Summary

This is an Invitation to Bid (ITB 2026-22) document from the Emerald Coast Utilities Authority (ECUA) for the Twin Spires Lift Station Upgrades project (RS0050). The project encompasses the rehabilitation of an existing pumping station located in Twin Spires Subdivision, Mint Julep Trail, Pensacola, Florida, including demolition of existing infrastructure and installation of new connectivity piping to transfer operational control to ECUA. The scope of work includes selective demolition of existing equipment, rehabilitation of the wet well with new piping and valves, installation of electrical equipment and controls, concrete pad construction, new driveway connections, fencing replacement, sedimentation and erosion control measures, and site restoration with sod and grassing. Key dates include a non-mandatory pre-bid conference on September 17, 2026, at 9:00 AM; a mandatory site visit on September 17, 2026, at 10:00 AM; a question submission deadline of September 29, 2026, at 5:00 PM; and bid submission deadline of October 6, 2026, at 2:00 PM. The anticipated Notice of Intent to Award is October 8, 2026, with Board approval scheduled for October 27, 2026, and a Notice to Proceed expected in November 2026. Substantial completion is required within 180 calendar days, with final completion within 210 calendar days.

Bidders must submit a 5% bid bond with their proposals and will be required to provide a 100% performance and payment bond upon contract award. ECUA will provide the control panel and pumps; the contractor is responsible for all other materials, labor, and equipment necessary for complete project delivery. Liquidated damages are assessed at $500 per day for late substantial completion and $250 per day for late final completion. The contractor must perform at least 50% of service costs using its own employees, excluding material costs. All work must comply with ECUA's Engineering Manual, FDOT standards, Florida Statutes requirements including those related to iron and steel products, and applicable OSHA and industry codes. Contract documents include the EJCDC C-700 Standard General Conditions of Construction Contract (2018), supplementary and special conditions, and detailed specifications and plans provided by ECUA.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Invitation to Bid Number: ITB 2026-22 Twin Spires Lift Station Upgrades

CIP Project Number: RS0050

Stacy Hayden, P.E.

Director of Engineering

Emerald Coast Utilities Authority

Engineering Department

September 2026

PAGE LEFT INTENTIONALLY BLANK

Project Name: Twin Spires Lift Station Upgrades Project No.: RS0050

TABLE OF CONTENTS

1. Introduction

2. Advertisement

3. Instructions to Bidders

4. Contractor’s Bid

a. Licenses of Bidder

b. Quantities of Price of Base Bid

c. List of Subcontractors and Suppliers

d. Required Certifications and Disclosures

e. Bid Bond

f. Acknowledgement

5. Notices

a. Notice of Intent to Award

b. Notice of Award

c. Notice to Proceed

6. Insurance Requirements Upon Award

a. Risk Management Policy and Standard for Agreements, Contracts, and Leases

b. Insurance Certificate(s) of Contractor

7. Documents to be completed by Contractor upon award and completion of work

a. Standard Form of Agreement

b. Public Construction Bond

c. Contractor’s Final Affidavit

d. Warranty

8. Additional Project Documents

a. ECUA Engineering Manual Incorporated by Reference

b. EJCDC C-700, Standard General Conditions of Construction Contract (2018)

c. Supplementary General Conditions

d. Special Conditions

e. Plans and Specifications

INTRODUCTION

This information is subject to change and intended for ease of reference only. Always refer to the solicitation for information related to this project.

Summary of Project

Project Name Twin Spires Lift Station Upgrades

Project Number RS0050

ITB Number 2026-22

General Description of Project

The intent of this Contract is the rehabilitation of the existing Twin Spires pumping station, as well as demolition and connectivity piping required to transfer the pumping station to the Emerald Coast Utilities Authority.

Project Location Twin Spires Subdivision, Mint Julep Trail, Pensacola, Florida

Days to Substantial Completion 180 calendar days

Total Construction Time 210 calendar days

Liquidated Damages $500/day late for Substantial Completion, $250/day late for Final Completion

Anticipated Timeline

Event Date

Bid Advertisement Thursday, September 3, 2026

Pre-Bid Conference(s) Thursday, September 17, 2026 at 9:00 AM

Pre-Bid Site Visit(s) Thursday, September 17, 2026

Question Submission Deadline Tuesday, September 29, 2026 at 5:00 PM

Bid Submission Deadline / Bid Opening Tuesday, October 6, 2026 at 2:00 PM

Notice of Intent to Award Thursday, October 8, 2026

Board Meeting Tuesday, October 27, 2026

Notice to Proceed November 2026 (TBD)

Relevant Contact Information

ECUA Purchasing ECUA Engineering

Department ECUA Public Records

Custodian

Tony Howard

(850) 969-6530 bids@ecua.fl.gov

Mark Evan Robertson II, P.E.

(850) 969-6501 mark.robertson@ecua.fl.gov

Amanda Miller

(850) 969-3302 publicrecordsrequest@ecua.fl.gov

ADVERTISEMENT

Emerald Coast Utilities Authority (ECUA) requests sealed bid proposals for:

Bid Number: ITB 2026-22

Project Name: Twin Spires Lift Station Upgrades

Project Number: RS0050

Project Description: Rehabilitation of the existing Twin Spires pumping station, as well as demolition and connectivity piping required to transfer the pumping station to the Emerald Coast

Utilities Authority

Specifications and instructions for this project may be obtained from ECUA by sending an email to bids@ecua.fl.gov or visiting www.bidnetdirect.com/florida/emeraldcoastutilitiesauthority.

Sealed bids will be received by ECUA until 2:00 p.m. (CT) on Tuesday, October 6, 2026. Bids received after such time will not be opened. Submission of bids may be made electronically, by

U.S. Mail, or by hand delivery as provided in the solicitation.

