internet, it will be accomplished within a site to site VPN tunnel.
G. Each proposed service demarcation point must be clearly labeled with applicable Circuit Identification.
H. All Contractor Ethernet connections must be configured to support IEEE 802.1Q “tagging”.
I. All proposed bandwidths must be symmetrical.
J. Contractors bidding on this service must bid Ethernet or other comparable technology for connectivity from the park to a Contractor’s aggregation location, then from the Contractor’s aggregation location to a State aggregation site. Contractors may bid on connecting to one, some, or all of the State aggregation sites listed in the IFB. Contractors must establish connectivity in the most cost-effective manner possible. The cost for this connectivity must be shown on Official Price Sheet Table 3 and Official Price Sheet Table 5. Service will be terminated in State-provided routers located in State aggregation sites.
K. Contractor(s) should choose one, some, or all of the eight (8) State aggregation sites listed in Figure A above as their transport end point for any of the location addresses. Contractor(s) should choose State aggregation points that produce the most cost-effective solution for each location address.
L. If awarded multiple park addresses, the Contractor must consolidate transport from multiple parks on the connection between the Contractor aggregation location and the State aggregation site. The State’s expectation is that individual aggregation circuits will be used for a combination of school, rural health, and State agency transport. The State will apportion the bandwidth on the aggregation circuits, and backbone circuits, individually between federal programs (E-rate and Rural Health) and other entities. Where the circuits provide transport to different typed of entities, only a decimal part of the Contractor cost will be used to file for E-rate reimbursement for each circuit including internet. There should be no Contractor input needed for the State to make this apportionment. State of Arkansas only applies for E-rate and Rural Health Care discounts for bandwidth/connectivity delivered to eligible recipients of service.
1.8 SUPPORT REQUIREMENTS
A. Restoration of service after catastrophic events such as fires, storms, earthquakes, or accidental damage must be on an around-the-clock basis. (24 hours a day/7 days a week).
B. The Prospective Contractor shall accept trouble reports from DIS in conjunction with the services being provided under this contract. There must not be an additional charge for this service.
C. The Contractor shall provide the one point of contact where all troubles will be reported for any of the services or facilities specified in this IFB. The personnel at this location shall be responsible for coordinating all efforts to correct the trouble and will update DIS at intervals to be established by DIS and the Contractor.
D. The Contractor shall provide a toll-free number, which must be attended 24 hours a day, 7 days a week, with qualified personnel to handle trouble reports from the State. Under normal circumstances, as opposed to catastrophic events above, DIS expects trouble to be cleared within 8 business hours.
E. The Contractor shall specify or provide an overview of how they handle critical outages. For the purpose of this contract, a critical outage is defined by DIS as an outage that has denied connectivity to a large segment of the State’s customers or isolated a critical site or service. Examples of a critical outage include, but is not limited to, an ice storm, earthquake, contractor fiber cut, or tornado disrupting State operations, etc.
F. The Contractor shall provide an escalation procedure with contact information (i.e. names, titles, phone numbers, and pager/cell phone numbers) for 24/7 support for all service types bid. DIS must be able to initiate the escalation procedure 24 hours a day, 7 days a week for critical outages.
1.9 INSTALLATION
A. Contractor installation must include all required products and services needed to install a functional service.
B. Any installation costs listed on the Official Bid Price Sheet must also include all costs associated with site preparation (wiring, poles [if any], equipment set up, safety requirements, cleanup, etc.) to fully install the site and restore the site to pre-installation conditions as determined by the site owner.
C. Contractor shall conduct worksite cleanup. All packing crates, boxes, paper, packing material, and all other such extraneous material must be removed from the premises by the Contractor at the Contractor’s expense after installation.
D. Contractor will not be responsible for paying colocation fees inside the State sites. Installation of external towers, antennae, etc., are not expected.
E. Contractor shall un-box and install Contractor equipment in locations designated by DIS.
F. The State will perform all customer site preparation activities including, but not limited to, power, ventilation, proper environmental conditions as per the equipment manufacturer’s specifications, and the installation of equipment racks.
G. Contractor shall conduct technical interviews relating to Contractor needs at the State’s site. Entrance facilities (typically conduit) are the responsibility of the owner/occupant of the property where services are being installed. Contractor(s) shall meet with site contact (owner/occupant of property where services are being installed) to arrange and assign necessary site preparation responsibilities (conduit, power, backboard, etc.) in a mutually agreed upon time frame to ensure established due dates are met. Contractor(s) shall coordinate with State sites for equipment installations.
