RP004_27 Exhibit A.pdf

PDF 359 KB Posted

Attached to
RP004-27 Gwinnett County 2050 Unified Plan, Comprehensive Mobility Plan, and Parks and Recreation M
Solicitation number
PE-77023-NONST-2027-000000832
Issued by
Gwinnett County, Georgia

About this file

This document is a Scope of Work for the Gwinnett County Comprehensive Transportation Plan (CTP), jointly developed by Gwinnett County and the Atlanta Regional Commission (ARC). The project encompasses the development of a long-range, county-wide transportation plan covering Gwinnett County's jurisdictional boundary and including all constituent municipalities, with coordination extending three to five miles beyond the county's borders. The scope of work consists of six primary tasks: Project Management, Engagement, Inventory of Existing Conditions, Assessment, Recommendations, and Documentation. Key deliverables include a Project Management Plan, Public Engagement Plan, Inventory of Existing Conditions Report, Needs Assessment Report, project prioritization methodology, and final CTP documentation with ArcGIS mapping layers. The engagement component requires robust and meaningful community outreach targeting 1.5 to 3 percent of the county population through multiple touchpoints, including a Community Council, Technical Advisory Committee, project website, in-person outreach events, surveys, and public meetings. The project must be completed by July 1, 2028, with implementation expected within 12 to 18 months following the notice to proceed.

The total project cost is $1,250,000, with ARC providing 80 percent ($1,000,000) and the Subgrantee (Gwinnett County) providing 20 percent ($250,000) in local matching funds. The budget allocation by task is: Project Management ($62,500), Engagement ($312,500), Inventory ($125,000), Assessment ($375,000), Recommendations ($312,500), and Documentation ($62,500). ARC will reimburse the Subgrantee at 80 percent of approved invoiced costs on a monthly basis, with invoices due by the 10th of the following month and final payment due within ten days of project completion. The project is supported by federal funding through the Atlanta Regional Commission's Cost Center 806ECP for County Transportation Planning and must comply with all Federally mandated Planning Factors outlined by IIJA. ARC's Director of the Center for Livable Communities serves as the designated agent for contract administration.

View the file

Other files

File Type Posted
RP004_27 Inv.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A-1

ATTACHMENT A

GWINNETT COUNTY COMPREHENSIVE TRANSPORTATION PLAN

SCOPE OF WORK

I. General

The work to be accomplished is in support of the following Atlanta Regional Commission (ARC) Cost Center:

Cost Center 806ECP: County Transportation Planning

II. Area Covered

The area of study (Study Area) for the plan development is defined, but not limited to, the Gwinnett County jurisdictional boundary, including all County municipalities (including Cities, local governments, and communities). Coordination with adjacent jurisdictions within an area three to five miles outside Gwinnett County is also required to promote coordinated long-range transportation planning efforts across jurisdictional boundaries.

III. Goal

The Comprehensive Transportation Plan (CTP) Program was established to ensure the transportation infrastructure has a positive impact on strengthening the Atlanta Region’s economy and communities at both the local and regional levels. It accomplishes this by providing financial assistance for counties and their constituent municipalities to develop joint long-range transportation plans. These plans, while focused on local issues and needs, also serve as the foundation for regional planning efforts led by the Atlanta Regional Commission.

Coordination with the regional transportation planning process and regional development plan policies, and consideration of the Department of Community Affair’s (DCA) minimum standards will help ensure jurisdictions develop plans that meet regional goals and are based on sound technical analysis.

IV. Background

The CTP Program will assist local governments by clearly defining county-wide goals, needs, and priorities. While ARC typically completes needs assessments and transportation plans focusing on regional needs and solutions, a successful local transportation plan and program is also

A-2 critical. Local transportation plans are a key mechanism in which governments define programs and projects they are prepared to support and assist in funding. It is a critical program objective that these identified priorities will form the basis for future funding requests during Transportation Improvement Program (TIP) and Metropolitan Transportation Plan (MTP) update cycles. No MTP can be successfully implemented without local support for plan goals, programs, and projects.

Transportation plans resulting from the CTP Program shall be informed by existing county and local government comprehensive plans. Elements of existing comprehensive plans may include, but are not limited to, community goals, needs and opportunities, land use, housing and economic development where required by the Georgia Planning Act, thereby strengthening the connection between required and optional plan elements addressing the county and local governments’ immediate needs, and transportation planning. CTP plan recommendations will clearly reference alignment with these efforts. Additionally, CTP plans must address all Federally mandated Planning Factors as outlined by IIJA.

All work tasks herein refer to the development of the CTP. If the CTP is developed as part of a broader local comprehensive plan, program funding shall only be spent on the transportation planning component.

V. Work Tasks

This scope of work outlines the minimum requirements which Gwinnett County (Subgrantee) must fulfill to receive funding from ARC. The Subgrantee may include additional or more detailed tasks in their contract with their consultants based on individual needs (Trails, Transit, Stormwater, Safety, Sidewalks, etc.)