A non-mandatory pre-bid conference will be held at 9:00 AM (CT) on Thursday, September 17, 2026, in the Engineering Conference Room at 9255 Sturdevant Street, Pensacola, Florida.

A mandatory pre-bid site visit will be held at Twin Spires Subdivision, Mint Julep Trail, Pensacola, Florida, at 10:00 AM (CT) on Thursday, September 17, 2026.

PAGE LEFT INTENTIONALLY BLANK

INSTRUCTIONS TO BIDDERS

General

1. Schedule. The following deadlines apply to this solicitation:

a. A non-mandatory pre-bid conference will be held in the Engineering Conference Room at 9255 Sturdevant Street, Pensacola, Florida, at 9:00 AM (CT) on Thursday, September 17, 2026.

b. A mandatory site visit must be completed on Thursday, September 17, 2026.

c. Attendance at the non-mandatory pre-bid conferences is strongly encouraged.

d. Bids are presently scheduled to be publicly opened and read at 2:00 p.m. (CT) on

Tuesday, October 6, 2026, in the Finance Conference Room (Rm #2202), 9255

Sturdevant Street, Ellyson Industrial Park.

e. Within two (2) business days following the bid opening, a bid tabulation showing the list of bidders along with the proposed prices and methods of submittable, if applicable, will be posted to BidNet Direct at www.bidnetdirect.com/florida/emeraldcoastutilitiesauthority.

f. Upon completing review of all bids, ECUA staff will publish a notice of intent to award the bid via BidNet Direct. ECUA staff may, at the sole discretion of the ECUA Executive

Director and in accordance with the governing documents of ECUA, forward their recommendation of award to the ECUA Citizens’ Advisory Committee presently scheduled to meet at 3:00 p.m. (CT) on Tuesday, October 20, 2026, in the ECUA Board

Room, 9255 Sturdevant Street, Ellyson Industrial Park. The recommendation of ECUA

Staff and/or Citizens’ Advisory Committee is presently scheduled to be presented to the

ECUA Board at their meeting scheduled for 3:00 p.m. (CT) on Tuesday, October 27, 2026, in the ECUA Board Room, 9255 Sturdevant Street, Ellyson Industrial Park.

2. Submission. All bids must be in the possession of ECUA as follows to be considered:

a. All bids must be made on the required bid form included herewith. All blank spaces for bid prices must be filled in, in ink or typewritten, and the form must be fully completed and executed when submitted.

b. In order to allow ECUA to fully evaluate the bid, the bidder must include product literature, data, and/or information as indicated in the specifications. Any deviation from the specifications or exceptions to the requirements contained herein must be clearly identified, in writing, separately from the product literature provided. Failure to comply with this provision shall be grounds for rejection of any bid.

c. Bids may be submitted electronically, by U.S. Mail, or by hand delivery. If submitting electronically, the bid must be submitted via www.bidnetdirect.com/florida/emeraldcoastutilitiesauthoriity. If submitting by U.S. Mail or hand delivery, the bid must be delivered in a sealed envelope (or other sealed packaging) clearly marked with the project name and bid number and must contain one

(1) original hard copy of the submission and one (1) electronic copy (stored on electronic media such as a USB flash drive). U.S. Mail and hand delivery bids must be delivered to the Finance Conference Room (Rm #2202), 9255 Sturdevant Street, Ellyson

Industrial Park, Pensacola, Florida 32514. If there are any discrepancies between the submitted versions of the bid, the hard copy shall govern.

d. Regardless of the method of delivery, each bidder shall be responsible for delivery of the bid prior to the start of the bid opening, and ECUA assumes no responsibility for same.

e. Bids offered or received after the start of the bid opening will be rejected.

f. Bidders must satisfy themselves as to the accuracy of the estimated quantities in the bid schedule by examination of the site and reviewing the drawings and specifications including any addenda. After bids have been submitted the bidder shall not assert that there has been any misunderstanding concerning the quantities of work or of the nature of the work to be done.

3. Award. ECUA reserves the right to waive informalities in any bid; reject any or all bids, in whole or in part; re-post a project, in whole or in part; and to accept a bid that, in ECUA’s judgment, is the lowest responsive and responsible bid. In accepting a bid, ECUA may award a contract based on the base bid, the base bid plus any or all alternates, or the base bid less any or all deductions, which ECUA selects in its sole discretion. All decisions made by ECUA shall be based upon what ECUA believes to be the best interests of its ratepayers, in its sole discretion. ECUA further reserves the right to increase or decrease quantities, as may be required to meet the needs of ECUA, at the unit price which was bid, and to award the contract to, or purchase items from, a single or multiple bidder(s). ECUA may make such investigations as deemed necessary to determine the ability of the bidder to perform the work, and the bidder shall furnish to ECUA all such information and data for this purpose that ECUA may request. ECUA reserves the right to reject any bid if the evidence submitted by, or investigation of, such bidder fails to satisfy ECUA that such bidder is properly qualified to carry out its obligations and to complete the work contemplated herein.

4. Documents. The official documents relating to this solicitation can be obtained via BidNet

Direct at www.bidnetdirect.com/florida/emeraldcoastutilitiesauthority, which contains all information deemed pertinent to this project in ECUA’s possession. The BidNet Direct service will also provide notification of updates and/or addenda when tracking this project is selected. Each potential bidder shall be responsible for selecting tracking in BidNet Direct, and ECUA assumes no responsibility for same. Absent a specific request in writing via email to the Purchasing and Stores Division at Bids@ecua.fl.gov, potential bidders will only be advised of updates and/or addenda when tracking is initiated by the potential bidder in

BidNet Direct. ECUA advises potential bidders, suppliers, and sub-contractors to rely only on information personally obtained from BidNet Direct and not from third parties.

