RR-23-4939_AddendumNo1_04032024.pdf
PDF 597 KB Posted
- Attached to
- RR-23-4939 Reagan Memorial Tollway (I-88) Pavement Repairs IL 251 to IL 56, MP 76. 1 to MP 113. 6
- Solicitation number
- 24-557THA-ENGCO-B-41778
- Issued by
- Monroe County, Illinois
About this file
This document is an Addendum to Contract RR-23-4939 issued by the Illinois State Toll Highway Authority. The contract is for Reagan Memorial Tollway (I-88) Pavement Repairs between Mile Post 76.1 and Mile Post 113.6 in Ogle, Dekalb and Kane Counties, Illinois. The scope of work includes intermittent partial depth pavement repairs, shoulder treatment, raised pavement marker work, crack repairs, pavement marking, maintenance of traffic, and other miscellaneous work. The Pre-Bid Meeting was held on March 12, 2024, and the bid opening is scheduled for April 12, 2024. The anticipated Notice-to-Proceed is July 15, 2024, with an Interim Completion Date of November 1, 2024, Substantial Completion Date of August 29, 2025, and Contract Completion Date of September 30, 2025.
The contract has Disadvantaged Business Enterprise (DBE) and Veteran-Owned Small Business (VOSB) participation goals of 24% and 2% respectively. Other diversity programs such as the Earned Credit Program, Technical Assistance Program, Partnering for Growth, and Construction Works are available. Coordination with the Illinois Department of Transportation (IDOT) is required for work near interchanges. Responses to plan holder questions will be provided in Addendum No. 1, scheduled for the week of April 1, 2024.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Illinois State Toll Highway Authority Contract No. RR-23-4939 Addendum 1 Page 1 of 1 April 3, 2024
ADDENDUM NO. 1
TO
CONTRACT REQUIREMENTS
FOR CONTRACT RR-23-4939
ILLINOIS STATE TOLL HIGHWAY AUTHORITY
Date: 4/3/2024
For which proposals will be received by the Illinois State Toll Highway Authority through electronic bidding via BidBuy until 10:30:00 A.M. local time, April 12, 2024
NOTICE OF REVISION TO CONTRACT
NOTES:
1. The minutes and sign-in sheet from the Optional Pre-Bid Meeting held on March 12, 2024 are included in this Addendum.
END OF ADDENDUM CHANGES
Illinois State Toll Highway Authority Contract No. RR-23-4939 Addendum 1 1 of 6 April 3, 2024
Capital Program
PRE-BID MEETING MINUTES
MEETING PURPOSE: Optional Pre-Bid Meeting - Contract RR-23-4939
MEETING DATE: March 12, 2024
MEETING TIME: 1:00 pm
CHAIRPERSON: Kathi Hacking – Senior Contract Negotiator
LOCATION: Illinois Tollway Teams
TO:
Names Initials Organization / Title
Eric Occomy EO Procurement / Chief of Contract Services Maria Campuzano MC Procurement/Deputy Chief of Procurement Kathi Hacking KH Procurement/Senior Contract Negotiator Ruth Howe RH Procurement / Contract Analyst Sainey Jobe SJ Procurement / Deputy Chief of Contract Compliance Tim Ersfeldt TE Engineering / Project Manager Brenda Lowery BL DSE / Ames Engineering
TOPICS TO BE DISCUSSED:
1.0 Open: Welcome; Self-introduction by Procurement Representative
2.0 Self-Introduction of Attendees – State name and affiliation loudly for all to hear (Please sign-in using the provided sign-in sheet)
2.1 Tollway Procurement – Contract Services
2.2 Tollway Procurement – Contract Compliance
2.3 Tollway – Diversity
2.4 Tollway – Engineering Project Manager
2.5 Design Section Engineer
2.6 Other Attendees
3.0 Brief Project Description (by Procurement Representative)
3.1 Contract Title: Reagan Memorial Tollway (I-88) Pavement Repairs
3.2 Contract Location: Reagan Memorial Tollway (I-88) between Mile Post 76.1 and Mile Post 113.6 in Ogle, Dekalb and Kane Counties, Illinois
3.3 Scope of Work: The work under this contract includes intermittent partial depth pavement repairs, shoulder emulsified maltene-based sealer treatment, removal
Illinois State Toll Highway Authority Contract No. RR-23-4939 Addendum 1 2 of 6 April 3, 2024
Capital Program
PRE-BID MEETING MINUTES
and/or replacement of raised pavement markers, various crack repairs, pavement marking, maintenance of traffic, and other miscellaneous work.
4.0 Advertisement Schedules (by Procurement Representative)
4.1 Plan Holder questions should be provided to 4864D.4939_Questions@docs.e-builder.net as identified on Page A-1
4.2 Final Date for Plan Holder Questions – March 25, 2024 at 2:00 pm.
4.3 Bid Opening Date – April 12, 2024
5.0 Compliance Goals (by Procurement Compliance)
5.1 Disadvantaged Business Enterprise Program (DBE) – 24%
5.2 Veteran-Owned Small Business Program (VOSB) - 2%
5.3 Workforce
5.3.1 Equal Employment Opportunity (EEO)
• Minority 16.3%
• Female 6.9%
6.0 Diversity Programs – Overview of Available Programs (by Diversity Representative)
6.1 Earned Credit Program (ECP) Bid Credit Cap - $325K
6.2 Technical Assistance Program
6.3 Partnering for Growth (P4G)
6.4 Construction Works
7.0 Project Schedule (by Engineering Project Manager)
7.1 SP 104 Anticipated Notice-to-Proceed – July 15, 2024
7.2 SP 103.3 Interim Completion Date – November 1, 2024
7.3 SP 103.2 Substantial Completion Date – August 29, 2025
7.4 SP 103.1 Contract Completion Date – September 30, 2025
8.0 Special Items to Note (by Design Section Engineer)
8.1 All work near Toll Plazas shall be coordinated with the Illinois Tollway Business
Systems to ensure continuing operation of the toll collection. No electrical or communication work is anticipated for this project.
8.2 Attention is made to SP 106.1 for Coordination with IDOT for work on I-88 near the interchanges of I-39 and IL 251 (DWG-8 and 9). IDOT Highway Permit Form OPER 1045 and OPER 1046 will be required.
9.0 Responses to Plan Holder Questions (by Design Section Engineer)
9.1 Questions received to date
9.2 Addendum No 1 scheduled to be published the week of April 1, 2024
10.0 Open Discussion / Questions
Related Notes
Optional Pre-Bid Meeting RR-23-4939 Reagan Memorial Tollway (1-88) Pavement Repairs IL 251 to IL 56, Mile Post
Attendance:
Name First Join Howe, Ruth 3/12/24, 12:53:25 PM Hacking, Kathi 3/12/24, 12:45:21 PM Coleman, Timothy 3/12/24, 12:44:08 PM Ersfeldt, Tim 3/12/24, 12:51:55 PM Myers, Lindia 3/12/24, 12:52:11 PM
16304370789 3/12/24, 12:53:35 PM
Spencer, Seannica 3/12/24, 12:56:13 PM Kim Bolanowski 3/12/24, 12:56:13 PM
13123151846 3/12/24, 12:56:27 PM
Brenda D Lowery 3/12/24, 12:57:19 PM Karn, Jon 3/12/24, 12:57:37 PM Andre Hammel 3/12/24, 12:59:07 PM Coleman, Belynzia 3/12/24, 1:00:21 PM Hinton, Marcita 3/12/24, 1:02:02 PM Rachel Borenstein 3/12/24, 1:02:13 PM Mike Sumrall (Guest) 3/12/24, 1:03:45 PM Rachel Lang - CAM 3/12/24, 1:05:09 PM
Illinois State Toll Highway Authority Contract No.
RR-23-4939 Addendum 1
76.1 to Mile Post 113.6
Last Leave Email Role 3/12/24, 1:09:18 PM RAHowe@getipass.com Organizer 3/12/24, 1:09:18 PM KHacking@getipass.com Organizer 3/12/24, 1:09:04 PM TJColeman@getipass.com Presenter 3/12/24, 1:09:06 PM TErsfeldt@getipass.com Presenter 3/12/24, 1:09:13 PM LMyers@getipass.com Attendee 3/12/24, 1:09:18 PM Attendee 3/12/24, 1:09:08 PM SSpencer@getipass.com Presenter 3/12/24, 1:09:07 PM kbolanowski@currancontracting.com Attendee 3/12/24, 1:09:08 PM Attendee 3/12/24, 1:09:06 PM BrendaLowery@amesengineeringinc.com Presenter 3/12/24, 1:09:18 PM jonk@k-five.net Attendee 3/12/24, 1:09:06 PM AHammel@ICUTechAssist.net Attendee 3/12/24, 1:09:10 PM BColeman@getipass.com Attendee 3/12/24, 1:09:12 PM mhinton@getipass.com Attendee 3/12/24, 1:06:30 PM rborenstein@aaaengineering.net Attendee 3/12/24, 1:09:18 PM Attendee 3/12/24, 1:09:18 PM Attendee
6 of6 April 3, 2024
| PC_AMES_BDL_4939C-AddendumNo1-Final_04022024 |
| PC_AMES_BDL_4939C-AddendumNo1-almostfinal_03262024 |
| PC_AMES_BDL_4939C-AddendumNo1-Draft_03262024 |
| PC_AMES_BDL_4938C-AddendumNo2-draft_03212024 |
| PC_AMES_BDL_4938C-AddendumNo2_03202024 |
| Addendum 2 minus attendance roster new date |
| PC_GEC_RJY_Addendum_Template_10_16_2020.dotx (1) |
| 4939 Pre-Bid Meeting Minutes 03262024 - Draft |
| TOPICS TO BE DISCUSSED: |
| 3 sheets |
| PC_AMES_BDL_4939C-AddendumNo1-Final_04022024 |
File details come from the government source that posted it. Updated .