This is a Rough Order of Magnitude (ROM) cost estimate spreadsheet for Air Force carpet, furniture, and asbestos abatement services at a facility designated as 9 CS B2445. The document serves as market research input and is not an official solicitation or request for quotation. The estimate is organized into four priority levels, with Priority 1 representing the base scope and Priorities 2-4 as optional contract line items (CLINs).
Priority 1 includes carpet tile materials (93 square yards), carpet tile installation labor, adhesive materials (7 gallons), cove base materials (239 linear feet), cove base installation labor, miscellaneous materials, complete asbestos abatement services with EPA notification and air clearance sampling, and furniture removal and storage for approximately 1,530 square feet. Priority 2 expands the scope with additional carpet tile materials (103 square yards) and cove base (122 linear feet). Priority 3 significantly increases carpet coverage to 884 square yards with 875 linear feet of cove base and 59 gallons of adhesive. Priority 4 adds 608 square yards of carpet tiles and 912 linear feet of cove base with 41 gallons of adhesive. All cost fields in the spreadsheet are blank ($0 entries), indicating this is a template awaiting contractor pricing responses. The point of contact is Teresa Romig at teresa.romig@us.af.mil or (530) 634-3405.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CONTRACTOR EAL.xlsx | XLSX spreadsheet | |
| SON-9 CS B2445 CarpetFurnitureAsbestos_FINAL Aug 2026.....pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| 9 CONS |
| Rough Order Magnitude (ROM) |
| 9 CS B2445 Carpet/Furniture/Asbestos |
| *Disclaimer: Information below is a cost estimate. This does not depict actual cost of work to be performed. It is an estimate ONLY. |
| POC: Teresa Romig / PKB |
| Email/Phone: teresa.romig@us.af.mil / (530) 634-3405 |
| Priority 1 | |||||
| CLINS | ITEM/SERVICE | UNIT OF MEASURE | QTY | COST | TOTAL |
| CLI+D50+A11+A11:F18 | Carpet Tile Materials Supply of carpet tiles meeting the specifications outlined in the Statement of Need (SON) | Square Yard | 93 | $ - 0 | |
| CLIN 0002 | Carpet Tile Installation Labor. All labor required specifically for the installation of carpet tiles, excluding material costs. | Square Yard | $ - 0 | ||
| CLIN 0003 | Adhesive Materials Supply of adhesive compatible with the specified carpet tiles and suitable for the existing subfloor. Must meet all applicable regulations and standards | Gallon | 7 | $ - 0 | |
| CLIN 0004 | Cove Base Materials. Supply of cove base meeting the specifications outlined in the Statement of Need (SON). | Linear Foot | 239 | $ - 0 | |
| CLIN 0005 | Cove Base Installation Labor. All labor required specifically for the installation of cove base, excluding material costs | Linear Foot | $ - 0 | ||
| CLIN 0006 | All other materials needed to complete carpetremoval/installation. | Lot | 1 | $ - 0 | |
| CLIN 0007 | Asbestos Abatement. Complete asbestos abatement services as described in the SON, including: Removal of ACM in designated areas; Preparation of concrete subfloor; Submission of required plans, certifications, and notifications (including EPA notification); Removal and disposal of all asbestos-containing materials according to regulations; Air clearance sampling and reporting; Hazardous waste manifestsubmission | Lot | 1 | $ - 0 | |
| CLIN 0008 | Furniture Removal and Storage. Removal, storage, and reinstallation of all furniture within the designated area (approx. 1530 sq ft) as described in the SON. This includes: Packing and protection of furniture items; Transporting furniture to and from the designated storage location; Secure storage of furniture during the project; Returning furniture to its original location andconfiguration. | Lot | 1 | $ - 0 | |
| Overall Total | $ - 0 |
| Priority 2 | |||||
| CLINS | ITEM/SERVICE | UNIT OF MEASURE | QTY | COST | TOTAL |
| CLIN 1001 Optional CLIN | Carpet Tile Materials Supply of carpet tiles meeting the specifications outlined in the Statement of Need (SON) | Square Yard | 103 | $ - 0 | |
| CLIN 1002 Optional CLIN | Carpet Tile Installation Labor. All labor required specifically for the installation of carpet tiles, excluding material costs. | Square Yard | $ - 0 | ||
| CLIN 1003 Optional CLIN | Adhesive Materials Supply of adhesive compatible with the specified carpet tiles and suitable for the existing subfloor. Must meet all applicable regulations and standards | Gallon | 7 | $ - 0 | |
| CLIN 1004 Optional CLIN | Cove Base Materials. Supply of cove base meeting the specifications outlined in the Statement of Need (SON). | Linear Foot | 122 | $ - 0 | |
| CLIN 1005 Optional CLIN | Cove Base Installation Labor. All labor required specifically for the installation of cove base, excluding material costs | Linear Foot | $ - 0 | ||
| CLIN 1006 Optional CLIN | All other materials needed to complete carpetremoval/installation. | Lot | 1 | $ - 0 | |
