Richmond Salt Dome Reroof MainSpec.docx

DOCX document 154 KB Posted

Attached to
FY27 KC Richmond Salt Dome Roof Replacement Project
Solicitation number
300000235028313
Issued by
Missouri

About this file

This is a specification document for the FY27 Kansas City Richmond Salt Dome Roof Replacement Project administered by the Missouri Department of Transportation (MoDOT). The project requires removal of existing polyurethane foam roofing, three-tab shingles, felt underlayment, roof vents (20+/-), flashing, and entrance fascia down to decking, with installation of 30-year or greater manufactured warranty composite architectural shingles, synthetic underlayment, galvanized flashing, and 750 metal roof vents to create a complete and watertight roof system. The specifications establish comprehensive general requirements including contract administration procedures, submittal protocols, quality control standards, construction facilities and temporary controls, material and equipment handling, system startup procedures, and contract closeout requirements. Specific product specifications are detailed for wood framing and sheathing (Division 6), asphalt shingles (Division 7), weather barriers, metal roof and wall panels, flashing and sheet metal work, and joint sealers. Bids are accepted electronically through MissouriBUYS, by mail, UPS, or FedEx, with contractors required to contact buyer Logan Wilbers at logan.wilbers@modot.mo.gov at least five business days prior to bid closing if submitting hard copy proposals. Site visit attendance is mandatory for bids to be accepted.

The specifications establish standard contracting terms requiring contractors to submit schedules of values within 20 days of the Owner-Contractor Agreement, applications for payment with 30-day payment periods, and certified payroll records. Change order procedures allow for both architect-issued notices of change and contractor-proposed changes using stipulated sum, construction change directive, or time and material methods. Quality assurance requirements mandate compliance with manufacturers' instructions and specified industry standards, with testing and inspection services provided by MoDOT personnel. Contractors are responsible for all temporary electricity, telephone service, facsimile service, water service, sanitary facilities, security, fencing, and protection of installed work. Contract closeout requires final cleaning, project record documents, operation and maintenance manuals in three-ring binders, spare parts delivery, and execution of transferable warranties. Projects shall not be accepted until all punch list items are completed, with vendors having 30 days to submit required closeout paperwork or face potential debarment or suspension from future MoDOT projects.

View the file

Other files

File Type Posted
MODOT 0000000280SL_SUPPLIER.pdf PDF
Richmond Salt Dome Reroof Pictures.docx DOCX document
AWO 32.pdf PDF
section 01300 and 01700.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TABLE OF CONTENTS

DIVISION PAGE

DIVISION 1 – GENERAL REQUIREMENTS (BROAD SCOPE)

01019CONTRACT REQUIREMENTS2
01039COORDINATION AND MEETING REQUIREMENT4
01300SUBMITTAL REQUIREMENTS7
01400QUALITY CONTROL REQUIREMENTS10
01500CONSTRUCTION FACILITIES AND TEMPORARY CONTROL REQUIREMENTS12
01600MATERIAL AND EQUIPMENT REQUIREMENT14
01650STARTING OF SYSTEMS REQUIREMENT16
01700CONTRACT CLOSEOUT REQUIREMENT17

DIVISION 6 - WOOD AND PLASTIC

06112 FRAMING AND SHEATHING 19

DIVISION 7 - THERMAL AND MOISTURE PROTECTION

07311ASPHALT SHINGLES22
07250WEATHER BARRIERS26
07411METAL ROOF AND WALL PANELS31
07600FLASHING AND SHEET METAL36
07900JOINT SEALERS41

01019

CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 SCHEDULE OF VALUES

A. Submit a printed schedule on Contractor's standard form. Electronic media printout will be considered.

B. Submit Schedule of Values in duplicate within 20 days after date of Owner-Contractor Agreement.

C. Revise schedule to list approved Change Orders, with each Application For Payment.

1.2 APPLICATIONS FOR PAYMENT

A.Submit four copies of each application on Contractor's electronic media driven form.
B.Content and Format: Utilize Schedule of Values for listing items in Application for Payment.
C.Payment Period: 30 days.
D.Include an updated construction progress schedule.
E.Certified payroll records.

1.3 CHANGE PROCEDURES

A. The Architect/Engineer/Designer may issue a Notice of Change that includes a detailed description of a proposed change with supplementary or revised Drawings and specifications, a change in Contract Time for executing the change with a stipulation of any overtime work required.

B. The Contractor may propose changes by submitting a request for change to the Architect/Engineer/Designer describing the proposed change and its full effect on the Work. Include a statement describing the reason for the change, the effect on the Contract Sum/Price and Contract Time, and a statement describing the effect on Work by the MoDOT District or other Contractors.

C. Stipulated Sum/Price Change Order: Based on Notice of Change and Contractor's fixed price quotation or Contractor's request for a Change Order as approved by Architect/Engineer/Designer.

D. Construction Change Directive: Architect/Engineer/Designer may issue a directive instructing the Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order. Document will describe changes in the Work, and designate method of determining any change in Contract Sum/Price or Contract Time. Promptly execute the change.

E. Time and Material Change Order: Submit itemized account and supporting data after completion of change, within time limits indicated in the Conditions of the Contract. Architect/Engineer/Designer will determine the change allowable in Contract Sum/Price and Contract Time as provided in the Contract Documents.

F. Maintain detailed records of work done on Time and Material basis. Provide full information required for evaluation of proposed changes, and to substantiate costs for changes in the Work.

G. Execution of Change Orders: Architect/Engineer/Designer will issue Change Orders for signatures of parties as provided in the Conditions of the Contract.

1.4 DEFECT ASSESSMENT

A. Replace the Work, or portions of the Work, not conforming to specify requirements.

B. If, in the opinion of the Architect/Engineer/Designer, it is not practical to remove and replace the Work, the Architect/Engineer/Designer will direct an appropriate remedy or adjust payment.