Comprehensive monthly progress reports detailing progress on each task will be submitted to ARC with each invoice. The Subgrantee will present draft deliverables to ARC for comment, involve ARC in relevant stakeholder and technical committee meetings and notify ARC of key public outreach activities, beginning with the issuance of the Notice to Proceed.

https://apps.dca.ga.gov/development/PlanningQualityGrowth/DOCUMENTS/Laws.Rules.Guidelines.Etc/DCARules.LPRs.pdf https://ops.fhwa.dot.gov/fastact/

A-3

TASK 1 – PROJECT MANAGEMENT

The purpose of Task 1 is to ensure that the CTP begins with a clear understanding of the project’s processes, schedule, and desired outcomes. Task 1 establishes an effective working relationship among County staff, the Project Management Team, the Community Council, and the Technical Advisory Committee.

The Subgrantee will host a project kickoff meeting with the Project Management Team (PMT) to review major transportation issues facing Gwinnett County, clarify agency roles, define priorities, and identify relationships to other local and regional planning efforts. The PMT meetings should take place regularly (monthly at a minimum) throughout the length of the project and should include an ARC representative in addition to the appropriate County staff and Consultant team.

The subgrantee and consultant teams will work with artists or creative designers with relevant skill, experience, and familiarity with the study area in the development of (the CTP). A preliminary outline of the Project Management Plan (PMP) will be presented for discussion and feedback. The kickoff meeting will also include a review of the prior CTP’s vision, goals, and objectives.

Following the kickoff meeting, the Subgrantee will finalize the Project Management Plan (PMP).

The PMP will refine the contract scope of work and drive the work schedule for the duration of the project. The PMP will be submitted to the PMT no later than two weeks following the project kick-off meeting for review and comment.

At a minimum, the PMP will:

• Identify an organizational chart and provide key staff contact information.

• Define protocols and procedures for the Project Team to adhere to, including:

o Communications protocols o Quality Assurance and Quality Control protocols which will ensure a high standard of professionalism with respect to all deliverables to be made available to the public, stakeholders, and elected officials.

o Administrative and Invoicing procedures, which will follow ARC’s provided templates and procedures for collecting invoices monthly

• Refine work tasks, subtasks, review/comment points, and the timing and content of deliverables.

• Describe how the PMT will interface with entities working on any other concurrent land use/ transportation planning efforts in the Study Area.

• Outline a comprehensive communications strategy / public participation plan to ensure integration of a central message among the PMT, stakeholders and the public.

A-4 o This includes branding the CTP and documenting a communications strategy linking the CTP to ongoing and recently completed planning studies and initiatives and capital improvement programs.

• Specify roles and responsibilities of study participants, including the composition of a Community Council and Technical Advisory Committee.

• Outline a project schedule and deliverable dates.

• Outline a Budget Allocation by Task.

TASK 1 DELIVERABLES:

• Kickoff meeting and summary notes

• Draft and Final Project Management Plan

• Regular PMT Meetings Calendar Invite

• PMT Meeting Notes

• Monthly invoices following ARC invoicing procedures

A-5

TASK 2 – ENGAGEMENT

The purpose of Task 2 is to utilize ROBUST, EQUITIBLE, and MEANINGFUL community engagement throughout the CTP development process. The engagement effort will provide input for countywide transportation vision and goals; input for the technical planning process;

and collaboration in the creation of project and policy recommendations. The community shall be engaged early and often in the planning process with the intention of creating as many touchpoints1 as possible. All groups in the community will be actively engaged with an emphasis on groups that have not been historically involved in the planning process. Creativity in reaching communities which are traditionally not well represented in the planning process, including minorities, low-income individuals, people with limited English proficiency, and students, will be essential to the overall success of this effort.

The goal of the engagement process shall be generating a verifiable number of touchpoints equal to 1.5 to 3 percent of the total County population. For example, if there are 400,000 residents in your County, the goal is to generate verifiable touchpoints with 6,000 – 12,000 residents. These touchpoints shall be a proportionate representation of the overall demographics in the County, including race, ethnicity, age, and language spoken at home (per the Demographic Analysis from the County’s Unified Plan, to be updated simultaneously with the CTP).

2a. Public Engagement Plan

The exact process, schedule, and methods of community engagement will be defined in an associated Public Engagement Plan (PEP). The PEP is an early deliverable and shall be developed and finalized within 4 weeks of the kickoff meeting. ARC’s Public Participation Plan (PPP) shall be used as a guide and the engagement techniques and tools identified within the PPP are encouraged.

The Community Council (see Section 2b) and the Project Management Team shall review, comment and approve the PEP and any subsequent changes to the document. Subgrantee will utilize the County’s Unified Plan and Language Equity analysis to fulfill the demographic analysis requirements for use in identifying the different community groups that need to be represented on the Community Council.

Engagement activities include interactions with the public, as well as entities such as federal, state and local governments, transit agencies, and development community representatives.