H. Contractor shall coordinate with DIS or their Contractors to facilitate uninterrupted services to each site.
I. DIS will provide on-site personnel to assist with the installation as deemed necessary by DIS.
J. DIS will provide Contractor building access necessary to implement the service.
K. DIS will ensure circuit demarcation points are clearly identified.
L. The Contractor shall provide experienced and knowledgeable onsite support during installation, as deemed necessary by DIS. Onsite support must be at no additional cost to DIS.
M. Contractor must comply with all applicable codes, licenses, certifications, and standards in the State of Arkansas as it relates to the proposed installation services.
N. Installation Involving Building Modification:
1. Contractor(s) must have Arkansas Contractors Licenses for any installation services that modify existing building structures.
2. State Agencies: Installation services that do not modify existing building structures as covered under Arkansas Building Authority Regulations are allowed for State agencies. Any installation services over $35,000 that modify existing building structures shall be regulated by Division of Building Authority (DBA) regulations.
3. Any other entity utilizing this contract shall follow their rules and regulations regarding installation services.
O. Contractor shall only accept move, add, and change orders from authorized DIS employees via email or online only.
P. Installation shall be the sole responsibility of the Contractor.
Q. Contractor shall provide installation services in a manner and under a timeframe designed to minimize service disruption.
1. Contractor shall coordinate with DIS throughout installation so that affected DIS customers can be notified and emergency alternative communications can be provided by DIS, if necessary.
2. Services must be performed on a schedule that supports DIS and DIS’ customers’ operational needs, and may include nights, weekends, and holidays.
3. Within fourteen (14) days of contract award, Contractor shall work with DIS to provide an installation plan for the services.
4. The installation plan provided to DIS must be negotiable and subject to modification and approval by DIS.
5. Contractor will receive written approval by DIS prior to commencement of installation.
R. The Contractor shall notify both the ordering entity and DIS in writing within ten (10) business days after receipt of order if the Contractor is unable to provide services ordered that were awarded as a result of this IFB. DIS may, at their discretion, notify the Office of State Procurement (OSP)
1.10 TESTING & CUTOVER
A. Contractor shall perform testing after installation of services to ensure said services are operating properly.
B. Contractor shall provide documentation of test results within five (5) business days to DIS.Network.implementation@arkansas.gov if so requested in writing by DIS.
C. Installation will not be considered satisfactorily complete until the Contractor has received notification from DIS that the installation is accepted, and the installed service is working.
D. The Contractor shall be the solely responsible for testing.
E. The Contractor shall provide testing services in a manner and timeframe designed to minimize disruption to purchasing entities:
1. The Contractor shall coordinate with DIS throughout testing so that affected DIS customers can be notified and emergency alternative communications can be provided by DIS, if necessary.
2. Services must be performed on a schedule that supports DIS and DIS’ customers’ operational needs and may include nights, weekends, and holidays.
F. Acceptance Testing:
1. DIS will test the system in a live DIS-provided environment for a maximum of thirty (30) consecutive calendar days.
2. DIS shall not accept the service until the availability of 99.95% is met for thirty (30) consecutive calendar days max.
3. If the service up-time falls below 99.95% during DIS testing process, DIS’s testing measurement period shall be restarted beginning with the first day of the thirty (30) consecutive calendar days max. DIS shall continue testing until either the 99.95% availability requirement is met or ninety (90) consecutive calendar days max have passed since the testing process began.
4. If the service fails to meet the availability requirement within ninety (90) calendar days after the cutover date, DIS shall continue acceptance testing on a daily basis upon written mutual agreement of all parties.
5. If the service fails acceptance testing, DIS will notify the Contractor of the deficiencies in writing and may submit a below standard State Contractor Performance Report (VPR).
1.11 SUPPORT SERVICES
A. The Contractor shall provide the State with an Account Manager that will be the single point of contact for account issues and support escalation requests within thirty (30) days of contract award.
B. Contractor shall only take direction from DIS as the customer of record. End using entities must go through DIS with their support issues.