| CLIN 1007 Optional CLIN | Asbestos Abatement. Complete asbestos abatement services as described in the SON, including: Removal of ACM in designated areas; Preparation of concrete subfloor; Submission of required plans, certifications, and notifications (including EPA notification); Removal and disposal of all asbestos-containing materials according to regulations; Air clearance sampling and reporting; Hazardous waste manifestsubmission | Lot | 1 | $ - 0 | |
| CLIN 1008 Optional CLIN | Furniture Removal and Storage. Removal, storage, and reinstallation of all furniture within the designated area (approx. 1530 sq ft) as described in the SON. This includes: Packing and protection of furniture items; Transporting furniture to and from the designated storage location; Secure storage of furniture during the project; Returning furniture to its original location andconfiguration. | Lot | 1 | $ - 0 | |
| Overall Total | $ - 0 |
| Priority 3 | |||||
| CLINS | ITEM/SERVICE | UNIT OF MEASURE | QTY | COST | TOTAL |
| CLIN 2001 Optional CLIN | Carpet Tile Materials Supply of carpet tiles meeting the specifications outlined in the Statement of Need (SON) | Square Yard | 884 | $ - 0 | |
| CLIN 2002 Optional CLIN | Carpet Tile Installation Labor. All labor required specifically for the installation of carpet tiles, excluding material costs. | Square Yard | $ - 0 | ||
| CLIN 2003 Optional CLIN | Adhesive Materials Supply of adhesive compatible with the specified carpet tiles and suitable for the existing subfloor. Must meet all applicable regulations and standards | Gallon | 59 | $ - 0 | |
| CLIN 2004 Optional CLIN | Cove Base Materials. Supply of cove base meeting the specifications outlined in the Statement of Need (SON). | Linear Foot | 875 | $ - 0 | |
| CLIN 2005 Optional CLIN | Cove Base Installation Labor. All labor required specifically for the installation of cove base, excluding material costs | Linear Foot | $ - 0 | ||
| CLIN 2006 Optional CLIN | All other materials needed to complete carpetremoval/installation. | Lot | 1 | $ - 0 | |
| CLIN 2007 Optional CLIN | Asbestos Abatement. Complete asbestos abatement services as described in the SON, including: Removal of ACM in designated areas; Preparation of concrete subfloor; Submission of required plans, certifications, and notifications (including EPA notification); Removal and disposal of all asbestos-containing materials according to regulations; Air clearance sampling and reporting; Hazardous waste manifestsubmission | Lot | 1 | $ - 0 | |
| CLIN 2008 Optional CLIN | Furniture Removal and Storage. Removal, storage, and reinstallation of all furniture within the designated area (approx. 1530 sq ft) as described in the SON. This includes: Packing and protection of furniture items; Transporting furniture to and from the designated storage location; Secure storage of furniture during the project; Returning furniture to its original location andconfiguration. | Lot | 1 | $ - 0 | |
| Overall Total | $ - 0 |
| Priority 4 | |||||
| CLINS | ITEM/SERVICE | UNIT OF MEASURE | QTY | COST | TOTAL |
| CLIN 3001 Optional CLIN | Carpet Tile Materials Supply of carpet tiles meeting the specifications outlined in the Statement of Need (SON) | Square Yard | 608 | $ - 0 | |
| CLIN 3002 Optional CLIN | Carpet Tile Installation Labor. All labor required specifically for the installation of carpet tiles, excluding material costs. | Square Yard | $ - 0 | ||
| CLIN 3003 Optional CLIN | Adhesive Materials Supply of adhesive compatible with the specified carpet tiles and suitable for the existing subfloor. Must meet all applicable regulations and standards | Gallon | 41 | $ - 0 | |
| CLIN 3004 Optional CLIN | Cove Base Materials. Supply of cove base meeting the specifications outlined in the Statement of Need (SON). | Linear Foot | 912 | $ - 0 | |
| CLIN 3005 Optional CLIN | Cove Base Installation Labor. All labor required specifically for the installation of cove base, excluding material costs | Linear Foot | $ - 0 | ||
| CLIN 3006 Optional CLIN | All other materials needed to complete carpetremoval/installation. | Lot | 1 | $ - 0 | |
| CLIN 3007 Optional CLIN | Asbestos Abatement. Complete asbestos abatement services as described in the SON, including: Removal of ACM in designated areas; Preparation of concrete subfloor; Submission of required plans, certifications, and notifications (including EPA notification); Removal and disposal of all asbestos-containing materials according to regulations; Air clearance sampling and reporting; Hazardous waste manifestsubmission | Lot | 1 | $ - 0 | |
| CLIN 3008 Optional CLIN | Furniture Removal and Storage. Removal, storage, and reinstallation of all furniture within the designated area (approx. 1530 sq ft) as described in the SON. This includes: Packing and protection of furniture items; Transporting furniture to and from the designated storage location; Secure storage of furniture during the project; Returning furniture to its original location andconfiguration. | Lot | 1 | $ - 0 | |
| Overall Total | $ - 0 |
File details come from the government source that posted it. Updated .