Rough River Industry Day Slides.pdf
PDF 14 MB Posted
- Attached to
- Rough River Dam Safety Modification Phase 2: New Outlet works and Cutoff Wall - Industry Day
- Solicitation number
- Not on record
About this file
This document appears to be a set of slides from an Industry Day event related to the Rough River Dam Safety Modification Phase 2 project. The event is hosted by the Department of the Army Corps of Engineers Engineering District Louisville, and will be held virtually on October 23, 2024, and in-person at the project site on October 24, 2024. Contractors interested in attending either or both sessions are required to complete and submit a pre-registration form by October 16, 2024. The project involves the construction of a new outlet works and cutoff wall at the Rough River Lake in Falls of Rough, KY. The purpose of the Industry Day is to provide contractors with additional information about the project requirements and the procurement process. No further details about the specific products, services, or pricing terms are provided in this document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ROUGH RIVER DAM SAFETY
MODIFICATION PHASE 2: NEW OUTLET
WORKS AND CUTOFF WALL PROJECT
DATE: 23 October 2024
TIME: 1:00 PM EST
MICROSOFT TEAMS:
https://dod.teams.microsoft.us/l/meetup-join/19%3adod%3ameeting_5b7b9cd4e2b34d2a97f464c5b2f696e7%4 0thread.v2/0?context=%7b%22Tid%22%3a%22fc4d76ba-f17c-4c50-b9a7-8f3163d27582%22%2c%22Oid%22%3a%2217e1933c-433c- 4332-833c-0f8e6abdfc97%22%7d
Meeting ID: 993 735 589 063 Passcode: iU5Gbj
”The views, opinions and findings contained in this report are those of the author(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”
• Please ensure that you have signed in
• Company Name, POC Name, Email, Phone
• Are you interested in being the Prime or Subcontractor
• No recording
• This briefing and the attendee roster will be posted to SAM
• Please be advised that none of the information discussed today is contractually-binding
ADMINISTRATIVE ANNOUNCEMENTS
CONTRACTING
Richard Van De Linde, III Contracting Officer USACE, Louisville District richard.vandelinde@usace.army.mil
Andrew (AJ) Fleming Contract Specialist USACE, Louisville District andrew.j.fleming@usace.army.mil
ISSUE SOLICIATION: November 2024
SOLICITATION CLOSES: January 2025
EVALUATION BOARD: January 2025
AWARD: May 2025
PROCUREMENT SCHEDULE
DATES ARE APPROXIMATE AND SUBJECT TO CHANGE
• SAM.gov – www.sam.gov
• Solicitation Numbers will begin with “W912QR”
• Rough River Dam Safety Modification Phase 2: New
Outlet Works & Cutoff Wall Solicitation is
W912QR24R0048
• View interested vendors list and register as an interested vendor.
• Register/Follow to receive notifications and updates / amendments
• RFP technical information will be posted on www.sam.gov
HOW TO OBTAIN THE SOLICITATION
• Requirements to download Technical Data Package:
• Need to be registered in System for Award Management
(SAM) database. You must sign up and sign-in to your account to use many features of SAM.gov (saving searches, viewing solicitations, etc.)
• You must register your business entity (you as an individual or your organization) to be able to propose on contracts or apply for federal assistance (grants, loans, etc.) from the federal government.
• Any amendments issued to the RFP will also be posted on www.sam.gov
• Pre-Solicitation Notice – will be posted on www.sam.gov at least 15 days prior to the initial issuance of the Solicitation package.
• Advertisement – minimum 30 days to prepare proposals.
OBTAINING THE ISSUE DOCUMENTS
• The Rough River project will be a Design-Bid-Build (DBB) Request for Proposal (RFP)
• Project award will be made via a “Firm Fixed Price (FFP) contract using a Best Value Tradeoff” basis as described in the evaluation criteria.
• Proposals must be submitted on time.
• The Louisville District is located within the Eastern time zone.
• The Source Selection Evaluation Board (SSEB) evaluates contractors' proposals based on specific factors which are defined in the RFP package.
THE PROCUREMENT PROCESS
• Source Selection Criteria for “Best Value” will consist of the following factors:
• Prime Contractor’s Past Performance (Recent projects, similar in size and scope)
• Technical Approach
• Small Business Participation Plan
• Price Evaluation
• All Evaluation factors, other than price, when combined are considered approximately equal to price.
• Submit your best proposal the 1st time. If we receive an initial proposal that is awardable, discussions may not be opened.
• Read evaluation criteria carefully and be sure to fully comply with the evaluation criteria submission requirements for each.
PROPOSAL REQUIREMENTS
• Instructions for submitting a Request for Information (RFI) will be included in the solicitation.
• RFI’s for this project will be received and answered through the ProjNet system, http:www.ProjNet.org/ProjNet
• Any RFI’s submitted directly to the project team will not receive a response and will be directed to the ProjNet system.
• ProjNet Bidder’s Key for this project is QKBQE4-
E6SZZW.
PROPOSAL REQUIREMENTS (cont.)
• Project Labor Agreement : All offerors are required to submit an executed Project Labor Agreement. All offerors shall submit a Project Labor Agreement in accordance with FAR Solicitation Provision 52.222-33 and FAR Clause 52.222-34. To be acceptable, the agreements must adequately address the required statutory elements and provide sufficient information to enable the Contracting Officer to answer affirmatively the requirements laid out in FAR 22.504(b).
• FAR 22.504(b) states:
A project labor agreement shall-
(1) Bind all contractors and subcontractors engaged in construction on the construction project to comply with the project labor agreement;
(2) Allow all contractors and subcontractors to compete for contracts and subcontracts without regard to whether they are otherwise parties to collective bargaining agreements;
(3) Contain guarantees against strikes, lockouts, and similar job disruptions;
(4) Set forth effective, prompt, and mutually binding procedures for resolving labor disputes arising during the term of the project labor agreement;
(5) Provide other mechanisms for labor-management cooperation on matters of mutual interest and concern, including productivity, quality of work, safety, and health; and
(6) Include any additional requirements as the agency deems necessary to satisfy its needs.
PROPOSAL REQUIREMENTS (cont.)
PLA Resource Guide may be found at: https://safe.menlosecurity.com/https://www.dol.gov/general/good-jobs/project-labor-agreement-resource-guide
Crystal Harbin Deputy for Small Business
Louisville District
SBO-LRL@usace.army.mil
Courtney Luckett Small Business Professional
Louisville District
• The Small Business Participation Plan is a rated evaluation factor in all unrestricted procurements
• Both large and small business offerors must submit a participation plan
• The participation plan is based on total contract value
• The Small Business Participation Plan must meet the minimum Total Small Business Participation goal. The percentage will be included the solicitation.
• Small Business primes’ self-performance counts as Small Business Participation.
• Large Business offerors must submit a Small Business Subcontracting Plan
• Mandated by FAR 19.702
• This is not a rated element as a part of the Source Selection process but the offeror shall submit an acceptable plan prior to award
• The subcontracting plan is based on total subcontracted dollars
• Failure to comply in good faith is in material breach of the contract
SMALL BUSINESS PARTICIPATION PLAN &
SUBCONTRACTING PLAN
OBTAIN INFORMATION
• Attend Site Visits, Pre-Proposal Conferences, & Industry Days (Obtain copies of attendee listings for subcontracting opportunities)
• Register as an Interested Vendor on SAM
• Attend Workshops, Conferences, Trade Fairs
• Louisville District Open House: Tentative 05 February 2025
• Review Agency Forecasts (posted on website)
• Construction & IDIQ Forecast is maintained on the Business with Us page of the Great Lakes and Ohio River Division website, https://www.lrd.usace.army.mil/Opportunity-Forecast/.
OPPORTUNITIES
• We anticipate executing approximately $1.4B in FY24 through both small and large businesses.
• Contracting opportunities are posted in the System for Award Management (SAM) website at www.sam.gov. Use “W912QR” to search for Louisville District projects.
• Actively Respond to Sources Sought Notices (Market Surveys) posted to SAM
• Actively Respond to Competitive Requirements posted to SAM (limited number of sole source opportunities)
ROUGH RIVER DAM SAFETY MODIFICATION PHASE
2: NEW OUTLET WORKS AND CUTOFF WALL
TECHNICAL PRESENTATION
24 October 2024
*This presentation is For Information Only and is not part of the Draft RFP
All documents released with the Industry Day Package are subject to revision prior to the official solicitation for the project.
This presentation is For Information Only and is not part of the Draft RFP and will not be part of the official solicitation.
SPECIAL NOTE
Existing Project Overview
Dam Safety Modification Phase 2 Project Overview
Miscellaneous Project Information (FIO)
PRESENTATION OUTLINE
PROJECT LOCATION
Rough River Dam
• Flood Control - Authorized per Flood Control Act of 1938 (Public Law 761, 75th Congress, 3rd Session)
• Recreation - Authorized per Section 4 of the Flood Control Act of 1944 (P.L. 78-534)
• Water Supply - Authorized per the Water Supply Act of 1958 (43 U.S. Code § 390b)
• Water supply agreements
• Leitchfield, KY – 120 acre-feet
• Grayson County, KY – 260 acre-feet
PROJECT AUTHORIZATION
Earth Fill, partial Inclined FilterDam Type
130 feetMaximum Height
1,590 feetCrest Length
~600-ft long, 12-ft x 12-ft Semi-elliptical Concrete Conduit 65-ft wide Rock Spillway
Outlet Features
Outlet Works Construction:
Nov. 1955 to Jan. 1958
Dam & Spillway Construction:
May 1957 to Dec. 1958
Control Tower
Emergency Spillway
Stilling Basin Extension
Retreat Channel
Downstream Embankment
Conduit
Reservoir
Upstream Embankment
Relief Wells
ROUGH RIVER DAM - GENERAL PROJECT LAYOUT
KY79
Project Office 2006 Slurry Wall
Dam Crest Phase IB Exploratory Grouting
Service Bridge
Apron
Historic Channel
Control Sill Top of Active Storage (TAS)
Phase IA Hwy 79 Road Relocation
Rock Toe
GENERAL GEOLOGY AND DAM PROFILE
Beech Creek Limestone DAM GEOLOGIC PROFILE
GENERALIZED
STRAT COLUMN
Golconda Formation
- Beech Creek Limestone Member, Big Clifty Sandstone Member, and Haney Limestone Member.
Spillway
EXISTING DAM PROFILE AT STATION 22+30
El. 523.6 Spillway Sill
El. 489.6 Summer Pool
El. 469.6 Winter Pool
El. 555
100100D 200200D300D 0 300
El. 527.0 Record Pool
Beech Creek Limestone
Big Clifty Weathered Shale
Alluvial Foundation
Impervious Embankment
2’ Blanket and 12” Drains 2’ Blanket and 12” Drains
10’ Inclined Drain
Impervious Embankment
Rock Toe
Cofferdam
2.5:1
3:1
2:1
3:1
8’ 4:1
2:1
Elwren Shale
50’40’
2:1
El. 550 Phase 1 Upstream Rockfill Platform (complete)
2.5:1
Sandstone Spalls
Phase 1 Grout Lines (complete)
El. 558.9 Parapet Wall
Not to Scale
Winter (Flood Pool) = 470
Summer Pool (Restricted) = 490
Summer Pool (Recreational Pool) = 495
Spillway Control Sill = 524
Record Pool = 527.4
Top of Dam = 555
Parapet Wall = 559
ADAS Master Station
111 Automated including 58 VW 11 Manual Read PZ’s 47 Movement Monuments and Carriage Bolts 3 Relief Wells 3 Seismic Instruments
EXISTING DAM INSTRUMENTATION
• ADAS System Installed - 2013 Fully Grouted Vibrating Wire (VW)
• Transducers – 2014/2015
• Post Grouting Instrumentation - 2017
Miscellaneous Project Information (FIO)
PHASE II: NEW OUTLET WORKS AND CUTOFF WALL
27KEY FEATURES OF WORK
Dredged Spoil Area 4
SPECIAL RESTRICTIONS – NO DEVIATION
1. The tunnel excavation heading is from the downstream portal.
2. The tunnel, portals, and final excavations for the foundation of the control tower and stilling basin are limited to mechanical methods only. Blasting may be used at higher elevations for production.
3. The operating gates, bulkheads, and valves on the control tower must be installed in a watertight condition before the tunnel may progress across the dam centerline. Temporary mechanical controls may be implemented to satisfy this requirement.
4. The upstream cofferdam must not be removed until the control tower has been completed and is watertight above elevation 525.
5. Underwater blasting must only occur at reservoir levels below elevation 490 between November and April.
SPECIAL RESTRICTIONS – NO DEVIATION
6. The upstream portal must be constructed as part of the control tower transition section. The control tower excavation must be sequenced to facilitate upstream portal construction.
7. The tunnel excavation must be fully complete before the tunnel lining is allowed to proceed.
8. Cutoff wall panels must not be excavated/installed within 80 feet of the tunnel unless the tunnel liner has reached 75% of the design compressive strength.
9. Abandonment of the existing outlet works cannot commence until 30 days after the new outlet works is fully commissioned and accepted by the Government.
10. Cutoff wall work between Stations 19+50 and 23+50 must start at Critical Area A and/or immediately adjacent elements and can only proceed after the existing outlet works is abandoned and slurry control grouting is completed.
SITE USAGE PLAN
Key Contractor Considerations
1) Contractor Work Limits define site boundaries
2) EA only covers area within Contractor Work Limit
3) Contractor to submit Site Usage Plan.
4) Highway 79 to remain open to public.
5) Spillway Haul Road.
- Connects upstream to downstream construction.
- Conceptual road design provided in plans
- Some subgrade stabilization can be expected.
2) On-Site Batch Plant is Required.
3) Office Trailer Locations by Government Approval.
- Locate QA/QC trailers with Contractor trailers.
4) On-Site Lab and Storage Facility Required.
5) Old Campground Spoil Area.
- Area needs filled, graded, and developed per plans.
- Available for additional laydown.
6) Cutoff Wall Work Platform.
- Designed by Contractor.
- Utilize excavated rock.
- Expected early construction.
7) Dewatering of Tower and Stilling Basin Areas
- Contractor Submittals Required for Approval.
9) Rough River Airport - FAA coordination is required.
10) Upland Spoil/Disposal Area
- Place controlled fill from excavations.
- Cutoff wall spoil processing in same area.
11) Partnering important for:
- Severing the existing outlet conduit.
- Control tower excavation Sequence of Work.
- Reservoir Operations for Flood Control
DEPICTION OF HAUL ROAD AND OLD
CAMPGROUND
Haul Road
Dam
Cutoff Wall
Phase IB Grouting
Cofferdam
Control Tower Control Tower Excavation
U/S Portal
Dredge
Stilling Basin D/S Portal Retreat Apron
Retreat Channel – Rip Rap
Tunnel
Tunnel
Approach Channel
OUTLET WORKS PROFILE
3-D MODEL OF THE
PRIMARY EXCAVATIONS
180’ Dredging
540’ Rock Excavation 6V:1H
300’ Concrete
Apron
Soil Excavation
DamNew Tower
• Cofferdams are required for both the control tower and the stilling basin.
• The amount of underwater excavation will vary based on reservoir levels.
• Excavation extents must be sequenced.
• The majority of excavated material is rock.
Stilling Basin
700’ Retreat Channel
Left Abutment
Rock Excavation 4V:1H Slopes
Dredged Spoils
EXCAVATION AND DISPOSAL AREAS
Abandon Channel Spoil Area 6
Upland Disposal Spoil Area 1
Work Platform Spoil Area 2
Dredged Spoil Area 4
New Tower Access Spoil Area 5
SB Access Spoil Area 7
Abandon Campground Spoil Area 3Haul Road
Spoils Area 8
COFFERDAMS AND EXCAVATIONS
D/S STILLING BASIN
SEEPAGE CUTOFF AND
COFFERDAM
Sheet-Pile to E.453.5 feet
New Retreat Channel
Foundation Bedrock
• Downstream sheet-pile is required for stability and to limit seepage from the Stilling Basin Excavation.
• Cofferdam El is 453.5 feet.
• Sheetpile driven to refusal at top of rock.
– Grouting is required as part of dewatering and cofferdam design.
– Grout lines are 8 feet apart with hole spacing on 10’ centers (lines staggered).
– ~1,000-foot long double line grout curtain (~2,000 lf); additional quantities included for additional holes as directed by the Contracting Officer.
– Grouting in the karstic Haney Limestone.
– Use balanced, stable grout mix.
CONTROL TOWER EXCAVATION – GROUT CURTAIN
CONTROL TOWER EXCAVATION - COFFERDAM
Dental Treatment
• Stage 1 Cofferdam: 300 feet long lime stabilized embankment.
• Purpose: Allow foundation treatment to occur for the Stage 2 Cofferdam.
• Stage 2 Cofferdam: 650 feet long embankment.
• Foundation stripped to bedrock with core trench.
• Double line grout curtain for seepage control.
• Filter construction above dentally treated foundation.
10’ Inspection Trench8’ Core Trench
Grout Curtain
BRIDGE ABUTMENT PLAN VIEW
Advance 11 grout holes shown;
8 to be assigned by COR.
BRIDGE ABUTMENT GROUTING
Advance 11 grout holes shown;
8 to be assigned by COR
BLASTING AND INSTRUMENTATION
OUTLET WORKS
• Controlled blasting with pre-splitting and line drilling.
• Vibrations measured at nearby structures will be limited to 2 in/sec.
• Mechanical excavation is required above foundations and at portal faces.
• Test blasts will be required for each type of bedrock encountered.
• Rock reinforcement and rock fence included in the excavation designs.
CONTROL TOWER AND STILLING
BASIN BLASTING
4v:1H
UNDERWATER EXCAVATION – SEASONAL WORK
• Winter pool is at 470; restricted summer pool at 490;
normal summer pool at 495.
• Approach Channel Invert is 435.
• There is a public beach located approximately 2,000 feet away at the state park.
• Underwater blasting shall be completed at reservoir levels below elevation 490.
Restricted Summer Pool 490
Winter Pool 470
CONTROL TOWER EXCAVATION
• Upstream control, dry-type tower
• 60’x56’ footprint at base, 177 feet high
• Cast against rock excavation from El. 435’ to 482’±
• Tower will be cast against 10H:1V slopes.
• Open excavation will be 6H:1V
• Permanent rock fence: Haney Limestone
• Temporary rock fence: Big Clifty
• Upper shale requires protective bulkhead
BIG CLIFTY UPPER SHALE
BULKHEAD
ROCK
FENCE
(TYPICAL)
• Rock fence and rock reinforcement requirements are shown in the Volume 1 OTW-CG-500 plans.
• Specification 31 68 13 Rock Slope Reinforcement and Permanent Rockfall Protection.
TUNNEL AND
PORTAL EXCAVATIONS
970’ Tunnel 300’ Radius 14’ Diameter
20’ Down-stream Portal
60’ Upstream Portal
60’x56’x177’ Control Tower
115’x40’ Stilling Basin
• Upstream portal constructed integral to control tower as the transition.
CONTROL TOWER RENDERINGS
60’
UPSTREAM PORTAL
Upstream Portal
10V:1H with Rock Fence
Concrete Bulkhead
Upstream Transition MonolithsSupport Columns
Portal Face
6V:1H Permanent Rock Fall Protection
10’ Wide Bench
SERVICE BRIDGE
MAINTENANCE BULKHEAD
(STORAGE LOCATION)
BULKHEAD SLOT
JIB CRANE
STILLING WELL
TRASH RACK
BULKHEAD DOOR
• Central hydraulic power unit is utilized, factory inspection & testing required.
• 14ft x 7.2ft Service & Emergency (passage) Gates, factory inspection & testing required
• 4 Valves in the low flow bypass system (1 hydraulic and 1 manual valve per side)
• 1 Service Platform Bulkhead Door
• Actuators will be hydraulic cylinders.
• Service & Emergency Gates: Mill type cylinder, contractor designed
• Compatible to USACE designed bonnet cover. 350-kip capacity @ 1750 psi
COMPONENTS OF CONTROL TOWER
BRIDGE CRANE (20 TON) WITH 170’ LIFT
PASSAGE AIR VENT
INTAKE
ELEVATOR SHAFT (LADDER
OTHER SIDE)
SERVICE GATE
EMERGENCY GATE
BYPASS OUTLET
OH DOOR
HYDRUALIC CONTROL
STATION (HCS) AND
ELECTRICAL EQUIPMENT
BYPASS VALVES
HYDRAULIC POWER UNIT (HPU) ROOM
UNIT HEATER
EXHAUST FAN AND LOUVER
Service and Emergency Gate Leaves (2 each)
• 14’-6” x 7’-2½”, painted carbon steel
• Aluminum bronze seats and seals
Maintenance Bulkheads (2)
• 24’-3” x 9’-11”, painted carbon steel
• Neoprene seals, UHMW-PE rub blocks
Bypass Bulkheads (2)
• 8’ x 6’ max dimensions, painted carbon steel
• Neoprene seals, UHMW-PE rub blocks
Bypass Trash Screen (2)
• 7’ high x 10’ diameter, stainless steel, sectional
Service Deck Bulkhead Door
• AWWA C560 Cast iron sluice gate with wall thimble.
• Foundry & factory inspection required.
• Capable of 57 ft. reverse seated head.
Stilling basin stoplogs (3)
• 24’-6” x 3’-8”, painted carbon steel
All HSS to be fabricated by AISC IBR, ABR, HYD, or HYDA certified shop, with FCE and
CCE-1.
SERVICE/EMERGENCY
GATE LEAF
MAINTENANCE BULKHEAD
HYDRAULIC STEEL STRUCTURES
BYPASS TRASH SCREEN
BYPASS BULKHEAD
• Post-tensioning used to accommodate large service openings and service loads
• One-way post-tensioned slab on post-tensioned beams
• Strands are fully grouted
• All anchors within tower walls. Beams bear on inner half of walls.
• Conventional reinforcing for negative moment, temperature and shrinkage crack control
POST TENSIONED FLOORS
54DOWNSTREAM PORTAL – STAGE 1 EXCAVATION
Stage 1 Excavation
Stage 2 Excavation
Proposed Tunnel
Proposed Stilling Basin
6V:1H with Rock Fence
10V:1H with Rock Fence
Downstream Portal
20’
55DOWNSTREAM PORTAL SUPPORT
Steel Sets first 20’
• Permanent Suppport – Government.
• Temporary Support - Contractor
• Roadheader used at Yatesville Dam in a sandstone bedrock.
• Tunnel has radius similar to proposed at Rough River.
TUNNEL PROTOTYPE: YATESVILLE DAM
57Upper Big Clifty Shale
Interbedded Big Clifty Sandstone and Shale
Projected Based on ADC-1806 O/ATV
TUNNEL
• Temporary support designed by the Contractor.
• Grouting, shotcrete, and dowels expected.
58Upper Big Clifty Shale
Interbedded Big Clifty Sandstone and Shale
Projected Based on ADC-1806 O/ATV
TUNNELING – EXPECTED
INITIAL SUPPORT
• The tunnel is located withing the Big Clifty Sandstone.
• Thin shale beds will be encountered which require a combination of initial support methods including rock bolts, shotcrete, and other methods as proposed by the Contractor.
• The tunnel excavation must be mapped and documented.
• Neat lines are shown with the payment line defined in the specifications.
• Control of water is the responsibility of the Contractor.
Grouting can be utilized to reduce inflows.
• Water inflows are anticipated to be higher near the reservoir.
• Cast-in-place, 6,000 psi abrasion resistant concrete, with Class B finish.
• 20’ monoliths. Monoliths within the curve are 20’ with a mitered angle every 10’.
• 14’ ID, 1’ minimum liner thickness.
• Non-metallic water stops at contraction joints.
TUNNEL LINER DESIGN
Tunnel Section Tunnel Reinforcement Stilling Basin Headwall
• USBR Type III basin (115’x40’) with 5 monolithic sections.
• Dentated end-sill provides debris sweep out.
STILLING BASIN
Rock Excavation 4V:1H Slopes
Concrete Apron
New Stilling Basin
15’ Bench El 456
El 429.3
El 456
Rock Excavation 10V:1H Slopes Below 456+’
• Stilling basin utilizes mass to resist uplift.
• Redundant foundation drainage system.
• Extended sill slab provides space for dewatering systems at normal tailwater elevations.
Apron
– The stilling basin rock excavation will extend 300 feet downstream from the stilling basin and require a 1-feet thick concrete apron to protect exposed shale in the excavation.
– The outlet channel bottom width is 40 feet.
– Rock side slopes ate 6V:1H and are benched 15 feet wide at both elevation 456 and at top of rock.
– Side slopes in overburden soils are 4H:1V.
STILLING BASIN APRON
STILLING BASIN
Typical cross-section through basin
Isometric of stilling basin, end sill, and completed downstream portal. Stop logs are shown installed.
63RETREAT CHANNEL
Existing Retreat Channel
Riprap Slope Sta 24+20 End Apron Begin Riprap
Concrete apron
Riprap
Riprap
Riprap
Riprap
10V:1H Slopes
KEY FEATURES OF WORK – SERVICE BRIDGE
BRIDGE ABUTMENT
TOWER SERVICE BRIDGE
• 148’-0” long by 16’-0” feet wide, single span composite concrete bridge deck 8 ½” thick with top and bottom steel reinforcement.
• Two, 76 ¾” deep, built-up weathering steel girders with lateral cross-frames and service catwalk between girder bottom flanges.
• Bridge steel to be fabricated by AISC IBR or ABR certified shop, with
FCE
• Reinforced elastomeric bearings seated on reinforced concrete abutment and corbel.
- Fixed bearings at tower and expansion bearings at abutment.
BRIDGE ABUTMENT
• Semi-integral abutment used to isolate joint from bearings and girders.
• Approach slab connected to and supported by abutment to prevent differential settlement at joint.
• Abutment rests on bridge approach engineered fill.
• Access to catwalk provided approx. 10’ from abutment.
KEY FEATURES OF WORK – CUTOFF WALL
WORK PLATFORM – CONTRACTOR DESIGNED
Work Platform
- Contractor Designed
- Filled with processed fill from control tower/stilling basin excavation.
- Does require
- Aggregate surface
- Processed Fill
- Maintenance of ADAS
Aggregate surface
Aggregate surface
ADAS SYSTEM AND WORK PLATFORM
– Use series of slotted grout pipe and valves to ensure complete grouting in 2 Placements.
– Placement 1 placed from tower; Placement 2 from stilling basin headwall.
– Use non-shrinking, flowable material.
ABANDONMENT OF EXISTING CONDUIT
GROUT CURTAIN AT CONDUIT
CRITICAL AREA B3 AND A)
Embankment
Alluvial Soils
Residual Soils
1) Grout Critical Area B3 Before Abandonment of the Conduit.
2) Grout Through the Existing Conduit at Critical Area A.
General Test Section (15+50 – 17+50)Closure (13+50 – 15+50)
Valley Restriction 19+50-23+50
Critical Area B1 10+40-13+00
Critical Area B2 17+50-19+20
Critical Area B3 21+80-22+40
Critical Area A 22+40- 22+70
Critical Area B4 23+80- 25+00
Closure (13+50-15+50) General Test Section (15+50-17+50)
CUTOFF WALL
New Tunnel
Concrete Cutoff Wall
Length: 1,640’
Width: 2’
Depth: 75’ - 190’
74CRITICAL AREA A - AS-BUILT CONDUIT
SEEPAGE BARRIER THROUGH EXISTING CONDUIT
– Completely sever the existing conduit to construct a continuous seepage barrier.
• Dimensions per plans and specifications.
• Requires the conduit to be cored or cut.
– Means and methods for conduit demolition submitted with RFP for consideration.
– The existing outlet works to be fully abandoned.
75CONDUIT DEMOLITION AND
SEEPAGE BARRIER INSTALLATION
Slurry or Casing
DAM SAFETY REQUIREMENTS: Conduit cannot be cut or demolished from the inside. The rebar must be cut, cored, or otherwise severed from the dam crest.
76CUTOFF WALL AT CRITICAL AREA A
ABANDONMENT OF RETREAT CHANNEL
ROCK FILL AT TOE
Backfill area between new retreat Channel and existing retreat channel.
• Construct filter drain in tailwater area (shown in red)
• Place rock spoils as shown in the Grading drawings above the filter and to the limits shown (dashed blue line).
ABANDONMENT OF RETREAT CHANNEL
• Remove work platform and dispose of fill material in existing retreat channel.
• Place rock spoils as shown on the grading plan.
• Extend rock-fill to new retreat channel.
Considerations:
• Abandon to 507 level and re-establish roof drain.
• Unit Weight of CLSM ~90 pcf vs tower flooded design scenario based on unit weight of water.
• Electrical – Maintain power on upper two floors. New transformer on operations level.
• Mechanical – Drain hydraulic system and abandon in place.
ABANDONMENT OF CONTROL TOWER
SITE RESTORATION
Miscellaneous Project Information (FIO)
PROVIDED DOCUMENTS
• Volume 1: New Outlet Works (OTW) [Civil]
• Volume 2: New Outlet Works (OTW) [Facilities]
• Volume 3: Cutoff Wall (CTW) and State Road Relocation (STR)
• Volume 4: Technical Specifications
• Volume 5: Tunneling Geotechnical Baseline Report (GBR) and Tunneling Geotechnical Data Report (GDR), Joint Instrumentation and Monitoring Plan - Contractual Documents
• Volume 6: FIO Miscellaneous Documents - Geologic Interpretive Report (GIR), Rough River Dam Phase IB - Exploratory Drilling and Grouting Completion Report, Phase IB Boring Logs, As-Builts, etc.
* Project SOW is in Volume 4:Technical Specification Section 00 11 00 Summary of Work
Facility Designations on the Plans.
Description Facility Designator Outlet Works OTW Cutoff Wall CTW State Road Relocation STR Control Tower CT Service Bridge BR Tunnel and Portals TU Stilling Basin SB Tailwater Shelter SH Tailwater Restroom RR
DRAWING SET ORGANIZATION
Plan Set Discipline Designations
Discipline Discipline Designator Content General GI General Information – Drawing Cover, Index, Orientation Maps
GS General Site – Haul Routes, staging and spoil, Dewatering, etc GC General Contract – Erosion Control
Survey/Map V Control Points and Contractor work limits Traffic TC Traffic Control Geotech BS Boring Locations and Logs Civil CD Civil Demolition – Structure removal and site clearing
CI Civil Instruments – Piezometers, control stations, etc.
CS Civil Site CP Civil Paving CG Civil Grading CM Civil Pavement Markings CU Civil Utilities
Reference RF Reference Drawings – Historical As-builts, hydrographs, etc.
Electrical E Site Electrical ES Electrical Plan Sheets Communications T Fire Protect F Mechanical M Structural S Architecture A
Sheet Number Designator Sheet Type 100 Plan Views 200 Elevations and Profile Views 300 Volume 3: Cross Sections (CTW and STR) 400 Enlarged Plan Views or Typical Sections 500 Details 600 Volume 1 Cross Sections (OTW) 600 Volume 2: Miscellaneous Details and Schedules 700 Volume 1: Cross Sections (OTW - Continued) 700 Volume 2: Hydraulic Steel Structures and KYTC Standard Details 900 Volume 1: Miscellaneous Drawings and Hydrographs 900 Volume 2: Isometrics and Tunnel Mapping Sheets
Volume 4:
SECTION 00 80 00.00 06 SPECIAL PROVISIONS: Typical USACE Special Provisions
Specification modified with procedures for inspection, demonstration, re-inspection, and acceptance of the new outlet works.
SECTION 01 35 00.00 06 SPECIAL PROCEDURES includes but not limited to requirements for Dam Safety Training, Work time restrictions, emergency preparedness.
SECTION 01 78 23 OPERATION AND MAINTENANCE DATA: Includes but not limited to specific information required for Operations and Maintenance of installed equipment.
CONTRACTOR SPECIAL PROVISIONS AND SPECIAL PROCEDURES
RESERVOIR OPERATION RESTRICTIONS
*Rough River Dam is a flood control reservoir with a fluctuating pool and tailwater.
Additional information is in Volume 4:Technical Specification Section 00 31 19.23 06 WEATHER AND WATER STAGE DATA/RESTRICTIONS and associated references.
- Specification contains weather data and restrictions pertinent to the Contract for both reservoir and tailwater fluctuations.
- Reservoir levels are governed by rainfall and maximum release rates from the reservoir. Review hydrographs and hydrologic data for understanding of rainfall events which result in prolonged elevated pools.
- Contains a provision to request an early drawdown of the reservoir; subject to Government approval and prevailing weather conditions.
- Floating plant operations must allow time to target multiple working seasons.
Volume 4 SECTION 01 33 16.00 06 CONTRACTOR SUBMITTALS REQUIRING ENGINEERING AFTER AWARD including but not limited too:
1) Cutoff Wall methods, Special Panel/Secants at Critical Area A, Conduit Demolition, slurry and slurry handling systems.
2) Work Platform – Sheet-piling, MSE walls, or other methods meeting the performance criteria.
3) Dewatering – excluding the stilling basin well points.
4) Mass Excavation and Disposal.
5) Tunnels and Portals – Excluding permanent support.
6) Area Use Plan/Site Usage Plan – KTR required to obtain SWPPP and KPDES permit.
7) Metal building systems for tailwater and laboratory structure.
8) Additional miscellaneous.
CONTRACTOR SUBMITTALS REQUIRING ENGINEERING
AFTER AWARD
Volume 4 SECTION 31 23 05.00 06 MASS EXCAVATION contains general mass excavation and disposal requirements for the project including but not limited to requirements applicable for:
- Section 31 23 18.00 06 SURFACE BLASTING
- Section 31 23 17.00 06 UNDERWATER BLASTING
- Section 31 68 13 ROCK SLOPE REINFORCEMENT AND PERMANENT ROCKFALL
PROTECTION
- Section 31 60 00.00 06 FOUNDATION PREPARATION
- Section 03 37 13 SHOTCRETE
- Section 31 00 00.00 06 EARTHWORK
The mass excavation and disposal plan includes but is not limited to associated requirements for measurement and payment, definitions applicable to mass excavation, classification of excavation, rock processing plant, processed rock fill, floating plant requirements, rock cut slopes, special excavation requirements, master slope protection plan, and special conditions.