C. Contractor shall own and maintain trouble tickets reported by DIS until trouble tickets are resolved.
D. Toll-Free Telephone Support Center:
1. Contractor shall provide toll-free telephone support.
2. Telephone support must be available twenty-four (24) hours a day, seven (7) days per week to begin the restoration process. If access to a facility is required, the ticket may be placed on hold until access can be granted.
3. Contractor’s telephone support center staff shall be fluent in the English language.
4. Contractor’s telephone support center should be located within the continental United States of America.
5. Contractor shall provide, no later than thirty (30) calendar days from contract award, the toll-free telephone support center number. Contractor shall email the toll-free number to dis.network.implementation@arkansas.gov . Prospective Contractors should not include this with their bid response
E. Contractor’s staff shall log trouble calls including, at a minimum, the following information:
1. DIS Ticket Number (to be issued by DIS and provided to the Contractor when reporting trouble).
2. Date & Time of call
3. Circuit ID(s)
4. Apparent nature of trouble
5. Arrival time of maintenance personnel (if applicable)
6. Date/time trouble was cleared
7. Cause of trouble
F. Online Trouble Ticket Reporting System Availability:
1. Contractor is expected to provide an online trouble ticket reporting system. All tickets entered by Contractor’s personnel via telephone or entered by DIS via the Contractor’s web portal must be viewable by DIS.
2. Online trouble reporting system should include, but not be limited to, the following functionality:
a. Ability to create trouble tickets on new or recurring problem(s)
b. Ability to create tickets for informational and test assist purposes.
c. Ability to view trouble ticket information, including but not limited to the information listed in Section 1.11(E).
d. Ability to monitor the status of open tickets and update open tickets.
e. Ability to generate trouble history reports for chronic problem isolation and monitoring with detailed summary.
f. Ability to generate detailed performance overview reports
g. Ability to send email notifications to appropriate parties of trouble ticket status changes and updates.
G. Contractor shall participate in Contractor meetings as part of DIS’s Contractor management program to review service results and arrive at remedies to improve or correct deficiencies. Contractor meetings may be monthly or quarterly.
1. The agenda and location for each meeting will be sent out in advance.
2. Contractor shall name a single point of contact. This contact shall address all agenda items on- site at a facility provided by DIS, or available by Contractor-provided and Contractor-paid conference bridge and/or web meeting, unless otherwise authorized in writing by DIS. This contact shall be the central point of contact for advanced escalation of all issues and shall be responsible for all aspects of the contract, including but not limited to Contractor performance.
H. Contractor shall provide, no later than fourteen (14) calendar days following contract award, the following information. Contractor shall email the information to dis.network.implementation@arkansas.gov. Prospective Contractors should not include this with their bid response.
1. Trouble notifications and response procedures, including time, method, and frequency of Contractor acknowledgement of DIS trouble tickets. All response and resolution times in Figure B: Severity Levels must be applied.
2. Contact information for Contractor’s assigned account specific resources for administrative and technical support to assist in initiating orders, resolving service problems, trouble escalation, billing errors, etc. Personnel should be familiar with the State Network and DIS processes. Local resources are preferred.
I. Contractor shall provide, no later than thirty (30) calendar days following contract award, the following information. Contractor shall email the information to dis.network.implementation@arkansas.gov & dis.contracts@arkansas.com Prospective Contractors should not include this with their bid response
1. Information for accessing the Contractor’s trouble reporting system.
2. Contact information for an Account Manager where all troubles will be reported for any of the services or facilities specified in this IFB. The personnel at this location shall be responsible for coordinating all efforts to correct troubles and will update DIS at intervals to be established by DIS and the Contractor
J. Two weeks prior to monthly or quarterly Contractor meetings, Contractor shall provide a report in “.xls” format, via email to the designated DIS staff, of the diagnostic findings, including at a minimum:
1. Trouble ID
2. Time and date the trouble is reported
3. Time and date the trouble is resolved.
1.12 OUTAGES
A. Catastrophic Events
1. Restoration of service after catastrophic events such as fires, storms, earthquakes, or accidental damage must be on an around-the-clock basis until service is restored.
2. Contractor shall describe the anticipated level of response and response procedures in case of a catastrophe. Contractor shall email the information to dis.network.implementation@arkansas.gov within thirty (30) calendar days of contract award for DIS approval. Prospective Contractors should not include this with their bid response.
B. Figure B below defines outages and specifies the maximum response time and resolution times based on level of severity.
