This is an Owner's Criteria and Narrative Scope of Work document and Special Conditions package for a design-build Request for Quote (RFQu 27-752-811) issued by the DeKalb County School District (DCSD) in Georgia for elevator modernization services at thirteen school facilities. The project scope encompasses complete design and construction services for elevator cab modernization at Cedar Grove High School, Champion Theme Middle School, Columbia Elementary School, Dunwoody High School, Lithonia High School, Martin Luther King Jr. High School, Montgomery Elementary School, Rockbridge Elementary School, Rock Chapel Elementary School, Shadow Rock Elementary School, Snapfinger Elementary School, Southwest DeKalb High School, and Woodward Elementary School. Work includes replacement of elevator control systems, door operators, hydraulic power units, signal fixtures, electrification components (including Wi-Fi access points and security cameras), signalization systems, and hoistway equipment to current generation standards while complying with DCSD Design Guidelines and all applicable federal, state, and local codes. The Design Builder must mobilize and commence work no later than March 2027, achieve substantial completion by July 2028, and complete final work within thirty days thereafter. Work must be performed without interruption to school operations during regular school hours, with scheduling accommodated during evenings, weekends, and summer vacancy periods as coordinated with the Owner.
The Design Builder is responsible for all sales taxes on material purchases per Georgia Law, obtaining all necessary permits and DeKalb Board of Education approvals, surveying existing conditions, coordinating equipment delivery during normal business hours, and managing material storage upon site possession. Key responsibilities include protecting existing systems (electrical, security, fire alarm, intercom, energy monitoring, TV/cable, and computer networks), maintaining separation between construction activities and existing facilities, obtaining written consent at least thirty days in advance for any utility interruptions not to exceed forty-eight hours, and submitting detailed demolition procedures for Owner approval. The Design Builder must clean roadways and work areas daily, provide final cleaning to DCSD satisfaction, restore all damaged areas to original or better condition, properly dispose of debris offsite while offering salvageable materials to the Owner for reuse, and include labor and materials warranty. All work must comply with OSHA safety regulations, maintain existing facility evacuation plans, restrict construction and vehicle parking to designated areas, and restrict work interruptions to specific weekend hours unless written Owner consent is obtained. The Design Builder shall submit progress payment applications with photographs and updated schedules, prepare a pre-construction defects list signed by all parties, and assume existing buildings are structurally sound except as noted on the defects list, with responsibility for repairing any defects discovered after work commences that were not recorded on the initial list.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQu 27_752_811 Attachments Package (1).pdf | ||
| RFQu 27_752_811 DBuild Services for Elevator .pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Owner's Criteria and Narrative Scope of Work Page 1 of 2
Appendix A1: Owner's Criteria and Narrative Scope of Work - RFQu 27-752-811 Design/Build Services for Elevator Modernizations at Cedar Grove High School.
The elements of construction are as follows:
• Provide design-build services to modernize the elevators at the locations identified in this RFQu.
• Replacement of control system, door operator, hydraulic power unit, and signal fixtures to current generation of equipment including but not limited to:
o Elevator controller
• includes selector system for leveling.
o Door operator system
• New car door, tracks, hangers, clutch
• Interlocks, pick up roller assembly and door Spirator
• Card reader access/operation o Electrification
• Traveling cable
• Wi-Fi access point in cab
• Hoist way wiring
• Verify existing electrical services and provide upgrades including but not limited to replacement primary switches, conductors, and raceways
• Security camera in cab o Signalization
• Car operating panel
• Hall push button stations
• Hall lanterns and/or car direction lanterns depending on what's existing.
o Power unit (Submersible or Dry mount) depending on what's existing.
• Includes pump, valve, motor, muffler.
o Hoistway
• Replacement/installation of hoistway equipment including but not limited to ladders, hoist beams, lighting, buffers, sump pump, rails, fire alarm devices, and cab.
• Verification of hoistway condition per code including restoration of wall and ceiling ratings.
• The modernized elevator shall at a minimum comply with DCSD Design Guidelines for Facility Construction
(Appendix D) along with all federal, state, and local guidelines.
1. The Design Build Firm shall be responsible for paying all sales tax in accordance with GA Law section 48-8-63(c) on all material purchases.
2. The Design Build Firm shall be responsible for coordinating with the DCSD Project Manager and all material and equipment suppliers to schedule delivery of equipment and material to the school/facility during normal business hours. Once the Design Builder takes possession of material at the site, the care and storage of the material becomes the responsibility of the Design Builder.
3. The Design Builder shall obtain all necessary permits required for construction of all work in this scope. The Design Builder shall complete all phases of his work in strict accordance with all applicable local, state, and federal codes and guidelines. The Design Builder will verify that the necessary DeKalb Board of Education approvals have been obtained prior to beginning of construction.
4. The Design Builder is responsible for surveying the existing conditions at the site, to assess installation requirements.
The Design Builder is responsible for installing equipment & material in a workmanlike manner, in compliance with DCSD standards as well as all applicable codes and regulations.
5. Care shall be taken to minimize damage to surrounding structures and surfaces. The Design Builder is responsible for repair of any disturbed areas, including ceiling tiles, patching and/or repainting walls and floors, and restoring any disturbed landscaped or paved areas. The Design Builder shall submit color samples to Owner for any new materials and/or paint used for these corrections, to ensure the best match possible for existing finishes. It is the responsibility of the Design Builder to restore any areas damaged by their work to the original condition, or better.