5. Manufacturer’s Name and Approved Equivalents. Unless otherwise specified, any manufacturers’ names, trade names, brand names, information, or catalog numbers listed in a specification are descriptive, not restrictive. With ECUA’s prior approval, the bidder may provide any product that meets or exceeds the applicable specifications. The bidder shall demonstrate comparability in the form of catalog materials, literature, specifications, test data, etc., as applicable. ECUA shall determine, in its sole discretion, whether a product is acceptable as an equivalent. Any such request by a bidder must be submitted to ECUA by the question submission deadline.

6. Questions. All questions must be submitted to ECUA, in writing via email, up to seven (7) business days prior to the bid opening. Questions received outside this time frame will not be answered. Interpretations or clarifications in response to such questions will be issued by addenda via BidNet Direct, and only questions answered by addenda will be binding.

Other interpretations or clarifications, whether issued orally or in writing, will be without legal effect. Questions must be submitted in writing via email to the Purchasing and Stores

Division at Bids@ecua.fl.gov or during the pre-bid conference.

7. Withdrawal. Any bid may be withdrawn prior to the start of the bid opening. No bids may be withdrawn within 90 days after the actual date of the opening thereof.

8. Modification. A bidder may not modify its bid after the start of the bid opening. Errors in the extension of unit prices stated in a bid or in multiplication, division, addition, or subtraction in a bid may be corrected by ECUA prior to award. In such cases, unit prices shall not be changed. Additionally, in the event of a conflict between a written number and a numerically listed number, the written number shall control, and ECUA may correct the numeric number, so it conforms to the written number prior to award

9. Addenda. No information obtained from any source shall affect the risks or obligations assumed by the bidder or relieve the bidder from fulfilling any of the conditions of the contract, unless properly documented by an issued addendum.

10. Limitation on Contact During Solicitation Period. There shall be a Cone of Silence in place during the period of time beginning when the bids/proposals for solicitations (Invitation to Bid or the Request for Proposal), or Requests for Letters of Interest, Qualifications, or

Invitation to Negotiate, as applicable, are advertised and ending once the ECUA Board awards the contract, and any resulting Bid Protest is resolved or the Solicitation is otherwise cancelled. All communications concerning any aspect of any Solicitation, during the Cone of Silence period, shall be sent in writing and only to the sole point of contact identified in the Specifications included in the Solicitation. Conduct inconsistent with this section may be grounds for disqualifying the offending proposer from consideration or from submitting any future proposal.

11. Bonds.

a. Each bid must be accompanied by a bid bond payable to ECUA for five percent (5%) of the total amount of the bid. Electronic bid bonds shall be accepted if submitted through

BidNet Direct.

b. Upon execution of an agreement for this contract, a public construction bond in the amount of one hundred percent (100%) of the maximum contract price with a corporate surety will be required for the faithful payment and performance of the contract. Pursuant to Section 255.05 of the Florida Statutes, before commencing the work, the contractor shall record the bond and provide ECUA with a certified copy of the recorded bond.

c. An attorney-in-fact who signs a bond required herein must submit with each bond a certified copy of their power of attorney, which provides that it is current or effective as of the date of execution of the bond.

d. Pursuant to Section 255.05 of the Florida Statutes, a contractor may provide an alternative form of security in the form of cash; a money order; a certified check; a cashier's check; or a domestic corporate bond, note, or debenture as authorized in

Section 625.317 of the Florida Statutes.

12. Subcontractors and Suppliers. A bidder shall include in its bids the names and addresses of the subcontractors and suppliers it has solicitated or whose prices were used to calculate the bid. Unless specifically approved in writing by ECUA, the low bidder will be required to perform at least fifty percent (50%) of the cost of the services (excluding material costs) required by the contract by using its own employees. A bidder to whom the contract is awarded shall supply the names and addresses of subcontractors and suppliers used for the project when requested by ECUA.

13. Insurance. The bidder shall be required to certify it currently has, or has the ability to obtain, the insurance required for the solicitation. Certificate(s) of insurance, as specified herein, shall be submitted at the time of execution of the contract.

14. Safety. The bidder shall conform to all ECUA safety policies and procedures applicable to this solicitation.

15. Taxes. A bidder shall not include taxes in its bid. ECUA is exempt from federal, state, and local taxes, and the tax-exempt number 85-8012640152C-4 applies.

16. Contract Formation.

a. No contract shall be formed between ECUA and a Bidder until ECUA and the bidder have fully executed the Standard Form of Agreement. ECUA shall not be liable for any costs incurred by a bidder in preparing or producing its response or for any work performed before the contract is effective.

b. This ITB shall be incorporated into the final contract between ECUA and the Bidder.

c. The Bidder to whom the contract is awarded shall execute the contract and obtain the bond and insurance certifications within fifteen (15) business days following delivery of the Notice of Award to the Bidder. If the Bidder fails to properly execute the agreement or obtain the required bond or insurance within the allotted time, ECUA may consider the Bidder in default, in which case the bid bond or check accompanying the Bid shall become payable to ECUA, the contract may be awarded to the next highest responsive bidder, and the Bidder may not be considered as a responsive bidder for future contracts for a period of at least one (1) year.

d. ECUA, within twenty (20) business days of receiving acceptable public construction bond, insurance certificate(s), and the executed Standard Form of Agreement, shall sign the agreement and return to the Bidder an executed duplicate of the agreement. Should

ECUA not execute the agreement within such period, the Bidder may withdraw the signed agreement by providing written notice to ECUA of its election to withdraw.

e. A notice to proceed, executed by an authorized ECUA representative, shall be issued by ECUA and delivered to the Bidder when the Bidder may begin work on the project.