1. DIS shall have the right to further define outage terms as deemed necessary during the course of the contract.
2. “Response time” must be calculated as the time from which the outage is reported until the time maintenance personnel arrive on site.
3. “Resolution time” must be calculated as the time from which the trouble ticket is opened with the Contractor until the trouble is cleared and notification is received by DIS from the Contractor.
4. Response times may be met via remote maintenance procedures.
C. DIS business hours are 8:00 a.m. to 5:00 p.m. (Central Time) Monday through Friday excluding State holidays, https://portal.arkansas.gov/pages/State-employees/. However, there are critical locations which operate around the clock and require 7x24x365 Contractor support.
D. Trouble Ticket Reports Two weeks prior to monthly or quarterly Contractor meetings, Contractor shall provide a report in “.xls” format, via email to the designated DIS staff, of the diagnostic findings, including at a minimum:
1. Trouble ID
2. Trouble circuit ID
3. Time and date the trouble is reported
4. Time and date the trouble is resolved
5. Trouble resolution
Figure B: Severity Levels Severity Level
Definitions Maximum Response Initial Time
Resolution Time
Critical outages and situations when network services are down and DIS customers are unable to use/access the network.
Four (4) hours Around the clock As quickly as possible, which on average must not exceed four (4) business hours, unless otherwise authorized in writing by the DIS.
For any critical outage that cannot be fixed remotely, DIS shall have the right to require an on-site response. DIS requested Contractor on-site response time should be no more than four (4) business from time of request.
Major outages and/or repeated failure of service preventing its successful operation. The service may operate but is severely restricted (i.e. slow response, intermittent but repeated inaccessibility, etc.).
Six (6) business hours
As quickly as possible, which on average must not exceed six (6) business hours, unless otherwise authorized in writing by the DIS. DIS shall retain the right to escalate Level 2 outages to Level 1 at its discretion.
For any major outage that cannot be fixed remotely, DIS shall have the right to require an on-site response. DIS requested Contractor on-site response time should be no more than six (6) business hours from time of request.
Minor outages and/or a problem that exists with the service, but the majority of the functions/services are still usable, and some circumvention may be required to provide service.
Eight (8) business hours
As quickly as possible, which on average shall not exceed eight (8) business hours, unless otherwise authorized in writing by the DIS.
E. Contractor shall provide samples of available performance and maintenance reports that are available to DIS for the services bid and describe how they can be accessed by DIS (i.e., Web Interface, telephone or other electronic access). Performance and maintenance reports must include, but are not limited to:
1. Network Provisioning Performance
2. Network Maintenance Performance
3. Service Billing Performance
Contractor shall email the information to dis.network.implementation@arkansas.gov no later than thirty (30) calendar days following contract award. Prospective Contractors should not include this with their bid response.
F. Contractor’s Service Manager shall be required to prepare a Service Action Plan (SAP) for complex outstanding service issues if requested to do so by DIS. The SAP must be agreed upon by DIS. DIS shall conduct reviews to audit progress in implementing Service Action Plans in order to document and measure progress toward the desired outcome.
G. Contractor shall submit a sample Service Action Plan (SAP). Contractor shall email the information to dis.network.implementation@arkansas.gov no later than thirty (30) calendar days following contract award. Prospective Contractors should not include this with their bid response.
H. Contractor(s) shall comply with the Telecommunications Service Priority (TSP) Program, a Federal Communications Commission (FCC) mandate for prioritizing service requests by identifying those services critical to National Security and Emergency Preparedness (NS/EP) and be in compliance with all Arkansas Public Service Commission and FCC Requirements.
1.13 SCHEDULE
A. Contractor shall submit a proposed timeline schedule, in calendar days, of the time required for the various components consisting of: facilities check, design, engineering, construction, central office or point of presence upgrades, installation, training, testing, and service acceptance to provide for a cutover date. Contractor shall email the information to & dis.contracts@arkansas.gov no later than thirty (30) calendar days following contract award. Contractor should not include this with their bid response.
B. If the proposed timeline schedule exceeds the requested initial installation interval of thirty (30) calendar days or the proposed initial Contractor service date, it must be subject to DIS approval.
C. No later than thirty (30) calendar days following contract award, DIS and the Contractor shall negotiate a mutually agreeable installation plan for the services.
D. The service must be installed in a manner and within a time frame designed to minimize disruption of normal functions of all entities.