1.5 ALTERNATIVES

A. Accepted Alternatives will be identified in Owner-Contractor Agreement.

END OF SECTION

01039

COORDINATION AND MEETING REQUIREMENT

PART 1 GENERAL

1.1 COORDINATION AND PROJECT CONDITIONS

A. Coordinate scheduling, submittals, and Work of the various sections of the Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements.

B. Verify utility requirements and characteristics of operating equipment are compatible with building utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to and placing in service, such equipment.

C. Coordinate space requirements, supports, and installation of mechanical and electrical Work, which are indicated diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduit, as closely as practicable; place runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.

D. In finished areas, except as otherwise indicated, conceal pipes, ducts and wiring within the construction. Coordinate locations of fixtures and outlets with finish elements.

E. Coordinate completion and clean up of Work of separate sections in preparation for Completion.

F. After Owner occupancy of premises, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of Owner's activities.

1.2 FIELD ENGINEERING

A.Employ a Land Surveyor registered in the State of Missouri and acceptable to Architect/Engineer/Designer.
B.Owner will locate and protect survey control and reference points.
C.Control datum for survey is that established by Owner provided survey.
D.Verify setbacks and easements; confirm drawing dimensions and elevations.
E.Provide field engineering services. Establish elevations, lines and levels, utilizing recognized engineering survey practices.

1.3 PRECONSTRUCTION MEETING

A.Architect/Engineer/Designer will schedule a meeting after Notice of Award.
B.Attendance Required: District engineer or representative, Architect/Engineer/Designer and Contractor.
C.Record minutes and distribute copies within 5 days after meeting to participants, with two copies to District Engineer, Architect/Engineer/Designer, participants and those affected by decisions made.

1.4 SITE MOBILIZATION MEETING

A. Architect/Engineer/Designer will schedule a meeting at the Project site prior to Contractor occupancy.

B. Architect/Engineer/Designer will record minutes and distributes copies within 5 days after meeting to participants, with two copies to Architect/Engineer/Designer, participants and those affected by decisions made.

1.5 PROGRESS MEETINGS

A. Schedule and administer meetings throughout progress of the Work at when arranged by Architect/Engineer/Designer.

B. Architect/Engineer/Designer will make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings.

C. Attendance Required: Job superintendent, major Subcontractors and suppliers, District engineer representative, Architect/Engineer/Designer, as appropriate to agenda topics for each meeting.

D.Agenda:
1.Review of Work progress.
2.Field observations, problems, and decisions.
3.Identification of problems, which impede planned progress.
4.Maintenance of progress schedule.
5.Corrective measures to regain projected schedules.
6.Coordination of projected progress.
7.Effect of proposed changes on progress schedule and coordination.

E. Record minutes and distributes copies within 5 days after meeting to participants and those affected by decisions made.

1.6 PREINSTALLATION MEETING

A.When required in individual specification sections, convene a pre-installation meeting at the site prior to commencing work of the section.
B.Notify Architect/Engineer/Designer seven days in advance of meeting date.
C.Prepare agenda and preside at meeting:
1.Review conditions of installation, preparation and installation procedures.
2.Review coordination with related work.
D.Record minutes and distributes copies within 5 days after meeting to participants and those affected by decisions made.

PART 2 PRODUCTS

Not used

PART 3 EXECUTION

3.1 CUTTING AND PATCHING

A. Employ skilled and experienced installer to perform cutting and patching.

B.Submit written request in advance of cutting or altering elements, which affect:
1.Structural integrity of element.
2.Integrity of weather-exposed or moisture-resistant elements.
3.Work of Owner or separate contractor.
C.Execute cutting, fitting, and patching to complete Work, and to:
1.Uncover Work to install or correct ill-timed Work.
2.Remove and replace defective and non-conforming Work.
3.Provide openings in elements of Work for penetrations of mechanical and electrical Work.

D. Cut masonry and concrete materials using masonry saw or core drill.

E. Fit Work tight to pipes, sleeves, ducts, conduit and other penetrations through surfaces.

F. Maintain integrity of wall, ceiling, or floor construction; completely seal voids.

G. Refinish surfaces to match adjacent finishes. For continuous surfaces, refinish to nearest intersection; for an assembly, refinish entire unit.

H. Identify hazardous substances or conditions exposed during the Work to the Architect/Engineer/Designer for decision or remedy.

3.2 ALTERATION PROJECT PROCEDURES

A. Materials: As specified in Product sections; match existing Products and work for patching and extending work.

B. Close openings in exterior surfaces to protect existing work from weather and extremes of temperature and humidity.

C. When finished surfaces are cut so that a smooth transition with new Work is not possible, terminate existing surface along a straight line at a natural line of division and submit recommendation to Architect/Engineer/Designer for review.

D. Patch or replace portions of existing surfaces that are damaged, lifted, discolored or showing other imperfections.

E. Finish surfaces as specified in individual Product sections.

01300

SUBMITTAL REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

A. AGC Associated General Contractors of America publication "The Use of CPM in Construction - A Manual for General Contractors and the Construction Industry".

1.2 SUBMITTAL PROCEDURES

A.Submittals shall be submitted electronically with Architect/Engineer/Designer accepted form.
B.Identify Project, Contractor, Subcontractor or supplier; pertinent drawing and detail number and specification section number, as appropriate.
C.Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of Products required, field dimensions, adjacent construction Work and coordination of information is in accordance with the requirements of the Work and Contract Documents.
D.Schedule submittals to expedite the Project, and deliver to Architect/Engineer/Designer at business address. Coordinate submission of related items.
E.For each submittal for review, allow 15 days excluding delivery time to and from the contractor.
F.Identify variations from Contract Documents and Product or system limitations, which may be detrimental to successful performance of the completed Work.
G.Submittals not requested will not be recognized or processed.