The PEP shall include a plan for engaging the public officials responsible for adopting the CTP

1 A touchpoint is de�ined as any way a member of the public interacts with the planning process - whether in-person meeting, pop-up event, through a website, survey response(s), email, or any form of communication about the CTP with a member of the community.

http://www.gwinnettcounty.com/documents/d/gwinnett-county/3-economic-development-pdf https://atlantaregional.org/what-we-do/transportation-planning/community-engagement/public-participation-plan-2024-update/ https://www.gwinnettcounty.com/government/departments/planning-development/land-use-planning/2045-unified-plan https://www.gwinnettcounty.com/government/departments/elections/language-equity

A-6 throughout the planning process. These officials should be briefed a minimum of two times during the plan development process (additional meetings may be conducted as necessary).

The Subgrantee shall anticipate and allow for review of any materials to be released to the public to have adequate review time by the PMT within the schedule.

A template will be provided by ARC for the Subgrantee to use to track all public engagement touchpoints. The tracking sheet will be submitted back to ARC after all engagement for the CTP is complete.

2b. Community Council

A Community Council (CC) will be formed and consulted regularly to represent the public’s interests throughout the CTP process. The composition of the Community Council shall reflect the demographic makeup of the community as identified in the demographic analysis portion of the PEP. Community Council membership shall prioritize representatives of communities which are traditionally not well represented in the planning process, including minorities, low-income individuals, people with limited English proficiency, and students. ARC strongly recommends that the Community Council actively engages community-based organizations (CBOs) and that the CBOs are involved in the development of the Public Engagement Plan and the planning process. Please see ARC’s Community Engagement and Culture (CEC) Team for additional resources, including a database of existing Community Based Organizations that have been vetted by ARC and are aware of planning projects, and willing to participate in their area.

The Community Council will convene a minimum of four times during the plan development process (additional meetings may be conducted as necessary). All significant findings and recommendations of the CTP will be presented to the council for review and feedback, starting with the Public Engagement Plan. The CC will help to shape the CTP by providing input on the Goals and Objectives, draft Needs Assessment and draft Project Recommendations, including policy recommendations.

The CC is intended to be a conduit for communication to the community at-large. CC members are expected to disseminate information to the communities they represent and shall be consulted on the methods, timing, and messaging of the Public Engagement process.

In an effort to reduce barriers and incentivize all parts of the community to participate, compensation for CC members per allowable costs and federal guidelines is recommended.

Please see ARC's PPP for details and regulations.

2c. Technical Advisory Committee

In addition to the CSC, a Technical Advisory Committee (TAC) will be formed and consulted regularly. The TAC shall consist of transportation and planning professionals and elected officials such as Mayors, City Council members, GDOT Planning staff, Community Improvement https://atlantaregional.org/what-we-do/community-development/regional-arts-culture/

A-7

Districts, transit operators, local engineering and planning departments, and/or economic development entities may be included.

The TAC will meet a minimum of four times during the plan development process (additional meetings may be conducted as necessary). All significant findings and recommendations of the CTP will be presented to the committee for review and feedback. The TAC will help to shape the CTP by providing input on the Goals and Objectives, draft Needs Assessment and draft Project Recommendations, including policy recommendations.

2d. Methods of Engagement

The ARC Public Participation Plan shall be consulted as a resource for approved methods of Public Engagement. While the engagement methods for this CTP will be defined in the PEP, at a minimum they shall include the following:

• Community Council (as defined in section 2b)

• Technical Advisory Committee (as defined in section 2c)

• Standalone Project Website o The project website will be capable of both disseminating information and collecting input. The project website is intended to be the most visible and comprehensive communication piece for the planning process. At minimum, the website shall include the following items:

Project Background / Intent Schedule (Project Phases and Public Engagement Events) Interactive Map where people can provide input on issues/needs, project recommendations, and other suggestions Asynchronous meetings / recording of meetings Data / Documents (Draft and Final)

• The Public Engagement Plan with its demographic analysis shall be published on the website, including a high-level summary.

Methods to leave general comments and contact project team Email collection for mailing list (opt in to receive further info about project, popups, surveys) 24 months minimum of live website o Suggestion: multi-media video or recording that is social media friendly

• Face-to-Face Outreach (In-person) (Minimum Two Rounds) o While virtual engagement has proven cost effective and successful, face-to-face interactions are still a critical component of the PEP. In-person small group outreach is intended to occur in the community where people are already gathering to create awareness of the planning process and the opportunities for involvement.

A-8 o This outreach is intended to occur as small popups at multiple locations (5 to 10 each round) throughout the county/city that utilize places where people are already gathering, such as:

Public libraries Festivals Parks and popular trails Transit stops Youth sports Shopping centers / commercial districts School events (high schools) Government service centers Senior centers / senior housing Others

• Surveys o Surveys will be utilized during the initial phase to identify issues from members of the public and a second time after recommendations have been formed to get feedback on the proposed recommendations.

o Two (2) surveys will be available for a minimum of 30 days o Paper surveys shall be made available as appropriate, such as at pop-up events to engage with the public who do not have access to online surveys. A portable device should also be made available so that people can complete the surveys while engaging with the project team.

o The surveys must ask for demographic information that can be provided to ARC in the summary report.

