Text version
To Whom It May Concern:
Please see the response to the following question:
Question: Is there any correspondence needed from DCF regarding contingent license upon receipt of award? Or is it due during the 30 day window if awarded?
Answer: A treatment facility license, if required by the state in which services will be provided, to provide outpatient treatment must be provided prior to contract award. The treatment facility license must be in the name of the Quoter (Prime Contractor). If the Quoter does not currently possess a necessary treatment facility license, then the Quoter has thirty days from notice of awardee status to produce the necessary treatment facility license.
Please be informed that the FBOP will not accept questions seven (7) days before the solicitation closing date.
If you have any additional questions, please let me know.