1.3 CONSTRUCTION PROGRESS SCHEDULES

A.Submit initial schedule in duplicate within 15 days after date established in Notice to Proceed.
B.Revise and resubmit as required.
C.Submit revised schedules with each Application for Payment, identifying changes since previous version.
D.Submit a horizontal bar chart with separate line for each major portion of Work or operation, identifying first workday of each week.

1.4 PROPOSED PRODUCTS LIST

A.Within 15 days after date of Notice to Proceed, submit list of major products proposed for use, with name of manufacturer, trade name and model number of each product.
B.For products specified only by reference standards, give manufacturer, trade name, model or catalog designation and reference standards.

1.5 PRODUCT DATA

A.Product Data for Review:
1.Submitted to Architect/Engineer/Designer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the contract documents.
2.After review, provide copies and distribute in accordance with SUBMITTAL PROCEDURES article above and for record documents purposes described in Section 01700 - CONTRACT CLOSEOUT.

B. Product Data for Information:

1. Submitted for the Architect/Engineer/Designer’s knowledge as contract administrator or for the Owner.

C. Product Data for Project Closeout:

1. Submitted for the Owner's benefit during and after project completion.

D. Submit the number of copies, which the Contractor requires, plus two copies that will be retained by the Architect/Engineer/Designer.

E. Mark each copy to identify applicable products, models, options and other data. Supplement manufacturers' standard data to provide information specific to this Project.

F. After review distribute in accordance with the Submittal Procedures article above and provide copies for record documents described in Section 01700 - CONTRACT CLOSEOUT.

1.6 SHOP DRAWINGS

A.Shop Drawings for Review:
1.Submittals shall be submitted electronically with Architect/Engineer/Designer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the contract documents.
2.After review, produce copies and distribute in accordance with SUBMITTAL PROCEDURES article above and for record documents purposes described in Section 01700 - CONTRACT CLOSEOUT.
B.Shop Drawings for Information:
1.Submitted for the Architect/Engineer/Designer’s knowledge as contract administrator or for the Owner.
C.Shop Drawings for Project Closeout:
1.Submitted for the Owner's benefit during and after project completion.

D. Indicate special utility and electrical characteristics, utility connection requirements and location of utility outlets for service for functional equipment and appliances.

E. Submit in the form of one reproducible transparency and one opaque reproduction.

1.7 SAMPLES

A.Samples for Review:
1.Submitted to Architect/Engineer/Designer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the contract documents.
2.After review, produce duplicates and distribute in accordance with SUBMITTAL PROCEDURES article above and for record documents purposes described in Section 01700 - CONTRACT CLOSEOUT.
B.Samples for Information:
1.Submitted for the Architect/Engineer/Designer’s knowledge as contract administrator or for the Owner.
C.Samples for Selection:
1.Submitted to Architect/Engineer/Designer for aesthetic, color, or finish selection.
2.Submit samples of finishes for Architect/Engineer/Designer selection.
3.After review, produce duplicates and distribute in accordance with SUBMITTAL PROCEDURES article above and for record documents purposes described in Section 01700 - CONTRACT CLOSEOUT.

1.8 DESIGN DATA

A.Submit for the Architect/Engineer/Designer’s knowledge as contract administrator or for the Owner.
B.Submit for information for the limited purpose of assessing conformance with information given and the design concept expressed in the contract documents.

1.9 TEST REPORTS

A.Submit for the Architect/Engineer/Designer’s knowledge as contract administrator or for the Owner.
B.Submit test reports for information for the limited purpose of assessing conformance with information given and the design concept expressed in the contract documents.

1.10 CERTIFICATES

A.When specified in individual specification sections, submit certification by the manufacturer, installation/application subcontractor, or the Contractor to Architect/Engineer/Designer, in quantities specified for Product Data.
B.Indicate material or Product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits and certifications as appropriate.
C.Certificates may be recent or previous test results on material or Product but must be acceptable to Architect/Engineer/Designer.

1.11 MANUFACTURER'S INSTRUCTIONS

A.When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, and start-up, adjusting and finishing, to Architect/Engineer/Designer for delivery to owner in quantities specified for Product Data.
B.Indicate special procedures, perimeter conditions requiring special attention and special environmental criteria required for application or installation.
C.Refer to Section 01400 - Quality Control, Manufacturers' Field Services article.

1.12 MANUFACTURER'S FIELD REPORTS

A.Submit reports for the Architect/Engineer/Designer's benefit as contract administrator or for the Owner.
B.Submit for information for the limited purpose of assessing conformance with information given and the design concept expressed in the contract documents.

1.13 ERECTION DRAWINGS

A.Submit drawings for the Architect/Engineer/Designer’s benefit as contract administrator or for the Owner.
B.Submit for information for the limited purpose of assessing conformance with information given and the design concept expressed in the contract documents.
C.Data indicating inappropriate or unacceptable Work may be subject to action by the Architect/Engineer/Designer or Owner.

01400

QUALITY CONTROL REQUIREMENTS

PART 1 GENERAL

1.1 QUALITY ASSURANCE - CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, Products, services, site conditions and workmanship, to produce Work of specified quality.

B. Comply with manufacturers' instructions, including each step in sequence.

C. Should manufacturers' instructions conflict with Contract Documents, request clarification from Architect/Engineer/Designer before proceeding.

D. Comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes or specified requirements indicate higher standards or more precise workmanship.

E. Perform Work by persons qualified to produce required and specified quality.

F. Verify that field measurements are as indicated on shop drawings or as instructed by the manufacturer.

G. Secure Products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, or disfigurement.

1.2 TOLERANCES

A.Monitor fabrication and installation tolerance control of Products to produce acceptable Work. Do not permit tolerances to accumulate.
B.Comply with manufacturers' tolerances. Should manufacturers' tolerances conflict with Contract Documents, request clarification from Architect/Engineer/Designer before proceeding.
C.Adjust Products to appropriate dimensions; position before securing Products in place.

1.3 REFERENCES AND STANDARDS

A. For Products or workmanship specified by association, trade or other consensus standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.