6. The Design Builder is responsible for the proper demolition, removal and disposal of existing material disturbed in the installation of the new equipment. The Design Builder is to dispose of all debris and remove materials
Owner's Criteria and Narrative Scope of Work Page 2 of 2 offsite, with the exception of any salvageable material: any salvageable material shall be offered to the Owner for possible reuse. All construction waste is to be recycled to the extent practicable.
7. The Design Builder is to keep the work area clean during the completion of the project and must provide final cleaning of the work area to the satisfaction of DCSD.
8 The Design Builder is responsible for coordinating work and ensuring that Project Manager, Stakeholders, and project parties are informed of where work is taking place
9. The Design Builder shall restore all construction areas to a condition acceptable to the Owner.
10. The Design Builder shall include a warranty for labor and materials.
Substantial Completion
The Design Builder is to mobilize and commence work no later than March 2027. All work must be substantially completed by July 2028. Final Completion must take place no later than 30 days after Substantial Completion. The Design Builder will be allowed to work evening and weekend hours as long as the facility is returned to normal building functions for regular school hours While the facility is in operation, all work shall be performed without interruption to facility operations and activities.
Appendix A2: Owner's Criteria and Narrative Scope of Work - RFQu 27-752-811 Design/Build Services for Elevator Modernizations at Champion Theme Middle School.
The elements of construction are as follows:
• Provide design-build services to modernize the elevators at the locations identified in this RFQu.
• Replacement of control system, door operator, hydraulic power unit, and signal fixtures to current generation of equipment including but not limited to:
o Elevator controller
• includes selector system for leveling.
o Door operator system
• New car door, tracks, hangers, clutch
• Interlocks, pick up roller assembly and door Spirator
• Card reader access/operation o Electrification
• Traveling cable
• Wi-Fi access point in cab
• Hoist way wiring
• Verify existing electrical services and provide upgrades including but not limited to replacement primary switches, conductors, and raceways
• Security camera in cab o Signalization
• Car operating panel
• Hall push button stations
• Hall lanterns and/or car direction lanterns depending on what's existing.
o Power unit (Submersible or Dry mount) depending on what's existing.
• Includes pump, valve, motor, muffler.
o Hoistway
• Replacement/installation of hoistway equipment including but not limited to ladders, hoist
• The modernized elevator shall at a minimum comply with DCSD Design Guidelines for Facility Construction
1. The Design Build Firm shall be responsible for paying all sales tax in accordance with GA Law section 48-8-63(c) on
2. The Design Build Firm shall be responsible for coordinating with the DCSD Project Manager and all material and equipment suppliers to schedule delivery of equipment and material to the school/facility during normal business hours. Once the Design Builder takes possession of material at the site, the care and storage of the material becomes the responsibility of the Design Builder.
3. The Design Builder shall obtain all necessary permits required for construction of all work in this scope. The Design Builder shall complete all phases of his work in strict accordance with all applicable local, state, and federal codes and guidelines. The Design Builder will verify that the necessary DeKalb Board of Education approvals have been obtained prior to beginning of construction.
4. The Design Builder is responsible for surveying the existing conditions at the site, to assess installation requirements.
The Design Builder is responsible for installing equipment & material in a workmanlike manner, in compliance with DCSD standards as well as all applicable codes and regulations.
5. Care shall be taken to minimize damage to surrounding structures and surfaces. The Design Builder is responsible for repair of any disturbed areas, including ceiling tiles, patching and/or repainting walls and floors, and restoring any disturbed landscaped or paved areas. The Design Builder shall submit color samples to Owner for any new materials and/or paint used for these corrections, to ensure the best match possible for existing finishes. It is the responsibility of the Design Builder to restore any areas damaged by their work to the original condition, or better.
6. The Design Builder is responsible for the proper demolition, removal and disposal of existing material disturbed in the installation of the new equipment. The Design Builder is to dispose of all debris and remove materials offsite, with the exception of any salvageable material: any salvageable material shall be offered to the Owner for possible reuse. All construction waste is to be recycled to the extent practicable.
7. The Design Builder is to keep the work area clean during the completion of the project and must provide final cleaning of the work area to the satisfaction of DCSD.
8 The Design Builder is responsible for coordinating work and ensuring that Project Manager, Stakeholders, and project parties are informed of where work is taking place
9. The Design Builder shall restore all construction areas to a condition acceptable to the Owner.
10. The Design Builder shall include a warranty for labor and materials.
Substantial Completion
The Design Builder is to mobilize and commence work no later than March 2027. All work must be substantially completed by July 2028. Final Completion must take place no later than 30 days after Substantial Completion. The Design Builder will be allowed to work evening and weekend hours as long as the facility is returned to normal building functions for regular school hours While the facility is in operation, all work shall be performed without interruption to
Appendix A3: Owner's Criteria and Narrative Scope of Work - RFQu 27-752-811 Design/Build Services for Elevator Modernizations at Columbia Elementary School.
The elements of construction are as follows:
• Provide design-build services to modernize the elevators at the locations identified in this RFQu.
