SITE VISIT NOTES

Site Visit was scheduled on March 27, 2015 at FCI Herlong. Below are items brought up during the visit.

The monitoring system should provide readings to both the Garage and Powerhouse.

The system equipment and installation needs to be compliant with California Regulations.

Provide Fuel Management System for Vehicle Diesel and Vehicle Gas.

Is it a two hoses system? - Yes, one hose for gas and one for diesel Keypad entry authorization be ok? - Yes

One tank with three compartments. Vehicle Diesel, Vehicle Gas, Boiler/Generator Generator Day Tank 1 Generator Day Tank 2 - No they are all individual tanks

1. New probes and fuel monitoring system - Yes

2. High Intensity Overfill Alarm - Yes

Are the following two tanks only need to install "high" level sensors?

Waste Oil - Yes Waste Antifreeze - Yes

Provide a new fuel controller and monitoring system to allow each of the generator day tanks to control their own fuel flows separate from each other.

Could you elaborate on the above scope of works? - New system needs to operate the same as the existing system. There are 2 separate day tanks, each one needs to operate separate from the other.

Please be as detailed as possible with your bids, itemize each line item. Also, you must have a DUNS and are registered in SAM.