B.Conform to reference standard by date of issue current on date for receiving bids or date specified in the individual specification sections, except where a specific date is established by code.
C.Neither the contractual relationships, duties or responsibilities of the parties in Contract nor those of the Architect/Engineer/Designer shall be altered from the Contract Documents by mention or inference otherwise in any reference document.

1.4 TESTING SERVICES

A.Contractor to provide all testing services as called out in these specifications.
B.Testing and source quality control may occur on or off the project site. Perform off-site testing as required by the Architect/Engineer/Designer or the Owner.
C.Testing does not relieve Contractor to perform Work to contract requirements.
D.Re-testing required because of non-conformance to specified requirements shall be performed by the same MoDOT personnel on instructions by the Architect/Engineer/Designer.

1.5 INSPECTION SERVICES

A.Owner will employ MoDOT Personnel to perform inspection.
B.Inspecting may occur on or off the project site. Perform off-site inspecting as required by the Architect/Engineer/Designer or the Owner.
C.Inspecting does not relieve Contractor to perform Work to contract requirements.

1.6 MANUFACTURERS' FIELD SERVICES

A.When specified in individual specification sections, require material or Product suppliers or manufacturers to provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, start-up of equipment, test, adjust and the balancing of equipment as applicable and to initiate instructions when necessary.
B.Report observations and site decisions or instructions given to applicators or installers that are supplemental or contrary to manufacturers' written instructions.
C.Refer to Section 01300 - SUBMITTALS, MANUFACTURERS' FIELD REPORTS article.

PART 2 EXECUTION

2.1 EXAMINATION

A.Verify that existing site conditions and substrate surfaces are acceptable for subsequent Work. Beginning new Work means acceptance of existing conditions.
B.Verify that existing substrate is capable of structural support or attachment of new Work being applied or attached.

2.2 PREPARATION

A.Clean substrate surfaces prior to applying next material or substance.
B.Seal cracks or openings of substrate prior to applying next material or substance.
C.Apply manufacturer required or recommended substrate primer, sealer or conditioner prior to applying any new material or substance in contact or bond.

01500

CONSTRUCTION FACILITIES AND TEMPORARY CONTROL REQUIREMENTS

PART 1 GENERAL

1.1TEMPORARY ELECTRICITY
A.Cost: By Contractor; pay for temporary power service furnished by MoDOT.
1.2TELEPHONE SERVICE
A.Provide, maintain, and pay for telephone service to field office and Architect/Engineer/Designer’s field office at time of project mobilization.
1.3FACSIMILE SERVICE
A.Provide, maintain and pay for facsimile service and a dedicated telephone line to field office and Architect/Engineer/Designer’s field office at time of project mobilization.
1.4TEMPORARY WATER SERVICE
A.Connect to existing water sources directed for construction operations at time of project mobilization.
B.Contractor will reimburse Owner for water used in construction as agreed upon at time of project mobilization.
1.5TEMPORARY SANITARY FACILITIES
A.Provide and maintain required facilities and enclosures. Provide at time of project mobilization.
1.6FENCING
A.Construction: Use plastic mesh safety fencing or better.
B.Provide 48” high fence around construction site; equip with vehicular and pedestrian gates with locks.
1.7WATER CONTROL
A.Grade site to drain. Maintain excavations free of water. Provide, operate and maintain pumping equipment.
B.Protect site from puddling or running water. Provide water barriers as required to protect site from soil erosion.
1.8EXTERIOR ENCLOSURES
A.Provide temporary weather tight closure of exterior openings to accommodate acceptableworking conditions and protection for Products, to allow for temporary heating and maintenance of required ambient temperatures identified in individual specification sections, and to prevent entry of unauthorized persons. Provide access doors with self-closing hardware and locks.
1.9PROTECTION OF INSTALLED WORK
A.Protect installed Work and provide special protection where specified in individual specification sections.
B.Provide temporary and removable protection for installed Products. Control activity in immediate work area to prevent damage.
C.Provide protective coverings at walls, projections, jambs, sills and soffits of openings.
D.Protect finished floors, stairs, and other surfaces from traffic, dirt, wear, damage or movement of heavy objects, by protecting with durable sheet materials.
E.Prohibit traffic or storage upon waterproofed or roofed surfaces. If traffic or activity is necessary, obtain recommendations for protection from waterproofing or roofing material manufacturer.
F.Prohibit traffic from landscaped areas.
1.10SECURITY
A.Provide security and facilities to protect Work and existing facilities and Owner's operations from unauthorized entry, vandalism or theft.
B.Coordinate with Owner's security program.
1.11ACCESS ROADS
A.Provide and maintain access to fire hydrants, free of obstructions.
B.Provide means of removing mud from vehicle wheels before entering streets.
C.Designated existing on-site roads may be used for construction traffic.
1.12PROGRESS CLEANING AND WASTE REMOVAL
A.Maintain areas free of waste materials, debris and rubbish. Maintain site in a clean and orderly condition.
B.Remove debris and rubbish from pipe chases, plenums, attics, crawl spaces and other closed or remote spaces, prior to enclosing the space.
C.Broom and vacuum clean interior areas prior to start of surface finishing and continue cleaning to eliminate dust.
D.Collect and remove waste materials, debris and rubbish from site periodically and dispose off-site.
E.Open free-fall chutes are not permitted. Terminate closed chutes into appropriate containers with lids.
1.13FIELD OFFICES AND SHEDS
A.Office: Weather tight, with lighting, electrical outlets, heating and ventilating equipment and equipped with drawing rack and drawing display table.
B.Provide space for Project meetings, with table and chairs to accommodate 6 persons.
1.14REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS
A.Remove temporary utilities, equipment, facilities and materials prior to Final Application for Payment inspection.
B.Clean and repair damage caused by installation or use of temporary work.
C.Restore existing facilities used during construction to original condition. Restore permanent facilities used during construction to specified condition.

