RSA Town of Madison WTP ARPA Improvement Project_Addendum No.2.pdf

PDF 292 KB Posted

Attached to
Town of Madison WTP ARPA Improvements Project
Solicitation number
18221
Issued by
Mathews County, Virginia

About this file

This document is Addendum No. 2 for the Town of Madison WTP ARPA Improvements Project, prepared for the Rapidan Service Authority (RSA) by Mangrum Consulting & Design. The project entails installing a new 0.25 MGD flocculation/sedimentation/filtration train to provide redundancy for the existing single-train system at the Town of Madison Water Treatment Plant. Additional project elements include intake rehabilitation, a pre-engineered filter building, new electrical service, yard piping, electrical and controls, and furnishing and installing all ancillary components. The bid date has been moved from July 13th at 2 PM to July 20th at 11 AM. A mandatory pre-bid conference was held on June 15th, 2023 at the Town of Madison WTP.

The project is located in Madison County, Virginia. The sealed bids are due by 11 AM on July 20th, 2023 at the RSA Ruckersville Office. There are no changes to the drawings or project manual noted in this addendum.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM No. 2 for the

Town of Madison WTP ARPA Improvements Project

Prepared For

Rapidan Service Authority 11235 Spotswood Trail Ruckersville, VA 22968

Prepared by C. Robert L. Mangrum, P.E., BCEE

Mangrum Consulting & Design 1500 Clayton Avenue Lynchburg, VA 24503

Addendum Date: July 6, 2023

This Addendum No. 2, dated July 6, 2023 amends or supplements the Contract Documents titled Town of Madison WTP ARPA Improvements Project Dated June 5, 2023 as indicated below:

Changes to Drawings:

None.

Changes to Project Manual:

None.

Questions & Responses:

Question 1: Can the bid date be moved from July 13th at 2PM to July 20th at 11:00 AM?

Response 1: Yes, the bid date has been moved to July 20th 2023 at 11:00 AM with this Addendum.

Attachments None.

END OF ADDENDUM NO. 2

END OF ADDENDUM NO. 2

File details come from the government source that posted it. Updated .