• Email List / Blast o Collect emails from people who have specifically opted-in or utilize lists that the

County / cities already have.

o Email blasts can be sent to notify of upcoming events, posted surveys, or any other project-related announcements.

• Public Meetings o A minimum of 2 public meetings shall be held. The meetings may be in-person or virtual (no hybrid options).

o Any materials presented at the public meetings shall be made available on the project website.

o Suggestion: walking audit, tactical demonstration project, peer site visits, workshops

Engagement materials shall be translated into languages other than English where appropriate based on the findings in the demographic analysis.

2e. Supplemental Methods of Engagement

A-9

Supplemental forms of engagement that are not required but are encouraged and allowed within the scope of the CTP include the following:

• Demonstration Project that includes a temporary and tactical demonstration of a transportation project to show the public what a project could look like if constructed.

• Focus Groups that include various sectors of the public such as elderly or youth populations, various sub-areas within the County, etc.

TASK 2 DELIVERABLES:

• Draft and Final Public Engagement Plan

• Small group outreach and public meeting materials and summary documentation

(conducted as part of Tasks 4 and 5) o Including photos of engagement

• Revised vision, goals and objectives

• Project website materials (prepared throughout CTP development process)

• Community Council membership list, meeting materials, and summary documentation

(conducted throughout CTP development process)

• Technical Advisory Committee meeting materials and summary documentation

(conducted throughout CTP development process)

• PMT meeting summary notes (conducted throughout CTP development process)

• Completed Public Engagement touchpoints tracking spreadsheet (provided by ARC)

A-10

TASK 3 – INVENTORY OF EXISTING CONDITIONS

With the previous CTP as a foundation, Task 3 will include an inventory of the study area’s transportation network and its performance, including existing conditions and the identification of specific focus areas. The following need to be reviewed and included in the deliverables:

• Report of Accomplishments since the last CTP with a focus on transportation related policies and projects that have either been started, funded, or completed (using ARC provided template).

o This can be a high-level overview and does not need to be a full matrix of the entire project list from the previous CTP.

• Inventory of Existing Plans and Regionally Significant Studies that are relevant to the CTP, such as studies from the Atlanta Regional Commission (ARC), the Atlanta-region Transit Link Authority (ATL), Georgia Department of Transportation (GDOT).

• Inventory of core transportation elements and land use conditions including, but not limited to:

o Land Use and Zoning Conditions, Population and Demographics Data, Employment Data, and Community Resources will be reviewed and updated through the Unified Plan update process. This analysis will be referenced in the Gwinnett County CTP.

o Roadways Functional classification, current traffic volumes, bridge locations and sufficiency rating, laneage, posted speed limits, traffic signals, pavement condition index (including material type), and roadway elevations

Existing stormwater infrastructure (if available) including drainage systems, retention and detention ponds, green infrastructure, and outfalls o Transit Transit routes, transit stops, and ridership data Human Services Transportation (HST) – description of service type, service area and usage Transportation Demand Management Programs o Active Transportation Bike and pedestrian facilities (including bike lanes, side paths, paved multi-use trails, and sidewalks if available) Rideshare program providers and areas of service (bikes, e-bikes, scooters, micromobility) o Freight and Goods Movement (Truck and Rail)

Federal, state, regional and local truck routes and/or truck prohibitions Rail corridors

A-11

At-grade rail crossing locations Truck and Train volumes, if available o A full Transportation Systems Management & Operations (TSMO) analysis was conducted as part of the County’s Connected Vehicle Master Plan Update (2025).

This CTP will reference that document but not repeat any analyses.

o Climate adaptation and transportation infrastructure resiliency Rivers, streams, and bodies of water FEMA Floodplains ARC Regional Transportation vulnerability index (when available) o System Performance Monitoring and Reporting Program Document how each jurisdiction within the County collects, maintains and reports system performance data for their own purposes.

Document what infrastructure and services are included in that program.

The Subgrantee may include additional optional elements in its CTP work scope, as the schedule and budget permit. Such elements may include additional analysis of transit services or high priority roadway corridors, development of smart city, technology and data recommendations, and consideration of the impacts of emerging transformative mobility options.

All inventoried items must be mapped digitally and converted to a standard ArcGIS layer, as applicable, for future use. Adequate data will be collected to allow a thorough assessment that identifies and addresses potential issues and solutions. Data collected may include (and is not limited to) location, facility type (functional classification), conditions, crash data, average daily travel volumes, and TIP/MTP programs and projects.

As appropriate, the Subgrantee will access and collect data from each defined municipality within the study area. ARC and other members of the PMT will make all readily accessible documents, data summaries and ArcGIS files associated with previous planning initiatives available to the Subgrantee as identified and needed.

