RR-23-4939 Reagan Memorial Tollway (I-88) Pavement Repairs IL 251 to IL 56, MP 76. 1 to MP 113. 6
Solicitation number
24-557THA-ENGCO-B-41778
Issued by
Monroe County, Illinois

About this file

This document is an Addendum to Contract RR-23-4939 issued by the Illinois State Toll Highway Authority. The contract is for Reagan Memorial Tollway (I-88) Pavement Repairs between Mile Post 76.1 and Mile Post 113.6 in Ogle, Dekalb and Kane Counties, Illinois. The scope of work includes intermittent partial depth pavement repairs, shoulder treatment, raised pavement marker work, crack repairs, pavement marking, maintenance of traffic, and other miscellaneous work. The Pre-Bid Meeting was held on March 12, 2024, and the bid opening is scheduled for April 12, 2024. The anticipated Notice-to-Proceed is July 15, 2024, with an Interim Completion Date of November 1, 2024, Substantial Completion Date of August 29, 2025, and Contract Completion Date of September 30, 2025.

The contract has Disadvantaged Business Enterprise (DBE) and Veteran-Owned Small Business (VOSB) participation goals of 24% and 2% respectively. Other diversity programs such as the Earned Credit Program, Technical Assistance Program, Partnering for Growth, and Construction Works are available. Coordination with the Illinois Department of Transportation (IDOT) is required for work near interchanges. Responses to plan holder questions will be provided in Addendum No. 1, scheduled for the week of April 1, 2024.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Illinois State Toll Highway Authority Contract No. RR-23-4939 Addendum 1 Page 1 of 1 April 3, 2024

ADDENDUM NO. 1

TO

CONTRACT REQUIREMENTS

FOR CONTRACT RR-23-4939

ILLINOIS STATE TOLL HIGHWAY AUTHORITY

Date: 4/3/2024

For which proposals will be received by the Illinois State Toll Highway Authority through electronic bidding via BidBuy until 10:30:00 A.M. local time, April 12, 2024

NOTICE OF REVISION TO CONTRACT

NOTES:

1. The minutes and sign-in sheet from the Optional Pre-Bid Meeting held on March 12, 2024 are included in this Addendum.

END OF ADDENDUM CHANGES

Illinois State Toll Highway Authority Contract No. RR-23-4939 Addendum 1 1 of 6 April 3, 2024

Capital Program

PRE-BID MEETING MINUTES

MEETING PURPOSE: Optional Pre-Bid Meeting - Contract RR-23-4939

MEETING DATE: March 12, 2024

MEETING TIME: 1:00 pm

CHAIRPERSON: Kathi Hacking – Senior Contract Negotiator

LOCATION: Illinois Tollway Teams

TO:

Names Initials Organization / Title

Eric Occomy EO Procurement / Chief of Contract Services Maria Campuzano MC Procurement/Deputy Chief of Procurement Kathi Hacking KH Procurement/Senior Contract Negotiator Ruth Howe RH Procurement / Contract Analyst Sainey Jobe SJ Procurement / Deputy Chief of Contract Compliance Tim Ersfeldt TE Engineering / Project Manager Brenda Lowery BL DSE / Ames Engineering

TOPICS TO BE DISCUSSED:

1.0 Open: Welcome; Self-introduction by Procurement Representative

2.0 Self-Introduction of Attendees – State name and affiliation loudly for all to hear (Please sign-in using the provided sign-in sheet)

2.1 Tollway Procurement – Contract Services

2.2 Tollway Procurement – Contract Compliance

2.3 Tollway – Diversity

2.4 Tollway – Engineering Project Manager

2.5 Design Section Engineer

2.6 Other Attendees

3.0 Brief Project Description (by Procurement Representative)

3.1 Contract Title: Reagan Memorial Tollway (I-88) Pavement Repairs

3.2 Contract Location: Reagan Memorial Tollway (I-88) between Mile Post 76.1 and Mile Post 113.6 in Ogle, Dekalb and Kane Counties, Illinois

3.3 Scope of Work: The work under this contract includes intermittent partial depth pavement repairs, shoulder emulsified maltene-based sealer treatment, removal

Illinois State Toll Highway Authority Contract No. RR-23-4939 Addendum 1 2 of 6 April 3, 2024

Capital Program

PRE-BID MEETING MINUTES

and/or replacement of raised pavement markers, various crack repairs, pavement marking, maintenance of traffic, and other miscellaneous work.

4.0 Advertisement Schedules (by Procurement Representative)

4.1 Plan Holder questions should be provided to 4864D.4939_Questions@docs.e-builder.net as identified on Page A-1

4.2 Final Date for Plan Holder Questions – March 25, 2024 at 2:00 pm.

4.3 Bid Opening Date – April 12, 2024

5.0 Compliance Goals (by Procurement Compliance)

5.1 Disadvantaged Business Enterprise Program (DBE) – 24%

5.2 Veteran-Owned Small Business Program (VOSB) - 2%

5.3 Workforce

5.3.1 Equal Employment Opportunity (EEO)

• Minority 16.3%

• Female 6.9%

6.0 Diversity Programs – Overview of Available Programs (by Diversity Representative)

6.1 Earned Credit Program (ECP) Bid Credit Cap - $325K

6.2 Technical Assistance Program

6.3 Partnering for Growth (P4G)

6.4 Construction Works

7.0 Project Schedule (by Engineering Project Manager)

7.1 SP 104 Anticipated Notice-to-Proceed – July 15, 2024

7.2 SP 103.3 Interim Completion Date – November 1, 2024

7.3 SP 103.2 Substantial Completion Date – August 29, 2025

7.4 SP 103.1 Contract Completion Date – September 30, 2025

8.0 Special Items to Note (by Design Section Engineer)

8.1 All work near Toll Plazas shall be coordinated with the Illinois Tollway Business

Systems to ensure continuing operation of the toll collection. No electrical or communication work is anticipated for this project.

8.2 Attention is made to SP 106.1 for Coordination with IDOT for work on I-88 near the interchanges of I-39 and IL 251 (DWG-8 and 9). IDOT Highway Permit Form OPER 1045 and OPER 1046 will be required.

9.0 Responses to Plan Holder Questions (by Design Section Engineer)

9.1 Questions received to date

9.2 Addendum No 1 scheduled to be published the week of April 1, 2024

10.0 Open Discussion / Questions

Related Notes

Optional Pre-Bid Meeting RR-23-4939 Reagan Memorial Tollway (1-88) Pavement Repairs IL 251 to IL 56, Mile Post

Attendance:

Name First Join Howe, Ruth 3/12/24, 12:53:25 PM Hacking, Kathi 3/12/24, 12:45:21 PM Coleman, Timothy 3/12/24, 12:44:08 PM Ersfeldt, Tim 3/12/24, 12:51:55 PM Myers, Lindia 3/12/24, 12:52:11 PM

16304370789 3/12/24, 12:53:35 PM

Spencer, Seannica 3/12/24, 12:56:13 PM Kim Bolanowski 3/12/24, 12:56:13 PM

13123151846 3/12/24, 12:56:27 PM

Brenda D Lowery 3/12/24, 12:57:19 PM Karn, Jon 3/12/24, 12:57:37 PM Andre Hammel 3/12/24, 12:59:07 PM Coleman, Belynzia 3/12/24, 1:00:21 PM Hinton, Marcita 3/12/24, 1:02:02 PM Rachel Borenstein 3/12/24, 1:02:13 PM Mike Sumrall (Guest) 3/12/24, 1:03:45 PM Rachel Lang - CAM 3/12/24, 1:05:09 PM

Illinois State Toll Highway Authority Contract No.

RR-23-4939 Addendum 1

76.1 to Mile Post 113.6

Last Leave Email Role 3/12/24, 1:09:18 PM RAHowe@getipass.com Organizer 3/12/24, 1:09:18 PM KHacking@getipass.com Organizer 3/12/24, 1:09:04 PM TJColeman@getipass.com Presenter 3/12/24, 1:09:06 PM TErsfeldt@getipass.com Presenter 3/12/24, 1:09:13 PM LMyers@getipass.com Attendee 3/12/24, 1:09:18 PM Attendee 3/12/24, 1:09:08 PM SSpencer@getipass.com Presenter 3/12/24, 1:09:07 PM kbolanowski@currancontracting.com Attendee 3/12/24, 1:09:08 PM Attendee 3/12/24, 1:09:06 PM BrendaLowery@amesengineeringinc.com Presenter 3/12/24, 1:09:18 PM jonk@k-five.net Attendee 3/12/24, 1:09:06 PM AHammel@ICUTechAssist.net Attendee 3/12/24, 1:09:10 PM BColeman@getipass.com Attendee 3/12/24, 1:09:12 PM mhinton@getipass.com Attendee 3/12/24, 1:06:30 PM rborenstein@aaaengineering.net Attendee 3/12/24, 1:09:18 PM Attendee 3/12/24, 1:09:18 PM Attendee

6 of6 April 3, 2024

PC_AMES_BDL_4939C-AddendumNo1-Final_04022024
PC_AMES_BDL_4939C-AddendumNo1-almostfinal_03262024
PC_AMES_BDL_4939C-AddendumNo1-Draft_03262024
PC_AMES_BDL_4938C-AddendumNo2-draft_03212024
PC_AMES_BDL_4938C-AddendumNo2_03202024
Addendum 2 minus attendance roster new date
PC_GEC_RJY_Addendum_Template_10_16_2020.dotx (1)
4939 Pre-Bid Meeting Minutes 03262024 - Draft
TOPICS TO BE DISCUSSED:
3 sheets
PC_AMES_BDL_4939C-AddendumNo1-Final_04022024