This document is a Statement of Work (SOW) for a federal contract opportunity to perform lead abatement and painting work at the Rockefeller Hall building in Acadia National Park, Maine.

The SOW requires the contractor to perform lead abatement on interior water and storm damaged surfaces throughout the Rockefeller Hall building, utilizing State of Maine approved methods. Once the lead paint is removed, the contractor will apply one coat of white latex primer to the surfaces. The work includes providing all labor, equipment, and materials to accomplish the lead abatement and painting. The contractor must have a State of Maine licensed lead abatement certification. Some areas may also contain asbestos, which the contractor would need to have mitigated by a State of Maine licensed asbestos contractor if necessary. The work is to be performed Monday through Friday during normal business hours, with no weekend or holiday work authorized. The related federal contract opportunity is Solicitation Number 140P4324R0040 for "ACADIA NATIONAL PARK - ROCKEFELLER LEAD PAINT ABATEMENT" issued by the Department of the Interior National Park Service Northeast Region.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work Rockefeller Hall Interior Lead Abatement Acadia National Park

Bar Harbor, Maine.

National Park Service

TABLE OF CONTENTS

DIVISION 1 - GENERAL REQUIREMENTS

01110 Summary of Work……………………………………………………………………….3 01270 Definition of Contract Line Items………………………………………………………..5 01320 Schedules and Monthly Inspections……………………………………………………..7 01330 Submittals………………………………………………………………………………..9 01360 Accident Prevention……………………………………………………………………..13 01430 Contractor Quality Control ……………………………………………………………..17 01770 Project Closeout…………………………………………………………………………23

DIVISION 9- FINISHES

09900 Painting …………………………………………………………………………………25

SECTION 01110

SUMMARY OF WORK

PART 1

GENERAL

PART 1

GENERAL

1.1

DESCRIPTION

A.

This project involves lead abatement from water / storm damage throughout the interior of Rockefeller Hall building at Acadia National Park, Schoodic Institute, Winter Harbor, Maine. Surfaces to be lead abated utilizing State of Maine approved methods. Once removed apply one coat of white latex primer. The expectation of this work is for loose lead paint to be removed and encapsulate the surface area once the lead paint has been removed. No drywall / paster repair will be done at this time. Do not remove any drywall/ plaster. The contractor shall provide all labor, equipment, and materials to accomplish this work.

B.

All work will be performed under a single contract.

1.2.1 LOCATION

A.

Locations will be specified as per each individual task order. Rockefeller Hall building at Acadia National Park, Schoodic Institute, Winter Harbor, Maine.

1.3

CONTRACTOR'S USE OF PREMISES

A.

Construction Camp: Establishment of a camp within the park will not be permitted.

B.

Confine storage of materials to National Park Service property in the immediate area around the construction site.

1.4

SPECIAL CONSTRUCTION REQUIREMENTS

Work hours shall be 7:00 AM to 3:30 PM. No weekend or holiday work is authorized.

B.

Contactor must Submit a copy of their State of Maine of Licensed Lead Abatement Certification for both contractor and employees that will be doing the abatement work using the CM-16 Transmittal Form.

C.

See attached asbestos report. Some areas of work may have asbestos in plaster, we don’t anticipate any disturbance of asbestos material but if necessary, contractor will have to State of Maine licensed contractor to mitigate any exposure to that area.

1.5

FIELD VERIFICATION

Field verify all new and existing dimensions affecting the work of this contract before ordering products.

1.6

CONSTRUCTION MATERIALS

All materials shall be Contractor‑furnished from outside the park.

PART 3

EXECUTION

Not used.

END OF SECTION

SECTION 01270

DEFINITION OF CONTRACT LINE ITEMS

PART 1

GENERAL

1.1

DESCRIPTION

The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut‑off points where one item ends, and another begins.

B.

If no contract line item exists for a portion of the work, include the costs in a related item.

1.2 CONTRACT LINE ITEMS NO. 001 thru 013- Abate lead base paint and cover area with one coat of white latex paint.

A.

These items consist of abatement of loose / flaking / fallen / or bubbled lead base paint on walls and ceilings structures and their features

Measurement will be by the square foot, linear foot, or each.

C.

Payment will be made at the contract lump sum price for each line item.

D. Line Items:

Line Item
Description
0010
Lead Abatement water damaged area, Rockefeller Hall suite B Ceiling Finance Office 11’x6’ = 66sqft. Abate loose peeling paint and then - utilize lead paint stabilization procedures- 1 primer coat.
0020
Lead Abatement water damage area, Rockefeller Hall suite A (164) south Kitchen Ceiling 7’x8’=56sqft. Conference or kitchen table room 12’x9’= 108sqft Living room area ceiling 11’x4’=44sqft Abate loose peeling paint and then - utilize lead paint stabilization procedures- 1 primer coat.
0030
Lead Abatement water damaged area, Rockefeller Hall suite C Kitchen north and west walls 7’x 8’= 56sqft, Ceiling 6’x3’=18sqft, Kitchen pantry closet 10’x 8’=56sqft + 6sqft for ceiling in pantry=62sqft, Foyer closet to suite C Walls 10’x 8’=80sqft ceiling 6’x4’= 24sqft, Foyer ceiling

9’x3’=27sqft. This is not the entire ceiling. Abate loose peeling paint and then - utilize lead paint stabilization procedures- 1 primer coat.

0040
Lead Abatement water damaged area, Rockefeller Hall north breakout (100) and fireplace room, Fireplace room 1sqft next to ceiling light, Breakout room 10’x11’=110sqft. Abate loose peeling paint and then - utilize lead paint stabilization procedures- 1 primer coat.
0050
Lead Abatement water damaged area, Rockefeller Hall front desk lobby Outside Megan’s office Ceiling 6’x5’=30sqft Abate loose peeling paint and then - utilize lead paint stabilization procedures- 1 primer coat.
0060
Lead Abatement water damaged area, Rockefeller Hall north stairwell suite C (211) Wall 13.5”x 8’= 108sqft, Ceiling 4’x18’= 72sqft, Ceiling inside exterior door 7’x7’=49sqft. Abate loose peeling paint and then - utilize lead paint stabilization procedures- 1 primer coat.
0070
Lead Abatement water damaged area, Rockefeller Hall south stairwell first floor. Wall adjacent to storage room 8’x6’=48sqft Wall above display” everyone’s a naturalist” 1x11=11sqft. Abate loose peeling paint and then - utilize lead paint stabilization procedures- 1 primer coat.
0080
Lead Abatement water damaged area Rockefeller Hall main center entrance ceiling. 6’x8’=48 sqft. Abate loose peeling paint and then - utilize lead paint stabilization procedures- 1 primer coat.
0090
Lead Abatement water damaged area, Rockefeller Hall Schoodic institute lobby ceiling 13’x13’= 169sqft, 13’x12’= 156sqft. Abate loose peeling paint and then - utilize lead paint stabilization procedures- 1 primer coat.
0100
Lead Abatement water damaged area, Rockefeller Hall south suite B (176)

Utility closet just inside suite on left Ceiling and maybe wall paint bubbling (20sqft for estimating purposes). Abate loose peeling paint and then - utilize lead paint stabilization procedures- 1 primer coat.

0110
Lead Abatement water damaged area, Rockefeller Hall suite B (176)

South stairwell Wall first floor 14’x9’=126sqft. Abate loose peeling paint and then - utilize lead paint stabilization procedures- 1 primer coat.

0120
Lead Abatement water damaged area, Rockefeller Hall south stairwell second floor Suite H (275), 8’x4’= 32sqft. Abate loose peeling paint and then - utilize lead paint stabilization procedures- 1 primer coat.
0130
Lead Abatement water damaged area, Ceiling Finance Office 11’x6’ = 66sqft. Abate loose peeling paint and then - utilize lead paint stabilization procedures- 1 primer coat.

PART 2

PRODUCTS

Not used.

PART 3

EXECUTION

Not used.

END OF SECTION

SECTION 01320

SCHEDULES AND MONTHLY INSPECTIONS

PART 1

GENERAL

PART 1

GENERAL

The work of this section consists of schedule requirements before and during construction.

1.2

SCHEDULES

As specified in Section 01330.

B.

As soon as possible after Notice of Award and before beginning any work, the Contractor shall submit a Progress Schedule and Schedule of Values as a package. Contracting Officer will review the Progress Schedule and the Schedule of Values for format and content.

1.

Progress Schedule: Submit one copies of the Progress Schedule. Show each bid item and area of work and break down work into the smallest element. The schedule shall correspond to each specification section and shall identify the critical path of the project. No progress payments will be made until acceptable progress schedule is provided.

2.

Schedule of Values:

a.

Submit a schedule of dollar values based on the Contract Bid Schedule. Include bond costs, mobilization, general condition costs, overhead, and profit in the total dollar value of unit price items and in the component parts of work for each lump-sum item, as described below. Do not include bond premiums, mobilization, general condition costs, overhead, or profit as separate items; however, payment for bond premiums can be made based upon evidence of payment to the surety. Bond premiums may be shown as a separate item.

b.

Break down each lump-sum bid item into component parts of work for which progress payments may be requested. The total costs for the component parts of work shall equal the bid amount for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values.

c.

Do not break down unit price bid items. Use only the bid amount for unit price items.

d.

The total cost of all items shall equal the contract sum. The Schedule of

Values will form the basis for progress payments as provided for in the terms of the contract.PART 2

Not used.

PART 3

EXECUTION Not used.

PART 4

MEASUREMENT AND PAYMENT

PART 2

MEASUREMENT AND PAYMENT

2.1

SCHEDULES AND MONTHLY INSPECTIONS

Payment will be included in the bid item to which this work relates.

END OF SECTION

SECTION 01330

SUBMITTALS

PART 1

GENERAL

The work of this section consists of submittal requirements before and during construction.

1.2 SUBMITTAL AND APPROVAL PROCEDURES

A.

All submittals shall be transmitted using the latest National Park Service form Transmittal Form CM-16. No action will be taken on a submittal item unless accompanied by the transmittal form.

B.

As specified in the individual sections, forward submittals to Contracting Officer at least 30 days before need for approval.

Samples: Samples shall be large enough to illustrate clearly the functional characteristics and full range of color, texture, or pattern.

3.

Manufacturers' Catalog Sheets: Submit only pertinent pages; mark each copy of standard printed data to identify specific products proposed for use 4.

Manufacturer's Installation Instructions: When contract documents require compliance with manufacturer's printed instructions, provide one complete set of instructions for Contracting Officer and keep another complete set of instructions at the project site until substantial completion.

C.

Contracting Officer reserves the right to require submittals in addition to those called for in individual sections.

D.

Approved Equals:

For each item proposed as an "approved equal," submit supporting data, including:

Drawings and samples as appropriate.

Comparison of the characteristics of the proposed item with that specified.

Changes required in other elements of the work because of the substitution.

Name, address, and telephone number of the vendor.

e.

Manufacturer's literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists. Describe availability of maintenance service, and state source of replacement materials.

A request for approval constitutes a representation that Contractor:

Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.

Will provide the same warranties for the proposed item as for the item specified.

Has determined that the proposed item is compatible with interfacing items.

Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.

e.

Waives all claims for additional expenses that may be incurred as a result of the substitution.

Construction Materials: The Contractor is encouraged to submit for approval products that are locally available and do not utilize proprietary materials.

E.

Coordinate all submittals and review them for legibility, accuracy, completeness, and compliance with contract requirements. Forward submittals that are related to or affect one another as a package to facilitate coordinated review. Each transmittal shall contain only data specific to that individual submittal.

F.

Submittal Identification:

Project submittal identification shall be applied by the Contractor. Identification shall include the park name-package number, project title, contract number, and transmittal number.

All sets of shop drawings, manufacturer's catalog sheets, samples, and other documents submitted to the Contracting Officer must have the identification information on the submittal.

Identification information shall be applied to the bottom right margin on each page. Identification information on samples shall be applied to the most readily visible area on the sample or on tags attached to sample.

G.

Submittal Numbering:

Number each submittal consecutively.

For re-submittals use the original submittal number, plus a letter suffix beginning with A.

Additional re-submittals of the same item shall contain the original number with the next consecutive letter.

H.

Contracting Officer's Review:

1.

Submittals will be returned disapproved without technical review if identification information is missing, not filled in, or if placed on the back of the submittal; an incorrect number or format of submittals is provided; the transmittal form is incorrectly filled out; submittals are not coordinated; or submittals do not show evidence of Contractor's approval.

Any work done or orders for materials or services placed before approval shall be at the Contractor's own risk.

After reviewing submittals, the Contracting Officer will return one copy of form

CM-16 and one copy of applicable (marked up) submittal sheets to the

Contractor. Shop drawing review notations will be returned on the reproducible original shop drawing. All other submitted items will be retained. The

Contractor is responsible for producing additional copies for his/her own use.

The returned submittal will be marked in one of three ways as defined below:

APPROVED: Acceptable with no corrections.

APPROVED WITH NOTATIONS: Minor corrections or clarifications required. All comments are clearly expressed, and no further review is required. The Contractor shall address all review comments when proceeding with the work.

DISAPPROVED - RESUBMIT: Rejected as not in accordance with the contract or as requiring major corrections or clarifications. The

Contracting Officer will identify the reasons for disapproval. The

Contractor shall revise and resubmit with changes clearly identified.

1.1 PART 2

PRODUCTS

Not used.

PART 2

PRODUCTS

Not used.

1.1 PART 3

EXECUTION

Not used.

PART 3

EXECUTION

Not used.

1.1 PART 4

MEASUREMENT AND PAYMENT

END OF SECTION

SECTION 01360

ACCIDENT PREVENTION

PART 1

GENERAL

PART 1

GENERAL

1.1

DESCRIPTION

A.

The work of this section consists of establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.

1.2

SUBMITTALS

A.

Accident Prevention Program: Before on‑site work begins, submit for approval an accident prevention program. The Contracting Officer will review the proposed program for compliance with OSHA and project requirements. If the program requires any revisions or corrections, the Contractor shall resubmit the program within 10 days. No progress payments will be made until the program is approved. The program shall include:

Name of responsible supervisor to carry out the program.

Weekly and monthly safety meetings.

First aid procedures.

Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase by reference to specification section or division numbers.

5.

Training, both initial and continuing.

6.

Planning for possible emergency situations, such as floods, fires, cave‑ins, slides, explosions, power outages, and windstorms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.

7.

Housekeeping.

8.

Fire Protection.

Submit a copy of test reports, as required by OSHA, for personnel working with hazardous materials.

Submit a report of safety meetings and of inspections.

Upon request, submit proof of employees' qualifications to perform assigned duties in a safe manner.

1.3

QUALITY ASSURANCE

Clauses entitled "Accident Prevention" and "Permits and Responsibilities" of the contract. In case of conflicts between Federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.

Qualifications of Employees:

Ensure that employees are physically qualified to perform their assigned duties in a safe manner.

Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.

Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment. Provide operating instructions for all equipment. Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.

1.4

ACCIDENT REPORTING

Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of

$100, and fires. Notify Contracting Officer immediately in the event of a reportable accident. Within 7 days of a reportable accident, fill out and forward to Contracting

Officer an Accident/Property Damage Report (Form CM-22). Form may be obtained from the Contracting Officer.

All Other Accidents: The Contractor shall report all other accidents to the Contracting

Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.

PART 2

PRODUCTS

PART 2

PRODUCTS

2.1

FIRST AID FACILITIES

Provide adequate facilities for the number of employees and the type of construction at the site.

2.2

PERSONNEL PROTECTIVE EQUIPMENT

Meet requirements of NIOSH and MSHA.

2.3

BARRIERS

See Requirements in Section 09900.

4 PART 3

EXECUTION

PART 3

EXECUTION

4 EMERGENCY INSTRUCTIONS

A.

Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.

4 EGRESS

Provide and maintain adequate egress at all times in accordance with the Life Safety

Code (NFPA 101). No corridor, aisle, stairway, door, or exit shall be obstructed or used in a manner that interferes with egress.

4 PROTECTIVE EQUIPMENT

A.

Inspect personal protective equipment daily and maintain in a serviceable condition. Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.

B.

Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.

C.

Follow guidelines recommended by the CDC for protection from COVID-19.

4 SAFETY MEETINGS

As a minimum, conduct weekly 15‑minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite.

Conduct monthly safety meetings for all levels of supervision. Notify the Contracting

Officer of meeting dates and times. These meetings shall be used to review the effectiveness of the Contractor's safety effort, to resolve current health and safety problems, to provide a forum for planning safe construction activities, and for updating the accident prevention program. The Contracting Officer will attend the meeting and enter the results of the meetings into the daily log.

4 HARD HATS AND PROTECTIVE EQUIPMENT AREAS

A hard hat area will be designated by the Contracting Officer. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.

It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary protective equipment at all times. As a minimum, provide six hard hats for use by visitors. Change liners before reissuing hats.

4 TRAINING

First Aid: Provide adequate training to ensure prompt and efficient first aid.

B.

Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.

5 PART 4

MEASUREMENT AND PAYMENT

PART 4

MEASUREMENT AND PAYMENT

5 ACCIDENT PREVENTION

No separate payment will be made for the requirements contained within this Section.

Any costs associated with this section shall be evenly distributed throughout the existing line items.

END OF SECTION

SECTION 01430

CONTRACTOR QUALITY CONTROL

6 PART 1

GENERAL

PART 1

GENERAL

6 DESCRIPTION

6 The work of this section consists of preparing and executing a quality control program.

6 SUBMITTALS

6 As specified in section 01330.

6 Quality Control Plan:

6 At the time of the preconstruction conference, submit for approval a written Contractor Quality Control (CQC) plan.

6 If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days.

6 The Government reserves the right to require changes in the plan during the contract period as necessary to obtain the quality specified.

6 No change in the approved plan may be made without written concurrence by the Contracting Officer.

6 The plan shall include:

6 A list of personnel responsible for quality control and assigned duties. Include each person's qualifications.

6 A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.

6 Methods of performing, documenting, and enforcing quality control of all work.

6 Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.

6 Contractor's Quality Control Daily Reports: Submit showing all inspections and tests on the first workday following the date covered by the report.

6 If the CQC plan and Quality Control Daily Reports are not submitted as specified, the Contracting Officer may retain all payments until such time a plan is approved and implemented.

6 QUALITY ASSURANCE

6 General:

1.

The quality of all work shall be the responsibility of the Contractor.

2.

Inspect all work often enough to ensure that the quality of materials, workmanship, and finish is in compliance with applicable specifications and drawings.

3.

Quality Control Daily Reports shall be completed by the Quality Control Supervisor.

6 Quality Control Staff:

1.

The Contractor's Quality Control Supervisor may also perform the duties of Project Superintendent.

2.

The Contractor's designated Quality Control Supervisor shall be on the project site whenever contract work is in progress.

3.

The Contractor's job supervisory staff may be used to assist the Quality Control Supervisor, supplemented as necessary by additional certified testing technicians.

7 PART 2

PRODUCTS

Not used.

PART 2

PRODUCTS

Not used.

8 PART 3

EXECUTION

PART 3

EXECUTION

8 ON-SITE CONTROL

8 Notification:

1.

Notify the Contracting Officer at least 48 hours in advance of the preparatory phase meeting.

2.

Notify the Contracting Officer at least 24 hours in advance of the initial and follow-up phases.

8 Preparatory Phase: Perform before beginning each feature of work.

1.

Review control submittal requirements with personnel directly responsible for the quality control work. As a minimum, the Contractor's Quality Control Supervisor and the foreman responsible for the feature of work shall be in attendance.

2.

Review all applicable specifications sections related to the feature of work.

3.

Ensure that copies of all referenced standards related to sampling, testing, and execution for the feature of work are available on site.

4.

Examine the work area to ensure that all preliminary work has been completed.

5.

Verify all field dimensions and advise the Contracting Officer of discrepancies with contract documents.

8 Ensure that necessary equipment and materials are at the project site and that they comply with approved submittals.

8 Prepare a report on all preparatory phase activities and discussions. Attach report to Contractor's Quality Control Daily Report.

8 Initial Phase:

1.

As soon as work begins, inspect a representative portion of a specific feature of work for quality of workmanship.

2.

Prepare a report on all initial phase activities and discussions. Attach report to Contractor's Quality Control Daily Report. Exact location of initial phase shall be indicated for future reference and comparison with follow-up phases.

8 Follow-Up Phase: Inspect and as work progresses to ensure compliance with contract requirements until completion of work.

8 Additional Preparatory and Initial Phases: Additional preparatory and initial phases may be required on the same feature of work for the following reasons:

1.

Quality of on-going work is unacceptable.

2.

Changes occur in the applicable quality control staff, on-site production supervision, or work crew.

3.

Work on a specific feature of work is resumed after a substantial period of inactivity.

8 DOCUMENTATION

8 Maintain Quality Control Daily Reports of quality control activities and tests.

8 Quality Control Daily Reports may not be substituted for other written reports required under clauses of the contract, such as Disputes, Differing Site Conditions, or Changes.

8 ENFORCEMENT

8 The Contractor shall stop work on any item or feature pending satisfactory correction of any deficiency noted by the quality control staff or the Contracting Officer.

9 PART 4

MEASUREMENT AND PAYMENT

PART 4

MEASUREMENT AND PAYMENT

9 CONTRACTOR QUALITY CONTROL

9 No separate payment will be made for the requirements contained in this Section. Any costs associated with this section shall be evenly distributed throughout the existing line items.