• Replacement of control system, door operator, hydraulic power unit, and signal fixtures to current generation of equipment including but not limited to:
o Elevator controller
• includes selector system for leveling.
o Door operator system
• New car door, tracks, hangers, clutch
• Interlocks, pick up roller assembly and door Spirator
• Card reader access/operation o Electrification
• Traveling cable
• Wi-Fi access point in cab
• Hoist way wiring
• Verify existing electrical services and provide upgrades including but not limited to replacement primary switches, conductors, and raceways
• Security camera in cab o Signalization
• Car operating panel
• Hall push button stations
• Hall lanterns and/or car direction lanterns depending on what's existing.
o Power unit (Submersible or Dry mount) depending on what's existing.
• Includes pump, valve, motor, muffler.
o Hoistway
• Replacement/installation of hoistway equipment including but not limited to ladders, hoist
• The modernized elevator shall at a minimum comply with DCSD Design Guidelines for Facility Construction
1. The Design Build Firm shall be responsible for paying all sales tax in accordance with GA Law section 48-8-63(c) on
2. The Design Build Firm shall be responsible for coordinating with the DCSD Project Manager and all material and equipment suppliers to schedule delivery of equipment and material to the school/facility during normal business hours. Once the Design Builder takes possession of material at the site, the care and storage of the material becomes the responsibility of the Design Builder.
3. The Design Builder shall obtain all necessary permits required for construction of all work in this scope. The Design Builder shall complete all phases of his work in strict accordance with all applicable local, state, and federal codes and guidelines. The Design Builder will verify that the necessary DeKalb Board of Education approvals have been obtained prior to beginning of construction.
4. The Design Builder is responsible for surveying the existing conditions at the site, to assess installation requirements.
The Design Builder is responsible for installing equipment & material in a workmanlike manner, in compliance with DCSD standards as well as all applicable codes and regulations.
5. Care shall be taken to minimize damage to surrounding structures and surfaces. The Design Builder is responsible for repair of any disturbed areas, including ceiling tiles, patching and/or repainting walls and floors, and restoring any disturbed landscaped or paved areas. The Design Builder shall submit color samples to Owner for any new materials and/or paint used for these corrections, to ensure the best match possible for existing finishes. It is the responsibility of the Design Builder to restore any areas damaged by their work to the original condition, or better.
6. The Design Builder is responsible for the proper demolition, removal and disposal of existing material disturbed in the installation of the new equipment. The Design Builder is to dispose of all debris and remove materials offsite, with the exception of any salvageable material: any salvageable material shall be offered to the Owner for possible reuse. All construction waste is to be recycled to the extent practicable.
7. The Design Builder is to keep the work area clean during the completion of the project and must provide final cleaning of the work area to the satisfaction of DCSD.
8 The Design Builder is responsible for coordinating work and ensuring that Project Manager, Stakeholders, and project parties are informed of where work is taking place
9. The Design Builder shall restore all construction areas to a condition acceptable to the Owner.
10. The Design Builder shall include a warranty for labor and materials.
Substantial Completion
The Design Builder is to mobilize and commence work no later than March 2027. All work must be substantially completed by July 2028. Final Completion must take place no later than 30 days after Substantial Completion. The Design Builder will be allowed to work evening and weekend hours as long as the facility is returned to normal building functions for regular school hours While the facility is in operation, all work shall be performed without interruption to
Appendix A4: Owner's Criteria and Narrative Scope of Work - RFQu 27-752-811 Design/Build Services for Elevator Modernizations at Dunwoody High School.
The elements of construction are as follows:
• Provide design-build services to modernize the elevators at the locations identified in this RFQu.
• Replacement of control system, door operator, hydraulic power unit, and signal fixtures to current generation of equipment including but not limited to:
o Elevator controller
• includes selector system for leveling.
o Door operator system
• New car door, tracks, hangers, clutch
• Interlocks, pick up roller assembly and door Spirator
• Card reader access/operation o Electrification
• Traveling cable
• Wi-Fi access point in cab
• Hoist way wiring
• Verify existing electrical services and provide upgrades including but not limited to replacement primary switches, conductors, and raceways
• Security camera in cab o Signalization
• Car operating panel
• Hall push button stations
• Hall lanterns and/or car direction lanterns depending on what's existing.
o Power unit (Submersible or Dry mount) depending on what's existing.
• Includes pump, valve, motor, muffler.
o Hoistway
• Replacement/installation of hoistway equipment including but not limited to ladders, hoist
• The modernized elevator shall at a minimum comply with DCSD Design Guidelines for Facility Construction
1. The Design Build Firm shall be responsible for paying all sales tax in accordance with GA Law section 48-8-63(c) on
2. The Design Build Firm shall be responsible for coordinating with the DCSD Project Manager and all material and equipment suppliers to schedule delivery of equipment and material to the school/facility during normal business hours. Once the Design Builder takes possession of material at the site, the care and storage of the material becomes the responsibility of the Design Builder.
3. The Design Builder shall obtain all necessary permits required for construction of all work in this scope. The Design Builder shall complete all phases of his work in strict accordance with all applicable local, state, and federal codes and guidelines. The Design Builder will verify that the necessary DeKalb Board of Education approvals have been obtained prior to beginning of construction.
4. The Design Builder is responsible for surveying the existing conditions at the site, to assess installation requirements.
The Design Builder is responsible for installing equipment & material in a workmanlike manner, in compliance with DCSD standards as well as all applicable codes and regulations.