PART 2 PRODUCTS Not Used.

PART 3 EXECUTION Not Used.

END OF SECTION

01600

MATERIAL AND EQUIPMENT REQUIREMENT

PART 1 GENERAL

1.1PRODUCTS
A.Do not use materials and equipment removed from existing premises, except as specifically permitted by the Contract Documents.
B.Provide interchangeable components of the same manufacture for components being replaced.
1.2TRANSPORTATION AND HANDLING
A.Transport and handle Products in accordance with manufacturer's instructions.
B.Promptly inspect shipments to ensure that Products comply with requirements, quantities are correct and products are undamaged.
C.Provide equipment and personnel to handle Products by methods to prevent soiling, disfigurement or damage.
1.3STORAGE AND PROTECTION
A.Store and protect Products in accordance with manufacturers' instructions.

B. Store with seals and labels intact and legible.

C. Store sensitive Products in weather tight, climate controlled, enclosures in an environment favorable to Product.

D. For exterior storage of fabricated Products, place on sloped supports above ground.

E. Provide bonded off-site storage and protection when site does not permit on-site storage or protection.

F. Cover Products subject to deterioration with impervious sheet covering. Provide ventilation to prevent condensation and degradation of Products.

G. Store loose granular materials on solid flat surfaces in a well-drained area. Prevent mixing with foreign matter.

H. Provide equipment and personnel to store Products by methods to prevent soiling, disfigurement or damage.

I. Arrange storage of Products to permit access for inspection. Periodically inspect to verify Products are undamaged and are maintained in acceptable condition.

1.4PRODUCT OPTIONS
A.Products Specified by Reference Standards or by Description Only: Any Product meeting those standards or description is acceptable.
B.Products Specified by Naming One or More Manufacturers: Products of manufacturers named and meeting specifications, no options or substitutions allowed.
C.Products Specified by Naming One or More Manufacturers with a Provision for Substitutions: Submit a request for substitution for any manufacturer not named in accordance with the following article.

1.5 SUBSTITUTIONS

A. Architect/Engineer/Designer will consider requests for Substitutions only within 15 days after date established in Notice to Proceed.

B. Substitutions may be considered when a Product becomes unavailable through no fault of the Contractor.

C. Document each request with complete data substantiating compliance of proposed Substitution with Contract Documents.

D.A request constitutes a representation that the Contractor:
1.Has investigated proposed Product and determined that it meets or exceeds the quality level of the specified Product.
2.Will provide the same warranty for the Substitution as for the specified Product.
3.Will coordinate installation and make changes to other Work that may be required for the Work to be complete with no additional cost to Owner.
4.Waives claims for additional costs or time extension that may subsequently become apparent.
5.Will reimburse Owner for review or redesign services associated with re-approval by authorities.

E. Substitutions will not be considered when they are indicated or implied on shop drawing or product data submittals, without separate written request or when acceptance will require revision to the Contract Documents.

F.Substitution Submittal Procedure:
1.Submit three copies of request for Substitution for consideration. Limit each request to one proposed Substitution.
2.Submit shop drawings, product data and certified test results attesting to the proposed Product equivalence. Burden of proof is on proposer.
3.The Architect/Engineer/Designer will notify Contractor in writing of decision to accept or reject request.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Not Used.

01650

STARTING OF SYSTEMS REQUIREMENT

PART 1 GENERAL

1.1STARTING SYSTEMS
A.Coordinate schedule for start-up of various equipment and systems.
B.Notify Architect/Engineer/Designer seven days prior to start-up of each item.
C.Verify that each piece of equipment or system has been checked for proper lubrication, drive rotation, belt tension, and control sequence and for conditions that may cause damage.
D.Verify tests, meter readings, and specified electrical characteristics agree with those required by the equipment or system manufacturer.
E.Verify that wiring and support components for equipment are complete and tested.
F.Execute start-up under supervision of applicable manufacturer's representative or Contractors' personnel in accordance with manufacturers' instructions.
G.When specified in individual specification Sections, require manufacturer to provide authorized representative to be present at site to inspect, check and approve equipment or system installation prior to start-up and to supervise placing equipment or system in operation.
H.Submit a written report in accordance with Section 01300 that equipment or system has been properly installed and is functioning correctly.
1.2DEMONSTRATION AND INSTRUCTIONS
A.Demonstrate operation and maintenance of Products to Owner's personnel two weeks prior to date of Final Completion.

B. For equipment or systems requiring seasonal operation, perform demonstration for other season within six months.

C. Utilize operation and maintenance manuals as basis for instruction. Review contents of manual with Owners' personnel in detail to explain all aspects of operation and maintenance.

D. Demonstrate start-up, operation, control, adjustment, troubleshooting, servicing, maintenance and shutdown of each item of equipment at agreed time, at equipment location.

E. Prepare and insert additional data in operations and maintenance manuals when the need for additional data becomes apparent during instruction.

F. The amount of time required for instruction on each item of equipment and system that’s specified in individual sections.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

01700

CONTRACT CLOSEOUT REQUIREMENT

PART 1 GENERAL

1.1CLOSEOUT PROCEDURES
A.Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for Architect/Engineer/Designer’s review.
B.Provide submittals to Owner that is required by governing or other authorities.
C.Submit final Application for Payment identifying total adjusted Contract Sum, previous payments and sum remaining due.
D.Owner will occupy portions of the building as specified in Section 01010.
E.Projects shall not be accepted by MoDOT until the vendor has completed all punch list items. The vendor will then have 30 days to submit all required paperwork necessary to close the project. Failure to submit the required paperwork within 30 days could result in the debarment or suspension of the contractor from future projects.
1.2FINAL CLEANING
A.Execute final cleaning prior to final project assessment. Clean interior and exterior glass, surfaces exposed to view; remove temporary labels, stains and foreign substances, polish transparent and glossy surfaces, vacuum carpeted and soft surfaces.