TASK 3 DELIVERABLES:

• Report of Accomplishments since previously completed CTP

• Draft and Final Inventory of Existing Conditions Report (including maps, text, and tables) o Final Report must incorporate ARC submitted comments

• Project website materials (prepared throughout CTP development process)

A-12

TASK 4 – ASSESSMENT

Task 4 will take the inventory of core transportation elements and land use conditions from Task 3 and identify existing and future gaps and needs in the transportation system of GWINNETT County. Transportation facilities should be assessed at two points in time – current and the MTP planning horizon year.

Equity considerations must be used in the identification of needs, specifically in Justice40 disadvantaged areas, where communities have been identified that spend more, and take longer, to get where they need to go.

Additionally, as the needs assessment is completed, the impacts of climate change must be considered. Specifically, identifying and prioritizing projects that will set the region on a path towards net zero greenhouse gas emissions, as well as promoting projects that will enhance the resiliency of our communities, infrastructure, and natural systems to climate change and extreme weather events.

The following section lists the assessment topic and potential assessments and tools that could be used in Task 4 where applicable.

• Land Use and Zoning Conditions o Assessment of the impact of land use, development, and related policies and regulations in place on the transportation network o Possible Data Source(s): ARC’s Community Development Group, Co-Star

Multifamily Data (provided by ARC)

• Travel Patterns & Roadways o Identification of where county employees live, and where county residents work o ARC Travel Demand Model future trips analysis o Origin-Destination Analysis o Existing and Future Level of Service (LOS) o Existing and Future Travel Time Index (TTI) o Bottleneck Location Analysis o Possible Data Source(s): Passive data that uses existing personal GPS device data, such as AirSage; Streetlight Data, Replica (GDOT and ARC have a purchasing contract that can be used), U.S. Census Longitudinal Employer-Household Dynamics, ARC Travel-Demand Model

• Transit o Route characteristics, access to fixed route transit and to frequent transit, and rider experience Ridership by route or by stop if possible Boarding and alighting by stops if applicable https://www.costar.com/products/market-analytics https://www.costar.com/products/market-analytics https://airsage.com/ https://www.streetlightdata.com/ https://lehd.ces.census.gov/ https://lehd.ces.census.gov/

A-13 o Transit Coverage (number of miles) / level of service (Vehicle Revenue Miles or Hours) except for MARTA counties o Assessment of gaps in microtransit services (where applicable) o Access measures for transit hubs and network o Assessment of transit rider infrastructure most vulnerable to extreme heat o Possible Data Source(s): Atlanta-Region Transit Link Authority, Local Transit

Authority

• Active Transportation o Bicycle and pedestrian propensity (demand, attraction, and character) o Crash data that involves pedestrians and bicyclists (including crash density) o Gap analysis on infrastructure (especially sidewalks near destinations such as parks and schools as well as on arterials and major collectors or near transit stops) ADA Transition Plan and whether the condition of public right-of-way has been documented o Bicycle or walking level of comfort analysis o Access measures for bicycle network o Possible Data Source(s): Strava, People for Bikes, ARC Active Transportation

Inventory, Roadway Element Validation and Mapping (REVAMP) provided by ARC

• Freight and Goods Movement (Truck and Rail) o Level of Service on Truck Routes Can be calculated shorthand as the volume-to-capacity ratio, but it is more accurately based on the Highway Capacity Manual, which considers multiple factors, including a road’s size and urban/rural context o Travel Time Index (TTI) and / or truck travel time reliability (TTTR) on truck routes o Bottlenecks on Truck Routes

Can be incorporated from other plans or studies, or can be derived from original analysis of freight congestion, reliability, network characteristics (e.g., convergence of multiple roads), physical barriers (e.g., low clearance overpasses), truck restrictions, or roadway characteristics (e.g., reductions in the number of lanes o Truck parking Parking needs for short- or long-duration truck staging or driver rest periods, field observations, stakeholder knowledge, or other data sources such as truck probe data.

o Crashes involving freight trains at at-grade railroad crossings o Truck-Involved crashes

Focus on fatal and serious injury crashes. There are multiple methods for highlighting fatal and serious injury crashes, including examining fatal and serious injury crash rates, or calculating equivalent property damage only https://metro.strava.com/ https://garc.maps.arcgis.com/apps/webappviewer/index.html?id=ac9b81cce02741d98e967afff3c247f9 https://garc.maps.arcgis.com/apps/webappviewer/index.html?id=ac9b81cce02741d98e967afff3c247f9

A-14

(EPDO), which places higher weight on more serious crashes in calculations.

o Possible Data Source(s): County traffic counts, Highway Capacity Manual, National Performance Management Research Data Set (NPMRDS), Altitude by GeoTab ITS, GDOT Numetric, Federal Railroad Administration Crossing Inventory

