4th Quarter Delivery Instructions
View the file
Other files
| File | Type | Posted |
|---|---|---|
| breadsol.pdf | ||
| Cover_Letter_-_bread_4thQtr.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AWARD DELIVERY INFORMATION – RFQ
Fiscal Year: ____2017______ Quarter: _4th___ Institution: __FCI THREE RIVERS, TEXAS____________________
DELIVERY SCHEDULE
A complete delivery of all awarded items is expected by July 13, 2017 Deliveries will be made Monday thru Thursday from 7:00 am to 2:00 pm.
Federal holiday deliveries will not be accepted.
****Contractor failure to meet delivery schedules without an excusable delay and/or failure to conform to contract specifications will negatively affect the contractor’s history of past performance. Past performance information may be used by the Government to make future award decisions and/or may result in a finding that the quoter is not responsible for the award of future requirements.
NOTE: Delivery is first come first served.
Warehouse Phone: 361-786-3576 x1537 - Brandon Fuentes or 361-786-3576 x1612 - Laury Brown
DELIVERY REQUIREMENTS
· All deliveries must be palletized unless prior arrangements were agreed to by warehouse staff.
· All non-frozen, perishable foods must be delivered between 34 degrees F and 40 degrees F.
· All canned goods must be delivered above 34 degrees F and not frozen.
· All frozen foods must be delivered at 0 degrees F or below.
· Any product that indicates prior thawing will be refused.
· All certified religious diet items must be marked with the Kosher Symbol on individual packages or the item will be refused.
· All items must strictly be in compliance with the BOP National Menu Specifications. Food Service Contractors have the responsibility of understanding these specifications. Contractors must obtain a copy of the National Menu Specifications prior to quoting.
· All items will be closely inspected.
· Some items may require thawing and cooking to determine specifications compliance.
· Receipt of delivery may be conditional for a period of three (3) days in order to allow for adequate examination and testing.
· Items that fail to meet specifications will be refused.
· Items which are conditionally received, and found to be unacceptable, must be picked up at the vendors’ expense within two (2) weeks of noncompliance notification.
· If the product is not picked up within two (2) weeks, it will be disposed of by warehouse staff.