5. Care shall be taken to minimize damage to surrounding structures and surfaces. The Design Builder is responsible for repair of any disturbed areas, including ceiling tiles, patching and/or repainting walls and floors, and restoring any disturbed landscaped or paved areas. The Design Builder shall submit color samples to Owner for any new materials and/or paint used for these corrections, to ensure the best match possible for existing finishes. It is the responsibility of the Design Builder to restore any areas damaged by their work to the original condition, or better.
6. The Design Builder is responsible for the proper demolition, removal and disposal of existing material disturbed in the installation of the new equipment. The Design Builder is to dispose of all debris and remove materials offsite, with the exception of any salvageable material: any salvageable material shall be offered to the Owner for possible reuse. All construction waste is to be recycled to the extent practicable.
7. The Design Builder is to keep the work area clean during the completion of the project and must provide final cleaning of the work area to the satisfaction of DCSD.
8 The Design Builder is responsible for coordinating work and ensuring that Project Manager, Stakeholders, and project parties are informed of where work is taking place
9. The Design Builder shall restore all construction areas to a condition acceptable to the Owner.
10. The Design Builder shall include a warranty for labor and materials.
Substantial Completion
The Design Builder is to mobilize and commence work no later than March 2027. All work must be substantially completed by July 2028. Final Completion must take place no later than 30 days after Substantial Completion. The Design Builder will be allowed to work evening and weekend hours as long as the facility is returned to normal building functions for regular school hours While the facility is in operation, all work shall be performed without interruption to
Appendix A5: Owner's Criteria and Narrative Scope of Work - RFQu 27-752-811 Design/Build Services for Elevator Modernizations at Lithonia High School.
The elements of construction are as follows:
• Provide design-build services to modernize the elevators at the locations identified in this RFQu.
• Replacement of control system, door operator, hydraulic power unit, and signal fixtures to current generation of equipment including but not limited to:
o Elevator controller
• includes selector system for leveling.
o Door operator system
• New car door, tracks, hangers, clutch
• Interlocks, pick up roller assembly and door Spirator
• Card reader access/operation o Electrification
• Traveling cable
• Wi-Fi access point in cab
• Hoist way wiring
• Verify existing electrical services and provide upgrades including but not limited to replacement primary switches, conductors, and raceways
• Security camera in cab o Signalization
• Car operating panel
• Hall push button stations
• Hall lanterns and/or car direction lanterns depending on what's existing.
o Power unit (Submersible or Dry mount) depending on what's existing.
• Includes pump, valve, motor, muffler.
o Hoistway
• Replacement/installation of hoistway equipment including but not limited to ladders, hoist
• The modernized elevator shall at a minimum comply with DCSD Design Guidelines for Facility Construction
1. The Design Build Firm shall be responsible for paying all sales tax in accordance with GA Law section 48-8-63(c) on
2. The Design Build Firm shall be responsible for coordinating with the DCSD Project Manager and all material and equipment suppliers to schedule delivery of equipment and material to the school/facility during normal business hours. Once the Design Builder takes possession of material at the site, the care and storage of the material becomes the responsibility of the Design Builder.
3. The Design Builder shall obtain all necessary permits required for construction of all work in this scope. The Design Builder shall complete all phases of his work in strict accordance with all applicable local, state, and federal codes and guidelines. The Design Builder will verify that the necessary DeKalb Board of Education approvals have been obtained prior to beginning of construction.
4. The Design Builder is responsible for surveying the existing conditions at the site, to assess installation requirements.
The Design Builder is responsible for installing equipment & material in a workmanlike manner, in compliance with DCSD standards as well as all applicable codes and regulations.
5. Care shall be taken to minimize damage to surrounding structures and surfaces. The Design Builder is responsible for repair of any disturbed areas, including ceiling tiles, patching and/or repainting walls and floors, and restoring any disturbed landscaped or paved areas. The Design Builder shall submit color samples to Owner for any new materials and/or paint used for these corrections, to ensure the best match possible for existing finishes. It is the responsibility of the Design Builder to restore any areas damaged by their work to the original condition, or better.
6. The Design Builder is responsible for the proper demolition, removal and disposal of existing material disturbed in the installation of the new equipment. The Design Builder is to dispose of all debris and remove materials offsite, with the exception of any salvageable material: any salvageable material shall be offered to the Owner for possible reuse. All construction waste is to be recycled to the extent practicable.
7. The Design Builder is to keep the work area clean during the completion of the project and must provide final cleaning of the work area to the satisfaction of DCSD.
8 The Design Builder is responsible for coordinating work and ensuring that Project Manager, Stakeholders, and project parties are informed of where work is taking place
9. The Design Builder shall restore all construction areas to a condition acceptable to the Owner.
10. The Design Builder shall include a warranty for labor and materials.
Substantial Completion
The Design Builder is to mobilize and commence work no later than March 2027. All work must be substantially completed by July 2028. Final Completion must take place no later than 30 days after Substantial Completion. The Design Builder will be allowed to work evening and weekend hours as long as the facility is returned to normal building functions for regular school hours While the facility is in operation, all work shall be performed without interruption to
Appendix A6: Owner's Criteria and Narrative Scope of Work - RFQu 27-752-811 Design/Build Services for Elevator Modernizations at Martin Luther King Jr. High School.
