RP005_24 Ad 2.pdf
PDF 205 KB Posted
- Attached to
- RP005-24, Provision of Engineering Design Services and Construction Document Development
- Solicitation number
- PE-77023-NONST-2024-000000155
- Issued by
- Gwinnett County, Georgia
About this file
This document is an Addendum No. 2 for an RFP (Request for Proposal) from a government entity for the Provision of Engineering Design Services and Construction Document Development for a Loop Trail project from Sugarloaf Parkway to Saint Ives Court. The addendum revises the RFP by removing pages 61-86, which were a duplicate of the REQUIRED CONTRACT PROVISIONS FOR NON-FEDERAL ENTITY CONTRACTS UNDER FEDERAL AWARDS - THE FEDERAL HIGHWAY ADMINISTRATION (FHWA). It also provides a revised response to Question 8 from Addendum #1, allowing respondents to include the area class table on a separate sheet from the organizational chart and clarifying where the GDOT pre-qualifications should be included in the proposal.
The document indicates that respondents should acknowledge receipt of this addendum on the firm information page of the request for proposal. The project is being funded through federal highway administration sources, and respondents will need to comply with the associated requirements outlined in the RFP.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RP005_24 INV.pdf | ||
| RP005_24 Ad 1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
May 2, 2024 Addendum No. 2
RP005-24
Provision of Engineering Design Services and Construction Document Development for Loop Trail from
Sugarloaf Parkway to Saint Ives Court.
REVISION:
R1. Please remove pages 61-86 of the invitation. This was duplicate of the REQUIRED CONTRACT
PROVISIONS FOR NON-FEDERAL ENTITY CONTRACTSUNDER FEDERAL AWARDS – THE FEDERAL
HIGHWAY ADMINISTRATION (FHWA).
R2. Please replace the response to Question 8 on Addendum #1 with the following:
Q: Per Page 4 of the RFQ, "Respondents should submit a copy of the approval of the pre-qualification by GDOT for the area classes identified below. The area classes must be listed on the organizational chart with the prime and sub-consultants on a single 11”x17” page." Would the county allow the area class table to be included on a separate sheet from the org chart? And does the county want the GDOT prequals included in B. Qualifications or attached to the package with the required forms? Page 8 says, “Required proof of prequalification should be submitted as indicated in Section VI.B.4.,” but there is no Section VI.B.4. included in the RFQ.
A: Yes, you can include a separate sheet with area classes. You can include the pre-qualifications in the
Qualifications section. Section VI.B.4 is NOT included in the RFP. See below updated “Area Class Requirements and Certification” section:
RRE
Acknowledge receipt of this addendum on the firm information page of the request for proposal.
Sincerely, Michael Milstein Purchasing Associate II