Notwithstanding, before commencing any work, the Bidder shall record the public construction bond in the public records of Escambia County, Florida, and provide ECUA with a certified copy of the recorded bond.

17. Terms and Conditions. ECUA objects to and shall not consider any additional terms, modifications, or conditions submitted by a bidder, including but not limited to any additional terms, modifications, or conditions appearing in documents attached as part of a response.

In submitting its response, the bidder agrees that any additional terms, modifications, or conditions, whether submitted intentionally or inadvertently, shall have no force or effect.

Failure to comply with terms and conditions of the contract, including those specifying information that must be submitted with a response, shall be grounds for rejection of the response.

18. Conflict in solicitation. In the event of a conflict between any documents related to this

Solicitation, the conflict shall be resolved in the following order of priority (highest to lowest):

a. Addenda to this ITB, if any (in reverse order of issuance)

b. Plans and Specifications

c. Standard Form of Agreement

d. Special Conditions

e. Supplementary General Conditions

f. EJCDC C-700, Standard General Conditions of Construction Contract (2018)

g. ECUA Engineering Manual

h. This ITB document.

19. Public Records. Article 1, Section 24, Florida Constitution, guarantees every person access to all public records, and Section 119.011, Florida Statutes, provides a broad definition of public record. As such, all responses to a competitive solicitation are public records unless exempt by law. Bidder is required to comply with public records laws codified in Chapter 119, Florida Statutes, and is specifically required to:

a. Keep and maintain public records required by the public agency to perform the service.

b. Upon request from the public agency's custodian of public records, provide the public agency with a copy of the requested records or allow the records to be inspected or copied within a reasonable time at a cost that does not exceed the cost provided in this chapter or as otherwise provided by law.

c. Ensure that public records that are exempt or confidential and exempt from public records disclosure requirements are not disclosed except as authorized by law for the duration of the contract term and following completion of the contract if the contractor does not transfer the records to the public agency.

d. Upon completion of the contract, transfer, at no cost, to the public agency all public records in possession of the contractor or keep and maintain public records required by the public agency to perform the service. If the contractor transfers all public records to the public agency upon completion of the contract, the contractor shall destroy any duplicate public records that are exempt or confidential and exempt from public records disclosure requirements. If the contractor keeps and maintains public records upon completion of the contract, the contractor shall meet all applicable requirements for retaining public records. All records stored electronically must be provided to the public agency, upon request from the public agency's custodian of public records, in a format that is compatible with the information technology systems of the public agency.

IF THE BIDDER HAS QUESTIONS REGARDING THE APPLICATION OF CHAPTER 119,

FLORIDA STATUTES, TO THE CONTRACTOR'S DUTY TO PROVIDE PUBLIC RECORDS

RELATING TO THIS CONTRACT, CONTACT THE CUSTODIAN OF PUBLIC RECORDS

AT (850) 969-3302, publicrecordsrequest@ecua.fl.gov, AND/OR 9255 Sturdevant Street, Pensacola, Florida 32514.

20. Conflict of Interest. ECUA is subject to Part III, Chapter 112 of the Florida Statutes.

Accordingly, bidders shall disclose with their response the name of any officer, director, employee, or other agent who is also an employee, officer, board member, or committee member of ECUA. Bidders shall also disclose the name of any ECUA employee, officer, or director who owns, whether directly or indirectly, an interest of five percent (5%) or more in the bidder or its affiliates.

21. Social, Political, or Ideological Interests. Pursuant to Section 287.05701 of the Florida

Statutes, ECUA may not request documentation of or consider a vendor’s social, political, or ideological interests when determining if the vendor is a responsible vendor and may not give preference to a vendor based on the vendor’s social, political, or ideological interests.

22. Convicted Vendor. Pursuant to Section 287.133 of the Florida Statutes, no person or affiliate who has been placed on the convicted vendor list following a conviction for a public entity crime may do any of the following: submit a bid, proposal, or reply on a contract to provide any goods or services to a public entity; submit a bid, proposal, or reply on a contract with a public entity for the construction or repair of a public building or public work;

submit bids, proposals, or replies on leases of real property to a public entity; be awarded a contract with any public entity or perform work thereunder as a contractor, supplier, subcontractor, or consultant; or transact business with any public entity in excess of the threshold amount provided in Section 287.017 of the Florida Statutes for CATEGORY TWO for a period of 36 months following the date of being placed on the convicted vendor list.

23. Scrutinized Entities. Pursuant to Section 287.135 of the Florida Statutes, a company or other entity is ineligible to and may not bid on, submit a proposal for, or enter into or renew a contract with ECUA for certain goods or services if the company or other entity: is on the

Scrutinized Companies or Other Entities that Boycott Israel List, is engaged in a boycott of

Israel, is on the Scrutinized Companies with Activities in Sudan List or the Scrutinized

Companies with Activities in Iran Terrorism Sectors List, or is engaged in business operations in Cuba or Syria.

24. Lumber, Timber, or Other Forest Products. Pursuant to Section 255.2575 of the Florida

Statutes, any lumber, timber, or other forest products used in this project should be those produced and manufactured in this state, so long as such products are available and their price, fitness, and quality are equal to those produced or manufactured outside this state.

See Special Conditions for applicability.

25. United States-Produced Iron and Steel. Any iron or steel product permanently incorporated into this project must be produced in the United States as provided in Section

255.0993(2) of the Florida Statutes and Chapter 60D-16 of the Florida Administrative Code.

See Special Conditions for applicability.