E. The conversion of service must be performed on a schedule that supports DIS and their customers’ operational needs and may include nights, weekends, and holidays.
1.14 DELIVERY AND PROVISIONING OF SERVICE
A. The Contractor shall deliver service within service interval business days after receipt of the order (ARO). Extended delivery dates may be considered when in the best interest of the State, including situations involving crossing public rights-of-way. DIS shall have final determination into which of the following scenarios a service falls.
Figure C, Installation Intervals
Scenario
| Time to service interval |
| Deadline for Extension Request |
| Existing Fiber to site (if owned by awardee) or direct line of sight available for Fixed wireless or other technology |
| Up to 30 calendar days |
| Up to day 15 ARO |
Minor Build includes locations with spare fiber to the customer demarcation point and no major equipment installation is required by the awardee in the Central Office (CO) or inter-office.
Up to 60 calendar days Up to day 15 ARO
Major Build includes locations where construction is required including up to half mile of new fiber, multiple splice points and/or placing CO or inter-office equipment.
Up to 90 calendar days Up to day 60 ARO
Complex Build includes locations involving permits, conduit, and more than a half mile of new fiber and/or major central office projects including installing core routers
Up to 240 calendar days Up to day 210 ARO
B. Purchasing entities must go through DIS to acquire services. Contractor shall only accept orders in reference to the contract from DIS.
C. DIS will communicate in their purchase order the option to have Contractor equipment delivered to the end user service address or to DIS’s central warehouse at:
Arkansas Division of Information Systems One Capitol Mall Room 3C014 Little Rock, AR 72201
D. All deliveries must be made during normal State business hours and within the agreed upon number of days unless otherwise arranged and coordinated with DIS. The Contractor shall give DIS immediate notice of any anticipated delays or plant shutdowns that will affect the delivery requirement.
E. The Contractor shall be responsible for damage to property at agency facilities during installation of system and for damage to Contractor owned property caused by the Contractor.
F. If any agreed upon or established due date or interval is subject to being missed by more than three (3) business days, DIS must be notified immediately and a new due date negotiated. A planned due date must be established for tracking purposes. If an acceptable due date cannot be established, DIS may cancel the order and alternate methods of procurement may be pursued.
1.15 FORCE MAJURE
Except for payment of amounts due, neither party will be liable for any delay, failure in performance, loss, or damage due to fire, explosion, cable/fiber cuts, power blackout, earthquake, flood, embargo, acts of civil or military authority, war, terrorism, acts of God, acts of public enemy, acts of regulatory or governmental agencies, delays from third parties deterring the Contractor from obtaining necessary licensing/construction permits/right of ways, or other causes beyond such party’s reasonable control.
1.16 AWARD CRITERIA
A. Ethernet Transport The awards for Ethernet service from the parks site to the State aggregation site will be awarded by address based on the lowest average cost over 36 months. If a Contractor bids service to a park address, the Contractor shall provide pricing for all bandwidths associated with that address on Price Sheet Table 3 and Price Sheet Table 5 (unless already awarded the connectivity from the contractor aggregation site to the State aggregation site from bid SP-20-0060). The awardee for each address will be determined based on the lowest average cost per Mbps for that address over 36 months. The Contractor shall bid all required speeds from the Contractor aggregation location to at least one State aggregation site on Table 5 but are encouraged to bid to more than one State aggregation site. If the Contractor bids to more than one State aggregation site on Table 5, the State aggregation site with the lowest average cost per Mbps will be used to determine low cost.
B. Future new locations not bid The Contractor with the lowest average cost per Mbps of all Contractors for all locations who bid in that exchange will be given the first right of refusal to furnish service to the new location at the current prices quoted for the address where the Contractor was the lowest. Each subsequent low bidder will be given next right of refusal. If a Contractor cannot be obtained from the existing Contractor pool for that exchange, the State will then procure by the appropriate procurement vehicle based on the anticipated dollar amount.
1.17 BILLING PROCESS AND MANAGEMENT
A. Billing Errors Contractor shall describe their process for resolving billing errors and the timeline for correcting billing errors. Contractor shall send the information to dis.contracts@arkansas.gov no later than thirty (30) days following contract award. Prospective Contractors should not include this with their bid response.