The elements of construction are as follows:
• Provide design-build services to modernize the elevators at the locations identified in this RFQu.
• Replacement of control system, door operator, hydraulic power unit, and signal fixtures to current generation of equipment including but not limited to:
o Elevator controller
• includes selector system for leveling.
o Door operator system
• New car door, tracks, hangers, clutch
• Interlocks, pick up roller assembly and door Spirator
• Card reader access/operation o Electrification
• Traveling cable
• Wi-Fi access point in cab
• Hoist way wiring
• Verify existing electrical services and provide upgrades including but not limited to replacement primary switches, conductors, and raceways
• Security camera in cab o Signalization
• Car operating panel
• Hall push button stations
• Hall lanterns and/or car direction lanterns depending on what's existing.
o Power unit (Submersible or Dry mount) depending on what's existing.
• Includes pump, valve, motor, muffler.
o Hoistway
• Replacement/installation of hoistway equipment including but not limited to ladders, hoist
• The modernized elevator shall at a minimum comply with DCSD Design Guidelines for Facility Construction
1. The Design Build Firm shall be responsible for paying all sales tax in accordance with GA Law section 48-8-63(c) on
2. The Design Build Firm shall be responsible for coordinating with the DCSD Project Manager and all material and equipment suppliers to schedule delivery of equipment and material to the school/facility during normal business hours. Once the Design Builder takes possession of material at the site, the care and storage of the material becomes the responsibility of the Design Builder.
3. The Design Builder shall obtain all necessary permits required for construction of all work in this scope. The Design Builder shall complete all phases of his work in strict accordance with all applicable local, state, and federal codes and guidelines. The Design Builder will verify that the necessary DeKalb Board of Education approvals have been obtained prior to beginning of construction.
4. The Design Builder is responsible for surveying the existing conditions at the site, to assess installation requirements.
The Design Builder is responsible for installing equipment & material in a workmanlike manner, in compliance with DCSD standards as well as all applicable codes and regulations.
5. Care shall be taken to minimize damage to surrounding structures and surfaces. The Design Builder is responsible for repair of any disturbed areas, including ceiling tiles, patching and/or repainting walls and floors, and restoring any disturbed landscaped or paved areas. The Design Builder shall submit color samples to Owner for any new materials and/or paint used for these corrections, to ensure the best match possible for existing finishes. It is the responsibility of the Design Builder to restore any areas damaged by their work to the original condition, or better.
6. The Design Builder is responsible for the proper demolition, removal and disposal of existing material disturbed in the installation of the new equipment. The Design Builder is to dispose of all debris and remove materials offsite, with the exception of any salvageable material: any salvageable material shall be offered to the Owner for possible reuse. All construction waste is to be recycled to the extent practicable.
7. The Design Builder is to keep the work area clean during the completion of the project and must provide final cleaning of the work area to the satisfaction of DCSD.
8 The Design Builder is responsible for coordinating work and ensuring that Project Manager, Stakeholders, and project parties are informed of where work is taking place
9. The Design Builder shall restore all construction areas to a condition acceptable to the Owner.
10. The Design Builder shall include a warranty for labor and materials.
Substantial Completion
The Design Builder is to mobilize and commence work no later than March 2027. All work must be substantially completed by July 2028. Final Completion must take place no later than 30 days after Substantial Completion. The Design Builder will be allowed to work evening and weekend hours as long as the facility is returned to normal building functions for regular school hours While the facility is in operation, all work shall be performed without interruption to
Appendix A7: Owner's Criteria and Narrative Scope of Work - RFQu 27-752-811 Design/Build Services for Elevator Modernizations at Montgomery Elementary School.
The elements of construction are as follows:
• Provide design-build services to modernize the elevators at the locations identified in this RFQu.
• Replacement of control system, door operator, hydraulic power unit, and signal fixtures to current generation of equipment including but not limited to:
o Elevator controller
• includes selector system for leveling.
o Door operator system
• New car door, tracks, hangers, clutch
• Interlocks, pick up roller assembly and door Spirator
• Card reader access/operation o Electrification
• Traveling cable
• Wi-Fi access point in cab
• Hoist way wiring
• Verify existing electrical services and provide upgrades including but not limited to replacement primary switches, conductors, and raceways
• Security camera in cab o Signalization
• Car operating panel
• Hall push button stations
• Hall lanterns and/or car direction lanterns depending on what's existing.
o Power unit (Submersible or Dry mount) depending on what's existing.
• Includes pump, valve, motor, muffler.
o Hoistway
• Replacement/installation of hoistway equipment including but not limited to ladders, hoist
• The modernized elevator shall at a minimum comply with DCSD Design Guidelines for Facility Construction
1. The Design Build Firm shall be responsible for paying all sales tax in accordance with GA Law section 48-8-63(c) on
2. The Design Build Firm shall be responsible for coordinating with the DCSD Project Manager and all material and equipment suppliers to schedule delivery of equipment and material to the school/facility during normal business hours. Once the Design Builder takes possession of material at the site, the care and storage of the material becomes the responsibility of the Design Builder.
3. The Design Builder shall obtain all necessary permits required for construction of all work in this scope. The Design Builder shall complete all phases of his work in strict accordance with all applicable local, state, and federal codes and guidelines. The Design Builder will verify that the necessary DeKalb Board of Education approvals have been obtained prior to beginning of construction.