Note: See procedures for completing the retreat channel/tailwater tie-in for the new outlet works.
MASS EXCAVATION
TUNNELING GBR/GDR AND PROJECT GIR
A tunneling specific Geotechnical Baseline Report (GBR) and Geotechnical Data Report (GDR) have been developed specific to the tunnel and portal construction.
The GDR includes pertinent background information and data that led to development of the
GBR.
A project specific Geotechnical Interpretive Report (GIR) has been developed. The GIR describes subsurface conditions and variations at the overall site.
The GIR includes a narrative of the project construction history, boring logs, lab testing, photographs, and other pertinent information applicable to the entire project.
*The GBR and GIR will have some slight revisions prior to solicitation.
Volume 4 SECTION 31 71 16.00 06 ROCK TUNNELING has key references to the following specifications required to construct the tunnel and portals:
Section 00 31 31.13 06 SUBSURFACE INVESTIGATION INFORMATION Section 01 33 16.00 06 CONTRACTOR SUBMITTALS REQUIRING ENGINEERING
AFTER AWARD
Section 03 30 00 CAST-IN-PLACE CONCRETE OUTLET WORKS Section 03 37 13 SHOTCRETE Section 31 23 00.00 06 CONTROL OF WATER AND DEWATERING Section 31 23 05.00 06 MASS EXCAVATION Section 31 60 00.00 06 FOUNDATION PREPARATION Section 31 68 13 ROCK SLOPE REINFORCEMENT AND PERMANENT ROCKFALL
PROTECTION
Section 31 73 00 TUNNEL GROUTING
• Establishes roles and responsibilities for the contractor.
• Differentiates acceptable support methods, control of water, inspections, records, etc.
TUNNEL
Volume 4 SECTION 03 00 00 GENERAL CONCRETE REQUIREMENTS contains all general concrete requirements including but not limited to requirements applicable for:
- 03 70 00 MASS CONCRETE
- 03 30 00 CAST-IN-PLACE CONCRETE FOR OUTLET WORKS
- 03 15 00 BRIDGE CONCRETE ACCESSORIES
- 03 37 13 SHOTCRETE
- 03 37 29 CONCRETE FOR CUTOFF WALL
- 32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS
General Concrete Requirements include but not limited too associated requirements for materials investigations, mix designs, QA/QC, thermal studies and requirements, aggregate quality, cementitious materials, batch plant requirements, measurement and payment, etc., as applicable to other concrete specifications.
Additional specification requirements apply as appropriate in each individual specification.
CONCRETE SPECIFICATIONS
Volume 4 SECTION 31 32 23.00 06 SLURRY CONTROL DRILLING AND GROUTING
• Covers dam grouting and control tower excavation grouting.
• This specification does not cover tunnel grouting.
• Specification includes expanded section on Phase IB Exploratory Drilling and Grouting, anticipated soil conditions, and special coordination requirements.
• Includes grouting measurement and payment items, foundation drilling and grouting work plan, and required use of an instrumented packer. ***Measurement and Payment is under revision***
• Mix designs are prescribed based on successful grouting from Phase IB.
• See Volume 6 Phase IB Exploratory Grouting Contractor Completion Report, Phase IB Boring Logs, As- Builts, etc.
• Volume 3 plans have As-Builts included as Reference drawings.
FOUNDATION GROUTING
Volume 4 SECTION 31 56 10.00 06 CUTOFF WALL CONSTRUCTION includes but is not limited to:
• Subsurface conditions, pertinent history, special coordination, measurement and payment.
• Definitions specific to the cutoff wall and execution of the work as well as submittal requirements, including work plans and requirement to complete the work at Critical Area A, and applicable restrictions.
• General requirements, tolerances, verification.
• Test Section and closure requirements.
• Evaluation and acceptance requirements.
• Existing Outlet Works abandonment procedures.
CUTOFF WALL CONSTRUCTION
AVAILABLE SUBSURFACE INFORMATION AND SAMPLE INSPECTION
• Volume 4 SECTION 00 31 31.13 06 SUBSURFACE INVESTIGATION INFORMATION contains a summary of avalable geotechnical information applicable to the new outlet works, cutoff wall and general dam.
• The Solicitation will include notice for a time period that samples may be inspected at the USACE Storage Facility located in Louisville, Kentucky.
• All appointments will only be issued to Prime Contractor’s/JV’s; the prime is responsible to coordinate the visit date and time with subcontractors.
• Each Prime Contractor will be limited to what rock core can be examined during an 8-hour time period. Prime Contractor’s are limited to a maximum inspection time of 16 hours.
AVAILABLE SUBSURFACE INFORMATION AND SAMPLE INSPECTION
CONTRACTOR REQUIRED EXPLORATIONS
• Volume 4 SECTION 02 32 00 ADDITIONAL INVESTIGATIONS contains requirements for the Contractor to conduct additional field investigations in support of the following:
1) Work platform design and construction.
2) Downstream sheet pile cofferdam drive-ability analysis, pile test section, and piling termination depths.
3) Installation of new dam instrumentation.
THANK YOU!!!