Runway+Marking+S-100.pdf
PDF 121 KB Posted
- Solicitation number
- 645-DOTRFB-2920-2027
- Issued by
- Iowa
About this file
This file contains technical specifications for Item S-100 (Safety Plan, Traffic Control and Mobilization) issued by the Iowa Department of Transportation for runway marking projects at airports in Cresco, Rockwell City, and Winterset. The specifications establish mandatory requirements for contractor-submitted construction safety plans, which must be submitted within ten days after the preconstruction conference but before construction commences. The safety plan must address points of contact for the Owner, Engineer, FAA, and Contractor; emergency notification procedures; work sequence and staging plans; traffic control measures compliant with FAA Advisory Circular 150/5370-2E; foreign object debris (FOD) control procedures in Airport Operations Areas; onsite safety inspections and remediation; personnel training on safety procedures; and 48-hour advance notice to the Owner for any changes in construction operations requiring NOTAM issuance. Traffic control requirements mandate that the contractor furnish, erect, operate, maintain, move, and remove all traffic control devices in accordance with FAA Advisory Circular 150/5370-2G, with paint crews equipped with operable radios tuned to airport Unicom frequencies.
Mobilization costs encompassing preparatory work, personnel and equipment movement, facility establishment, and demobilization activities must be included in the contractor's bid as part of the contract deliverables. The specifications do not include pricing information, payment terms, contract duration, renewal options, or funding sources within this technical specification document. No specific quantities, delivery schedules, or award dates are identified in the S-100 specification item itself.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1414943-event.pdf | ||
| specs+Item+P+specifications (1).pdf | ||
| 2026 Runway marking plans.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Runway Marking Iowa Department of Transportation
S-100-1
TECHNICAL SPECIFICATIONS
ITEM S-100
SAFETY PLAN, TRAFFIC CONTROL AND MOBILIZATION
DESCRIPTION
100-1.1 SAFETY PLAN. Within ten (10) days after the preconstruction conference, but before construction commences, the Contractor shall submit a written Construction Safety Plan. The plan shall address the following minimum requirements:
a. Points of Contact. Include points of contact for the Owner, Engineer, FAA and Contractor. These will be identified during at the preconstruction conference.
b. Emergency Notification. Identify emergency notification procedures for medical, police and fire.
c. Procedures. Identify proposed work sequence, schedule, staging plan, and access points.
d. Traffic Control. Describe traffic control measures to be employed on the project. Traffic control measures shall be in accordance with this specification item and FAA Advisory Circular 150/5370-2E Operational Safety on Airports During Construction.
e. FOD. Identify foreign object debris (FOD) control procedures in Airport Operations Areas.
f. Monitoring. The Contractor shall perform onsite inspections of safety and operational practices throughout the project, with immediate remedy of any deficiencies, whether caused by negligence, oversight, or project scope change.
g. Training. Ensure that all construction personnel are familiar with safety procedures and requirements.
h. NOTAM. Provide 48 hour notice to the Owner prior to any change in construction operations so that a NOTAM can be issued. The point of contact shall be identified at the preconstruction conference.
101-1.2 TRAFFIC CONTROL. Traffic control will involve the various materials, equipment, and procedures involved in traffic control during construction. The Contractor shall furnish, erect, operate, maintain, move and remove all traffic control devices required for the project. Traffic control shall be in accordance with FAA Advisory circular 150/5370-2G, “Operational Safety on Airports During Construction” and the Contractor’s Construction Safety Plan.
The paint crew shall be equipped with an operable radio at all times, tuned to the airport’s Unicom frequency to monitor airport operations.
100-1.3 MOBILIZATION. Mobilization shall consist of preparatory work and operations for all items under the contract, including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site, and for the establishment of all offices, buildings, and other facilities, which must be performed or costs incurred prior to beginning work on the various items on the project site. This shall also include demobilization costs.
END OF ITEM S‐100