B. Billing Review
1. Contractor shall conduct a first bill review within thirty (30) days of the first bill cycle of each type of service to verify correctness of contract billing. It is the Contractor’s responsibility to initiate and coordinate this meeting by emailing dis.contracts@arkansas.gov. Failure to do so may result in a negative Vendor Performance Report (VPR).
2. At least one (1) Contractor representative must be on site at DIS for the bill review meeting unless permission has been given by email from DIS to not be on-site. The Contractor representative will provide at their expense a conference bridge or web-meeting allowing all necessary Contractor personnel to participate.
3. If incorrect rates or quantities are found, DIS must be notified and they must be corrected no later than the fourth (4th) billing cycle after error is found. The State shall have the right to withhold payment until corrections have been made and a corrected invoice is received.
4. All billing errors found in the first bill review or in a later bill review by DIS or the Contractor must be credited back to the original date of the error, but not beyond the beginning of the corresponding contract.
5. Contractor shall not impose any time restrictions upon DIS to identify billing errors and request a credit or refund.
C. Billing Invoices
1. Contractor shall set up and maintain account billing on an ongoing basis for no additional charge as directed by DIS to facilitate cost accounting and cost recovery.
2. Each service site billed on the Contractor invoice must have a service site address plus circuit ID, telephone number, or equivalent which will be used to identify the site and/or DIS customer being billed.
3. Contractor shall invoice DIS by line of service or speed and in the account format directed by DIS. An invoice with only the address, account number and amount shall not be acceptable.
D. Billing Discontinuance Contractor shall stop billing for service on the day notification to disconnect service is received or on a future date if requested. If the Contractor’s billing system does not allow this, credits must be issued within two billing cycles without DIS having to review each invoice and ask for the credits.
E. Billing (End to End Circuit) End to End Circuit billing must be provided on the same invoice. If manual billing or special billing is required by the Contractor to provide End to End Circuit billing, the Contractor must provide this billing free of charge. Failure to do so will result in negative Vendor Performance Reports.
F. Billing (Contract Rates) Detailed Contract Rate must match each line item bid as it appears on the monthly billing Statement and electronic media.
G. Billing Compatibility Detailed information in any form must be compatible with the current DIS tele-management system (currently Calero previously known as Compco).
H. Billing Fields Required The following fields for services, equipment, and onetime charges must be provided on each invoice if applicable:
· Contractor Name
· Invoice Number
· Account Number
· Contractor Billing Date
· Circuit Number
· Location Name
· Contract Number
· Address
· City
· Zip
· Zip4
· State
· Product Description
· Speed Mbps
· Circuit Charge Amount
· Circuit Tax Amount
· Circuit Fees Amount
· Total Bill Amount
I. Contractor shall work with DIS resources to establish some form of mutually acceptable electronic billing media, such as excel or file transfer within six (6) months after contract award. The media must also be in a mutually agreeable file format.
J. Contractor(s) must identify and provide the names of their company’s resources who will be responsible for this requirement no later than thirty (30) days after contract award to dis.contracts@arkansas.gov.
1.18 PAYMENT AND INVOICE PROVISIONS
A. Forward invoices to:
Arkansas Division of Information Systems Attention: Accounts Payable P.O. Box 3155 Little Rock, AR 72203-3155
B. By mutual agreement, invoices may be emailed to dis.accounts.receivable@arkansas.gov.
C. Payment will be made in accordance with applicable State of Arkansas accounting procedures upon acceptance of goods and services by the agency.
D. Do not invoice the State in advance of delivery and acceptance of any goods or services.
E. Payment will be made only after the Contractor has successfully satisfied the agency as to the reliability and effectiveness of the goods or services purchased as a whole.
F. The Contractor should invoice the agency by an itemized list of charges. The agency’s Purchase Order Number and/or the Contract Number should be referenced on each invoice.
G. Other sections of this Bid Solicitation may contain additional requirements for invoicing
1.19 DELIVERY: FOB DESTINATION
A. The Department requests delivery within thirty (30) calendar days after ordering. If this delivery date cannot be met, the Prospective Contractor must state the alternate number of days required to begin the service and/or place the commodity in the ordering Department’s designated location. (See Questions section of the Solicitation posting in ARBuy.) Failure to state the alternate delivery time obligates the Contractor to complete delivery by the Department’s requested date. Extended delivery dates may be considered when in the best interest of the State.
B. All deliveries must be…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .