RMS Cooler Addedndum #1.pdf

PDF 51 KB Posted

Attached to
RMS Walk-In Cooler Improvements
Solicitation number
RFP RCS 270000000230 2
Issued by
Macomb County, Michigan

About this file

This is an Addendum No. 1 to a Request for Proposals issued by Romeo Community Schools for RMS Cooler Improvements. The original RFP was issued on November 4, 2026, with proposals due on November 20, 2026. The addendum, issued on November 18, 2026, provides clarifications to address questions received from prospective bidders regarding the project scope and requirements. Bidders are required to acknowledge receipt of this addendum in accordance with the original RFP requirements.

The addendum clarifies that the District is not providing an estimated construction budget and that bidders should submit pricing based on the scope of work outlined in the RFP documents. No plan holders list is currently available. Regarding labor requirements, the project is not subject to specific union requirements; however, all work must comply with applicable federal Davis-Bacon prevailing wage requirements regardless of whether the contractor is union or non-union. All other terms, conditions, specifications, and requirements of the original RFP remain unchanged and in full force and effect.

View the file

Other files

File Type Posted
Romeo Walk In Cooler RFP.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ROMEO COMMUNITY SCHOOLS

ADDENDUM NO. 1

Request for Proposals – RMS Cooler Improvements

Date Issued:11/18/2026 RFP Issue Date:11/4/2026 Proposal Due Date:11/20/2026

This Addendum is issued to address questions received from prospective bidders regarding the above-referenced Request for Proposals (RFP). The following clarifications are hereby made part of the original RFP documents.

1. Estimated Construction Budget

Question:Is the District providing an estimated constructionbudget?

Response:The District is not providing an estimatedconstruction budget. Bidders should review the bid documents and submit pricing based on the scope of work outlined in the RFP.

2. Plan Holders List

Question:Is a plan holders list available?

Response:The District does not currently have a planholders list available.

3. Union Requirements

Question:Are there any union requirements for thisproject?

Response:There are no specific union requirementsfor this project. However, the project is subject to applicable federal Davis-Bacon prevailing wage requirements, which apply regardless of whether a contractor is union or non-union.

IMPORTANT:All other terms, conditions, specifications, and requirements of the original RFP remain unchanged and in full force and effect.

All prospective bidders should acknowledge receipt of this Addendum in accordance with the requirements of the original RFP.