Bid Protest Procedures

Any person whose substantial interests are directly and adversely affected by any portion of a

Solicitation (including plans, specifications, or other requirements) or any decision based thereon

(a “Protestor”) may file a Protest in accordance with the following rules. Failure of a Protestor to comply with the times provided herein shall constitute a waiver of Protest rights.

Notice of Protest of any portion of a Solicitation or intended decision based thereon shall be delivered to ECUA within three (3) business days of the Protestor’s receipt of the Solicitation or notice of any intended decision based thereon. A Notice of Protest shall be in writing, shall state the subject matter of the Protest, and shall be submitted to the following via hand delivery, registered or certified mail, postage prepaid, or electronic mail with the subject line clearly identifying the communication as a Protest and the Solicitation number (e.g. Bid Protest – ITB

2045-500) to:

Attn: Executive Director

9255 Sturdevant Street

Pensacola, FL 32514

Bidprotest@ecua.fl.gov

With a hard copy and electronic copy being provided to:

ECUA General Counsel, Robert O. Beasley

40 Palafox Place, Suite 300

Pensacola, FL 32502

ROBservice@lawpensacola.com

Or subsequent Board Attorney

A formal written Protest shall be delivered to ECUA within ten (10) business days after the submitting of Notice of Protest. A formal written Protest shall state with particularity the facts and the law on which the Protest is based.

Upon receipt of a Notice of Protest, which has been timely delivered to ECUA, the Executive

Director shall pause all actions of ECUA related to the Solicitation and subsequent award based thereon until the Protest has been resolved. However, if the Executive Director, at his/her sole discretion, determines that such a delay would be detrimental to the interests of ECUA or the public health, safety, or welfare, the Executive Director may direct that the Solicitation proceed and/or recommend to the ECUA Board that the Solicitation be awarded despite the pending

Protest. In such an event, the award based on such Solicitation shall be subject to the outcome of the Protest, and ECUA shall give notice of such to the Contractor which is awarded the

Contract. Notwithstanding, if ECUA does not prevail in the Protest, ECUA may take such action as it considers appropriate, which may include, but shall not be limited to, award based on the

Solicitation to the prevailing party, cancellation of the awarded Solicitation, or readvertisement.

The Executive Director may provide a reasonable opportunity to resolve a Protest by agreement.

If an agreement is not reached within such time as the Executive Director considers reasonable under the circumstances, the Executive Director shall review the facts and the law on which the

Protest is based and shall render a decision which shall be in writing and shall be promptly transmitted to the Protestor.

If the Protestor wishes to continue the Protest beyond the decision of the Executive Director, the

Protestor shall submit a petition for review by the ECUA Board. This petition shall be made in writing and delivered to the Executive Director within ten (10) business days after notice of the decision of the Executive Director. Such petition shall state the particular grounds on which it is based and may include pertinent documents and evidence relating thereto. Any grounds not stated shall be deemed to have been waived by the Protestor. This petition must also be accompanied by a Bond of an amount equal to five percent (5%) of the value of the Bid/proposal

(“Protest Bond”). This Protest Bond shall be in the form required by the Solicitation for other bonds. Failure of the protestor to timely deliver a petition for review by the ECUA Board or required

Bond shall constitute a waiver, and the decision of the Executive Director shall immediately be final and binding.

The Protest Bond shall be conditioned upon the payment of all costs and charges incurred by

ECUA as a result of the Protest. If the Protestor prevails in a Protest, the bond shall be returned to the Protestor. If ECUA prevails in a Protest, ECUA shall be entitled to recover the costs and charges incurred as a result of the Protest. Notwithstanding, the prevailing party of a Protest shall not be entitled to recover its reasonable attorney’s fees unless allowed by Florida Statutes.

BID

ITB Number 2026-22

Project Name: Twin Spires Lift Station Upgrades

Project Number: RS0050

Bidder / Company

Physical Address

Contact Person

Telephone Number

E-mail Address

Fax Number

Employer Tax ID Number

Bidder’s relevant federal, state, and/or local license(s):

Relevant License(s) License Number Issued By

Item Description Qty. Unit Unit Cost Total Cost

BASE BID

General

1.01 General Conditions and Supervision 1 LS $________________ $________________

1.02 Mobilization 1 LS $________________ $________________

1.03 Maintenance of Traffic 1 LS $________________ $________________

1.04 Select Backfill 1 LS $________________ $________________

1.05 Solid Sod 200 SY $________________ $________________

1.06 Grassing and Mulching 200 SY $________________ $________________

1.07 Silt Fence 150 LF $________________ $________________

1.08 Provide Record Documents 1 LS $________________ $________________

1.09 Remove existing wooden fence and replace fence in its entirety in accordance with ECUA's Engineering Manual Section 2830 except where amended elsewhere

1 LS

Item Description Qty. Unit Unit Cost Total Cost Sewer

2.01 Selective Demolition as required including, but not limited to, demolition of existing underground storage tank and removal of solids 1 LS $________________ $________________

2.02 Operation of LS (in any condition, existing, new, or bypassed) from NTP to final completion 1 LS $________________ $________________

2.03 Rehabilitation of Twin Spires Pump Station inc wet well piping, discharge piping, gravity piping, valves, pipe supports, connections and all other piping components 1 LS $________________ $________________

2.04 New concrete pads and any other concrete required exclusive of the driveway connection 1 LS $________________ $________________