4. The Design Builder is responsible for surveying the existing conditions at the site, to assess installation requirements.
The Design Builder is responsible for installing equipment & material in a workmanlike manner, in compliance with DCSD standards as well as all applicable codes and regulations.
5. Care shall be taken to minimize damage to surrounding structures and surfaces. The Design Builder is responsible for repair of any disturbed areas, including ceiling tiles, patching and/or repainting walls and floors, and restoring any disturbed landscaped or paved areas. The Design Builder shall submit color samples to Owner for any new materials and/or paint used for these corrections, to ensure the best match possible for existing finishes. It is the responsibility of the Design Builder to restore any areas damaged by their work to the original condition, or better.
6. The Design Builder is responsible for the proper demolition, removal and disposal of existing material disturbed in the installation of the new equipment. The Design Builder is to dispose of all debris and remove materials offsite, with the exception of any salvageable material: any salvageable material shall be offered to the Owner for possible reuse. All construction waste is to be recycled to the extent practicable.
7. The Design Builder is to keep the work area clean during the completion of the project and must provide final cleaning of the work area to the satisfaction of DCSD.
8 The Design Builder is responsible for coordinating work and ensuring that Project Manager, Stakeholders, and project parties are informed of where work is taking place
9. The Design Builder shall restore all construction areas to a condition acceptable to the Owner.
10. The Design Builder shall include a warranty for labor and materials.
Substantial Completion
The Design Builder is to mobilize and commence work no later than March 2027. All work must be substantially completed by July 2028. Final Completion must take place no later than 30 days after Substantial Completion. The Design Builder will be allowed to work evening and weekend hours as long as the facility is returned to normal building functions for regular school hours While the facility is in operation, all work shall be performed without interruption to
Appendix A8: Owner's Criteria and Narrative Scope of Work – RFQu 27-752-811 Design/Build Services for Elevator Modernizations at Rockbridge Elementary School.
The elements of construction are as follows:
• Provide design-build services to modernize the elevators at the locations identified in this RFQu.
• Replacement of control system, door operator, hydraulic power unit, and signal fixtures to current generation of equipment including but not limited to:
o Elevator controller
• includes selector system for leveling.
o Door operator system
• New car door, tracks, hangers, clutch
• Interlocks, pick up roller assembly and door Spirator
• Card reader access/operation o Electrification
• Traveling cable
• Wi-Fi access point in cab
• Hoist way wiring
• Verify existing electrical services and provide upgrades including but not limited to replacement primary switches, conductors, and raceways
• Security camera in cab o Signalization
• Car operating panel
• Hall push button stations
• Hall lanterns and/or car direction lanterns depending on what's existing.
o Power unit (Submersible or Dry mount) depending on what's existing.
• Includes pump, valve, motor, muffler.
o Hoistway
• Replacement/installation of hoistway equipment including but not limited to ladders, hoist
• The modernized elevator shall at a minimum comply with DCSD Design Guidelines for Facility Construction
1. The Design Build Firm shall be responsible for paying all sales tax in accordance with GA Law section 48-8-63(c) on
2. The Design Build Firm shall be responsible for coordinating with the DCSD Project Manager and all material and equipment suppliers to schedule delivery of equipment and material to the school/facility during normal business hours. Once the Design Builder takes possession of material at the site, the care and storage of the material becomes the responsibility of the Design Builder.
3. The Design Builder shall obtain all necessary permits required for construction of all work in this scope. The Design Builder shall complete all phases of his work in strict accordance with all applicable local, state, and federal codes and guidelines. The Design Builder will verify that the necessary DeKalb Board of Education approvals have been obtained prior to beginning of construction.
4. The Design Builder is responsible for surveying the existing conditions at the site, to assess installation requirements.
The Design Builder is responsible for installing equipment & material in a workmanlike manner, in compliance with DCSD standards as well as all applicable codes and regulations.
5. Care shall be taken to minimize damage to surrounding structures and surfaces. The Design Builder is responsible for repair of any disturbed areas, including ceiling tiles, patching and/or repainting walls and floors, and restoring any disturbed landscaped or paved areas. The Design Builder shall submit color samples to Owner for any new materials and/or paint used for these corrections, to ensure the best match possible for existing finishes. It is the responsibility of the Design Builder to restore any areas damaged by their work to the original condition, or better.
6. The Design Builder is responsible for the proper demolition, removal and disposal of existing material disturbed in the installation of the new equipment. The Design Builder is to dispose of all debris and remove materials offsite, with the exception of any salvageable material: any salvageable material shall be offered to the Owner for possible reuse. All construction waste is to be recycled to the extent practicable.
7. The Design Builder is to keep the work area clean during the completion of the project and must provide final cleaning of the work area to the satisfaction of DCSD.
8 The Design Builder is responsible for coordinating work and ensuring that Project Manager, Stakeholders, and project parties are informed of where work is taking place
9. The Design Builder shall restore all construction areas to a condition acceptable to the Owner.
10. The Design Builder shall include a warranty for labor and materials.
Substantial Completion
The Design Builder is to mobilize and commence work no later than March 2027. All work must be substantially completed by July 2028. Final Completion must take place no later than 30 days after Substantial Completion. The Design Builder will be allowed to work evening and weekend hours as long as the facility is returned to normal building functions for regular school hours While the facility is in operation, all work shall be performed without interruption to
Appendix A9: Owner's Criteria and Narrative Scope of Work - RFQu 27-752-811 Design/Build Services for Elevator Modernizations at Rock Chapel Elementary School.