• Transportation Systems Management & Operations (TSMO) o Identification of work zone incidents o Identification of non-recurring congestion o Identification of corridors needing efficiency improvements o Identification of areas with charging infrastructure gaps or areas where charging infrastructure would be most utilized (considering traffic volume, land use, and economic activity) o Assessment of environmental impact of EV Adoption Rates o Possible Data Source(s): Connected Vehicle Deployment Map, Transportation

Electrification Plan (ARC), Alternative Fuels Data Center, ARC EV Planning Tool, Department of Revenue Registered EVs

• Climate adaptation and transportation infrastructure resiliency o Flood vulnerability assessment of transportation infrastructure, including future precipitation assessment o Identification of critical transportation infrastructure, such as roads and bridges, that are critical during major storm events (for example, roadways to hospitals that are vulnerable to future flooding) o Identification of low tree canopy or stretches of linear transportation that have no shade o Planning level phasing for replacement of aging underground infrastructure that would conflict with transportation improvement project implementation or cause transportation funds to be spend inefficiently o Possible Data Source(s):District Stormwater Forecast (ARC Open Data), The Climate Explorer, Climate Mapping for Resilience and Adaptation, FEMA’s Resilience Analysis and Planning Tool (RAPT), Metro Atlanta Climate Action Plan (Available March 2025), Regional Resiliency Plan

• Safety o Analysis of crash trends, including pedestrian crash hotspots o Identification of roadways with a high number of risk factors, especially roadways with high risk for pedestrians.

o Identifying factors affecting safety, both physical features and operator experience (lighting, number of lanes, speed limit and travel speed, driver distractions) o A safety benefit-cost analysis for all road widenings using the cost factors in the Regional Safety Strategy as a minimum.

o Possible Data Source(s): GDOT Numetric, ARC Safety Strategy, ARC Risk Factors https://ops.fhwa.dot.gov/publications/fhwahop20028/index.htm https://its.geotab.com/ https://its.geotab.com/ https://railroads.dot.gov/safety-data/crossing-and-inventory-data/crossing-inventory-dashboards-data-downloads https://www.transportation.gov/research-and-technology/interactive-connected-vehicle-deployment-map https://afdc.energy.gov/stations#/find/nearest https://opendata.atlantaregional.com/content/6196e4e2547440418008b2d76c92c900/about https://crt-climate-explorer.nemac.org/ https://crt-climate-explorer.nemac.org/ https://resilience.climate.gov/ http://www.fema.gov/emergency-managers/practitioners/resilience-analysis-and-planning-tool http://www.fema.gov/emergency-managers/practitioners/resilience-analysis-and-planning-tool https://atlantaregional.org/what-we-do/climate-resiliency/ https://atlantaregional.org/what-we-do/climate-resiliency/ https://cdn.atlantaregional.org/wp-content/uploads/arc-regional-safety-strategy-9-may-23.pdf#page=131 http://atlantaregional.org/risk-factors

A-15

Building on the visioning and goals effort, the Subgrantee will follow a project evaluation framework which will be designed and tightly integrated with the overall CTP planning process to support decision-making, project selection and periodic re-evaluation and reviews. The framework will be based on data that is both qualitative and quantitative. Emphasis will be placed on ensuring that the framework is flexible, captures detailed datasets, and allows for adjustments. The evaluation framework will be developed with the intended use of determining which strategies and projects (identified in Task 5) are of the highest priority.

The evaluation framework will also reflect a performance-based planning approach required for MPO plans, which establishes that regions must set forth appropriate performance targets and show progress toward achieving the targets. The Subgrantee will then develop a set of criteria for evaluation and ranking projects. Because of the difference in the order of magnitude of potential measures, a scoring system will be developed that converts the measures to a common scale so that projects can be equally evaluated against each other. The scoring system allows for a more accurate evaluation and ranking on a common level and provides the level of transparency and depth of information required to achieve the strategic goals and objectives.

The complexity of Gwinnett County’s mobility needs, and multi-jurisdictional makeup means it is likely that a single type of prioritization approach will prove insufficient to provide decision makers with the information they need to make difficult and politically sensitive trade-offs between projects. Therefore, the Subgrantee will develop an evaluation framework that will allow project portfolios to be analyzed through different lenses. This will help provide credibility to decision-makers and demonstrate the trade-off analysis executed as part of the project evaluation process. This evaluation framework will be used when prioritizing project during the subsequent Task 5.

Task 4 Deliverables:

• Evaluation framework documentation

• Draft and Final Current and Planning Horizon Needs Assessment Report (including maps, text and tables) o Final Report must incorporate ARC submitted comments

• Project website materials (prepared throughout CTP development process)

A-16

TASK 5 – RECOMMENDATIONS

Task 5 will include the project recommendations that come out of the Needs Assessment.

These recommendations may take a variety of forms, and the precise outcomes will be dictated by the level of emphasis placed on each CTP element. The following should be guiding principles for all recommendations, regardless of their timeline.

• Recommendations should reflect the feedback received from the community engagement efforts and formally adopted by local government policy officials. A summary of the feedback and comments received from the community should be included in the final deliverables.