END OF SECTION

CONTRACTOR'S QUALITY CONTROL DAILY REPORT

REPORT NO. _________ SHEET 1 OF _________

PRIVATE

PROJECT

CONTRACT NO.

DATE

PARK

CONTRACTOR'S REPRESENTATIVE ON THE JOB

WEATHER (Rain, Snow, Cloudy, Windy, etc.)
RAINFALL

Inches

TEMPERATURE
GROUND CONDITIONS (Dry, Damp, Wet, Frozen, etc.)

MAX.

MIN.

1. PRIME CONTRACTOR

NO. EMPLOYEES BY JOB CATEGORIES

Hours
HEAVY EQUIPMENT ON JOB
NO. UNITS
HRS. WORKING
YES
NO
Comments

WORK PERFORMED BY PRIME CONTRACTOR:

MATERIALS DELIVERED

OFFICIAL VISITORS TO SITE

2A. SUBCONTRACTOR, _____________________________________________: (If more than one subcontractor use copies of following page.)

Hours
HEAVY EQUIPMENT ON JOB
NO. UNITS
HRS. WORKING
YES
NO
Comments

WORK PERFORMED BY SUBCONTRACTOR:

3. SPECIFIC INSPECTIONS: (Inspections performed, results, and corrective actions)

4. TESTING: 1 Check if any testing was performed today. (Complete and attach Test Report Information Sheets.)

Type and Location of Testing: ____________________________________________________________________________________

5. VERBAL INSTRUCTION RECEIVED FROM GOVERNMENT ON CONSTRUCTION DEFICIENCIES OR RE-TESTING REQUIRED:

6. REMARKS:

7. CERTIFICATION:

I certify that the above report is complete and correct and that I, or my authorized representative, have inspected all work performed this day by the prime contractor and each subcontractor and determined that all materials, equipment, and workmanship are in strict compliance with the plans and specifications except as may be noted above.

Contractor's Quality Control Representative

PRIVATE

SUBCONTRACTOR WORK CONTINUED:

CONTRACT NO.
REPORT NO. _______

SHEET ____ OF ____

2 SUBCONTRACTOR

Hours
HEAVY EQUIPMENT ON JOB
NO. UNITS
HRS. WORKING
YES
NO
Comments

WORK PERFORMED BY SUBCONTRACTOR:

2 SUBCONTRACTOR

Hours
HEAVY EQUIPMENT ON JOB
NO. UNITS
HRS. WORKING
YES
NO
Comments

WORK PERFORMED BY SUBCONTRACTOR:

2 SUBCONTRACTOR

Hours
HEAVY EQUIPMENT ON JOB
NO. UNITS
HRS. WORKING
YES
NO
Comments

WORK PERFORMED BY SUBCONTRACTOR:

2 SUBCONTRACTOR

Hours
HEAVY EQUIPMENT ON JOB
NO. UNITS
HRS. WORKING
YES
NO
COMMENTS

WORK PERFORMED BY SUBCONTRACTOR:

DAILY TEST REPORT INFORMATION SHEET

CONTRACT NO. REPORT NO. _____________

SHEET _____ OF _________

PRIVATE

1. Individual Making Inspection or Test:

2. Testing Laboratory; Name:
Phone #:

Address:

3. Description of Work and Test Method:

4. Location of Samples and Tests or Inspections:

5. Specification Section:

6. Inspection or Test Data:

7. Test Results and Interpretations of Test Results:

8. Comments or Professional Opinion About Compliance of Inspected Work or Tested Work with contract Document Requirements:

9. Recommendations:

10. Corrective Actions Taken:

CERTIFICATION:

I certify that the above testing report is complete and correct and that all testing performed this day for this contract is in strict compliance with the plans and specifications except as noted above.

Signature of Inspector

SECTION 01770

PROJECT CLOSEOUT

10 PART 1

GENERAL

PART 1

GENERAL

10 DESCRIPTION

10 The work of this section consists of final cleanup, closeout submittals, and final inspection procedures.

11 PART 2

PRODUCTS

PART 2

PRODUCTS

11 CLEANING MATERIALS

11 As recommended by the manufacturer of surface to be cleaned.

12 PART 3

EXECUTION

PART 3

EXECUTION

12 CLEANING

12 Before scheduling the final inspection, remove all tools, equipment, surplus materials, and rubbish. Restore or refinish surfaces that are damaged due to work of this contract to original condition. Remove grease, dirt, stains, foreign materials, and labels from finished surfaces. Pick up all construction debris from the site. At time of final inspection, project shall be thoroughly clean and ready for use.

12 CLOSEOUT SUBMITTALS

12 Submit before final inspection request.

1.

Guarantees and Bonds: As specified in individual sections.

12 SUBSTANTIAL COMPLETION AND FINAL INSPECTION

12 When project, or designated portion of project, is substantially complete, request in writing a final inspection. Upon receipt of written request that project is substantially complete, the Contracting Officer will proceed with inspection within 10 days of receipt of request or will advise the Contractor of items that prevent the project from being designated as substantially complete.

12 If, following final inspection, the work is determined to be substantially complete, Contracting Officer will prepare a list of deficiencies to be corrected before final acceptance and issue a Letter of Substantial Completion. Contractor shall complete the work described on the list of deficiencies within 30 calendar days, as weather permits. If the Contractor fails to complete the work within this time frame, the Contracting Officer may either replace or correct the work with an appropriate reduction in the contract price or charge for reinspection costs in accordance with the Inspection of Construction clause of the contract.

12 If, following final inspection, the work is not determined to be substantially complete, Contracting Officer will notify Contractor in writing. After completing work, Contractor shall request a new final inspection. All reinspection costs may be charged against the Contractor in accordance with the Inspection of Construction clause of the contract.

12 FINAL ACCEPTANCE OF THE WORK

12 After all deficiencies have been corrected, a Letter of Final Acceptance will be issued.

13 PART 4

MEASUREMENT AND PAYMENT

PART 4

MEASUREMENT AND PAYMENT

13 PROJECT CLOSEOUT

13 No separate payment will be made for the requirements contained in this Section. Any costs associated with this section shall be evenly distributed throughout the existing line items.

END OF SECTION

SECTION 09900

PAINTING

PART 1

GENERAL

1.1 DESCRIPTION

The work of this contract consists of the preparation and painting of structures and their features at multiple local locations throughout Acadia National Park, ME 04609 Surfaces to be coated include interior and exterior doors & windows, interior and exterior trim & molding, exterior siding & walls, fascia, overhangs, rafters & rafter tails, interior walls & ceilings, floors, partitions, cabinetry, masonry work, metal work, decking, railings, stairs, and fences. Coatings include primers, oil base & latex paints, solid coat, transparent & semi-transparent stains, polyurethanes, and lacquers.

1.2 LOCATION

A. Task orders will specify jobsite locations. All work takes place in Acadia National Park, ME 04609.

1.3 EXAMINATION OF THE SITE

A. A site visit for all contractors will be held on September 5, 2024 at 12:00 p.m. All attendees are to meet at the Rockefeller Hall, 9 Atterbury circle Winter Harbor, ME 04693. Please contact Dan Meggison with specific questions relating to the site visit at (207) 288-8767.

B. It is understood that the contractor has examined the site, field verified dimensions, and made their own estimates of the facilities and difficulties attending the execution of the work and has based their price thereon. Any discrepancies between the site conditions and dimensions stated within this contract and actual field conditions shall be reported to the Contracting Officer’s Representative immediately.

1.4 EXISTING CONDITIONS

A. Public Access: The area is to remain open to visitors and tenants during the contract period. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public and tenants. Specific closures will be permitted, when required, upon specific approval of Contracting Officer’s Representative.

1.5 SUBMITTALS

A. Prior to commencing work, submit written records of proposed application methods for each structure for approval by the COR.

B. Submit a comprehensive schedule for approval showing locations, the anticipated duration, and start and completion dates. Coordination of access to buildings and facilities, as well as any supply of coatings from the Government, will be based on the approved schedule.

C. Safety Plan that includes a fire prevention plan.

D.

Product Data: Manufacturer's data sheets on each paint and coating product should include:

1. Product characteristics

2. Surface preparation instructions and recommendations

3. Primer requirements and finish specification

4. Storage and handling requirements and recommendations

5. Application methods

6. Cautions

E. Color Samples: Submit a complete set of color chips that represent the manufacturer's color sample for each building element.

F. Verification Samples: For each finish product specified, submit samples that represent actual product, color, and sheen.

1.6 ENVIRONMENTAL QUALITY ASSURANCE

A. Paint shall conform to local requirements.

1.7 project conditions

A. Apply finish material within paint manufacturer's specified application temperature range. Do not apply exterior materials in damp, rainy weather. Do not apply paint on surfaces in direct sunlight. Apply finishes only when air is free of dust that would affect the finish.

B. Measure moisture content of surfaces using an electronic moisture meter. Do not apply finishes unless moisture content of surfaces are below following maximums:

1. Plaster and gypsum wallboard: 12 percent.

2. Masonry, concrete, and concrete block: 12 percent.

3. Interior wood: 15 percent.

4. Exterior wood: 18 percent.

5. Concrete floors: 10 percent.

C. Keep fire hazard to a minimum; remove from the area daily all oily rags, waste, and other combustibles not in covered metal containers.

D. Any surfaces that are not in proper condition for painting where preparation of the surface for painting would be outside the scope of this specification shall be reported to the COR. The NPS will make a determination to either repair or replace these surfaces.

1.8 CONSTRUCTION REQUIREMENTS

A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public and tenants. Specific closures will be permitted, when required, upon specific approval of Contracting Officer’s Representative.

B. Preservation of Natural Features: Confine all operations to work limits of the project. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

C. Contractor shall furnish, and be responsible for, all required scaffolding, ladders, or lifts. Any footings for scaffolding shall be placed so as not to damage landscape elements.

D. Contractor shall furnish all tarps, tenting, or masking required to protect window glass, sidewalks, landscape elements and public from overspray, and to shade building surfaces from direct sun exposure during painting if required by manufacturer’s instructions.

E. Prior to the start of work, Contractor shall furnish, install, and maintain barriers and signs required to protect the landscape and the public from construction operations.

F. Contractor shall limit cleaning of equipment to immediate area surrounding each jobsite and shall ensure no wastewater or cleaning agents are spilled on the buildings, grounds, or sidewalks.

G. Wastewater Disposal: Contractor shall take appropriate measures to collect and dispose of properly all water, cleaning agents, bleach and debris from the surface preparation work.

1.9 CONTRACTOR’S USE OF PREMISES

A. Hours of Work: Contractor may perform work between the hours of 7:00a.m. to 4:30p.m., Monday thru Friday. No on-site work shall be performed between the hours of 4:30p.m. and 7:00a.m. Hours of work may only be adjusted with the approval of the Contracting Officer or designated representative.

B. Holiday Work restrictions: No work shall be performed on Federal holidays.

C. Weekend Work Restrictions: No work shall be performed on weekends (Saturday or Sunday) D. Use of Vehicles: Vehicles shall be used only on roads, and not on sidewalk areas. Heavy equipment, including vehicles over ¾ ton shall not be permitted on site paths, walks, or sidewalks.

E. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

F. Public facilities, to include restrooms, shall not be used for cleaning of equipment.

1.10 ACCIDENT PREVENTION

A. The contractor shall be responsible for establishing an effective accident prevention program and providing a safe environment for all personnel and visitors. The Contractor shall ensure that work is accomplished in compliance with Federal, state and local safety and health requirements.

1.11 BARRIERS

A. The Contractor shall furnish, install, and maintain barriers and warning signs to protect the landscaping and prevent the public from entering construction area.

B. Fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry. Install warning signs.

C. Only barrier tape may be attached to buildings. Other barriers must be free standing.

D. Protect plantings and sidewalks with tarpaulins made of canvas or other breathable material.

1.12 CONSTRUCTION MATERIALS

A. The contractor may utilize electricity and water utilities at the job sites where available.

B. All other materials shall be Contractor-furnished from outside the Park, including paint, primer, sealer/preservative, stains, miscellaneous materials, caulking and fillers approved by the NPS.

PART 2

2.1 paint and finish products

Latex paint products shall meet federal requirements for low-VOC

(Volatile Organic Compound latex paints) (below 250 grams per liter of carbon).

The paint shall be 100% acrylic latex. The paint shall brush, roll, and spray easily, and shall dry to a smooth uniform film free from lap marks, excessive brush marks, orange peel, craters or dusting. Paint characteristics shall include excellent surface adhesion, scrub resistance, and cracking resistance. Paint products shall be fresh and well ground; shall not settle readily, cake, or thicken in the container;

shall be broken up readily with paddle to a smooth consistency;

and shall have easy application properties. Paint shall be low odor. Utilize the appropriate paints for the surface type to be coated (wood, metal, masonry).

Provide primers and other undercoat paint produced by same manufacturer as the finish paint.

Previously stained wood surfaces shall be coated with a high quality transparent or semi-transparent stain. Un-painted surfaces shall be coated with a high-quality sealer/preservative.

Masonry and stucco surfaces shall be coated with a high quality elastomeric acrylic paint.

E.

Concrete floors and up to 6” swales in selected locations shall be coated with a high-quality epoxy paint.

F.

Select paint/stain to match existing color and sheen of surfaces to be painted.

G.

Filling compounds: Use only high quality, non-shrink materials. The Contractor shall supply all other supplies including caulking and fillers, which are to be approved by the COR prior to use.

2.2 COLORS

A. Select paint/stain to match existing color and sheen of surfaces to be painted.

2.3 DELIVERY AND STORAGE OF MATERIALS

A. Deliver materials to the job site unbroken and undamaged. Store protected from the weather with supplier’s labels intact and visible.

B. Delivery of materials: Coordinate the delivery and on-site storage of materials and equipment with the Contracting Officer’s Representative.

PART 3

EXECUTION

3.1 general EXAMINATION AND PREPARATION

A. Carefully move to safe location any objects blocking access to surfaces to be painted. Cover and protect finished work, surfaces not to be painted, floor coverings, furnishings, and appliances. Use drop cloths of adequate size to protect adjacent areas.

B. Verify that substrates are completely dry, free of harmful substances, and in satisfactory condition to receive painting materials.

C. Mix and prepare painting materials in accordance with manufacturer’s directions.

D. As colors may not match precisely from one can to the next, mix paint of a given color together before starting the job.

E. Remove hardware, hardware accessories, machined surfaces, plates, lighting fixtures, and similar items in place and not to be painted or provide surface applied protection. Reinstall removed items when final coat is thoroughly dry.

F. Paint a 1 square foot section test section adjacent to the existing painted finish to verify the new paint duplicates the existing paint color and sheen.

3.2 SURFACE PREPARATION- LEAD PAINT STABILIZATION

A.

Lead Paint: The exterior surfaces of some buildings may be releasing lead paint chips and dust. The Contractor is therefore required to follow, at a minimum. the following procedures in prepping the buildings. No work will be started until the Contracting Officer has approved a plan of action. Perform preparation and cleaning procedures in strict accordance with the paint manufacturer’s instructions and as herein specified for each specific substrate condition. Observe lead safe work practices.

B. Recommended Action: Deteriorated surfaces are to be repaired to obtain a smooth surface that can be repainted. This will require corrective work starting with the removal of loose paint and dust, cleaning the surfaces and resealing the surface by painting. The purpose of this procedure is to restore the integrity of the exterior paint surface and control further deterioration of the paint. For the removal of loose paint or painted material, “wet scraping” is to be employed. This means both the painted surface and the scraping tool or sandpaper are to be keep wet with water during the removal process to minimize the release of lead dust and the dispersal of lead paint chips.

C. Because of the possibility of releasing and dispersing hazardous debris and dust during this corrective work, park visitors shall not be permitted in the vicinity of the work during the repair activities, nor shall NPS employees, unless wearing the proper PPE. The Contractor shall be required to fence or otherwise cordon off the immediate work area to prevent access or, if possible, to identify an alternate entrance to the buildings for NPS staff to use during the normal workday.

C.

Scheduling: The buildings may be occupied and in use on a daily basis. NPS staff must be permitted access during the period of the exterior corrective work. To allow normal day-to-day operations and the contract work to go on, only partial shutdown of the entry to these buildings will be permitted. A schedule will be submitted and approved by the Contracting Officer prior to any work being performed during the normal working day.