B. Clean equipment and fixtures to a sanitary condition with cleaning materials appropriate to the surface and material being cleaned.

C. Clean or replace filters of operating equipment used during construction and/or adjustment.

D. Clean debris from roofs, gutters, downspouts and drainage systems.

E. Clean site: sweep paved areas, rake clean landscaped surfaces.

F. Remove waste and surplus materials, rubbish and construction facilities from the site.

1.3ADJUSTING
A.Adjust operating Products and equipment to ensure smooth and unhindered operation.
1.4PROJECT RECORD DOCUMENTS
A.Store record documents separate from documents used for construction.

B. Record information concurrent with construction progress.

C.Specifications: Legibly mark and record at each Product section description of actual Products installed, including the following:
1.Manufacturer's name and product model and number.
2.Product substitutions or alternates utilized.
3.Changes made by Addenda and modifications.
D.Record Drawings and Shop Drawings: Legibly mark each item to record actual construction including:
1.Measured depths of foundations in relation to finish main floor datum.
2.Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.
3.Measured locations of internal utilities and appurtenances concealed in construction, referenced to visible and accessible features of the Work.
4.Field changes of dimension and detail.
5.Details not on original Contract drawings.

E. Submit documents to Architect/Engineer/Designer’s with claim for final Application for Payment.

1.5OPERATION AND MAINTENANCE DATA
A.Submit data bound in 8-1/2 x 11-inch (A4) text pages, three D side ring binders with durable plastic covers.
B.Prepare binder cover with printed title "OPERATION AND MAINTENANCE INSTRUCTIONS", title of project and subject matter of binder when multiple binders are required.
C.Internally subdivide the binder contents with permanent page dividers, logically organized; with tab titling clearly printed under reinforced laminated plastic tabs.
D.Submit 1 draft copy of completed volumes 15 days prior to final inspection. This copy will be reviewed and returned with Architect/Engineer/Designer comments. Revise content of all documents sets as required prior to final submission.
E.Submit two sets of revised final volumes, within 10 days after final inspection.
1.6SPARE PARTS AND MAINTENANCE PRODUCTS
A.Provide spare parts, maintenance, and extra Products in quantities specified individual

specification sections.

B.Deliver to Project site; obtain receipt prior to final payment.
C.Examine system components at a frequency consistent with reliable operation. Clean, adjust and lubricate as required.
D.Include systematic examination, adjustment, and lubrication of components. Repair or replace parts whenever required. Use parts produced by the manufacturer of the original component.
E.Maintenance service shall not be assigned or transferred to any agent or Subcontractor without prior written consent of the Owner.
1.7WARRANTIES
A.Execute and assemble transferable warranty documents from Subcontractors, suppliers and manufacturers.
B.Submit prior to final Application for Payment.
C.For items of Work delayed beyond date of Final Completion, provide updated submittal within 10 days after acceptance, listing date of acceptance as start of the warranty period.
PART 2PRODUCTS

Not Used.

PART 3 EXECUTION

06112

FRAMING AND SHEATHING

PART 1 GENERAL

1.1REFERENCES
A.AHA (American Hardboard Association) A135.4 - Basic Hardboard.
B.ALSC (American Lumber Standards Committee) - Softwood Lumber Standards.
C.ANSI A208.1 - Mat-Formed Wood Particleboard.
D.APA (American Plywood Association).
E.NFPA (National Forest Products Association).
F.SPIB (Southern Pine Inspection Bureau).
G.WCLIB (West Coast Lumber Inspection Bureau).
H.WWPA (Western Wood Products Association).
1.2SUBMITTALS FOR REVIEW
A.Shop Drawings For Site Fabricated Truss Frame: Indicate dimensions, wood species and grades, component profiles, drilled holes, fasteners, connectors, erection details and sequence.
1.3QUALITY ASSURANCE
A.In lieu of grade stamping exposed to view lumber and plywood, submitmanufacturer's certificate certifying that products meet or exceed specified requirements.
B.Design structural shop fabricated trusses under direct supervision of a Professional Structural Engineer experienced in design of this Work and licensed in the State of Missouri.
1.4DELIVERY, STORAGE AND PROTECTION
A.Section 01600 - Material and Equipment: Transport, handle, store and protect products.
B.Protect trusses from warping or other distortion by stacking in vertical position, braced to resist movement.

PART 2 PRODUCTS

2.1SHEATHING MATERIALS
A.Plywood Roof Sheathing: APA Rated Sheathing Structural I Exposure Durability 1; unsanded.
B.Wall Sheathing: ½” APA Rated.
C.Plywood Floor Sheathing: 23/32” Advantech tongue & groove.
D.Telephone and Electrical Panel Boards: Plywood.
2.2UNDERLAYMENT MATERIALS
A.Particleboard Underlayment: Structural Particleboard; wood flakes set with waterproof resin binder. Sanded faces.
2.3SHEATHING AND UNDERLAYMENT LOCATIONS
A.Sloped Roof Sheathing: 5/8” CDX, 48 x 96-inch sized sheets, square edges.
B.Above Grade Wall Sheathing: CDX, ½ inch thick, 48 x 96-inch sized sheets, square edges.
C.Floor Sheathing: ¾” thick, 48 x 96-inch sized sheets, tongue and groove edges.
D.Floor Underlayment: 3/8” thick, 48 x 96-inch sized sheets.
2.4ACCESSORIES
A.Fasteners and Anchors:
1.Fasteners: Stainless steel for high humidity and treated wood locations, galvanized steel elsewhere.
B.Sill Flashing (Under Sill Gasket): Galvanized steel.
C.Subfloor Glue: APA AFG-01, waterproof of solvent base, air cure type, cartridge dispensed.
D.Building Wrap: Tyvek building wrap, 7.1 mils. or equal.
E.Termite Shield: Galvanized sheet steel.
F.Fire Blocking: Provide as required by Building Code.
G.The Simpson Strong Tie shear wall hold down ties require a 5/8” wedge anchor with 5-1’/2” embedment depth. A hold down tie is required at each end of each wall section, each side of each door and window opening, and shall not exceed 25’ of continuous wall length. A double 2x6 or 2x8 is required at each anchor location.

PART 3 EXECUTION

3.1FRAMING
A.Set structural members level and plumb, in correct position.

B. Make provisions for erection loads and for sufficient temporary bracing to maintain structure safe, plumb and in true alignment until completion of erection and installation of permanent bracing.

C. Place horizontal members, crown side up.

D. Construct load bearing framing members’ full length without splices.

E. Double members at openings over 24 inches wide. Space short studs over and under opening to stud spacing.

F. Construct double joist headers at floor and ceiling openings and under wall stud partitions that are parallel to floor joists and framed rigidly into joists.

G. Bridge joists or other framing in excess of 8 feet span at mid-span. Fit solid blocking at ends of members. Bottom plate of the double top plate is not to stop short of nearest stud. It must fall on top of stud.

H. Place full width continuous sill flashings under framed walls on cementitious foundations. Lap all flashing joints at 4 inches.

I. Coordinate installation of wood decking, wood chord metal joists, glue-laminated structural units, prefabricated wood trusses or plywood web joists.

J. Use treated wood bottom plate for all stud walls on concrete foundations and/or floors.

3.2SHEATHING
A.Secure roof sheathing with longer edge perpendicular to framing members and with ends staggered and sheet ends overbearing.

B. Use sheathing clips between sheets between roof framing members. Provide solid edge blocking between sheets. Fully engage tongue and groove edges.

C. Secure wall sheathing with long dimension parallel to wall studs, with ends over firm bearing and staggered.

D. Place plywood or structural-use panel sheeting at building corners for a horizontal distance of 48 inches.

E. Place building paper horizontally over wall sheathing; weather lap edges and ends.

F. Secure subfloor sheathing with longer edge perpendicular to floor framing and with end joints staggered and sheet ends overbearing. Attach with subfloor glue and drywall screws.

G. Place building paper between floor underlayment and subflooring.

H. Install flooring underlayment after dust and dirt generating activities have ceased and prior to application of finished flooring. Apply perpendicular to subflooring, stagger joints of underlayment.

I. Install telephone and electrical panel backboards with plywood sheathing material where required. Size the backboard by 12 inches beyond size of electrical panel.

3.3TOLERANCES
A.Framing Members: 1/4 inch from true position, maximum.
B.Surface Flatness of Floor: 1/4 inch in 10 feet maximum and 1/2 inch in 30 feetmaximum.

07311

ASPHALT SHINGLES

PART 1 GENERAL

1.1REFERENCES
A.ASTM A361/A361M - Steel Sheet, Zinc-Coated (Galvanized) by the Hot-Dip Process for Roofing and Siding.
B.ASTM B209/B209M - Aluminum and Aluminum-Alloy Sheet and Plate.
C.ASTM D225 - Asphalt Shingles Surfaced with Mineral Granules.
D.ASTM D226 - Asphalt-Saturated Organic Felt Used in Roofing and Waterproofing.
E.ASTM D249 - Asphalt Roll Roofing (Organic Felt) Surfaced with Mineral Granules.
F.ASTM D2178 - Asphalt Glass (Felt) Used in Roofing and Waterproofing.
G.ASTM D2822 - Asphalt Roof Cement.
H.ASTM D3018 - Class A, Asphalt Shingles Surfaced with Mineral Granules.
I.ASTM D4586 - Asphalt Roof Cement, Asbestos Free.
1.2SUBMITTALS FOR REVIEW
A.Section 01300 - Submittals: Procedures for submittals.
B.Samples: Submit two samples of each shingle color indicating color range and finish texture/pattern, for color selection.
1.3SUBMITTALS FOR INFORMATION
A.Section 01300 - Submittals: Procedures for submittals.
B.Manufacturer's Certificate: Certify that Products meet or exceed specified requirements.
1.4REGULATORY REQUIREMENTS
A.Conform to applicable code for UL 55B Class C rating, UL 580 wind uplift for shingle types specified.
1.5MOCK-UP
A.Section 01400 - Quality Control: Requirements for mock-up.
B.Provide mockup of 4 sq ft.
C.Locate at job site.
D.Mockup may not remain as part of the Work.
1.6ENVIRONMENTAL REQUIREMENTS
A.Section 01600 - Material and Equipment: Environmental conditions affecting products on site.
B.Do not install eave edge protection and shingles when surface or wind chill temperatures are below 45 degrees F.
1.7EXTRA MATERIALS
A.Section 01700 - Contract Closeout.
B.Provide 50 sq ft of extra shingles of each color selected.

PART 2 PRODUCTS

2.1ASPHALT SHINGLES
A.Asphalt Shingles: ASTM D225, Type I uniform or non-uniform thickness UL Rating of C, Wind Resistance Label, organic felt base, mineral granule surfaced; 95 lb./100 sq ft wt.; standard interlocking type; square tab; color selected.
B.Eave (Ice Dam) Protection: ASTM D226, No. 15, unperforated asphalt saturated felts.
C.Underlayment: ASTM D226, No. 15 unperforated asphalt saturated felts as recommended for use in waterproofing and in construction of built-up roofs.

PART 2 PRODUCTS

2.1ASPHALT SHINGLES
A.3-Dimensional Laminated Strip Shingles: Mineral-surfaced, self-sealing, laminated multi-ply overlay construction, fiberglass-based strip shingles, minimum 30-year limited warranty complying with ASTM 3462, ASTM D-3018 type 1, bearing UL Class “A” external fire exposure label and UL “Wind Resistant” label, weighing not less than 210 lbs. Per square. Color shall be as approved by Owner from standard colors.

1. Hip and Ridge Shingles: Manufacturer’s standard factory pre-cut units to match shingles or job fabricated units cut from actual shingles used.

1. Subject to compliance with requirements, manufacturers offering products which may be incorporated in the work include, but are not limited to, the following:

“Timberline”GAF
“Independence Shangle”Certainteed
“Heritage”Tamko
“Summit”Gerogia-Pacific

Approved equal.

B.Eave (Ice Dam) Protection: Equal to Tamko Moisture Guard Plus.
C.Building Felt Underlayment: Asphalt felt, plain, 30 lb. Weight, 36 inch wide complying with ASTM D 250 for asphalt shingle applications.

1. Apply roofing felts in strict accordance with manufacturer’s instructions.

D.Fasteners for Asphalt Roofing: Aluminum or hot-dipped galvanized 11- or 12-gauge sharp pointed roofing nails with barbed shanks, minimum 3/8” diameter head, and of sufficient length to penetrate through plywood sheathing.
E.Metal Drip Edge: Minimum 0.024-inch baked enamel finish aluminum sheet, brake-formed to provide 3-inch roof deck flange, and 1-1/2” fascia flange with 3/8” drip at lower edge, Furnish in 8’ or 10’ lengths.
F.Continuous Ridge Vents: Provide high-density polyethylene, continuous, shingle over ridge vent with weather filter of manufacturer’s standard design. Provide product equal to “Shingle vent” as manufactured by Air Vent Inc.
2.2ACCESSORIES
A.Nails: Standard round wire shingle type hot dipped zinc coated steel type, of sufficient length to penetrate through roof sheathing.
B.Plastic Cement: ASTM D2822, Asphalt type with mineral fiber components, free of toxic solvents, capable of setting within 24 hours at temperatures of 75 degrees F and 50 percent RH. Cement: Fabricated cutback asphalt type, recommended for use in application of underlayment, free of toxic solvents.
2.3FLASHING MATERIALS
A.Sheet Flashings: ASTM A361/A361M; 24-gauge thick steel with minimum 1.25-oz/sq ft galvanized coating.
B.Bituminous Paint: Acid and alkali resistant type; black color.
C.Nails: Standard round wire roofing type, hot dipped zinc coated steel of sufficient length to penetrate through roof sheathing.
2.4FLASHING FABRICATION
A.Form flashings to protect roofing materials from physical damage and shed water.
B.Form sections square and accurate to profile, in maximum possible lengths, free from distortion or defects detrimental to appearance or performance.
C.Hem exposed edges of flashings minimum 1/4 inch on underside.
D.Apply bituminous paint on concealed surfaces of flashings.

PART 3 EXECUTION

3.1EXAMINATION
A.Verify that roof penetrations and plumbing stacks are in place and flashed to deck surface.
B.Verify roof openings are correctly framed.
C.Verify deck surfaces are dry, free of ridges, warps or voids.
3.2PREPARATION
A.Fill knotholes and surface cracks with latex filler at areas of bonded eave protection. Cover knotholes with sheet metal.
B.Broom clean deck surfaces under eave protection and underlayment.
3.3INSTALLATION - EAVE (ICE DAM) PROTECTION
A.Place eave edge and gable edge metal flashings tight with fascia boards. Weather lap joints 2 inches and seal with plastic cement. Secure flange with nails spaced 8 inches o.c.
B.Apply self-adhering modified-bitumen underlayment eave protection in accordance with manufacturer’s instructions.
C.Apply lap cement at rate of approximately 1 1/4-gal/100 sq ft over underlayment starter strip.
D.Starting from lower edge of starter strip, lay additional 36-inch-wide strips of underlayment in lap cement, to produce a two-ply membrane. Weather lap plies minimum 19 inches and nail in place. Lap ends minimum 6 inches. Stagger end joints of each consecutive ply.
E.Extend eave protection membrane minimum 4 ft up-slope beyond interior face of exterior wall.
3.4INSTALLATION - PROTECTIVE UNDERLAYMENT
A.Place one ply of underlayment over area not protected by eave protection; with ends and edges weather lapped minimum 4 inches. Stagger end laps of each consecutive layer. Nail in place.
B.Install protective underlayment perpendicular to slope of roof and weather lap minimum 4 inches over eave protection.
C.Weather lap and seal watertight with plastic cement items projecting through or mounted on roof.
3.5INSTALLATION - VALLEY PROTECTION
A.Place rubberized asphalt/polyethylene sheet as valley protection in accordance with manufacturer's instructions.
B.Apply a 4-inch wide band of lap cement along each edge of first ply and embed ply of roll roofing minimum 36 inches wide, centered. Place with mineral surface side up. Press into cement to encourage bond and nail in place minimum 18 inches o.c., 1 inch from edges.
3.6INSTALLATION - METAL FLASHING AND ACCESSORIES
A.Weather lap joints minimum 2 inches and seal weather tight with plastic cement.
B.Secure in place with nails at 8 inches o.c. Conceal fastenings.
C.Flash and seal work weather tight, projecting through or mounted on roofing with plastic cement.
3.7INSTALLATION - ASPHALT SHINGLES
A.Install shingles in accordance with manufacturer's instructions.

B. Place shingles in straight coursing pattern with 5-inch weather exposure to produce double thickness over full roof area. Provide double course of shingles at eaves.

C. Project first course of shingles 3/4 inch beyond fascia boards.

D. Extend shingles 1/2 inch beyond face of gable edge fascia boards.

E. Extend shingles on one slope across valley and fasten. Trim shingles from other slope 2 inches from valley centerline to achieve closed cut valley, concealing the valley protection.

F. Cap hips and ridges with individual shingles, maintaining 5-inch weather exposure. Place to avoid exposed nails.

G. Coordinate installation of roof mounted components or work projecting through roof with weather tight placement of counter flashings.

H. Complete installation to provide weather tight service.

3.8FIELD QUALITY CONTROL