2.05 Station Bypassing as required for rehabilitation 1 LS $________________ $________________

2.06 Installation of Manhole (> 10 VF Deep) 1 EA $________________ $________________

2.07 Electrical Equipment 1 LS $________________ $________________

2.08 Wetwell coating 1 LS $________________ $________________

Item Description Qty. Unit Unit Cost Total Cost Roadway

3.01 FDOT #57 Gravel for Lift Station inc geofabric, 8" thick 2,100 SF $________________ $________________

3.02 Aggregate Driveway 1,850 SF $________________ $________________

3.03 Concrete Driveway Connection 230 SF $________________ $________________

3.04 Water Line Connection 1 LS $________________ $________________

3.05 Bollards 4 EA $________________ $________________

3.06 Telephone Pedestal ALLOWANCE 1 EA $_10,000_________ $_10,000________

TOTAL BID

ECUA has the right to award the project on any combination of Base Bids, ALternates and Unit Prices that the ECUA deems in its best interest. ECUA will adjust unit quantities based on actual installed quantities. Bidder will complete the Work in accordance with the Contract Documents for the following price(s):

Quantities and Price of Base Bid

RS0050

ECUA Twin Spi

Project Number

Base Bid Total Written:

SECTION 01000

MEASUREMENT AND PAYMENT

01000-1

PART 1 – GENERAL

A. The unit price or lump sum bid items shall be compensation in full for furnishing all materials, labor, equipment and incidentals necessary to complete the item in place in every detail in accordance with the plans and specifications. There will be no direct compensation for clean-up, restoration of property, and incidentals not shown in the proposal, and such incidentals shall be included in the unit price for the related item of work.

B. All work shall be completed in accordance with the current edition of ECUA’s Engineering Manual.

C. All paving and storm drainage work shall be completed in accordance with the Florida Department of Transportation (FDM) Standard Specifications for Road and Bridge Construction, 2026 Edition, except as amended herein.

1.01 GENERAL CONDITIONS AND SUPERVISION

A. Payment under this item shall constitute full compensation for all project overhead and indirect costs necessary to complete the Work but not otherwise included in individual bid items. This includes, but is not limited to, project management, field supervision, superintendent, safety program implementation, temporary facilities, temporary utilities, quality control, scheduling, project coordination, permits (excluding utility agency permits specifically identified elsewhere), bonds, insurance, mobilization support activities not paid under separate bid items, construction documentation, record keeping, progress meetings, environmental compliance, traffic coordination, SWPPP implementation per Section 01100, housekeeping, security, and all labor, equipment, materials, and incidentals required for administration and management of the Work. No separate payment will be made for these activities, and all associated costs shall be included in the lump sum price for General Conditions and Supervision.

B. This item shall include all testing required to implement the plans, including but not limited to, compaction testing, concrete, pressure testing, leak testing, and any other item required in ECUA’s Engineering Manual.

1.02 MOBILIZATION

A. Perform preparatory work and operations in mobilizing for beginning work on the project, including, but not limited to, those operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site and for the establishment of temporary offices, buildings, safety equipment and first aid supplies, and sanitary and other facilities.

1.03 MAINTENANCE OF TRAFFIC

A. The lump sum bid for this item shall be compensation in full for all labor, material, and equipment required to secure the work zone for station bypassing should the work be

01000-2 needed. Additionally work on the driveway shall incorporate appropriate MOT in accordance with ECUA, FDOT and County requirements.

1.04 SELECT BACKFILL

A. The lump sum bid for this item shall be compensation in full for furnishing all materials, equipment, labor, and incidentals necessary to install the required quantity of select material used for backfill which shall include furnishing material meeting the requirements of the specifications, backfilling, compacting and hauling away existing material. All select material shall be approved by the Engineer before being used for backfill. The Contractor shall furnish a certificate from a commercial testing laboratory attesting to the percentage of clay in the select backfill. No material may be used if more than 12% by weight passes the #200 sieve.

1.05 SOLID SOD

A. The unit price bid for this item shall be compensation in full for one (1) square yard of solid sod complete and in place. Where sod is being replaced on an established lawn, the new sod shall match the type removed. Locations requiring sod will be as specified by the engineer. All the disturbed areas shall be sodded and included in the base bid. Additions/Deletions will be used for field adjustments.

1.06 GRASSING AND MULCHING

A. The unit price bid for this item shall be compensation in full for one (1) square yard of grassing and mulching under which pipe is laid, complete in place including ground preparation, fertilizing, seeding, straw, and maintenance. This bid item shall include the import/use of a minimum of 2 inches of topsoil, leveling, and removal of any deleterious debris prior to seeding. In measuring this item for payment, the length multiplied by the width authorized by the Engineer, shall be the amount paid for, regardless of the area actually grassed. Grassing and mulching areas outside of the construction easements will be considered the responsibility of the Contractor and will not be measured for payment. Locations requiring grassing and mulching will be as specified by the engineer. All disturbed areas shall be sodded and included in the base bid. Additions/Deletions will be used for the field adjustments.

1.07 SILT FENCE

A. The unit price bid for this item shall be compensation in full for one (1) linear feet of Class 3 erosion fencing installed in accordance with FDOT requirements. Fencing shall be maintained for the life of the project and removed upon full restoration.

1.08 PROVIDE RECORD DRAWINGS

01000-3

A. The lump sum bid for this item shall be compensation in full for all labor, material, and equipment required to record and provide autocad drawings as well as a signed and sealed survey by a registered Florida surveyor in accordance with ECUA’s engineering manual.

1.09 REMOVE EXISTING FENCING AND INSTALL NEW FENCING

A. The lump sum bid for this item shall be compensation in full for all labor, material, and equipment required to demolish and dispose of the existing fencing and replacement with a new fence system as shown on the plans. This line item shall include all gates, wire, fabric, posts, Contractor shall coordinate with the adjacent property owner to prevent damage to the property owner’s fencing. Fencing shall be in installed in accordance with ECUA’s Engineering Manual, Section 2830.