• Recommendations should leverage and complement regional facilities, services, and programs to address local needs and priorities.

• Recommendations should knit together previous plans and projects identified at the community level through Livable Centers Initiative (LCI) studies, Community Improvement District (CID) work programs, county/city Capital Improvement Programs (CIP), corridor studies, freight cluster plans, and other initiatives previously undertaken within the study area.

• Recommendations should be viewed through the lens of mitigating climate change and preparing for the effects of climate change.

• Recommendations shall try including green infrastructure projects where possible.

Regardless of the unique needs and priorities of the jurisdiction, the following general steps should be completed:

• Project list timelines need to follow logical funding sources, such as a SPLOST timeline.

For example, if the SPLOST timeline is to renew every 6 years, the short-term project list can use that as a funding resource for projects from 0-6 years. If there is not a timeline like that is logical to follow, you may do intervals of 5 years and 10 years.

o A summary of the last two SPLOST/T-SPLOST programs with a discussion on total funding, project by type, goals, deliverability, etc.

• A completely fiscally unconstrained project list should be the starting point. This list should identify a project solution for each need identified in Task 4.

• Next, this list should be prioritized based on the methodology developed. The short-term funding amounts should be calculated with the basic assumption that the near-term continuation of those resources is a reasonable possibility to continue.

• The mid-term and long-term project lists should be based on realistic ways to generate more funds for transportation projects, such as increasing SPLOST dollars, instituting a TSPLOST if one does not exist, or adding / increasing impact fees.

o Aspirational projects (projects that would be completed past the planning horizon) can be included on the fiscally unconstrained project list.

• An Action Plan should be developed that includes a lists of implementable action items that can be completed in a 6-month, 1-year, and 2-year time frame. The goal is to

A-17 identify specific actions that will be undertaken following adoption. This plan should also include how the County will demonstrate the progress of these actions.

• The final project list must identify the lead jurisdiction for each project.

o Each jurisdiction should also have a comprehensive project list broken out separately with a corresponding map.

Task 5 Deliverables:

• Project prioritization methodology and results

• Transportation funding analysis (current sources of funding and projection of future funding, including realistic funding source scenarios)

• Draft and Final Recommendations Report(s) o Final Recommendations Report must incorporate ARC submitted comments.

• Project website materials (prepared throughout CTP development process)

• Stakeholders Committee meeting materials and summary documentation (conducted throughout CTP development process)

• PMT meetings summary notes (conducted throughout CTP development process)

A-18

TASK 6 – DOCUMENTATION

The Subgrantee will prepare draft and final CTP documentation for review and submittal to ARC.

For the final documentation, the use of innovative and creative approaches to documentation is encouraged. For any deliverables for which printing is determined to be necessary, ARC must be provided with at least one hard copy.

The Subgrantee will organize all previously produced interim documents and use them in development of the final CTP Report. These documents include:

• Project Management Plan

• Public Engagement Plan

• Inventory of Existing Conditions Report

• Current and Planning Horizon Year Needs Assessment Report

While key findings, observations and conclusions of the interim deliverables will be integrated into the final plan document, the contents of those interim deliverables do not need to be replicated in their entirety. They may be included in the final document(s) by reference if desired.

The final document should be succinct and rely heavily on charts, maps, infographics, and other methods, and less on dense narrative, to convey information in a user-friendly manner.

ARC will provide a Project List template for the Subgrantee to use to detail each of the proposed projects (fiscally constrained and fiscally unconstrained). This template will include a way to list the project name, project type/category, costs, etc. as set up by ARC. The purpose of this template is so that ARC can collect project lists from each completed Subgrantee in a uniform way to use in the development of future MTPs. The following information on recommended projects must be developed and included in the final documentation as well as the submitted project list template:

• Type of project

• Short description of the project

• Current status of the project

• Location and/or termini

• Responsible implementation agency

• Total cost estimate(s)

• Likely funding source(s)

• Feasible implementation schedule

This Project List does not need to be included in the Final Document but can be submitted as a separate deliverable to ARC. The Subgrantee may still develop their own project list to use internally and for their public-facing deliverables, including the Recommendations Report.

A-19

To the extent possible, system inventory and assessment data, as well as the final project recommendations, should be mapped in ArcGIS. Relevant ArcGIS layers must be provided to ARC upon completion of the CTP, including the Project ID, location, implementation schedule, and cost estimates. The Project ID (or other project-based identification number) used in the layers must be identical to the Project ID used in the submitted project list template.

Mapped information developed in other software, whether conceptual in nature or geographically accurate, will also be provided, in either the original source format or exported into an intermediate format usable by ARC. All documents submitted must include a version that is editable by ARC (for example, please include a Microsoft Word version in addition to the Adobe InDesign version so that ARC may extract text for future use.