The elements of construction are as follows:
• Provide design-build services to modernize the elevators at the locations identified in this RFQu.
• Replacement of control system, door operator, hydraulic power unit, and signal fixtures to current generation of equipment including but not limited to:
o Elevator controller
• includes selector system for leveling.
o Door operator system
• New car door, tracks, hangers, clutch
• Interlocks, pick up roller assembly and door Spirator
• Card reader access/operation o Electrification
• Traveling cable
• Wi-Fi access point in cab
• Hoist way wiring
• Verify existing electrical services and provide upgrades including but not limited to replacement primary switches, conductors, and raceways
• Security camera in cab o Signalization
• Car operating panel
• Hall push button stations
• Hall lanterns and/or car direction lanterns depending on what's existing.
o Power unit (Submersible or Dry mount) depending on what's existing.
• Includes pump, valve, motor, muffler.
o Hoistway
• Replacement/installation of hoistway equipment including but not limited to ladders, hoist
• The modernized elevator shall at a minimum comply with DCSD Design Guidelines for Facility Construction
1. The Design Build Firm shall be responsible for paying all sales tax in accordance with GA Law section 48-8-63(c) on
2. The Design Build Firm shall be responsible for coordinating with the DCSD Project Manager and all material and equipment suppliers to schedule delivery of equipment and material to the school/facility during normal business hours. Once the Design Builder takes possession of material at the site, the care and storage of the material becomes the responsibility of the Design Builder.
3. The Design Builder shall obtain all necessary permits required for construction of all work in this scope. The Design Builder shall complete all phases of his work in strict accordance with all applicable local, state, and federal codes and guidelines. The Design Builder will verify that the necessary DeKalb Board of Education approvals have been obtained prior to beginning of construction.
4. The Design Builder is responsible for surveying the existing conditions at the site, to assess installation requirements.
The Design Builder is responsible for installing equipment & material in a workmanlike manner, in compliance with DCSD standards as well as all applicable codes and regulations.
5. Care shall be taken to minimize damage to surrounding structures and surfaces. The Design Builder is responsible for repair of any disturbed areas, including ceiling tiles, patching and/or repainting walls and floors, and restoring any disturbed landscaped or paved areas. The Design Builder shall submit color samples to Owner for any new materials and/or paint used for these corrections, to ensure the best match possible for existing finishes. It is the responsibility of the Design Builder to restore any areas damaged by their work to the original condition, or better.
6. The Design Builder is responsible for the proper demolition, removal and disposal of existing material disturbed in the installation of the new equipment. The Design Builder is to dispose of all debris and remove materials offsite, with the exception of any salvageable material: any salvageable material shall be offered to the Owner for possible reuse. All construction waste is to be recycled to the extent practicable.
7. The Design Builder is to keep the work area clean during the completion of the project and must provide final cleaning of the work area to the satisfaction of DCSD.
8 The Design Builder is responsible for coordinating work and ensuring that Project Manager, Stakeholders, and project parties are informed of where work is taking place
9. The Design Builder shall restore all construction areas to a condition acceptable to the Owner.
10. The Design Builder shall include a warranty for labor and materials.
Substantial Completion
The Design Builder is to mobilize and commence work no later than March 2027. All work must be substantially completed by July 2028. Final Completion must take place no later than 30 days after Substantial Completion. The Design Builder will be allowed to work evening and weekend hours as long as the facility is returned to normal building functions for regular school hours While the facility is in operation, all work shall be performed without interruption to
Appendix A10: Owner's Criteria and Narrative Scope of Work - RFQu 27-752-811 Design/Build Services for Elevator Modernizations at Shadow Rock Elementary School.
The elements of construction are as follows:
• Provide design-build services to modernize the elevators at the locations identified in this RFQu.
• Replacement of control system, door operator, hydraulic power unit, and signal fixtures to current generation of equipment including but not limited to:
o Elevator controller
• includes selector system for leveling.
o Door operator system
• New car door, tracks, hangers, clutch
• Interlocks, pick up roller assembly and door Spirator
• Card reader access/operation o Electrification
• Traveling cable
• Wi-Fi access point in cab
• Hoist way wiring
• Verify existing electrical services and provide upgrades including but not limited to replacement primary switches, conductors, and raceways
• Security camera in cab o Signalization
• Car operating panel
• Hall push button stations
• Hall lanterns and/or car direction lanterns depending on what's existing.
o Power unit (Submersible or Dry mount) depending on what's existing.
• Includes pump, valve, motor, muffler.
o Hoistway
• Replacement/installation of hoistway equipment including but not limited to ladders, hoist
• The modernized elevator shall at a minimum comply with DCSD Design Guidelines for Facility Construction
1. The Design Build Firm shall be responsible for paying all sales tax in accordance with GA Law section 48-8-63(c) on
2. The Design Build Firm shall be responsible for coordinating with the DCSD Project Manager and all material and equipment suppliers to schedule delivery of equipment and material to the school/facility during normal business hours. Once the Design Builder takes possession of material at the site, the care and storage of the material becomes the responsibility of the Design Builder.
3. The Design Builder shall obtain all necessary permits required for construction of all work in this scope. The Design Builder shall complete all phases of his work in strict accordance with all applicable local, state, and federal codes and guidelines. The Design Builder will verify that the necessary DeKalb Board of Education approvals have been obtained prior to beginning of construction.
4. The Design Builder is responsible for surveying the existing conditions at the site, to assess installation requirements.
The Design Builder is responsible for installing equipment & material in a workmanlike manner, in compliance with DCSD standards as well as all applicable codes and regulations.
5. Care shall be taken to minimize damage to surrounding structures and surfaces. The Design Builder is responsible for repair of any disturbed areas, including ceiling tiles, patching and/or repainting walls and floors, and restoring any disturbed landscaped or paved areas. The Design Builder shall submit color samples to Owner for any new materials and/or paint used for these corrections, to ensure the best match possible for existing finishes. It is the responsibility of the Design Builder to restore any areas damaged by their work to the original condition, or better.
6. The Design Builder is responsible for the proper demolition, removal and disposal of existing material disturbed in the installation of the new equipment. The Design Builder is to dispose of all debris and remove materials offsite, with the exception of any salvageable material: any salvageable material shall be offered to the Owner for possible reuse. All construction waste is to be recycled to the extent practicable.
7. The Design Builder is to keep the work area clean during the completion of the project and must provide final cleaning of the work area to the satisfaction of DCSD.
8 The Design Builder is responsible for coordinating work and ensuring that Project Manager, Stakeholders, and project parties are informed of where work is taking place
9. The Design Builder shall restore all construction areas to a condition acceptable to the Owner.
10. The Design Builder shall include a warranty for labor and materials.
Substantial Completion
The Design Builder is to mobilize and commence work no later than March 2027. All work must be substantially completed by July 2028. Final Completion must take place no later than 30 days after Substantial Completion. The Design Builder will be allowed to work evening and weekend hours as long as the facility is returned to normal building functions for regular school hours While the facility is in operation, all work shall be performed without interruption to
Appendix A11: Owner's Criteria and Narrative Scope of Work - RFQu 27-752-811 Design/Build Services for Elevator Modernizations at Snapfinger Elementary School.
The elements of construction are as follows:
• Provide design-build services to modernize the elevators at the locations identified in this RFQu.
• Replacement of control system, door operator, hydraulic power unit, and signal fixtures to current generation of equipment including but not limited to:
o Elevator controller
• includes selector system for leveling.
o Door operator system
• New car door, tracks, hangers, clutch
• Interlocks, pick up roller assembly and door Spirator
• Card reader access/operation o Electrification
• Traveling cable
• Wi-Fi access point in cab
• Hoist way wiring
• Verify existing electrical services and provide upgrades including but not limited to replacement primary switches, conductors, and raceways
• Security camera in cab o Signalization
• Car operating panel
• Hall push button stations
• Hall lanterns and/or car direction lanterns depending on what's existing.
o Power unit (Submersible or Dry mount) depending on what's existing.
• Includes pump, valve, motor, muffler.
o Hoistway
• Replacement/installation of hoistway equipment including but not limited to ladders, hoist
• The modernized elevator shall at a minimum comply with DCSD Design Guidelines for Facility Construction
1. The Design Build Firm shall be responsible for paying all sales tax in accordance with GA Law section 48-8-63(c) on
2. The Design Build Firm shall be responsible for coordinating with the DCSD Project Manager and all material and equipment suppliers to schedule delivery of equipment and material to the school/facility during normal business hours. Once the Design Builder takes possession of material at the site, the care and storage of the material becomes the responsibility of the Design Builder.
3. The Design Builder shall obtain all necessary permits required for construction of all work in this scope. The Design Builder shall complete all phases of his work in strict accordance with all applicable local, state, and federal codes and guidelines. The Design Builder will verify that the necessary DeKalb Board of Education approvals have been obtained prior to beginning of construction.
4. The Design Builder is responsible for surveying the existing conditions at the site, to assess installation requirements.
The Design Builder is responsible for installing equipment & material in a workmanlike manner, in compliance with DCSD standards as well as all applicable codes and regulations.
5. Care shall be taken to minimize damage to surrounding structures and surfaces. The Design Builder is responsible for repair of any disturbed areas, including ceiling tiles, patching and/or repainting walls and floors, and restoring any disturbed landscaped or paved areas. The Design Builder shall submit color samples to Owner for any new materials and/or paint used for these corrections, to ensure the best match possible for existing finishes. It is the responsibility of the Design Builder to restore any areas damaged by their work to the original condition, or better.
6. The Design Builder is responsible for the proper demolition, removal and disposal of existing material disturbed in the installation of the new equipment. The Design Builder is to dispose of all debris and remove materials offsite, with the exception of any salvageable material: any salvageable material shall be offered to the Owner for possible reuse. All construction waste is to be recycled to the extent practicable.
7. The Design Builder is to keep the work area clean during the completion of the project and must provide final cleaning of the work area to the satisfaction of DCSD.
8 The Design Builder is responsible for coordinating work and ensuring that Project Manager, Stakeholders, and project parties are informed of where work is taking place
9. The Design Builder shall restore all construction areas to a condition acceptable to the Owner.
10. The Design…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .