This is a Statement of Work (SOW) for mechanical services at the U.S. Embassy in Paramaribo, Suriname, dated April 12, 2023, requiring the removal and replacement of three roof-mounted HVAC units (RTUs) at the warehouse, workshop, and gym facilities.

The project is divided into two phases: engineering and construction documentation services, followed by construction services. The contractor must remove three existing York RTUs and install three new constant volume RTUs with specific corrosion-resistant features, including powder-painted steel casings certified to 1,000 hours salt spray test per ASTM B-117 standards. The workshop and warehouse buildings require two RTUs with 150,000 BTU cooling capacity each, while the gym requires one RTU with 80,000 BTU capacity, all at 460V, 3-phase, 60 Hz electrical systems with MERV 8 minimum return air filters. New equipment must include motor-operated outdoor air dampers, controls, thermostats, and building automation system connectivity with remote monitoring panels. The contractor is responsible for all mechanical, electrical, roofing, flashing, carpentry, and painting work; Test, Adjust, and Balance (TAB) procedures; startup and commissioning; and formal training to the Facility Manager. The contract is firm-fixed price with task orders payable in currency specified on SF1442, with no cost adjustments for material escalation or currency fluctuations. Work hours are 7:30 AM to 4:00 PM, five days per week, with potential weekend requirements if operations are disrupted. The contractor must submit detailed construction schedules, equipment submittals, and quality assurance plans for COR approval before equipment procurement, and any delays are subject to USD $500 per day penalties. All new equipment includes one-year limited warranties on complete units and five-year warranties on compressors and heater elements, with a 12-month contractor warranty on all workmanship required at no cost to the Embassy.

View the file

Other files

File Type Posted
Public Notice PR15809685.pdf PDF
CP RTU.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SENSITIVE BUT UNCLASSIFIED

US EMBASSY PARAMARIBO, SURINAME

STATEMENT OF WORK

For

MECHANICAL SERVICES

Warehouse, Shop and Gym HVAC equipment Replacement

12 APRIL 2023

1. GENERAL REQUIREMENT

The project is described as “Warehouse, Shop and Gym HVAC equipment Replacement”. The United States Department of State (DOS) requires engineering and construction services to remove and replace three (3) curb mounted roof top units (RTU’s) installed on the warehouse, Workshop and Gym at the U.S Embassy Compound in Paramaribo Suriname. The buildings are one (1) story buildings located around the perimeter of the compound. The intent is for the new RTU’s to fit on the existing to remain RTU curbs. The contractor shall remove and properly dispose of demolished equipment and materials or otherwise instructed by COR or Facility manager. This work will also include any necessary modifications to the building’s roofing/flashing, electrical, and HVAC systems and their associated components. The anticipated project schedule will be provided during the pre-bid walkthrough. The contractor shall furnish services under task orders issued by the Contracting Officer.

I. BACKGROUND

The Roof top units located at the warehouse, workshop and the Gym are required to be replaced, due to the local weather condition, high level of moisture and salty environment along the coast where the salts have negative impact coil fins and metal enclosures /surfaces.

II. SOLUTION

The intent is for the new RTU’s to fit on the existing RTU curbs with new like-for-like equipment as prescribed in Section 2.E in this scope of work under New Work - New Requirements. All roof top units should be replaced with powder-painted steel casing coatings certified at 1,000 hours salt spray test ASTM B-117 standards (to increase life expectancy, to include condensing coils protective layer e.g., OEM factory e-coats and spray-applied coatings) and other requirements as described in Exhibit E. This coating process is both cost-effective and provides a long-term solution against corrosive agents and can also include anti-microbial properties.

III. GENERAL CONDITIONS

CO: Contracting Officer

COR: Contracting Officer’s Representative

FM: Facility Manager

RSO: Regional Security Officer

POSHO: Post Occupational Safety and Health Officer

APOSHO: Assistant Post Occupational Safety and Health Officer

1. Contracting Officer Representative:

A Contracting Officer’s Representative (COR) will be assigned to ensure quality assurance goals are met.

2. Fixed-Price Proposal:

This contract is an engineering and construction services contract with firm-fixed prices. Task orders will be priced and payable entirely in the currency indicated in the SF1442. The Government will not pay any additional sums due to any escalation in the cost of materials, equipment, or labor, or because of the Contractor's failure to properly estimate or accurately predict the cost or difficulty of achieving the results required by this contract. Nor will the contract price be adjusted due to fluctuations in the currency exchange rates. The Government will make changes in the contract price or time to complete only due to changes made by the Government in the work to be performed, or by delays caused by the Government.

3. Work Criteria:

The Work shall be governed by referenced standards and drawings contained within this Scope of Work.

- A pre-bid walk-thru will be coordinated with invited bidders by the PD/COR and the Paramaribo Post Facility Manager (FM). The project schedule, along with other miscellaneous project specifics, will be reviewed during the walk-thru.

-The contractor is responsible for taking field measurements, take notice of existing condition and carefully compare the contract documents with such field measurements.

-Notify the COR in the event of conflicting work criteria. In general, the more stringent criteria shall be applied, subject to COR approval.

-The contractor is responsible for compliance with all design criteria and development of Quality Assurance/Quality Control Plan

-Work not in compliance shall be deemed unacceptable.

-After contract signing, the contractor should submit the following documents to the client for approval:

• Work Method Statement per work: the work procedure, quality control plan, health, and safety plan.

• Construction Plan: time schedule and cash flow estimate, personnel, and equipment.

• Site plan: location of facilities for the contractor and supervisor and location for storage of equipment and materials.

The contractor shall perform all work necessary to produce a complete set of plans and technical specifications sufficient for the tasks described in this project. No work shall be initiated until the Government has provided review comments under each submittal. The contractor shall provide all comments electronically and the actions taken in response to the comments.

The Government reserves the right to modify the contract to add services that may be required of the contractor during actual construction of the project.

4. Execution:

The Work shall be executed in a diligent and skillful manner in accordance with the negotiated fixed price, this Scope of Work, and the Project Schedule.

This HVAC equipment repair by replacement scope will be split into two (2) basic phases, with the first being Engineering and Construction Documentation Services and the second being Construction Services. The first phase will include developing construction documents capturing the installation intent and construction phases, which shall include site plans, demo / new work plans, equipment cut sheets, and relevant engineering calculations. Following approval of construction documents, the second phase (construction services) work will include installing new packaged RTUs, temporarily shutting down systems to switch over service to new RTUs

When pursuing the work, the contractor is to take extra care as not to damage existing structures.

The contractor is responsible for preventing any damage to surrounding properties arising from the Contractors performance of the work.

Contractor shall be responsible for repairing any damage to adjacent properties because of its activities on the Project Site. If the damage is not repairable, the cost will be calculated by the Facility Manager and deducted from the payment of the final invoice.

5. Work Hours:

The contractor shall work 5 days a week between the hours of 7:30 AM and 4:00 PM.

If any aspect of this work is deemed by the COR, the FM, the RSO or the POSHO/APOSHO to be interruptive of normal embassy operations, the Embassy security or safety, the contractor shall be required to perform that portion of the work on Saturdays and Sundays. If the contractor requires to work outside regular working hours, escort and access will be provided by post.

6. Safety:

The contractor shall be responsible for conducting the work in a manner that ensures the safety of employees, visitors at the US Embassy, and the Contractor’s employees.

The contractor shall be solely responsible for risk assessments, managing health, and safety issues associated with this project. Based on hazard assessments, Contractors shall provide or afford each affected employee personal protective equipment (PPE) that will protect the employee from hazards. At a minimum PPE shall consist of eye protection, hard hats, and closed toe shoes. Sandals or athletic shoes are not acceptable. PPE such as gloves, dust masks, are recommended. These items must be provided at the Contractor’s expense.

Workers may use discretion if they feel unsafe in using the equipment in a hostile environment.

Any worker at an elevated location above 1. meters, except for a portable ladder, must be provided and utilize a safety harness.

The contractor must document in the bid for work how the hazard controls will be implemented and maintained during the project.

The Contractor shall prepare and implement an Activity Hazard Analysis (AHA) prior to the start of work.

The Contactor must have a competent person on-site for inspection of equipment, training workers in the safe use of equipment and the recognition of hazards related to their use, supervision, and identifying and correcting unsafe work practices for high hazard work.

All contractor personnel shall wear hard hats, safety glasses, earplugs, gloves, close-toes shoes, and any other Personal Protection Equipment deemed necessary by the Facility Manager.

Safety Training:

1. Provide specific training to supervisory personnel and all craft workers of the contractor and subcontractors in proper use and care of specific personal protective gear, equipment, and clothing.

2. Contractor and subcontractor employees shall be trained and supervised by qualified persons to perform, safely and confidently, recognized hazardous work operations and work performed with hazardous conditions to which they have been assigned.

7. Workforce:

The contractor shall provide all supervision, skilled and unskilled labor needed to perform the work.

The contractor shall be responsible for total integration of effort and control of the works. The contractor shall be responsible for planning, monitoring, coordinating, and controlling the works.

The contractor shall provide a Project Superintendent with a minimum 5 years of professional employment record of demonstrated performance in comparable work. Project Superintendent shall have experience in all aspects of work execution.

The contractor shall provide Foremen and other supplemental staff as necessary to perform the work within the timelines and quality standards specified. Staff shall demonstrate knowledge, skill, and experience with the construction methods, techniques, and standards required by the contract.

8. Accommodations:

Toilets: The contractor may utilize guard toilets for the workers located in the CAC, or as instructed.

The contractor shall ensure they stay clean and usable.

Drinking water: The contractor shall also provide an adequate number of drinking water dispensers, distributed for convenience and efficiency-of-use around the construction areas.

Always maintain supply of disposable paper cups at each dispenser.

9. Subcontractors:

Contractor shall be responsible for the conduct and workmanship of Subcontractors engaged in the Project, and for Subcontractors compliance with the terms of this Statement of Work. The contractor is responsible for the behavior and workmanship of Subcontractors while on US Government property.

10. Modification to Contract:

The Contractor shall not incur any costs beyond those described in this SOW unless directed otherwise in writing by the Contracting Officer.

Any work performed by the contractor beyond this SOW without written direction from the Contracting Officer will be at the Contractor’s own risk and at no cost to the Embassy.

11. Stop Work:

At any time during the Project, the Contracting Officer (CO) reserves the right to Stop Work for protection of employees or visitors, security, or any other reason at his/her discretion.

12. General Submittals:

The contractor is responsible to submit a hazard control measure plan for the work.

The contractor is also responsible to submit a detailed construction schedule indicating when the various portions of the work will be commenced and completed within the required schedule in the form of a bar chart. This bar chart shall be in sufficient detail to include all significant milestones.

The new equipment shall be procured only after receiving approval on pre-requisite submittals (e.g., Issued for Construction (IFC) Drawings, Equipment Submittals) by the COR.

The contractor shall provide the detailed qualification of all the key personnel.

1. All submittals require approval by the Facility Manager before commencing activities.

Contractor must provide a chronograph work schedule with the proposal for the project.

2. Contractor must specify in his Quote/Bid: labor cost, the term/ timeframe of each specific categories as indicated in the line items.

3. Once job is finished, contractor will inform the U.S. Embassy to inspect and approve the work performed.

13. Close-out:

Prior to final acceptance, the COR will conduct a QA/QC inspection to check compliance with the SOW.

14. Housekeeping:

The contractor is responsible to clean up daily. The contractor is responsible to dispose of all dirt, concrete, stone, and construction debris outside of the property before the close of business each day. Any dirt, concrete, stone, and other construction debris may not be piled on the ground.

Immediately upon removal, it must be loaded into a truck and disposed of immediately once the vehicle is full. At the end of the day even partially loaded trucks must be removed from the US Embassy compound and the contents disposed of properly at authorized dump sites.

The contractor shall coordinate and supervise the protection, cleaning, and maintenance work at the Project Site during receipt, handling, storage, installation, curing, and similar stages of construction execution to affect minimum exposure to hazards by personnel and minimum deterioration to the Embassy compound.

15. Notification to Proceed:

The Contractor Shall Start Work Within 14 Days of Notice to Proceed.

Within 5 days of Notice to Proceed (NTP), the contractor shall provide the COR a project schedule showing start to completion dates including significant milestones.

Within 10 days of NTP, the Contractor shall provide the COR with details of the proposed installation utilizing written description or sketches or both.

16. Point of Contact:

The COR shall be the main point of contact for this Project. The Contractor shall report to the COR on (a) status of the Project, (b) changes in Schedule, (c) accidents and safety issues, (d) disruptions to the property accessibility; and all other essential information pertaining to the Project.

17. Contractor’s Representative:

The Contractor shall provide a representative on-site during all working hours with the authority to make all decisions on behalf of the Contractor and subcontractors.

18. Site Security:

The contractor shall comply with US Embassy security policy.

The contractor shall prepare list of all the names of personnel working for the contractor and any subcontractors, with national ID numbers and submit the list to the Facility Manager for vetting of employees by the RSO at least 30 days prior to commencement of work.

The contractor shall also provide a list of all equipment, listing the manufacturer, model, serial number of all equipment to be used on this project at least 7 days prior to the commencement of any work. Any vehicles utilized by the contractor are also considered equipment. The contractor must provide make, year, model number and license plate number. All vehicles will be inspected prior to entering and prior to leaving the premises.

The COR will assign a holding area for the equipment. Equipment, other than vehicles, should remain on site for the duration of the project to avoid having to have a security screening of it each time it enters the compound.

Any vehicle that leaks oil will be immediately removed from the compound.

The contractor must notify the COR in writing at least 24 hours in advance of the pending removal of any contractor owned equipment.

The contractor is 100% responsible for securing their working materials and equipment. Any damage to facilities or infrastructure, which happens due to a lack of security, will be the responsibility of the contractor to correct at no cost to the U.S. Government.

The following considerations must be followed by the Contractor:

- All documents received or generated under the contract are the property of the US Government.

- Reproduction and distribution is prohibited without express approval of the US Government.

- Proposed and actual contract documents will only be disseminated on a strict need-to-know basis and will not be further disseminated without prior authorization from the US Government.

- Contractor personnel receiving contract drawings will be responsible for these materials while in their possession, or that of any of their subcontractors.

- Photographs of any public area of any US Diplomatic Facility must be approved and authorized in advance by the RSO. The RSO will establish control, limits or restrictions as deemed necessary. The contractor shall submit a written request for photographs.

19. Coordination Meetings:

Pre-Construction Conference: The COR shall conduct an initial construction conference on or near the date of Notification to proceed. Agenda items shall include a review of the general plans, conditions, procedures, and requirements as shall be necessary for the effective scheduling and prosecution of the construction work. Further, all parties shall review security and material delivery requirements, personnel assigned, and contract communication procedures as have been established for the Project. This meeting shall be scheduled and conducted at the place agreed to by the COR and the Contractor.

Construction Coordination Meetings: The contractor and COR will hold weekly construction coordination meetings to discuss schedule and status of outstanding issues. Weekly coordination meetings shall commence immediately upon mobilization to the Project Site. All parties shall seek the expeditious resolution of issues before they become problems. Progress of the work shall be reviewed. contractor shall revise, balance, and submit an updated project execution. This review shall be based upon a subset report of the Project Execution Schedule in which all project execution activities have been entered. This review shall include:

• Status of continuing activities.

• Recent activity starts since last meeting.

• Activity planned completion dates.

• Activity interruptions.

• Activity completions.

Activity interruptions should include the reason for the interruption.

An activity will be considered complete only when it has been approved by the COR.

The contractor shall prepare a detailed written record of all conferences and meetings with representatives of Post related to the project. A copy of these records shall be submitted to the COR within 5 workdays of the event.

20. Defects in Work:

Where the Contractor’s QC procedures, or those undertaken by or for the USG, disclose patent or latent defects in the works, the contractor shall provide corrective actions. The contractor shall seek to repair, restore, reconstruct, replace, or otherwise correct defects in the works to comply with Contract Document requirements and criteria. The corrective action shall be acceptable to the

COR.

Provide re-inspection or re-testing of corrected work, repeat until compliance is achieved.

Neither the required quality control procedure, nor detection of defects, nor correction of defects, nor the re-inspection or re-testing of corrected work, provides a basis for Contractor's claim for Contract Modification/Additional Compensation, or request for extension of Contract Time.

21. Delays:

Delays that are found to be caused by the Contractor's actions or inactions shall not be a cause for a time extension to the contract completion date.

If the contractor's execution of the works falls behind the accepted Project Execution Schedule, the contractor shall take all steps necessary within the agreed work period parameters to improve progress. These attempts at recovery shall incur no additional cost to the USG. The contractor shall execute the works diligently and shall seek to complete all works at or before the agreed upon contract completion date.

The proposed contractor must submit with the proposal a construction schedule (chronograph) of the proposed work. If selected, the contractor must adhere to the construction schedule. Any delays will be penalized by USD 500.00 (five hundred north American dollars) per day for any delay deemed to be unreasonable by the COR.

22. Invoicing and Paying Instructions:

The contractor shall submit invoices in the original and three copies to the designated billing address indicated in the contract. The COR will determine whether the invoice is complete and proper as submitted. The COR also will determine whether billed services have been satisfactorily performed and whether reimbursable expenses billed are correct. If the amount billed is incorrect, the COR will, within seven days, ask the contractor to submit a revised invoice.

The contractor shall specifically identify its last invoice as ‘’Final invoice.’’

The final invoice shall include the remaining payments due under the basic contract and all modifications issued. The final invoice shall also attach a ‘’Contractor’s release’’.

2. SCOPE OF WORK

A. Site Organization:

1. The contractor shall have at least one safety monitor / traffic flagger to keep pedestrians out of the work area.

2. Install new barricades to delineate the project area.

B. Work Execution:

1. Coordinate all phases and aspects of the works carefully to achieve intended results, including best overall visual effect. Remove and replace workmanship and/or material that are found to be not in compliance.

2. In all aspects of the work, fully comply with construction safety and occupational health requirements.

3. Should there be a discrepancy between the U. S. Government Specifications and the applicable Building Code, the more stringent of the two shall govern.

4. The contractor is responsible for compliance with all Building Codes; work not in compliance with the Codes shall be deemed to be unacceptable.

5. Explosive Actuated Tools are not permitted.

6. Remove and properly dispose of the three (3) existing RTU’s and associated materials.

Unless otherwise dictated by the PD/COR, the contractor should expect to only be able to work on one (1) Roof Top Unit at a time to minimize the impact to normal operations.

7. Provide and install three (3) new RTU’s and associated devices, such as new electrical disconnects, thermostats, canvas/flex connections, p-trap and local condensate piping, etc.

8. Contractor shall use existing roof penetrations for new outdoor air (OA) intakes and controls wiring.

In addition to the new equipment: rigging, ductwork, duct connections, duct accessories, piping, piping accessories disconnect switches, electrical whip connectors, thermostats, controllers, and controls wiring are also included. Mechanical, electrical, light carpentry, roofing/flashing, and painting are involved. Test, Adjust, and Balance (TAB), Factory Representative Start-up, and basic adjustments of the new equipment are part of the Work.

9. Building Codes. Work is governed by the latest version of the International Building Code (IBC) and the OBO Supplements, which includes the International Mechanical Code, International Plumbing Code, and National Electric Code. Work shall comply with OBO standards and local jurisdictional requirements. Work not in compliance with the IBC and NEC shall be deemed not in compliance with the Contract.

Included with this Statement of Work narrative are attached exhibits including (Exhibit A) photos of existing conditions/equipment, (Exhibit B) existing York RTU literature, (Exhibit C) sketches of demolition and new work requirements, (Exhibit D) construction specifications.

(Exhibit E) glossary of coating recommended for mechanical equipment as a basis of design.

(Exhibit F) plans and sections of RTUs.

Project Orientation Photos. See Exhibit A for orientation photos of existing equipment/systems.

Shipping: The Contractor is responsible for shipping, delivery, and storage of all tools, materials, and equipment to the Work site.

Damage caused by the Contractor will be returned to original condition at the expense of the Contractor.

The Contractor shall maintain existing systems in service to the maximum extent possible and coordinate interruptions of any utility services in advance with the Facility Manager.

Handling / charging of refrigerants for use in air conditioning systems shall comply with U.S.

and Paramaribo, Suriname laws and regulations.

If needed for reference, available existing design/construction documentation, including AutoCAD files of the buildings to be worked at may be provided by the PD/COR if requested by the contractor. Availability and accuracy of existing files cannot be guaranteed.

The contractor shall provide submittals for all new equipment, materials, and chemicals. See included specifications exhibit for additional information.

C. Warranty:

1. The contractor shall correct any noted discrepancies by the COR within 7-days of being notified at no additional cost with the 12 months warranty period.

2. The contractor shall guarantee all the work that is performed under this contract, including all materials, workmanship, for a minimum of 12 (twelve) months from the date of full acceptance of the work.

3. The contractor is required to submit a copy of a warranty for a period of twelve months at no cost to the Embassy signed by the contractor.

4. The contractor shall provide warranties on all equipment, materials, and workmanship. See included specifications exhibit for additional information.

D. Utilities:

The contractor will have access to water and electricity on site. The electrical supply at the US Embassy is a 120Volts supply however the wall female sockets are American Nema-6 wall plates. Limited storage will be provided for equipment and material; however, the US Embassy holds no responsibility for contractor’s equipment stored onsite.

E. New Work:

General requirements

1. The new equipment shall be procured only after receiving approval on pre-requisite submittals (e.g., Issued for Construction (IFC) Drawings, Equipment Submittals) by the

COR.

2. The contractor shall also provide formal training to the Facility Manager (FM) and locally employed embassy staff, which shall include a detailed project specific preventive maintenance plan and operations / maintenance manuals.

3. All new equipment shall be installed and fully commissioned within 2 months after arrival at post. The Contractor shall provide a schedule to the project COR for review and approval.

4. Provide workers, equipment, and materials necessary to replace three (3) existing Roof Top Units (RTU’s) with three (3) new RTU’s. Trades shall include, but may not be limited to mechanical, electrical, roofing/flashing, carpentry, and painting.

5. In addition to the providing the new mechanical and electrical equipment; duct work, duct connections, miscellaneous duct accessories, piping, piping connections, valves, gages, thermostats, miscellaneous piping accessories, disconnect switches, circuit breakers, electrical conductors, thermostats, controls wiring, and other miscellaneous materials are part of the Work.

6. All used equipment, debris, trash, and hazardous materials will be removed from the property and disposed of properly by the contractor. At a minimum, materials shall be removed weekly. Locations for dumpsters are not guaranteed. Access for trucks/dumpsters shall be coordinated with the PD/COR and FM. The Contractor is responsible for ensuring that disposal of equipment, debris, and hazardous material complies with the laws and regulations Paramaribo, Suriname.

7. Start-up and commissioning of the new units is part of the Work. All mechanical and electrical functions at the mechanical equipment and at the thermostat(s)/controllers will be verified in all modes. Start-up and commissioning shall be completed with the FM or designated technical staff in attendance. Coordinate with PD/COR and FM.

8. Crane Study. The Contractor shall submit the proposed crane entry path and staging location in a graphical (site plan) format for review by the COR and FM. The contractor shall confirm an adequately sized crane can fit through the service CAC / compound entrances.

9. Demolition Plan: Show required demolition of existing architectural, mechanical, and electrical elements, and equipment.

10. Proposed New Work: Show layout of all new equipment. Provide narrative descriptions, details, and cross-sections of the proposed work as necessary to explain the project. All details shall indicate the difference between new and existing construction.

11. The government requires that the new equipment proposed by the contractor shall have the capability of being serviced locally. Equipment that does not have adequate local support shall be indicated to the COR/COR for review / approval.

12. The new RTUs are required to be connect to a building automation system (BAS);

however, they should also have remote control / monitoring panels located within each building. Remote panels shall allow viewing of RTU parameters / operating conditions and shall allow adjustment of set points.

Existing Equipment Modification / Removal / Demolition Requirements:

1. General: The contractor shall provide all means to shut-down equipment, isolate equipment, drain down, flush and refill the systems, and lock-out/tag-out systems as required to safely complete the specified tasks.

2. Remove the three (3) existing York RTUs and Accessories: Expect work to take place on one building at a time, unless otherwise noted. The contractor shall remove the existing York RTUs. Removal shall include any misc. ductwork/duct connections, electrical circuiting/breakers, controls wiring/devices, and piping that will not be used as part of the new work. The contractor shall try to keep infrastructure in place that can be reused as part of the new work tasks; however, devices associated with the RTU’s shall be replaced with new, such as condensate p-traps, natural gas pressure regulators, natural gas manual shut-off valves, natural gas dirt-legs, programmable thermostats, etc.

New Equipment and New Work Requirements – General Descriptions

New RTUs:

Requirement Summary:

1. The contractor shall install three (3) new RTU’s and all necessary mechanical and electrical accessories to provide a fully functioning system that meets the project requirements. Contractor shall modify and install flashing on existing roof curbs as necessary to accommodate new RTU’s.

2. The contractor shall provide new controllers/programmable thermostats, sensors, wiring, and necessary devices.

3. Perform air-side test, adjust, and balance (TAB) procedure on all three (3) new RTU’s.

ii. New Equipment Summary:

(Manufacturer/Model substitutions shall meet or exceed the York Series Equipment.

Substitutions are subject to approval by the PD/COR, FM, and FAC/PS Mechanical Engineer. If a substitution is accepted, the contractor is responsible for any curb/roof/flashing modifications. If curb adapters are to be provided, the contractor shall provide detailed/dimensioned drawings for review by FM and PD/COR.)

1. Workshop and warehouse building:

Two (2) New Constant Volume Roof Top Units, York Series, or other brands matching capacity and weight approved by FM/COR/Building Engineer/ Mechanical supervisor as equally acceptable. If RTUs with matching capacity and weight are not available, the contractor shall perform new heat load calculations based on indoor set point design.

•Basis of Design: York series 20 •Workshop & Warehouse RTU shall have 150.000 BTU cooling capacity.

•Electrical System: 460V, 3 Wire, 60 Hz •Return air filters shall be MERV 8 minimum.

•RTUs shall be Constant Volume •RTUs shall be furnished with motor operated outdoor air (OA) dampers and associated controls. Outdoor air dampers shall open to the balanced set point during occupied hours but remain closed during unoccupied hours.

•Ductwork shall match existing configuration. New RTU shall fit within existing curbs.

Equipment weight shall not exceed existing equipment weight or live load requirements, whichever is more stringent.

Where selected equipment size or weight has changed the contractor must confirm the existing structure has sufficient capacity to support the proposed equipment size or weight.

•Unit Cabinet Constructed of Powder Painted Steel, Certified At 1000 Hours Salt Spray Test (ASTMB-117 Standards).

•Through-the-Curb and Through-The-Base Utility Connections •Either Supply and/or Return can be Field Converted from Vertical to •Horizontal Configuration without Cutting Panels •Full Perimeter Base Rails with Built in Rigging Capabilities

•Hinged & Tool Free Filter, Blower, Motor and Electrical Access Panels •Stainless Steel Drain Pan •Dual Refrigerant Circuits for Efficient Part Load Operation with Scroll Compressors •Two Stage Cooling •Solid Core Liquid Line Filter Driers •Techni coat (or equivalent to) Copper Tube/Copper Fin Condenser Coil •Techni coat (or equivalent to) Copper Evaporator/copper fin Coil •No Factory Installed Electric Heat •High Static Belt Drive Blower •HACR Circuit Breaker/Disconnect •Powered Convenience Outlet (110 VAC / 15 Amp) •Phase Monitor •BAS Ready Economizer with Barometric Relief (Bottom Return Only) •Coil Guard •An Integrated Low-Ambient Control, Anti-Short Cycle Protection, Lead-Lag, •Fan on and Fan off Delays, Low Voltage Protection, On-Board Diagnostic and Fault Code Display.

•Safety Monitoring - Monitors the High and Low-Pressure Switches, the Freeze stats, the Gas Valve, if Applicable, and the Temperature Limit Switch on Gas and Electric Heat Units. The Unit Control Board Will Alarm on Ignition Failures, Safety Lockouts and Repeated Limit Switch Trips.

Warranty •One (1) Year Limited Warranty on the Complete Unit •Five (5) Year Warranty - Compressors and Electric Heater Elements

1. Gym building:

One (1) New Constant Volume Roof Top Unit, York Series, or other brands matching capacity and weight approved by FM/COR/Building Engineer/ Mechanical supervisor as equally acceptable. If RTUs with matching capacity and weight are not available, the contractor shall perform new heat load calculations based on indoor set point design.

Unit Features •Basis of Design: York Series 20 •Workshop RTU shall have 80000 BTU cooling capacity.

•Electrical System: 460V, 3 Wire, 60 Hz •Return air filters shall be MERV 8 minimum.

•RTUs shall be Constant Volume •RTUs shall have adjustable barometric relief for space pressurization control, to include all related control equipment e.g., dampers and sensors.

•RTUs shall be furnished with motor operated outdoor air (OA) dampers and associated controls. Outdoor air dampers shall open to the balanced set point during occupied hours but remain closed during unoccupied hours.

•Ductwork shall match existing configuration, new RTU shall fit within existing curbs.

Equipment weight shall not exceed existing equipment weight or live load requirements, whichever is more stringent.

Where selected equipment size or weight has changed the contractor must confirm the existing structure has sufficient capacity to support the proposed equipment size or weight.

•Unit Cabinet Constructed of Powder Painted Steel, Certified At 1000 Hours Salt Spray Test (ASTM B-117 standards) •Through-the-Curb and Through-the-Base Utility Connections •Full perimeter base rails with built in rigging capabilities •Hinged Access Panels •Slide-Out Stainless-Steel Drain Pan •Scroll Compressors •Two Stage Cooling •Solid Core Liquid Line Filter Driers •Techni coat Copper Tube/copper Fin Condenser Coil •Techni coat Copper Tube/copper Fin Evaporator Coil •Slide-out Blower/3 HP Belt Drive Motor Assembly •Single Point Power Connection •Non-Fused Disconnect Switch •Powered Convenience Outlet (110 VAC / 15 Amp) •Phase Monitor •BAS Ready Economizer w/Barometric Relief (Bottom Return Only) •Coil Guard •Safety Monitoring - Monitors the high and low-pressure switches, the freeze stats, the gas valve, if applicable, and the temperature limit switch on gas and electric heat units.

The unit control board will alarm on ignition failures, safety lockouts and repeated limit switch trips.

Warranty •One (1) Year Limited Warranty on the Complete Unit

•Five (5) Year Warranty - Compressors and Electric Heater Elements

2. Electrical: Circuit Breaker and Conductors

- Contractor shall provide new fused disconnects for all roof top units and shall be sized per manufacturer’s recommendations. Enclosures and conduit shall be rated for outdoor applications.

3. Contractor shall connect new RTU to existing building ductwork system through existing roof penetrations. Install new electrical conduit /conductors between new RTU and existing main electrical distribution panel also located on same roof.

Contractor shall install new controls.

4. STARTUP SERVICE

Complete installation and startup check according to manufacturer's written instructions and do the following:

1. Inspect for visible damage to unit casing.

2. Inspect for visible damage to compressor, coils, and fans.

3. Inspect internal insulation.

4. Verify that labels are clearly visible.

5. Verify that clearances have been provided for servicing.

6. Verify that controls are connected and operable.

7. Verify that filters are installed.

8. Clean condenser coil and inspect for construction debris.

9. Remove packing from vibration isolators.

10. Inspect operation of barometric relief dampers.

11. Verify lubrication on fan and motor bearings.

12. Inspect fan-wheel rotation for movement in correct direction without vibration and binding.

13. Adjust fan belts to proper alignment and tension.

14. Start unit according to manufacturer's written instructions.

a. Start refrigeration system.

b. Do not operate below recommended low-ambient temperature.

c. Complete startup sheets and attach copy with Contractor's startup report.

15. Inspect and record performance of interlocks and protective devices; verify sequences.

16. Operate unit for an initial period as recommended or required by manufacturer.

17. Calibrate thermostats.

18. Inspect outdoor-air dampers for proper stroke and interlock with return-air dampers.

19. Start refrigeration system and measure and record the following when ambient is a minimum of 15 deg F above return-air temperature:

a. Coil leaving-air, dry- and wet-bulb temperatures.

b. Coil entering-air, dry- and wet-bulb temperatures.

c. Outdoor-air, dry-bulb temperature.

d. Outdoor-air-coil, discharge-air, dry-bulb temperature.

20. Inspect controls for correct sequencing of heating, mixing dampers, refrigeration, and normal and emergency shutdown.

21. Measure and record the following minimum and maximum airflows. Plot fan volumes on fan curve.

a. Supply-air volume.

b. Return-air volume.

c. Relief-air volume.

d. Outdoor-air intake volume.

22. Simulate maximum cooling demand and inspect the following:

a. Compressor refrigerant suction and hot-gas pressures.

b. Short circuiting of air through condenser coil or from condenser fans to outdoor-air intake.

23. Verify operation of remote panel including pilot-light operation and failure modes.

Inspect the following:

a. Low-temperature safety operation.

b. Filter high-pressure differential alarm.

c. Economizer to minimum outdoor-air changeover.

d. Relief-air fan operation.

24. After startup and performance testing and prior to Substantial Completion, replace existing filters with new filters.

5. Test, Adjust, and Balance (TAB):

ATTACHMENTS

Exhibit A: Photos of existing conditions/equipment:

Roof top unit 1

Roof top unit 2

Roof top unit 3

Exhibit B: Existing York RTU literature, Exhibit C: sketches of demolition and new work requirements

RTU 1 & 2

RTU 3

Exhibit D: Construction specifications.

Choose applicable specifications….

• OBO Specification Section 230519 – METERS AND GAGES FOR HVAC PIPING (January

2012)

• OBO Specification Section 230523 – GENERAL-DUTY VALVES FOR HVAC PIPING

(January 2012)

• OBO Specification Section 230529 – HANGERS AND SUPPORTS FOR HVAC PIPING

AND EQUIPMENT (January 2012)

• OBO Specification Section 230548 – VIBRATION AND SIESMIC CONTROLS FOR

HVAC PIPING AND EQUIPMENT (January 2012)

• OBO Specification Section 230593 – TESTING, ADJUSTING, AND BALANCING FOR

HVAC (January 2012)

• OBO Specification Section 230719 – HVAC PIPING INSULATION (January 2014)

• OBO Specification Section 230905 – INSTRUMENTATION AND CONTROLS FOR

HVAC (January 2015)

• OBO Specification Section 232113 – HYDRONIC PIPING (January 2012)

• OBO Specification Section 232500 – HVAC WATER TREATMENT (January 2012)

• OBO Specification Section 236423 – SCROLL AIR-COOLED WATER CHILLERS

(January 2012) DUPLICATE CHILLER SPEC

• OBO Specification Section 236424 – MODULAR SCROLL AIR-COOLED WATER

CHILLERS (January 2015) DUPLICATE CHILLER SPEC

• OBO Specification Section 260505 – COMMON WORK RESULTS FOR ELECTRICAL, COMMUNICATIONS AND ELECTRONIC SAFETY (January 2016)

• OBO Specification Section 260519 – LOW-VOLTAGE ELECTRICAL POWER

CONDUCTORS AND CABLES (January 2012)

• OBO Specification Section 260525 – GROUNDING AND BONDING FOR ELECTRICAL

SYSTEMS (January 2012)

• OBO Specification Section 260534 – RACEWAYS AND BOXES (January 2012)

• OBO Specification Section 260553 – IDENTIFICATION FOR ELECTRICAL (January

2012)

• OBO Specification Section 262923 – VARIABLE FREQUENCY MOTOR CONTROLLERS

(January 2012)

7.3 Mechanical and Plumbing Systems

Structure/ Equipment/ Device

Exterior Direct

Exposure

Interior Indirect

Exposure

Interior Controlled

Space

Corrosivity environment

Low - C1

Corrosivity environment

Moderate - C2, C3

Corrosivity environment High -

C4, C5

Coatings* and Other Requirements Comments

Outside air, Outdoor AHU Cooling Coil & Fin

X X Coated Aluminum

Electrofin Coated Copper

Electrofin CCoated Copper

Coatings: Electrofin (dipped) Luvata or

Heresite (baked phenolic) or PoluAl XT

Blygold

OAHU Coil Frame Casing condenser drain pan

X 304 SS Coated 304 SS Coated 304 SS

ICI Devoe Devthane 379UVA – Urethane;

Devran 224HS Epoxy;

ZRC Galvanized

OAHU Fan Coil Cabinet X Galvanized steel

Galvanized steel with primer and factory applied enamel paint

Galvanized steel with primer and factory applied enamel paint

Polyeura-thane or epoxy; Devoe Devron 224 High Build Epoxy

Devron 379

Inner AHU lining X X Mild Steel 304 SS 304 SS 3044 SS lining

Dampers, louvres, rain caps, hoods, bird screens, vents, etc.

X 304 SS SS316 SS316

Epoxy paint or powder coated

Subject to blast require-ments X X 304 SS 304 SS 304 SS

Actuators X X

NEMA 4X Encased, UV resistant plastic or aluminum

NEMA 4X Encased, UV resistant plastic or aluminum

Aluminum to be powder coated

Standard AHU (UTL & WHE) X Copper tube

& fin

Copper tube & fin, 316SS coil/filter frame, drain pane & inner lining

Copper tube & fin, 316SS coil/filter frame, drain pane & inner lining

Heresite electrofin coating supply fan in lieu of SS

Filter frame, X X 304 SS 304 SS X Mild Steel Mild Steel Mild Steel

Fan Coil Unit X X No coating

Copper coils with Electrofin Coating

Copper coils with Electrofin Coating

Unit & components must be designed for severe environment

Specify unit components X No coating No coating No coating

SENSITIVE BUT UNCLASSIFIED

FriessLA Rectangle

FriessLA Rectangle

FriessLA Text Box

EXHIBIT E

FriessLA Text Box

6. APPENDIX: GLOSSARY OF OBO RELEVANT COATINGS USED FOR MECHANICAL EQUIPMENT

Advancoat 3-Coat OBO Use: HVAC exterior equipment including compressors, piping, valves, plumbing, etc.

Coating type: three coat process via spraying (a) primer with polymeric epoxy and corrosion inhibitors to encapsulate bare metal and provide firm anchorage on pre-painted powder coated surfaces (2-mil), (b) intermediate coat with immersion-grade cross-linked epoxy for chemical and corrosion resistance (5-mil), and (c) polyeurathane UV resistant for protection against impact, abrasion, and staining (3-mil) thick.

Substrate Materials: Steels Manufacturer: AdvanCoat Corrosion Specialists Application Method: Spraying Properties: thick coating with excellent corrosion, chemical, UV, abrasion, impact and staining resistance, in addition to aesthetic appeal.

Uses: exterior equipment including compressors, piping, valves, plumbing, etc.

Devran 224HS High Build Epoxy Coating and Devran 201H Universal Epoxy Primer OBO Use: Various interior & indirect exposure including ductwork Coating type: High build catalyzed polyamide epoxy and universal polyamide epoxy rust-inhibitive primer for interior and exterior steel, galvanized metal and aluminum surfaces Substrate Materials: Structural steels, metal, piping, tanks, concrete, drywall, wood and plaster Manufacturer: Devoe High Performance Coatings Application Method: Air or Airless Spray, brush, or roller Properties: Epoxy coating provides excellent corrosion protection, solvent and chemical resistance, abrasion resistant, cold weather cure, surface tolerant, self-priming, high-build and high-solids content; color change and loss of gloss due to exterior exposure unless finished with Devthane Urethane Enamel.

Uses: Multipurpose, surface tolerant, catalyzed polyamide two-component chemically cured epoxy semi-gloss coating for industrial or high-performance architectural applications.

Devthane 379UVA Aliphatic Urethane Gloss Enamel OBO Use: Various interior & indirect exposure including ductwork Coating type: High performance two-component chemically cured aliphatic urethane enamel for high gloss and color retention.

Substrate Materials: Properly prepared and primed structural steels, aluminum, galvanized metal, concrete, masonry, drywall, plaster, and glazed brick.

Manufacturer: Devoe High Performance Coatings Application Method: Airless spray, air spray, roller, or brush Properties: gloss and color retention, excellent abrasion and chemical resistance, high-solids content (63%), 2-3 mil dry thickness Uses: Ideal for use on exterior or interior structural steel, piping, metal buildings, control cabinetry, conveyors, pumps, storage tank exteriors, motors, machinery, and vehicles.

FriessLA Rectangle

FriessLA Highlight

6. APPENDIX: GLOSSARY OF OBO RELEVANT COATINGS USED FOR MECHANICAL EQUIPMENT

FriessLA Text Box

EXHIBIT E

FriessLA

ElectroFin E-Coat OBO Use: Chiller coil and fins Coating type: Organic water-based cationic epoxy polymer corrosion-inhibiting coating Substrate Materials: Copper, Aluminum Manufacturer: Modine Manufacturing Company (formerly Luvata); Carrier equipment Application Method: Factory applied electrophoretic deposition of epoxy paint resin and pigment particles (suspended in deionized water) on conducting metal surface. Process creates a smooth, consistent, and flexible coating that penetrates all coil cavities and covers entire coil assembly including fin edges, with no material bridging between foils. Process ensures complete coil encapsulation and uniform average dry-film thickness of 0.6-1.2 mils.

Properties: Suitable for corrosion resistance in high salinity coastal and industrial regions, with high humidity, aggressive pollutant environment, and buildings with permanent condensation.

Coating demonstrates resistance to thermal loss, UV degradation, and moisture intrusion.

Uses: HVAC heat transfer coils, fins, and other components

G90 Galvanized Steel OBO Use: Various interior and indirect exposure structures including ductwork Coating type: Hot-dip galvanized Zinc coating Substrate Materials: Mild steel or other steels Manufacturer: Various Application Method: Passing steel through molten bath of zinc at 860oF (460oC). Upon exposure to atmosphere, pure zinc reacts with oxygen to form zinc oxide which further reacts with CO2 to form zinc carbonate, a dull grey surface material that protects steel from further corrosion.

Properties: G-90 designates zinc coating of .90 oz/square foot; G-140 of 1.40 oz/square foot Uses: for use in various Outdoor Hardware, Heating/Cooling Systems, Electrical Protections, Decorative Applications

Heresite P-413 thermoset modified phenolic epoxy coating OBO Use: Chiller coil and fins, generator radiator coils and cores Coating type: thermoset modified cross-linked phenolic epoxy coating Substrate Materials: aluminum, copper, steel Manufacturer: Heresite Protective Coatings LLC Application Method: application through multiple coats by immersion or flow coating or spraying, with intermediate and final baking.

Properties: Dense crosslinking enables thin film application maintaining stable heat transfer.

Chemically resistant to acids, solvents, and inorganic salts.

Uses: High-performance coating developed specifically for heat-exchanger components and parts operating in moderate to severely corrosive coastal and industrial environment.

PoluAl XT Blygold Aluminized sprayed coating OBO Use: Chiller coil and fins Coating type: water based with corrosion inhibiting ingredients and high content of aluminum pigmentation (for diffusion control and heat conductivity) in polyeurathane as topcoat following chromate-free conversion layer primer

SENSITIVE BUT UNCLASSIFIED

FriessLA Rectangle

FriessLA Rectangle

FriessLA Text Box

EXHIBIT E

FriessLA

Substrate Materials: Aluminum, copper, galvanized steel Manufacturer: Blygold Application Method: Proprietary Blygold spray technology (in-factory or on-site) Properties: Excellent chemical and UV resistance, excellent adhesion with negligible effect on heat transfer of heat-exchanger components.

Uses: For corrosion protection and microbe resistance in heat exchanger components.

PPG Amerone Siloxane PSX 700 OBO Use: Various interior and indirect exposure structures including ductwork, including AirStack chiller panels Coating type: Engineered high gloss two-part epoxy siloxane self-priming coating Substrate Materials: Stainless and Plain Carbon Steel, Galvanized Steel, Non-ferrous metals, Concrete, Airstack galvannealed steel chiller panels Manufacturer: PPG Protective and Marine Coatings Application Method: Airless spray, air spray, brush, and roller without thinning Properties: high durability, abrasion resistant, high gloss, excellent resistance to acid and corrosion, high solids content Uses: adheres strongly to bare steel, coated steel, and inorganic zin silicate coated surfaces on construction, repair, field maintenance projects, offers corrosion control and weatherability

SHERWIN WILLIAM MACROPOXY 646 Fast Cure Epoxy Mastic OBO Use: Various structures Coating type: high solids, high build, fast drying, polyamide epoxy; high solids content ensures adequate protection of sharp edges, corners, and welds.

Substrate Materials: marginally prepared steel surfaces, Stainless steel, Aluminum, galvanized steel, concrete and masonry, ductile cast iron pipe Manufacturer: Sherwin Williams Protective and Marine Coatings Application Method: airless or conventional spray, brush,…

This is the start of the file's text. The full file is on GovTribe.