PART 2 – BID ITEMS - SEWER

2.01 SELECTIVE DEMOLITION

A. The lump sum bid for this item shall be compensation in full for all labor, material, and equipment required to demolish and dispose of the existing solids tank, piping, valves, appurtenances, electrical panels, slab, valve vault, fencing, and any incidentals necessary to complete the work at the appropriate time to keep the wet well operational during construction.

2.02 OPERATION OF TWIN SPIRES LIFT STATION

A. The lump sum bid for this item shall be compensation in full for all labor, material, and equipment required to operate the existing pump station and new pump station including repairs, pumping, cleaning, reporting, and general maintenance from the date of the Notice to Proceed until the date of final completion.

2.03 REHABILITATION OF TWIN SPIRES LIFT STATION

A. The lump sum bid for this item shall be compensation in full for all labor, material, and equipment required to rehabilitate the existing wet well including the proposed top, pumps, piping, valves, appurtenances, electrical, slab, valve pad, bypass connections, fencing, and any incidentals necessary to complete the work as shown on the plans.

B. ECUA will provide the pumps and pump cables.

C. All other items shall be provided by the Contractor

2.04 MISCELLANEOUS CONCRETE

A. The lump sum bid for this item shall be compensation in full for furnishing all materials, equipment, labor, and incidentals necessary to install concrete used for and any other items for a functioning system.

01000-4 foundations, top slabe, anchors, thrust blocks, encasement for pipe, pipe protection slabs, concrete collars around pipe, or concrete piers as shown on the plans.

2.05 BYPASS OF TWIN SPIRES LIFT STATION

A. The lump sum bid for this item shall be compensation in full for all labor, material, and equipment required to bypass the Pump Station when necessary for completion of work.

No equipment will be provided by ECUA.

2.06 MANHOLE

A. The unit price bid for this item shall be compensation in full for one (1) manhole of the

48 inch diam ter, types, and depths complete with frames and covers, inverts, connections, and stub-outs in place. The depth of manhole shall be the vertical distance from the top of manhole cover to the lowest pipe invert. This item shall include bypass pumping, dewatering, pipe extensions to manhole, manhole cover, watertight manhole insert, manhole joint wrap, non-structural liner (per specifications), 12 inches of #57 limestone base, and any incidentals necessary to complete the work. This line item shall include the removal and replacement of roadway base and asphalt for a diameter of 10’ around the proposed manhole, roadway to be installed per the details and specifications. No additional payment will be made for the extra roadway asphalt and base required. Payment shall include but not limited to;

i. Excavation, transporting, storing, protecting, drying, returning and backfill of excavation materials,

ii. Importing approved common fill, backfill compaction,

iii. Excavation sheeting and/or shoring, bracing whether or not shown on drawings including systems called out to be designed by the CONTRACTOR’s professional engineer,

iv. All trench and excavation cutting requiring protective sheeting, shoring, trench shields and boxes, and other OSHA required means, methods and devices shall be designed by a Florida Licensed Professional Engineer for live and dead loads and groundwater conditions when depth exceeds 20 feet.

B. The bid item shall include a protective liner for the manhole in accordance with ECUA’s Engineering Manual.

2.07 ELECTRICAL EQUIPMENT AND INSTALLATION

A. The lump sum bid for this item shall be compensation in full for all materials, labor, equipment, and incidentals necessary to complete all electrical construction, including excavation for foundations and utilities within the building perimeter, for building complete in-place, as shown on the drawings. ECUA shall provide the control panel and all wiring and incidentals shall be the responsibility of the Contractor

2.08 RELINING OF PS WETWELL

e

01000-5

A. The unit price bid for this item shall be compensation in full for rehabilitation of one vertical linear foot of the 10 foot diameter wetwell, including all internal surfaces and shall include, but not be limited to, cleaning, lining, reinstating service, sealing all pipe penetrations, and bypass pumping in accordance with ECUA Engineering Manual, Specification 2578.

PART 3 – BID ITEMS - MISC

3.01 #57 STONE PIPE BEDDING – 8” THICK - LIFT STATION

A. The unit price bid shall be compensation in full for the installation of one square foot of compacted FDOT #57 lift station restoration, complete in place. The contract measurement for a “square foot” shall be the area authorized by the Engineer or Owner. The restoration shall be installed to the limits of the new fence line and to a thickness of 8”. The contract unit price shall also include any incidentals necessary to complete the work.

B. Payment for this item shall be made at the Contract unit price per square yard. The unit price shall constitute full compensation for furnishing all labor, materials, equipment, and incidentals necessary to complete the work, including but not limited to:

a. Furnishing and placing approved crushed aggregate.

b. Excavating, removing, or redistributing excess fill as required to establish the specified finished elevation.

c. Fine grading, shaping, proof rolling, and compacting the subgrade.

d. Placing, spreading, watering, and compacting the gravel to a minimum compacted thickness of 8 inches.

e. Disposal of unsuitable or excess excavated material.

f. All testing, equipment, labor, and incidentals required to produce a completed gravel surface in accordance with the Contract Documents.

g. No separate payment will be made for excavation, grading, compaction, removal of excess fill, or other work necessary to prepare the site for installation of the gravel surface, as these costs shall be included in the Contract unit price.