Work activities that require more than one day’s work for completion shall be scheduled so that each day’s work (including cleanup) can be accomplished within the time frame of a normal working day (7:00 a.m. to 4:30 p.m.).

Area Protection: Cover all areas immediately adjacent to and below the work with a 6-mil polyethylene film to protect the ground and to retain the wet debris and dust that will be created during the surface treatment. This covering should extend out horizontally from the base of the wall surface being treated. Although a 6-mil film is reasonably tough, avoid unnecessary traffic over this surface to reduce the chance of puncture. In addition, if the ground surface is rough, an additional layer of polyethylene may be required. Joints and tears shall be repaired immediately with duct tape.

E.

Surface Preparation: The building surfaces to be corrected shall be moistened with a fine spray of water. Loose, peeling, flaking material shall be removed from the surface(s) by wet scraping to obtain a smooth, cleanable surface to be repainted. The scraping tool should have a soft, pliable blade of plastic or rubber that will not damage or gouge the material. The blade should be rigid enough, however, to remove rough edges of the broken paint surfaces with the resulting surface free of jagged, rough edges or snags that would interfere with the bridge any remaining gaps.

During the task of wet scraping, debris shall be regularly gathered with a wet vacuum. It may be necessary to spray or re-wet fallen debris to prevent its being scattered or blown off the protective cover.

Workers should be cautioned about the hazards of walking on the polyethylene film, which is extremely slippery when wet. Care should be taken to prevent the tracking of debris off the protective covering. The workers should clean or remove shoe coverings before the area of the work.

F.

Surface Cleaning: Following wet scraping, the surface shall be cleaned with a damp sponge to remove small particles and dust. Clean with Tri-Sodium Phosphate (TSP) followed by a clean water wash. The surface shall be permitted to dry thoroughly in the preparation for repainting or resealing.

G.

Surface Sealing: The clean, dry surface shall be sealed with paint to produce a smooth cleanable surface. The paint or coating shall be applied in accordance with the Manufacturer’s instructions.

H.

Removal of Protective Coverings: Remove protective coverings at the conclusion of the corrective work or at the end of the day on multi-day activities. If protective covering is left in place overnight, all debris shall be removed from covering prior to contractor leaving job site that day.

I.

Disposal of Waste and Debris: All retained liquid waste shall be poured through a filter cloth to remove paint chips and other debris prior to disposal. Lead-based paint waste shall be collected and bagged in 6-mil or double 4-mil plastic bags.

Labelled as lead waste. The Contractor shall make provisions for the safe storage of waste, adhering to NPS requirements. The contractor shall transfer the waste to the NPS for proper disposal.

3.3 preparation and pAINTING of INTERIOR & exterior wood

A.

Remove dust by brushing and remove grease and oil by washing with mineral spirits or other solvent. Wash surfaces as needed with TSP to assure new paint bonds well to surfaces. Remove sap on wood surfaces by scraping and washing with turpentine. Remove any old loose or flaking paint by scraping.

Seal all knots or resinous areas with knot sealer and allow to dry at least two hours before priming. Fill all gouges, dents, and small openings in interior wood with plastic wood tinted for stained or natural appearance.

Allow plastic wood to dry before painting.

Back prime backs, edges, and ends of interior and exterior wood.

Patch cracks and holes in wood surfaces, after priming, using a compatible patching compound. Sink, putty, and prime any exposed nail or screw heads prior to painting.

Sand wood trim lightly before applying primer, and sand lightly between coats of paint. Remove sanding dust before applying paint.

5. Adjust natural finishes as necessary to obtain a like appearance on veneers and solid stock.

Schedule:

1. General Painted Interior & Exterior Wood:

1st coat:

Utilize a quality primer paint recommended by the manufacturer of the finish coat paint.

2nd coat:

See Section 2.

3rd coat:

2. Painted Wood Trim:

Clear finished wood:

Utilize a quality clear latex sealer/finish.

Stained wood:

Utilize a quality stain to match existing color.

Additional coats:

Follow manufacturer's directions concerning multiple coats.

3.4

PREPARATION AND PAINTING OF INTERIOR GYPSUM WALLBOARD

Preparation: Fill minor irregularities with joint compound and sand to a smooth even surface.

Wash surfaces as needed with TSP to assure new paint bonds well to surfaces.

Interior Gypsum Wallboard:

3.5

PREPARATION AND PAINTING OF INTERIOR PLASTER

Preparation: Fill narrow cracks or small holes with spackle; fill larger openings with thin layers of patching plaster. Allow spackle to dry four hours and patching plaster to dry for

24 hours. Sand smooth before painting.

Wash surfaces as needed with TSP to assure new paint bonds well to surfaces.

Interior Plaster:

3.6

PREPARATION AND PAINTING OF EXTERIOR FERROUS METALS

A. Clean ferrous surfaces that are not galvanized or shop coated of oil, grease, dirt, loose mill scale, and other foreign substances by solvent or mechanical cleaning.

B. Touch up shop applied prime coats wherever damaged or bare.

C. Clean galvanized surfaces free of oil and surface contaminants with nonpetroleum based solvent.

D. Schedule:

1. Ferrous metals:

3.7 PREPARATION AND PAINTING OF INTERIOR & EXTERIOR CONCRETE, MASONRY, & STUCCO

A. Remove as much efflorescence as possible using a clean…

This is the start of the file's text. The full file is on GovTribe.