Task 6 Deliverables:

• Compiled set of interim deliverables (if not already provided at key milestones)

• ArcGIS layers of final project list (Project ID and Project Name/Information so that we can join this Geodatabase to the Unique IDs presented in the Project List template)

• Copy of county approval resolution (and any city approvals, as applicable)

• Project website materials (prepared throughout CTP development process)

• Community Council meeting materials and summary documentation (conducted throughout CTP development process)

• Technical Advisory Committee meeting materials and summary documentation

(conducted throughout CTP development process)

• PMT meetings summary notes (conducted throughout CTP development process)

• ARC Project List (using provided template)

• ARC Public Involvement List (using provided template)

• Final CTP documentation

• Presentation to the ARC Transportation Coordinating Committee (TCC) o May be virtual or in-person

A-20

SCHEDULE

All work and services required under this subgrant agreement shall be completed on or before July 1, 2028. These plans typically take 12-18 months to complete once a consultant team has been selected and the notice to proceed has been issued.

B-1

ATTACHMENT B

COMPENSATION AND METHOD OF PAYMENT

I. Compensation

The total cost of the Project (as described in “Attachment A”) is $1,250,000. ARC’s compensation to the Subgrantee will not exceed 80 percent of the actual costs incurred.

However, in no event will the total compensation and reimbursement, if any, to be paid to the Subgrantee under this contract exceed the sum of $1,000,000. All costs in excess of $1,000,000 are to be paid by the Subgrantee.

A breakdown of this compensation is shown in Exhibit B-1, “Budget Estimate”, which is attached to and made part of this contract for financial reporting, monitoring and audit purposes.

II. Method of Payment

The following method of payment replaces that specified in the main body of the contract.

A. Progress Payments: The Subgrantee shall be entitled to receive progress payments on the following basis. As of the last day of each month during the existence of this contract, the Subgrantee shall prepare an invoice for payment documenting work completed and costs incurred during the invoice period. This invoice shall be submitted to ARC along with the monthly report by the 10th of the following month. Any work for which reimbursement is requested may be disallowed at ARC’s discretion if not properly documented, as determined by ARC, in the required monthly narrative progress report.

Upon the basis of its audit and review of such invoice and its review and approval of the monthly reports called for in the paragraph concerning “Reports” in the main body of the contract, ARC will, at the request of the Subgrantee, make payments to the Subgrantee as the work progresses but not more often than once a month. Invoices shall reflect 100% of the allowable actual costs incurred, be numbered consecutively and submitted each month until the project is completed. Reimbursement payments from ARC shall be at 80% of the approved invoiced costs.

Subgrantee’s monthly invoices and monthly narrative progress reports are to be submitted to the ARC Executive Director or his authorized agent and must be received by him not later than

B-2 the 10th day of the following month. ARC may, at its discretion, disallow payment of all or part of an invoice received after this deadline.

B. Final Payment: Final payment shall only be made upon determination by ARC that all requirements hereunder have been completed. Upon such determination and upon submittal of a final invoice, ARC shall pay all compensation due to the Subgrantee, less the total of all previous progress payments made.

Subgrantee’s final invoice and summary document must be received by ARC no later than ten days after the project completion date specified in Paragraph 3 of the contract. ARC may, at its discretion, disallow payment of all or part of a final invoice received after this deadline.

III. Completion of Project

It is agreed that in no event will the maximum compensation and reimbursement, if any, to be paid to the Subgrantee under this contract exceed $1,000,000 and that the Subgrantee expressly agrees that he shall do, perform and carry out in a satisfactory and proper manner, as determined by ARC, all of the work and services described in Attachment A.

IV. Access to Records

The Subgrantee agrees that ARC, the Concerned Funding Agency or Agencies and, if appropriate, the Comptroller General of the United States, or any of their duly authorized representatives, shall have access to any books, documents, papers and records of the Subgrantee which are directly pertinent to the project for the purpose of making audit, examination, excerpts and transcriptions.

The Subgrantee agrees that failure to carry out the requirements set forth above shall constitute a breach of contract and may result in termination of this agreement by ARC or such remedy as ARC deems appropriate.

V. ARC’s Designated Agent

In accordance with Paragraph 5 of the main body of this contract, ARC’s Executive Director hereby designates ARC’s Director of the Center for Livable Communities, as his agent (“Cognizant Center Director”) for purposes of this contract only, except for executing amendments hereto.

B-3

EXHIBIT B-1

BUDGET ESTIMATE

Task 1: Project Management $62,500

Task 2: Engagement $312,500

Task 3: Inventory $125,000

Task 4: Assessment $375,000

Task 5: Recommendations $312,500

Task 6: Documentation $62,500

Total Cost $1,250,000

ARC Share (80%) $1,000,000

Local Share (20%) $250,000

Total $1,250,000

* Note: The estimates listed above are preliminary and actual costs by task may vary so long as the total contract value does not increase. Any change to the budget estimates shown above must be requested in writing and approved by ARC’s Cognizant COO or designee (ARC Project Manager/ CTP Program Manager/ ARC Finance Team).