C. This bid item shall include a geofabric below the aggregate meeting AASHTO M 288 Class 2.

3.02 Aggregate Driveway

A. The unit price bid shall be compensation in full for the installation of one square foot of compacted driveway, complete in place. The contract measurement for a “square foot” shall be the area authorized by the Engineer or Owner. The construction shall be installed to the limits of the plans. The contract unit price shall also include any incidentals necessary to complete the work. The work shall consist of the following section:

a. 12” stabilized subgrade to LBR 40 and 98% Modified Proctor

01000-6

b. 8” of FDOT #57 on top of geofabric

c. 3” of FDOT #89

B. Payment for this item shall be made at the Contract unit price per square yard. The unit price shall constitute full compensation for furnishing all labor, materials, equipment, and incidentals necessary to complete the work, including but not limited to:

a. Furnishing and placing approved crushed aggregate.

b. Excavating, removing, or redistributing excess fill as required to establish the specified finished elevation.

c. Fine grading, shaping, proof rolling, and compacting the subgrade.

d. Placing, spreading, watering, and compacting the gravel to a minimum compacted thickness of 6 inches.

e. Disposal of unsuitable or excess excavated material.

f. All testing, equipment, labor, and incidentals required to produce a completed gravel surface in accordance with the Contract Documents.

g. No separate payment will be made for excavation, grading, compaction, removal of excess fill, or other work necessary to prepare the site for installation of the gravel surface, as these costs shall be included in the Contract unit price.

C. This bid item shall include a geofabric below the aggregate meeting AASHTO M 288 Class 2.

3.03 CONCRETE DRIVEWAY CONNECTION

A. The Contract unit price per square yard for 12-Inch Reinforced Concrete Driveway Connection shall constitute full compensation for furnishing all labor, materials, tools, equipment, and incidentals necessary to complete the work, including but not limited to:

a. Excavation to the required lines and grades and disposal of excess or unsuitable material.

b. Preparation, proof-rolling, moisture conditioning, grading, and compaction of the subgrade.

c. Construction of 12 inches of stabilized subgrade meeting the minimum LBR

40, including furnishing and incorporating all stabilization materials.

d. Furnishing, placing, finishing, curing, and protecting 12-inch-thick, 4,000 psi

Portland cement concrete pavement.

e. Furnishing and placing No. 5 reinforcing bars spaced at 10 inches on center each way in each face, including chairs, supports, ties, laps, splice lengths, and all reinforcing accessories.

f. Furnishing, installing, and removing forms.

g. Construction and sealing of contraction, construction, expansion, and isolation joints as shown on the plans or specified.

h. Saw cutting, edge finishing, surface texturing, curing compound, and all concrete finishing operations.

i. Backfilling, grading, and restoration adjacent to the driveway.

01000-7

j. All testing, quality control, cleanup, and incidental work necessary to provide a complete and accepted installation.

k. Adjustment of subgrade due to existing utilities B. No separate payment will be made for excavation, stabilized subgrade, reinforcing steel, joint materials, forms, curing, testing, removal of existing concrete, or incidental items required to complete the driveway connection. All such costs shall be included in the Contract unit price for the concrete driveway connection.

3.04 WATER LINE SERVICE

A. Measurement and Payment and shall be compensation in full for the 2-Inch Water Service Assembly and shall be on a lump sum (LS) basis for each complete installation accepted by the Engineer. The measured quantity shall include furnishing all labor, materials, equipment, tools, testing, and incidentals required to install a new 2-inch potable water service and provide a complete operational hose connection assembly in accordance with the ECUA Engineering Manual, approved construction drawings, and all applicable AWWA, ASSE, and manufacturer requirements.

The work shall include, but not be limited to:

a. Installation of the new 2-inch potable water service line, including all fittings, couplings, restraints, valves, tapping saddles, and appurtenances complete and in place from the existing water main.

b. Demolition of the old service line including capping at the main.

c. Furnishing and installation of a 1.5-inch ECUA-approved backflow prevention assembly of the type shown on the plans and required by ECUA’s Cross-Connection Control Program. The assembly shall be installed immediately downstream of the owner’s control valve or as otherwise approved by ECUA and shall remain readily accessible for inspection and testing.

d. Furnishing and installation of a non-heated insulated freeze protection enclosure sized to completely house the backflow prevention assembly, piping, and associated appurtenances.

e. Furnishing and installation of one freeze-proof sanitary yard hydrant in accordance with the ECUA Engineering Manual, complete with drain feature, operating rod, foundation, drainage media where required, and all manufacturer-recommended accessories.

f. Furnishing and installation of one heavy-duty hose rack securely mounted adjacent to the yard hydrant.

g. Concrete pads, anchors, supports, blocking, stainless steel hardware, protective bollards if shown on the plans, and all miscellaneous fittings required for a complete installation.

h. Excavation, bedding, backfill, compaction, restoration, disposal of excess material, and site grading.

i. Pressure testing, flushing, disinfection, backflow testing and certification by a licensed tester, startup, and all documentation required for ECUA acceptance.

01000-8

j. Coordination with ECUA for inspections and all temporary measures necessary to maintain existing water service during construction.

k. All permit fees and other items detailed in ECUA’s Engineering Manual.

B. No separate payment will be made for fittings, connectors, supports, testing, excavation, restoration, concrete pads, anchors, insulation, hardware, or other incidental materials required to complete the installation, as these costs shall be included in the Contract Lump Sum price.

3.05 BOLLARD

A. The unit price bid for this item shall be payment for one (1) - 8-inch steel SCH 40 concrete-filled bollard, painted yellow and shall be made at the Contract unit price per each bollard installed and accepted. The unit price shall constitute full compensation for furnishing all labor, materials, equipment, concrete, coatings, excavation, backfill, and incidentals necessary to complete the work. No separate payment will be made for concrete fill, foundations, surface preparation, painting, or related appurtenant work

3.06 TELEPHONE PEDESTAL ALLOWANCE

A. The ALLOWANCE for this item is established to reimburse the Contractor for utility relocation work performed by the telephone service provider or its authorized representatives. Payment will be made as a pass-through allowance based on the actual invoiced cost incurred and approved by ECUA.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .